To: Planning and Climate Change Policy Board On: 23 August 2022 Report by: Chief Executive and Director of Finance and Resources Heading: Revenue and Capital Budget Monitoring as at 24 June 2022 1. Summary of Financial Position 1.1. The projected revenue outturn at 31 March 2023 for those services reporting to the Planning and Climate Change Policy Board is an overspend position of £0.050 million. 1.2. There are no capital projects reporting to the Planning and Climate Change Policy Board. 1.3. This is summarised in the table below and further analysis is provided in the Appendices. 2. Recommendations 2.1. Members are requested to: (a) Note the projected Revenue outturn position detailed in Table 1 above; and (b) Note the budget adjustments detailed at section 4. Table 1: Revenue Division Revised Annual Budget £000 Projected Outturn Core £000 Total Projected Outturn £000 Budget Variance £000 Budget Variance % Planning Services 694 744 744 (50) (7.2)
Page 2
3. Revenue 3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected overspend of £0.050 million (7.2% of total budget) for all services reporting to this Policy Board. Detailed division service reports can also be found here, together with an explanation of any significant projected variances. 3.2. The projected outturn is based on information currently available, and assumptions made by service budget holders. Any changes to these projections will be detailed in future reports to the Board. 3.3. The main reasons for the projected outturn position are indicated below the tables showing both the subjective analysis (what the budget is spent on) and the objective analysis (which division is spending the budget). 3.4. The projected overspend of £0.050 million includes an estimated under- recovery in planning fees of £0.072 million. This represents c. 12% of targeted income and reflects a reasonable estimate of income in the current economic and financial climate. 4. Revenue Budget Adjustments 4.1. Members are requested to note from Appendix 1 that budget adjustments totalling £0.031 million have been processed since the Budget was approved on 3rd March 2022. • £0.031m – Planning Services service budget realignment __________________________________________________________________ Implications of this report 1. Financial – The projected budget outturn position for the revenue budget reported to the Planning and Climate Change Board is an overspend of £0.051m. Income and expenditure will continue to be monitored closely for the rest of the financial year and, where necessary, steps will be taken to mitigate any overspend. Any changes to current projections in Revenue budgets will be reported to the board as early as possible, along with an explanation for the movement. 2. HR and Organisational Development None directly arising from this report. 3. Community/Council Planning None directly arising from this report. 4. Legal None directly arising from this report.
Page 3
5. Property/Assets 6. Information Technology None directly arising from this report. 7. Equality and Human Rights The recommendations contained within this report have been assessed in relation to their impact on equalities and human rights. No negative impacts on equality groups or potential for infringement of individuals’ human rights have been identified arising from the recommendations contained in the report because for example it is for noting only. If required following implementation, the actual impact of the recommendations and the mitigating actions will be reviewed and monitored, and the results of the assessment will be published on the Council’s website. 8. Health and Safety None directly arising from this report. 9. Procurement None directly arising from this report. 10. Risk The potential risk that the Council will overspend its approved budgets for the year will be managed at a Council-wide level by the Chief Executive and Directors. 11. Privacy Impact None directly arising from this report. 12. 13. Cosla Policy Position N/a. Climate Risk None directly arising from this report. __________________________________________________________________ List of Background Papers __________________________________________________________________ Author: Valerie Howie (Revenue)
Page 4
Appendix 1 Objective Summary Approved Annual Budget Budget Adjustments Revised Annual Budget P3 Projected Outturn Core Business Total Projected Outturn £000 £000 £000 £000 £000 £000 % Planning Strategy & Place 472 31 503 485 485 18 3.6% Development Management 191 0 191 259 259 (68) (35.6%) NET EXPENDITURE 663 31 694 744 744 (50) (7.2%) Objective Heading Planning Strategy & Place Development Management No significant projected year end variances to report. The overspend relates to a projected under-recovery in planning fee income. There is still an impact on fee income levels from the current economic and financial climate and income is projected to under-recover by c. 12% of targeted income. RENFREWSHIRE COUNCIL REVENUE BUDGET MONITORING STATEMENT 2022/23 1 April 2022 to 24 June 2022 Budget Variance (Adverse) or Favourable POLICY BOARD : PLANNING SERVICES Key Reasons for Projected Variance
Page 5
Appendix 1 Subjective Summary Approved Annual Budget Budget Adjustments Revised Annual Budget P3 Projected Outturn Core Business Total Projected Outturn £000 £000 £000 £000 £000 £000 % Employees 910 0 910 888 888 22 2.4% Premises Related 1 0 1 1 1 0 0.0% Transport Related 4 0 4 4 4 0 0.0% Supplies and Services 139 0 139 139 139 0 0.0% Third Party Payments 0 0 0 0 0 0 0.0% Transfer Payments 99 0 99 99 99 0 0.0% Support Services 142 0 142 142 142 0 0.0% Depreciation and Impairment Losses 0 0 0 0 0 0 0.0% GROSS EXPENDITURE 1,295 0 1,295 1,273 1,273 22 1.7% Income (632) 31 (601) (529) (529) (72) (12.0%) NET EXPENDITURE 663 31 694 744 744 (50) (7.2%) Budget Variance (Adverse) or Favourable POLICY BOARD : PLANNING SERVICES RENFREWSHIRE COUNCIL REVENUE BUDGET MONITORING STATEMENT 2022/23 1 April 2022 to 24 June 2022