___________________________________________________________________ 
To:  Planning and Climate Change Policy Board 
On:  5 November 2024
___________________________________________________________________ 
Report by: Chief Executive 
___________________________________________________________________ 
Heading:  S75 Agreements - Update
___________________________________________________________________ 
1. Summary 
1.1 This report seeks to provide an update in respect of S75 agreements which
are currently being negotiated by officers following a decision being made in
relation to the respective planning applications.   
1.2 S75 agreements secure planning obligations which seek to mitigate the
impacts of a proposed development and make it acceptable in planning terms. 
They can be used to secure financial contributions to, or in-kind provision of,
necessary new social and community infrastructure to support new
developments.
________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Board: 
(i) Note the ongoing negotiations which are taking place in respect of
securing planning obligations which will be secured by agreement, in
accordance with Section 75 of the Town and Country Planning (Scotland)
Act 1997.
___________________________________________________________________ 
3. Background 
3.1 Planning obligations seek to mitigate the impacts of a proposed development
and make it acceptable in planning terms. They can be used to secure
financial contributions to, or in-kind provision of, necessary new social and
community infrastructure to support new developments.

Page 2

3.2 Obligations are usually entered into in accordance under Section 75 of Town
and Country Planning (Scotland) Act 1997, as amended, and are commonly
referred to as “S75 Agreements”.  They are often used where a planning
condition or another form of legal agreement would not be appropriate to
address the impact of the development in question. 
3.3 Planning obligations can be entered into between a person with an interest in
the land and the planning authority; or via a unilateral undertaking by a person
with an interest in the land. S75 agreements run with the land and the
obligation continues to be enforceable against any subsequent owner of the
land until such time as the details of the agreement are fully discharged by the
local planning authority. 
3.4 Scottish Government’s policy on Planning Obligations is expressed in Circular
3/2012 (Planning Obligations and Good Neighbour Agreements - Revised
2020). The Circular sets out five tests which must be met when seeking to
secure a planning obligation: 
▪ Necessary to make a proposal acceptable in planning terms (and
overcome a barrier to the approval of planning permission);
▪ Serve a planning purpose where it is possible to identify infrastructure
provision requirements to advance, should relate to development plans;
▪ Be related to the proposed development either as a direct consequence of
it or arising from the cumulative impact of development in an area;
▪ Fairly and reasonably relate in scale and kind to the proposed
development (provide or contribute to the provision of infrastructure that
would not be necessary were it not for the development, on a
proportionate pro-rata basis as appropriate, but not to resolve existing
deficiencies); and
▪ Be reasonable in all other respects. 
3.5 A number of planning applications in Renfrewshire have been approved
subject to a Section 75 agreement being put in place.  For information, in
these instances, it should be noted that planning consent is not issued until
such time as the Section 75 agreement has been signed and registered as
required. Renfrewshire Council’s approach is for any Board decision involving
a Section 75 agreement, where that agreement is significantly altered during
negotiations with the applicant, will be reported back to Board for confirmation
of the changes.   
3.6 Further to the report considered at the March 2024 meeting of the Planning
and Climate Change Policy Board, no new applications have been granted
subject to a Section 75 agreement, while those that have been previously
approved subject to an agreement have not yet been concluded.
________________________________________________________________

Page 3

4. Agreements currently being negotiated 
4.1 In light of the above, the following applications are currently subject to Section
75 negotiations: 
▪ 19/0749/PP: Erection of residential development comprising 96 dwellings,
with associated open space, roads, access, landscaping, engineering and
infrastructure works at 40 Rannoch Road, Johnstone;
▪ 22/0178/PP: Residential development comprising 59 dwellinghouses and
24 flats, including access, drainage, landscaping and associated works at
a site between Sandieland Wood and Flourish Road, Erskine; and
▪ 22/0481/PP: Erection of residential development comprising 64 dwellings
with associated road and drainage infrastructure at former St. Brendan’s
Social and Recreation Club, Stirling Drive, Linwood. 
19/0749/PP: 40 Rannoch Road, Johnstone
4.2 The above noted application relates to the erection of a residential
development comprising 96 dwellings, with associated open space, roads,
access, landscaping, engineering and infrastructure works. 
4.3 The application was approved subject to conditions and a S75 legal
agreement at the meeting of the Communities, Housing and Planning Policy
Board in January 2022. 
4.4 The S75 legal agreement seeks to secure the provision of affordable housing
units by way of 8 affordable homes. 
4.5 Following the board decision, a draft S75 agreement has been exchanged
between all parties concerned however, to date, no agreement has been
reached. 
4.6 Negotiations are ongoing between officers and representatives of the
applicant and concern the mechanism and triggers associated with the
delivery of the 8 affordable housing units.  It is envisaged that this agreement
will be concluded in the coming weeks. 
22/0178/PP: Site between Sandieland Wood and Flourish Road, Erskine
4.7 The above noted application relates to the erection of residential development
comprising 59 dwellinghouses and 24 flats, including access, drainage,
landscaping and associated works. 
4.8 The application was approved subject to conditions and a S75 agreement at
the meeting of the Planning and Climate Change Policy Board in November
2022. 
4.9 The S75 agreement is required to secure the following:
▪ 24 affordable flats;

Page 4

▪ Financial contribution in respect of education provision within the school
catchment; and
▪ The provision of a formal pedestrian crossing point on Florish Road,
Erskine. 
4.10 Following the board decision, a draft S75 agreement has been exchanged
between all parties concerned however, to date, no agreement has been
reached. 
4.11 Negotiations had been ongoing in respect of a financial contribution towards
education provision and the details relating to the formal pedestrian crossing
point on Florish Road.  Delays however had been encountered as a result of
the wider education issues relating to school estate within the catchment in
question.   
4.12 Furthermore, following the demise of the applicant, Stewart Milne Group Ltd,
no further discussions have been had and in this regard the Council are
awaiting confirmation from the administrator or any new developer on how
they wish to proceed.  It is understood that the administrators are seeking to
sell the site to another developer.   
22/0481/PP: Former St. Brendan’s Social and Recreation Club, Stirling Drive,
Linwood
4.13 The above noted application relates to the erection of a residential
development comprising 64 dwellings with associated road and drainage
infrastructure. 
4.14 The application was approved subject to conditions and a S75 agreement at a
meeting of the Planning and Climate Change Policy Board in November 2023. 
4.15 The S75 agreement is required to secure the following:
▪ Financial contribution in respect of enhancements to an offsite play park to
the north of Gilmartin Road, Linwood and associated tree planting;
▪ Financial contribution in respect of education provision within the school
catchment; and
▪ The provision of affordable housing in line with the respective LDP
policies. 
4.16 Following the March 2024 meeting of the Planning and Climate Change Policy
Board, the representatives of the applicant have been in touch to commence
discussions in relation to the S75 agreement and as such negotiations are
ongoing.
___________________________________________________________________
Implications of the Report
1. Financial – Should the S75 agreements be signed and registered planning
consent will be issued and thereafter any financial contributions will require to

Page 5

be paid to the Council in line with the respective agreement.  Payments
received would then be released to the appropriate service as required to
meet the obligations set out in the associated legal agreement or returned to
the applicant where applicable.   
2. HR & Organisational Development – None. 
3. Community/Council Planning – None. 
4. Legal – S75 agreements require to be negotiated in line decision made at the
respective board meeting and thereafter registered as appropriate following
agreement and signing.  Thereafter obligations will require to be discharged or
varied where appropriate when monies have been spent or returned. 
5. Property/Assets - None 
6. Information Technology - None 
7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report.  If required following
implementation, the actual impact of the recommendations and the mitigating
actions will be reviewed and monitored, and the results of the assessment will
be published on the Council’s website.   
8. Health & Safety - None 
9. Procurement - None 
10. Risk - None 
11. Privacy Impact – None 
12. Children’s Rights – None
13. COSLA Policy Position - None.
14. Climate Risk – None.
___________________________________________________________________ 
Background Papers – 
1. Section 75 Agreements – update; Planning and Climate Change Policy Board;
19 March 2024 
Author: David Love, Chief Planning Officer
Tel: 07483410182; Email: david.love@renfrewshire.gov.uk