5 - Development Plan Update Board Report - AM reviewed

Renfrewshire Council · 5 November 2024
Back to Planning and Climate Change Policy Board — 5 November 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To:  Planning and Climate Change Policy Board
On:  5 November 2024
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Development Plan Update
___________________________________________________________________
1. Summary
1.1 This report provides an update on development planning activity in
Renfrewshire. The 2024 Development Plan Scheme, which sets out the
timetable for preparing the new Local Development Plan (LDP3), and how
stakeholders will be involved in its preparation, is included within this report for
Board approval. 
1.2 It is advised that consultation takes place on the evidence gathered to support
the preparation of the new Local Development Plan prior to it being brought to
Full Council for approval, and it is recommended that a Member/Officer
Working Group be established to consider this evidence also. 
1.3 A Draft Delivery Programme relating to the ongoing implementation of the
current Local Development Plan (LDP2) is also attached for approval. And
finally, the report provides an update on the preparation of Local Place Plans
by communities in Renfrewshire.
___________________________________________________________________ 
2. Recommendations
2.1 It is recommended that the Board:
1) approve the 2024 Renfrewshire Development Plan Scheme and
Participation Statement set out in Appendix 1;
2) note that evidence to be included in the Local Development Plan (LDP3)
Evidence Report will be consulted on ahead of being reported to Council;

Page 2

3) agree that a Members/Officers Working Group is established to consider
Local Development Plan evidence ahead of the submission of the LDP3
Evidence Report to Council; and
4) approve the Draft Local Development Plan (LDP2) Delivery Programme
Update, set out in Appendix 3, for consultation.
_________________________________________________________
3. Background
3.1 The current development plan for Renfrewshire comprises the fourth National
Planning Framework (NPF4) prepared by the Scottish Government and
adopted on 13 February 2023, and the Renfrewshire Local Development Plan
(LDP2), prepared by the Council and adopted on 15 December 2021. 
3.2 Together these documents set out the spatial strategy and planning policy for
the use of land and buildings in Renfrewshire and form the basis for the
decisions on individual planning applications. 
3.3 A new Local Development Plan (LDP3) is currently being prepared under a
new system for development planning introduced by the Planning (Scotland)
Act 2019.
_________________________________________________________
4. Development Plan Scheme and Early Engagement
4.1 The Council is required to prepare and publish a Development Plan Scheme
annually. A Development Plan Scheme is a document setting out the
Council’s programme for preparing and reviewing its Local Development Plan
and must include proposed timetabling for the preparation of the Local
Development Plan, details of what is involved at each stage of the preparation
process, and a Participation Statement setting out how stakeholders will be
involved in the preparation of the Local Development Plan.
4.2 The 2024 Development Plan Scheme is attached for Board approval at
Appendix 1. It sets out the following timetable for the preparation of the new
Local Development Plan (LDP3), and notes changes in the timetable since the
publication of the 2023 Development Plan Scheme. Whilst the delivery of
some key stages is now expected to be later, the adoption date for the new
Local Development Plan (LDP3) is in the same quarter as set out in the 2023
Development Plan Scheme. 
Key stage Date
Publication of Evidence Report and submission for
Gate Check
May 2025
Publication of Proposed Plan and draft Delivery
Programme for consultation
May 2026
Submission of Proposed Plan to Scottish Ministers for
examination
January 2027
Expected adoption of Local Development Plan (LDP3) December 2027

Page 3

4.3 The Participation Statement has been updated to provide more detail of
engagement and consultation that has and will be undertaken at different
stages of the plan preparation process.
4.4 Some early non-statutory engagement to inform the new Local Development
Plan has already taken place including:
▪ A ‘call for ideas’ survey which has generated 92 responses to date,
suggesting proposals for specific sites in Renfrewshire. A list of the
submissions is attached as Appendix 2. These proposals will be assessed
and consulted on in 2025 as part of the Proposed LDP preparation
process.
▪ A ‘have your say on Renfrewshire’s places’ survey which has
generated 254 responses to date. This survey is based on the Scottish
Government’s Place Standard tool and asks respondents to score and
comment their area against a range of factors. The responses received
provide qualitative information about places in Renfrewshire based on a
number of factors.
▪ In conjunction with the Council’s Youth Service, workshops with pupils
have been held at 8 of Renfrewshire’s 12 secondary schools (all
secondary schools have been offered workshops). The workshops are
based on the young persons’ version of the Place Standard tool, and over
100 young people of secondary school age identified what they liked and
didn’t like about their areas through commenting on maps about specific
areas, and in general terms in relation to specific topics.
4.5 A report on early engagement will form part of the LDP Evidence Report.
_________________________________________________________
5. Evidence Report
5.1 The first key stage in the preparation of the new Local Development Plan is
the publication of the Evidence Report and its submission to the Scottish
Ministers for a Gate Check. The purpose of the Evidence Report is to support
the quality and effectiveness of the Local Development Plan by front-loading
the collection of evidence that will be used to inform the Plan before the plan
looks at where development should take place. The Gate Check by
Government provides an independent assessment of the Evidence Report,
assessing whether the planning authority has sufficient information to prepare
its Local Development Plan. It is carried out by a person appointed by the
Scottish Ministers, usually a reporter from the Directorate of Planning and
Environmental Appeals (DPEA).
5.2 Legislation requires that the Evidence Report is to be approved by the Full
Council before it is submitted to the Scottish Ministers. Ahead of taking the
report to Full Council, draft Evidence Report templates will be shared with
stakeholders to allow for evidence to be commented on, additional evidence
to be submitted and evidence gaps to be identified.

Page 4

5.3 To enable elected members to consider evidence ahead of its submission to
Full Council, it is recommended that a Member/Officer Working Group be
established. Further details on the proposal for this will follow in due course
from officers but essentially the Group will have member representation in
broad proportion to the overall PCC Board political party representation, with
the PCC Board Convenor being asked to extend his role to also cover the
Working Group.
_________________________________________________________
6. Local Development Plan (LDP2) Delivery Programme
6.1 There is a statutory requirement for local development plans to be
accompanied by a Delivery Programme and for this to be updated every two
years. A Delivery Programme (previously known as an Action Programme)
associated with the current Local Development Plan (LDP2) was published in
2022. 
6.2 A draft Delivery Programme update has been prepared, and it is proposed
that this is published for consultation ahead of being finalised. To comply with
Scottish Government instructions, the draft Delivery Programme update
includes estimated 10-year programming for housing sites in Renfrewshire.
This is included at Appendix 3 to this report for members approval.
_________________________________________________________
7. Local Place Plans
7.1  Local place plans are community led plans which can be prepared by a
community council, or another community body as defined by the Community
Empowerment Act. They are to be focused on proposals for the development
and use of land.
7.2 An invitation to prepare local place plans was sent to community councils and
development trusts across Renfrewshire in May 2023. Information sessions
were held for these groups in March 2024, and several one-to-one meetings
with interested organisations have been held. Online drop-in sessions have
been arranged to allow community groups with an interest in preparing a local
place plan to share their experience and progress to date, and an opportunity
to ask Council officers questions around process and support. Two of these
sessions have been held to date, and these sessions will continue for as long
as community groups are finding value in them. There is no dedicated budget
to support the preparation of local place plans, with communities seeking
funding being directed to the Sustainable Communities Fund for potential
support.
7.3 Thirteen community councils or development trust have so far completed a
form expressing interest in preparing a local place plan. It is understood
around six Renfrewshire groups (to date) are proceeding with the preparation
of a local place plan. 
___________________________________________________________________

Page 5

Implications of the Report
1. Financial – there are financial implications associated with the Evidence
Report Gate Check and the Proposed Plan Examination, the cost of which are
to be met by the Council. There will also be costs associated with certain
studies required to inform the Local Development Plan, for example a
transport assessment. 
2. HR & Organisational Development – None.
3. Community/Council Planning – The Local Development Plan is a wide-
ranging document and is considered to support the priorities of the
Renfrewshire Community Plan and the Council’s strategic outcomes.
4. Legal – The preparation of a local development plan is a statutory
requirement for planning authorities. The Council is following statutory
procedures in preparing the plan.
5. Property/Assets – None.
6. Information Technology – None. 
7. Equality & Human Rights - The recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. The impact assessment has highlighted the need to ensure that certain
groups with protected characteristics and from areas of socio-economic
disadvantage are involved in the local development plan process. Equalities
monitoring of the local development plan participant database and
engagement processes will be undertaken to monitor and highlight groups or
areas where targeted consultation may be required.  A full copy of the
Equality Impact Assessment undertaken is available from the report author.
Following implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored. The results of the
assessment will be published on the Council’s website.
8. Health & Safety – None.
9. Procurement – None.
10. Risk – There is a risk that the Council’s Evidence Report may be found to be
insufficient at the Gate Check stage, as two of the four Evidence Reports
submitted by other planning authorities to date have been deemed
insufficient. To mitigate this risk, the Council is consulting on draft Evidence
Report templates, and having regard to the Gate Check findings of other
Evidence Reports.
11. Privacy Impact – None.
12. Climate Risk – The Local Development Plan will have regard to and support
the implementation of the Council’s Plan for Net Zero.
13. Children’s Rights – Through engagement with children and young people,
the approach being taken by the Council demonstrates compliance with
Article 12 ‘Respect for Children’s Views’.

Page 6

14. Cosla Policy Position – None
_______________________________________________________
Appendices 
Appendix 1 – LDP3 Development Plan Scheme and Participation Statement (2024)
Appendix 2 – List of ‘call for ideas’ submissions to LDP3
Appendix 3 - Draft LDP Delivery Programme Update (2024) 
List of Background Papers 
None 
___________________________________________________________________ 
Author: Alan Williamson, Strategy & Place Manager,
alan.williamson@renfrewshire.gov.uk, 07811 053968

Page 7

Appendix 1 
Renfrewshire Council
Local Development Plan (LDP3)
Development Plan Scheme and Participation
Statement
November 2024

Page 8

Contents
Introduction ..................................................................................................................................................................................................................................... 3
Current development plan in Renfrewshire ..................................................................................................................................................................................... 3
Preparing the next local development plan for Renfrewshire ......................................................................................................................................................... 3
Timeline for preparing the next local development plan for Renfrewshire ..................................................................................................................................... 5
Associated assessments ................................................................................................................................................................................................................... 6
Local place plans .............................................................................................................................................................................................................................. 6
Participation Statement ................................................................................................................................................................................................................... 7
Managing engagement ................................................................................................................................................................................................................ 7
Early engagement and evidence report preparation ................................................................................................................................................................... 8
Preparation of proposed local development plan ..................................................................................................................................................................... 11
Publication and consultation on proposed local development plan ......................................................................................................................................... 12
Examination and adoption ......................................................................................................................................................................................................... 14
Engagement with children and young people – activity up to October 2024. .......................................................................................................................... 15
Mediation ................................................................................................................................................................................................................................... 15
Contact us and follow us ................................................................................................................................................................................................................ 16

Page 9

Introduction
Thank you for your interest in the development plan for Renfrewshire.
The development plan sets out policy and strategy for the use of land and buildings, setting out how places will change into the future, including where
development should and should not happen. The planning system in Scotland is ‘plan-led’, and the development plan is the document the Council uses to
make decisions on planning applications and is intended to provide certainty to communities and the development industry about where different types of
development will be acceptable.
This development plan scheme sets out information on current development plan coverage in Renfrewshire, and on the process and timetable for preparing
a new local development plan (LDP3) for Renfrewshire, including how we will include communities and organisations in the preparation of the plan.
Current development plan in Renfrewshire
The development plan for Renfrewshire consists of:
The Fourth National Planning Framework (NPF4) – prepared by the Scottish Government and adopted on 13 February 2023, NPF4 is the national spatial
strategy for Scotland. It sets out spatial principles, regional priorities, national developments and national planning policies. For more information, please visit
https://www.gov.scot/publications/national-planning-framework-4/. 
Renfrewshire Local Development Plan (LDP2) – prepared by Renfrewshire Council and adopted on 15 December 2021, LDP2 sets out the spatial strategy for
Renfrewshire, identifying areas for development, improvement and protection. LDP2 is complemented by New Development Supplementary Guidance (2022),
which also forms part of the development plan. LDP2 is also supported by a Delivery Programme setting out how the policies and proposals of the plan will
be delivered. For more information, and to view these documents, please visit https://www.renfrewshire.gov.uk/article/3070/Renfrewshire-Development-
Plan.
Preparing the next local development plan for Renfrewshire
The Council is preparing a new local development plan for the Renfrewshire area (LDP3). Following changes introduced by the Planning (Scotland) Act 2019,
this plan will be prepared differently and have a different look from LDP2. The new plan will be place-based, people-centred and delivery-focused. It will be a
visual/graphic document, prepared with the intention that the spatial strategy is set out in a collection of maps, development briefs and masterplans, instead
of lengthy written text and policy. Local development plans are to be prepared collaboratively, giving communities an opportunity to help shape their local
neighbourhoods.

Page 10

The key stages in preparing the new plan are:
Development plan scheme including participation statement – the development plan scheme is an important communication tool for letting stakeholders
know when and how they can get involved in the preparation of the plan. It is updated annually.
Evidence report – the purpose of the evidence report is to support the quality and effectiveness of the local development plan. Its purpose is to front-load
the collection of evidence that will be used to inform the plan before the plan looks at where development should take place. It should be informed by the
views of those who will be affected by the plan.
Gate Check – this provides an independent assessment of the evidence report, assessing whether the planning authority has sufficient information to prepare
its local development plan. It is carried out by a person appointed by the Scottish Ministers, usually a reporter from the Directorate of Planning and
Environmental Appeals.
Proposed Plan – the proposed plan identifies where new development should take place and where it should not, articulating the ambitions and priorities for
the future development of the area. The preparation of the proposed plan is to be informed by community and stakeholder engagement. The proposed plan
is published for consultation for a minimum 12-week period. The proposed plan can be modified following this period of consultation.
Delivery Programme – the delivery programme sets out how the Council proposes to implement its local development plan. A proposed delivery programme
is published alongside the proposed local development plan. The delivery programme is to set out a list of actions required to deliver the polices and proposals
of the local development plan, including an explanation of how those actions are to be undertaken and the timescale for conclusion of each action. Additionally,
it is to include information on the expected sequencing and timescales for delivery of allocated housing sites.
Examination – the examination is an opportunity for independent consideration of any issues raised during the formal consultation on the proposed plan that
have not been resolved through modification. The Scottish Ministers will appoint a person to examine the proposed plan, usually a reporter from the
Directorate of Planning and Environmental Appeals. Once the examination is completed the appointed person will prepare a report setting out modifications
to be made to the plan. There are limited circumstances for when a planning authority can decline the appointed person’s recommended modifications.
Adoption – adoption occurs following the examination of the plan and the recommended modifications of the examination report are received and considered.

Page 11

Timeline for preparing the next local development plan for Renfrewshire
The estimated timeline for the preparation of the new local development plan and the dates for key stages are set out below (this includes reference to
financial year quarters as required by legislation). A timeline diagram is included in Appendix 1.
Key stage Date Change since 2023 development plan scheme
Publication of evidence report and submission for gate
check
May 2025 (Q1, 2025/26) The estimated submission of the evidence report for gate
check has been delayed by two quarters.
Publication of proposed plan and draft delivery
programme for consultation
May 2026 (Q1, 2026/27) The estimated submission of the evidence report for gate
check has been delayed by two quarters.
Submission of proposed plan to Scottish Ministers for
examination
January 2027 (Q4, 2027/28) The estimated submission of the proposed plan for
examination has been delayed by two quarters.
Expected adoption of local development plan (LDP3) December 2027 (Q3,
2027/28) 
The submission of the evidence report for gate check has been delayed by two quarters compared to the timetable set out in the 2023 development plan
scheme. The evidence report is a new requirement for local development plan preparation and the scale of the task and issues emerging from gate checks of
other planning authority evidence reports, and the need to avoid the February 2025 Council meeting has led to a short delay in the anticipated submission
for gate check. There is a knock-on effect for the submission of the proposed plan for examination, which is delayed by two quarters, but the overall timescale
for plan adoption remains the same.

Page 12

Associated assessments
The preparation of the local development plan will be informed by the following assessments.
Equalities Impact Assessment – local authorities have a duty to eliminate discrimination; advance equality of opportunity; and foster good relations between
people who share protected characteristics and those who don’t. The equalities impact assessment will help the Council to consider how people of different
characteristics are involved in the preparation of the plan, and how they are affected by the proposals of the plan.
Fairer Scotland Duty Assessment – the Fairer Scotland Duty places a legal responsibility on local authorities to actively consider how they can reduce
inequalities of outcome caused by socio-economic advantage when making strategic decisions.
Strategic Environmental Assessment – this assessment aims to ensure the environment is a primary consideration in the preparation of the plan. It can benefit
the preparation of the plan by supporting better understanding of its environmental context and setting out steps to avoid, mitigate or reduce adverse effects,
and enhance positive ones.
Habitat Regulations Appraisal – this assessment is required if the plan is capable of having an adverse effect on a Special Protection Area or Special Area of
Conservation. These are referred to collectively as ‘European Sites’ and protect species and habitats. The assessment considers the implications of the plan
for such designated sites in order to avoid adverse impacts.
Local place plans
Local place plans offer communities an additional chance to shape their local area. They provide an opportunity for local communities to set priorities for their
area and influence planning decisions.
In preparing the next local development plan, the Council will take into account any registered Local Place Plans.
An invitation to prepare local place plans was sent to local communities across Renfrewshire in May 2023. Communities have been asked to express an interest
in preparing a local place plan and identify any support that may be needed from the Council and other stakeholders.
Although they can be prepared at any time, local place plans should be completed and submitted to the Council by September 2025 so they can be taken
into account when preparing the next Local Development Plan. For more information on local place plans, please visit
https://www.renfrewshire.gov.uk/article/8667/Local-Place-Plans.

Page 13

Participation Statement
Everyone will have an opportunity to get involved in the preparation of the next Renfrewshire Local Development Plan.
Effective consultation and engagement are vital, as the Local Development Plan can affect where people live, work, visit, shop, play and travel in Renfrewshire.
Your involvement and feedback can help us understand priorities for Renfrewshire and deliver a spatial strategy that addresses the issues important to
communities.
We want to make it as easy as possible for everyone who has an interest to engage in the process.
The following pages set out how we intend to manage, facilitate and encourage engagement in the local development plan process.
Opportunities to become involved in the preparation of LDP3 will be advertised through social media, updates on the Councils website, emails/letters to
everyone who has registered interest in the local development plan process, and notices in the local newspaper (when required).
Those with protected characteristics under the Equality Act 2010, including disability, race, age, gender, sex and sexual orientation, religion and people from
a range of socio-economic backgrounds and their representatives will be supported where required to get involved in the preparation of the new plan.
There are a number of key stages to get involved in the plan preparation. The table below sets out the engagement activities that will be undertaken at each
stage, the purpose of it, progress at October 2024, and future activity.
Managing engagement
Engagement Activity Timescale Purpose Progress at October 2024 Future activity
Participation statement Updated annually To inform stakeholders
about the local
development plan process
and provide an
opportunity for
stakeholders to shape the
engagement process
A consultation was undertaken
in August 2023 to inform the
2023 development plan scheme
and participation statement, and
in August/September 2024 to
inform the 2024 participation
statement update. 
A consultation will be held
on significant changes in
future annual updates of
the participation
statement.
Participation database and
diary
Ongoing Maintain a record of
participants who have
registered interest in the
local development plan
process.
Participation registration form
created.
As of October 2024, there were
1126 participants registered in
the participant database.
Registration form remains
open, and all engagement
activity will be recorded.

Page 14

Engagement Activity Timescale Purpose Progress at October 2024 Future activity
Maintain a record of
engagement events
The participation diary had
recorded 38 engagement
activities since February 2024,
being a mix of meetings/events
and survey launches/
notifications.
Local development plan
webpages
Ongoing Promote engagement in
local development plan
and make consultation
information available
Webpage created. Keep webpage updated
and develop LDP3 hub
pages
Combined equalities
assessment
Ongoing To ensure compliance with
the Equality Act 2010 and
the United Nations
Convention of the Rights
of the Child.
An initial equalities assessment
focused on
consultation/engagement was
prepared in October 2024.
An equalities assessment
focused on the content of
the proposed plan will be
prepared in conjunction
with, and published
alongside, the proposed
plan, which is scheduled
for April 2026. 
Early engagement and evidence report preparation
Engagement Activity Timescale Purpose Progress at October 2024 Future activity
‘Have your say on
Renfrewshire’s places’ survey
(based on the Place
Standard)
March>December 2024 To enable communities to
offer comment on what is
good and what can be
improved in their local
area.
The survey was launched on 28
March 2024 and was made
available online and in libraries
through Renfrewshire. 253
responses had been received by
end of September 2024.
The survey remains open
and further engagement
and promotion work will be
undertaken to increase the
number of responses.
Other survey opportunities
and results will be used to
inform the local
development plan.

Page 15

Engagement Activity Timescale Purpose Progress at October 2024 Future activity
‘Call for ideas’ survey March > May 2024 To enable developers,
landowners and
communities to submit
ideas and proposals for
specific sites in
Renfrewshire
The survey was launched online
on 28 March 2024, and actively
promoted until 31 May 2024. 92
responses had been received by
end of September 2024. 
The initial survey remains
open and a second stage
‘Call for ideas’ survey will
be held during the
proposed plan preparation
period.
Children and young people
engagement
May > December 2024 To enable children and
young people to inform
the preparation of the
evidence report
Working with Youth Services, 8
of Renfrewshire’s secondary
schools have been visited to
gather views from pupils on
what they like and do not like
about their communities. Over
100 pupils have attended the
workshops.
Workshops were held with
children at the Council’s summer
holiday camps. These focused
on play opportunities.
Visits have been offered to
the remaining secondary
schools and will be offered
to primary schools to
engage with younger
children.
Engagement with MSYP
and Youth Councils will be
undertaken. 
Local place plans May 2023 > September
2025
Promote local place plans
as an opportunity for
communities to engage in
local development plan
process
Invitation to prepare local place
plans was issued to community
councils and development trusts
in May 2023 and placed on
webpage.
Information sessions were held
in March 2024, and online drop-
in sessions were held in August
and September 2024.
Communities will be
reminded of opportunity to
prepare local place plans
and start-up meetings and
other support will be
offered to interested
community groups. Online
drop-in sessions will
continue to be offered
while there is interest.
Engagement with gypsy/
traveller and travelling
showpeople communities
October 2024 > February
2025
To identify
accommodation needs
within Renfrewshire 
Direct engagement with
gypsy/traveller and
travelling show people

Page 16

Engagement Activity Timescale Purpose Progress at October 2024 Future activity
communities and/or their
representatives.
Engagement with disabled
people
October 2024 > February
2025
To identify housing needs
for disabled people within
Renfrewshire 
Direct engagement with
disabled people
communities and/or their
representatives.
Engagement with community
councils and development
trusts
March 2024 > February
2025
To identify the
expectations of
communities for the new
local development plan
and to promote the
preparation of local place
plans
All community councils and
development trusts were invited
to the March 2024 information
sessions on local place plans, 8
attended. Presentations have
been given to four community
councils/development trusts
since February 2024.
Community councils and
development trusts will be
offered meetings regarding
the evidence report
consultation.
Engagement with key
agencies and government
agencies
April 2024 > February
2025
To identify evidence that
key agencies will be able
to submit to inform
evidence report
Meetings held with Transport
Scotland, Strathclyde
Partnership for Transport,
Scottish Water and NHSGGC.
Meet with key agencies as
required and share
relevant evidence in
advance of submission of
evidence report.
Engagement with
development industry,
businesses and landowners
February 2024 > February
2025
To identify the general and
site specific ambitions of
the development industry
and landowners
Initial ‘call for ideas’ survey
produced 92 responses (not all
from development industry).
Several one-to-one meetings
held with developers and
landowners.
Continue to meet with
developers/ businesses/
landowners on request.
Seek meetings with
representative groups e.g.
Homes for Scotland,
Chamber of Commerce.
Consult on draft evidence
report templates
November 2024 >
February 2025
To test sufficiency of
evidence, and identify
disputes and gaps 
Draft evidence report
templates will be published
and views sought on
content.
Registered participants will
be notified of publication.

Page 17

Engagement Activity Timescale Purpose Progress at October 2024 Future activity
Publish evidence report on
council website
May 2025 To make evidence report
available to stakeholders 
Inform stakeholders of
publication of evidence
report 
Preparation of proposed local development plan
Engagement Activity Timescale Purpose Progress at October 2024 Future activity
Support communities with
finalisation of local place
plans
May 2025 > September
2025
To ensure as many local
place plans as possible are
finalised in time to inform
the proposed local
development plan
Information sessions were held
in March 2023, and online drop-
in sessions were held in August
and September 2024.
Engage with those
communities preparing
local place plans to
encourage and facilitate
validation and registration
of local place plans, and
discuss how local place
plan proposals can be
included in local
development plan.
Where appropriate, use
mediation to address
conflicts between local
place plans and alternative
proposals.
‘Call for ideas’ survey May 2025 > June 2025 To enable developers,
landowners and
communities to submit/
update ideas and
proposals for specific sites
in Renfrewshire. 
Publicise ‘Call for ideas’
survey to all registered
participants, and more
widely. Make submission
form available online.
Consultation on suggested
development sites
August > October 2025 To allow stakeholders to
comment on the Council’s
initial assessment of sites 
Publish initial/draft
assessments of proposed
development sites online

Page 18

Engagement Activity Timescale Purpose Progress at October 2024 Future activity
that have been suggested
for development sites
and invite stakeholder
comments.
Where appropriate, use
mediation to resolve
different views.
Preparation of masterplans
and site briefs in
collaboration with
stakeholders
May 2025- > March 2026 To provide an opportunity
for stakeholders to inform
the content of the
proposed local
development plan 
Work with communities
and developers to inform
and develop area
masterplans and
development briefs for
sites for inclusion in
proposed local
development plan.
Ongoing engagement with
statutory stakeholders,
community councils, children
and young people, older
people and gypsy/travellers
and travelling showpeople.
May 2025 > March 2026 To ensure statutory
engagement requirements
are met and that the
proposed plan is informed
by engagement with these
groups. 
Continue to engage with all
stakeholders through
meetings and events.
Liaise with organisations who
will be responsible for actions
included in the Draft Delivery
Programme
May 2025 > March 2026 To ensure that
organisations are aware
and supportive of their
role in delivering the local
development plan. 
Meetings with relevant
organisations. 
Publication and consultation on proposed local development plan
Engagement Activity Timescale Purpose Progress at October 2024 Future activity
Publish proposed local
development plan for
consultation, draft strategic
environmental assessment
May 2026 > August 2026 To provide an opportunity
for communities and
stakeholders to comment 
Publish proposed local
development plan and
assessment/appraisal
documents for minimum

Page 19

Engagement Activity Timescale Purpose Progress at October 2024 Future activity
environmental report and
draft habitat regulations
appraisal
on the proposed local
development plan.
12-week consultation
period. 
Make copy of proposed
plan available online, in
Council offices and
libraries. 
Publicise publication of
plan through social media,
press and posters and carry
out statutory notifications. 
Notify neighbours of sites
proposed for development
in the proposed plan. 
Attend meeting and events
to publicise publication of
proposed plan
Liaise with stakeholders who
are seeking modifications to
the proposed local
development plan
August > November 2026 To try and resolve
representations/objections
that are seeking changes
to the proposed plan 
Meetings with
individuals/organisations
that have submitted
representations/objections.
Where appropriate use
mediation to resolve
different views.

Page 20

Examination and adoption
Engagement Activity Timescale Purpose Progress at October 2024 Future activity
Examination further
information requests
January > September 2027 The Reporter undertaking
the examination may seek
further information to fully
understand
representations. 
Where required, facilitate
responses to further
information requests.
Publish modification report October > December 2027 To inform participants of
recommended changes to
the proposed plan. 
Publish modification report
and inform participants.
Publish adopted local
development plan
December 2027 To inform participants of
the adoption of the local
development plan. 
Publish the plan and make
available in Council offices
and libraries.
Notify participants and
place a press advert.

Page 21

Engagement with children and young people – activity up to October 2024.
The Place Strategy team is working closely with Youth Services colleagues within the Council to facilitate participation by children and young people in the
preparation of the local development plan (LDP3). This has involved several meetings with colleagues from each service, initially to explain the requirement
and benefit for children and young people involvement in the process, then to discuss the practicalities of this.
The initial engagement event was with Renfrewshire Youth Voice (https://www.ryv.org.uk/about-us/), which includes members of the Scottish Youth
Parliament. This discussion focused on how participation with children and young people should be undertaken, and provided advice such that the place
standard tool for children and young people would be a good way to engage, but that online surveys would not be likely to generate many responses.
Based on this information, contact with local secondary schools was made and engagement sessions arranged. A session plan based around the young person’s
version of the place standard tool was designed in collaboration with Youth Services colleagues, and delivered jointly to eight secondary schools (Renfrew HS,
Johnstone HS, Gryffe HS, St Benedict’s HS, Gleniffer HS, St Andrew’s HS, Linwood HS & Park Mains HS) over this period. Sessions were attended by over 100
secondary school pupils. Information was collected via maps, where participants highlighted places they liked and disliked, via flipchart where place standard
questions were answered, and via the place standard wheel. Work is ongoing to digitise the information collected so that it can be better recorded and more
fully analysed.
Engagement has also taken place at the Council ‘Summer of Fun’ camps. This focused on play with questions around closest and favourite play parks, and
where else children like to play. Children were engaged with at these sessions which were held in 6 locations in Paisley, Linwood and Johnstone.
Mediation
The Council will work with all stakeholders to discuss any issues which could lead to potential challenges/concerns throughout the plan preparation process.
One method that can be used to support this is mediation, which can help aid discussions.
The preparation of the Evidence Report will provide the opportunity for any concerns/disputes in the evidence base to be discussed and negotiated. Mediation
may also be used in the latter stages of the plan preparation when the proposed plan is published and subject to further representations.
The Council will be open to considering any requests from stakeholders to use mediation, taking into account the potential benefits in terms of saving time
and cost, and fostering better relationships going forward. This could be on an informal basis or through an independent third party.

Page 22

Contact us and follow us
Mailing list – to be added to the local development plan mailing list, email us at localplanconsultation@renfrewshire.gov.uk, call us on 0300 300 0144, or write
to us at Place Strategy, Renfrewshire Council, 4th Floor, Renfrewshire House, Paisley, PA1 1BR
Social media – we will share updates on the Council’s X and Facebook pages
Website – latest updates and documents will be published on the LDP3 webpage
Meetings – if you would like a presentation or meeting on the local development plan, please get in touch via localplanconsultation@renfrewshire.gov.uk or
0300 300 0144.

Page 23

Appendix 2
Renfrewshire Local Development Plan (LDP3) – ‘Call for ideas’ submission (2024)
To inform the preparation of the new Local Development Plan (LDP3) for Renfrewshire and to
encourage early engagement, Renfrewshire Council held a ‘Call for ideas’ survey in 2024. The
ideas/proposals submitted by the end of September 2024 are listed below for information.
The Council has not yet assessed these ideas/proposals or reached a view on their suitability for
inclusion in LDP3. The ideas/proposals will be fully assessed as part of the preparation of the LDP3
Proposed Plan. As part of that assessment, a consultation on the ideas/proposals will be held. This is
scheduled for 2025.
The mapping associated with the ideas is available to view at
https://ren.maps.arcgis.com/apps/instant/basic/index.html?appid=778d449ec6f44bb887ceffd8b516
e883. The site boundaries on the map are as submitted, and the Council is not responsible for the
accuracy of the boundaries.
* denotes a proposal submitted by a local resident or community group
SITE REFERENCE ADDRESS PROPOSAL
LDP3001 Intersection of Well Street,
High Street and Broomlands
Street, Paisley
Enhancement of intersection
including narrowing of road.
LDP3002 Corsebar Road, Paisley Amendment of road layout*
LDP3003 Forbes Place, Paisley Allow planning permission to
develop existing buildings*
LDP3004 Main Road, Elderslie Development or temporary
greenspace*
LDP3005 Main Road, Elderslie Development or temporary
pocket park*
LDP3006 Main Road, Elderslie Development or temporary
pocket park*
LDP3007 High Street, Johnstone  Development or temporary
pocket park*
LDP3008 Thornhill, Johnstone Commercial or residential
development, and tidy-up of
site.*
LDP3009 Crosbie Drive, Paisley Enclosed dog exercise area*
LDP3010 County Square, Paisley Enhancement of public space*
LDP3011 White Cart corridor (from
Hawkhead Road to Blackhall
Lane), Paisley
Active travel route
LDP3012 Castlehead High School,
Paisley
Redevelop high school*
LDP3013 Old Howwood Road,
Johnstone
Residential development
LDP3014 Land at Dykebar Hospital,
Paisley
Protect land from
development*
LDP3015 Greenock Road, Inchinnan Accessible nature space*
LDP3016 Fisher Drive, Paisley Play area*
LDP3017 Slateford Road, Bishopton Introduce pelican crossing*

Page 24

SITE REFERENCE ADDRESS PROPOSAL
LDP3018 Beechburn Crescent,
Lochwinnoch
Residential development
LDP3019 Barbush North, Linwood Residential development
LDP3020 Barbush South, Johnstone Residential development
LDP3021 Auchengreoch Road,
Johnstone
Residential development
LDP3022 Auchengreoch Road,
Johnstone
Residential development
LDP3023 High Street at Paisley Museum,
Paisley
Pedestrianise road*
LDP3024 Erskine waterfront A mixed development of
commercial and residential
uses and improved public
transport and active travel*
LDP3025 Public park, Houston Road,
Bridge of Weir
Creation of football pitch*
LDP3026 Woodend House, Houston Residential development
(conversion and new build)
LDP3027 Throughout Renfrewshire Require special legal
permission to develop or alter
former railways and canals
LDP3028 Hurlet Road, Paisley Residential development
LDP3029 Fodston, Bridge of Weir Residential development
LDP3030 Greenock Road at Inchinnan
Industrial Estate
Business and industrial
development
LDP3031 Meadowside Street, Renfrew
Clyde Waterfront and Renfrew
Riverside Area
Residential or industrial
development
LDP3032 Fishers Road, Renfrew
Clyde Waterfront and Renfrew
Riverside Area
Residential or industrial
development
LDP3033 Meadowside Street, Renfrew
Clyde Waterfront and Renfrew
Riverside Area
Residential or industrial
development
LDP3034 Fishers Road, Renfrew
Clyde Waterfront and Renfrew
Riverside Area
Residential or industrial
development
LDP3035 Land near Meadowside Street,
Renfrew
Residential or industrial
development
LDP3036 Meadowside Street, Renfrew Residential development
LDP3037 Land near Golf Road,
Bishopton
Re-profile the land to create an
area that can store water in
times of flood
LDP3038 Land east of Moss Road,
Bridge of Weir
Residential and retail
development
LDP3039 Low Barholm, Kilbarchan Retail development*
LDP3040 Land east of Moss Road,
Bridge of Weir
Residential development
LDP3041 Land east of Moss Road,
Bridge of Weir
Residential development

Page 25

SITE REFERENCE ADDRESS PROPOSAL
LDP3042 North Muirdykes Farm,
Bowfield Road, Howwood
Residential development
LDP3043 St James Avenue, Paisley Roadside service facilities
LDP3044 Ingliston Drive, Bishopton Develop the area for wildlife by
encouraging biodiversity.
Informal recreation area*
LDP3045 Station Road, Howwood Cycle path link*
LDP3046 Craigton Farm, Bishopton Residential development.
LDP3047 Thriplee Road, Bridge of Weir Land to be protected from
development through
greenbelt allocation*
LDP3048 Scottish Leather, Kilbarchan
Road Plant, Bridge of Weir
Protect plant from implications
of volume build housing
LDP3049 Thriplee Road, Bridge of Weir Residential development
LDP3050 Gas Street, Johnstone Commercial/employment
development
LDP3051 Barochan Road, Houston Residential development
LDP3052 Branscroft, Kilbarchan Residential development
LDP3053 Kilmacolm Road, Houston Residential development
LDP3054 Land north of Tylney, Paisley Residential development
LDP3055 Arkleston, Paisley Residential development, new
employment zone, cemetery
extension
LDP3056 Caplethill Road, Paisley Residential development
LDP3057 Mossland Drive, Hillington Business, industrial, storage
and distribution, and vehicles
sales, repair and servicing
LDP3058 Locher Road (Bog Park),
Kilbarchan
Residential development
LDP3059 Southbar, Erskine Residential development, local
neighbourhood
shops/services, educational
facilities, energy hub.
LDP3060 Barochan Road, Brookfield Residential development and
commercial centre
LDP3061 Southbar, Erskine Residential development, local
neighbourhood
shops/services, educational
facilities, energy hub
LDP3062 Ardgrye Crescent, Houston Residential development
LDP3063 Caplethill Road, Paisley Residential development
LDP3064 Old Bridge of Weir Road,
Houston
Residential development
LDP3065 Barochan Road, Houston Residential development
LDP3066 Torr Road, Bridge of Weir Residential development
LDP3067 Houston Road, Bridge of Weir Residential development
LDP3068 Sandieland Wood and Florish
Road, Erskine
Creation of Nature Reserve* 
LDP3069 Maxwellton Street, Paisley Residential development

Page 26

SITE REFERENCE ADDRESS PROPOSAL
LDP3070 Beith Road, Howwood Residential development
LDP3071 Thriplee Road, Bridge of Weir Protect land from
development- restore
greenbelt allocation*
LDP3072 Kilmalcom Road, Bridge of
Weir
Residential development
LDP3073 Land south of Bridge of Weir Residential development
LDP3074 Auchenlodment Road,
Elderslie
Residential development
LDP3075 Goldenlea Farm, Houston Residential development
LDP3076 Glenpatrick Road, Elderslie Residential development
LDP3077 Houston Road, Bridge of Weir Active travel corridor to link
Houston and Bridge of Weir*
LDP3078 Clippens Road to Fulton Drive,
Linwood/Houston
A footway/cycle way
connecting Houston to
Linwood*
LDP3079 Barochan Road, Houston Road realignments*
LDP3080 Fulton Drive, Houston Create a link to National Cycle
Network from Fulton Drive in
Houston*
LDP3081 Highcraig Quarry, Johnstone Redevelopment of quarry once
extraction has ceased – variety
of uses considered
LDP3082 Houston and Bishopton station Houston to Bishopton Station
cycle link*
LDP3083 Greenock Road/M8, near
Langbank
Electric vehicle charging
station with ancillary
development and battery
energy and storage system
LDP3084 Magnus Road to Crosslee
Road, Houston
Formalised active travel path
and crossing*
LDP3085 Erskine waterfront Increased protection for and
enhancement of nature
conservation sites*
LDP3086 Main Street, Houston Public realm improvements
and cycle infrastructure*
LDP3087 Sandieland Wood, Erskine Creation of green
corridor/nature reserve*
LDP3088 Blackstone Road, Paisley Woodland or community
garden*
LDP3089 Kilmacolm Road, Bridge of
Weir
Residential development
LDP3090 Nether Johnstone Small
Holdings, Milliken Road,
Johnstone
Residential development
LDP3091 Glasgow Airport Glasgow Airport Cluster-
Investment Zone status
LDP3092 Lyle Crescent, Bishopton (no
mapping associated with this
proposal)
Upgraded play park including
skatepark*

Page 27

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 1
Contents
Proposed Plan v9
FOR BOARD CONSIDE
New Development
S l t G id  
Renfrewshire Local Development Plan 
Draft Delivery Programme Update 2024

Page 28

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 2
Contents

Page 29

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 3
Contents 
Introduction         4
Programme of Delivery 
Delivering the Economy Strategy     6 
Delivering the Centres Strategy      13 
Delivering the Places Strategy      18
Delivering the Infrastructure Strategy     29 
Delivering the Environment Strategy     36 
Anticipated delivery of housing sites     42

Page 30

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 4
Introduction 
Introduction
This Draft Delivery Programme Update
relates to the Renfrewshire Local
Development Plan (LDP2, adopted 2021)
and provides an update on the actions and
partnerships required to successfully
implement the Plan’s Spatial Strategy, it’s
policies and assist in delivering its
proposals. 
In accordance with Section 21 of the Town
and Country Planning (Scotland) Act 1997
and associated Regulations, the Draft
Delivery Programme sets out:
• A list of actions required to deliver
each of the plan’s policies and
proposals and an explanation as to
how those actions are to be taken;
• The timescale for the conclusion of
each action; and 
• The expected sequencing of, and
timescales for, delivery of housing
on sites allocated by the local
development plan. 
The Delivery Programme follows the five
themes of the Renfrewshire Local
Development Plan: 
• Economy; 
• Centres; 
• Infrastructure; 
• Places; 
• Environment.
The Delivery Programme will be updated
every two years with information from key
stakeholders, key agencies, developers,
investors and funders and from carrying
out regular reviews.
The Draft Delivery Programme is
published for consultation and
discussion purposes and will be
finalised in early 2025.

Page 31

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 5
Delivering the Economy Strategy  Programme of Delivery

Page 32

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 6
Delivering the Economy Strategy
Advanced Manufacturing and Innovation District Scotland (AMIDS) 
Action 1 
Support delivery of the Advanced Manufacturing and Innovation District
Scotland (AMIDS). 
AMIDS will create an internationally recognised centre for innovation,
research and advanced manufacturing. 
A Strategic Economic Investment Location with the core site adjacent to
Glasgow Airport. Includes over 50 hectares of developable space to
assist in the delivery of advanced manufacturing, industrial, office,
aviation services and ancillary supporting uses.  
Timescales 
Glasgow Airport Investment Area (GAIA) infrastructure: Construction
complete 2022. 
AMIDS core site commercial development from 2019/2020. 
Policy/Proposal 
E1, E2, E5, I1, I2, I3, I7, P1, ENV2, ENV3, ENV4 & ENV5 
Lead/Partners 
Renfrewshire Council in partnership with Tarras Park Properties, part of
Buccleuch Property are working with a range of key stakeholders
including the Scottish Government, Scottish Enterprise, Glasgow Airport,
Glasgow City Region and Strathclyde University.

Page 33

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 7
Delivering the Economy Strategy
Delivering the Economy Strategy - Advanced Manufacturing and Innovation District Scotland (AMIDS) 
Funding 
AMIDS is supported by over £200 million public sector investment
including: 
• £39million City Deal infrastructure funding to provide the enabling
infrastructure including key roads and bridge connections 
• £75million National Manufacturing Institute for Scotland (NMIS)
• £88million Medicines Manufacturing Innovation Centre (MMIC) 
Progress and future actions 
The enabling infrastructure was completed in 2022 and Planning
Permission in Principle is in place for the AMIDS masterplan. £9m
Lightweight Manufacturing Centre, opened in 2018 to support the
aerospace and automotive industries. 
Work on the initial infrastructure to support development was completed
in 2022. The NMIS facility opened in June 2023 and the MMIC opened
in November 2022. Marketing of available development opportunities is
also currently taking place. 
AMIDS Programme Delivery Board, chaired by Renfrewshire Council
and attended by Scottish Government and Scottish Enterprise has been
established and an AMIDS Stakeholder Engagement Group is in place
to support delivery. 
There requires to be on going investigation of access enhancement
to/from the site and the surrounding travel and transport network.

Page 34

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 8
Delivering the Economy Strategy
Delivering the Economy Strategy – Clyde Waterfront and Renfrew Riverside 
Action 2
Support delivery of the Clyde Waterfront and Renfrew Riverside.
The Clyde Waterfront & Renfrew Riverside (CWRR) Project aims to
regenerate the Clyde Waterfront to support existing and promote new
residential, commercial and environmental opportunities.
The proposals include the construction of a new opening road bridge
across the River Clyde, the construction of the Renfrew North
Development Road and improved cycle connections.
Timescales
Construction work commenced in 2022.
Completion of CWRR project infrastructure expected in 2025.
Policy/Proposal
E1, E2, E3, I1, I3, P1, P2, ENV2, ENV4 & ENV5 
Lead/Partners
Led by Renfrewshire Council in partnership with a range of key
stakeholders including the Scottish Government, Renfrewshire Council,
Glasgow City Region, other land owners and stakeholders.

Page 35

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 9
Delivering the Economy Strategy
Delivering the Economy Strategy – Clyde Waterfront and Renfrew Riverside 
Funding 
CWRR Project is supported by £90.7 million City Deal funding and
funding from Renfrewshire Council for the initial infrastructure to enable
development. Regeneration and development of the Clyde Riverfront will
come through private investment.
£282 million private sector investment into the CWRR Project is
expected.
Progress and future actions
Construction started in 2022 and will complete in 2025.

Page 36

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 10
Delivering the Economy Strategy  
Action 3: Deliver actions/interventions set out Renfrewshire’s Economic Strategy 2020-2030
Policy/Proposal: E1, E2, E3, E4, E5, C1, I1, I2, I5, P1, P2, ENV3, ENV5 & ENV7
Lead/ Partners: Renfrewshire Council  & Renfrewshire
business community. 
Progress and future actions: Renfrewshire’s Economic Strategy was
published covering the period 2020-2030. Strategy to support economic activity
and employment opportunities as well as social and cultural development for
Renfrewshire. 
Officers from Economy and Development are currently carrying out a review of
the Strategy, to determine progress against each of the challenges identified in
the Strategy and to re-evaluate the Strategy in a post-pandemic environment. 
Action 4: Assist to deliver and monitor Hillington Business Park Simplified Planning Zone (SPZ)
Policy/Proposal:  E1, I1, I2, I3 & I5
Lead/Partners: Renfrewshire Council, Glasgow City
Council, Frasers Property (majority landowner) and local
businesses. 
Progress and future actions: Hillington Park Simplified Planning Zone (SPZ)
was adopted in 2014 and ended on 1 October 2024. There are no future
actions. A report on what was achieved during the period of the Simplified
Planning Zone was reported to the Council’s Planning and Climate Change
Policy Board on 5 November 2024. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 37

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 11
Delivering the Economy Strategy 
Action 5: Prepare a Development Framework for area to north of Paisley Town Centre to facilitate a co-ordinated approach to re-
development and enhance the gateway between Paisley Town Centre and Glasgow Airport
Policy/Proposal:  E2, E3, I1, I3, P1, ENV3, ENV4 & ENV5 
Lead/ Partners:  Renfrewshire Council, local business
community, various land owners within the area and
West College Scotland.
Progress and future actions: Development Framework to be prepared. There is
continuing assessment of the potential delivery mechanisms and funding for this
project.
Renfrewshire Council's AMIDS South project, which includes a 1.7km 'gateway
route' along the White Cart river, has been awarded £38.7million from the UK
Government Levelling Up Fund. 
Action 6: Prepare development frameworks to guide investment in Transition Areas and Economic Investment Locations
Policy/Proposal: E1, E2, E3, I1, I3, I4, I5, I7, P1, P2, P5, P6, ENV3, ENV5 & ENV7
Lead/ Partners: Renfrewshire Council, landowners and
local community. 
Progress and future actions: Development frameworks have not been prepared
and their preparation is not within the current work programme. LDP2 Transition
Areas and Economic Investment Locations will be reviewed as part of LDP3
preparation. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 38

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 12
Delivering the Economy Strategy
Action 7:  Support Delivery of Renfrewshire’s Tourism Plan 2024-2027 (action updated 2024)
Policy/Proposal: E4, C1, I1, P1, P5, P6, ENV2 & ENV3 
Lead/ Partners: Renfrewshire Council,
OneRenStrategic Tourism Leadership Group,
VisitScotland, Scottish Enterprise, Renfrewshire
Chamber of Commerce and Glasgow City Region. 
Progress and future actions: Renfrewshire Council worked with partners to
develop a Tourism Plan (2024-2027) with work now ongoing to deliver the Plan. 
The Tourism Plan identified 5 key priorities, cross cutting themes and a series of
targets to grow Renfrewshire’s visitor economy.  The first key step for the plan was
to set up a Tourism Leadership Group, which will support and drive growth in
Renfrewshire’s tourism economy. The Group had its first meeting in September
2024. 
Work will now be progressed to deliver tourism related development including
projects to boost the tourism potential of Paisley Town Centre as set out in Paisley
Vision 2030. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 39

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 13
Delivering the Centres Strategy
Paisley Town Centre Action Plan 
Action 8 
Delivery of Paisley Town Centre Action Plan and Paisley Vision 2030. 
Proposals are being taken forward to transform Paisley's town centre
venues and cultural infrastructure while supporting work to promote
Paisley as a visitor destination and drive new footfall into the town
centre and preserve the areas architectural heritage and culture. 
Paisley was chosen by the Scotland’s Town Partnership and the
Scottish Government to be a pilot case for a piece of work reimagining
how a town centre could be redesigned to better meet future needs.
Paisley Vision 2030 builds on the actions in the Town Centre Action
Plan. 
Policy Proposal 
C1, I1, P1, ENV3 & ENV5 
Lead/ Partners 
Renfrewshire Council, Paisley First BID Group, Renfrewshire
Economic Leadership Panel & Renfrewshire business community.

Page 40

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 14
Delivering the Centres Strategy
Paisley Town Centre Action Plan  
Progress and future actions 
Within Paisley High Street and University Campus a number of
properties have been improved through the Townscape
Heritage/Conservation Area Regeneration Scheme. 
Updates on other key projects: 
• Paisley Museum - a £42m transformation to showcase the town's
unique heritage and collections, predicted to bring around 125,000
visitors a year. The museum closed in September 2018 and will
reopen in 2025. 
• Paisley Town Hall - a £22m internal refurbishment to become a
landmark entertainment venue.  The Town Hall reopened in 2023
and is proving to be a great success with a number of acts booked
to perform at the venue.. 
• Learning and Cultural Hub – the £7m Learning and Cultural Hub
opened in 2023 and is designed to promote education, culture and
community engagement. It combines library services, learning
spaces, and cultural activities under one roof, offering a variety of
resources such as books, digital media, study areas, and event
spaces.. 
• Paisley Arts Centre - a £3m upgrade of the existing building to
improve the performance facilities completed in June 2024. 
• Paisley Centre – Planning permission in principle approved for a
masterplan which includes retail space, residential, hotel,
healthcare facility and enhanced public spaces. The owner is in
ongoing discussions with the Council and Scottish Government
about potential funding options to deliver the masterplan.

Page 41

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 15
Delivering the Centres Strategy
Braehead Master Plan 
Action 9 
Support the delivery of Braehead Master Plan 
Braehead continues to be a key economic driver and has supported
the wider regeneration of the Clyde Waterfront delivering urban
renewal and environmental transformation. A masterplan has been
granted planning consent as part of the centre’s evolution to provide a
range and choice of uses and activities. 
Timescales 
The development continues to evolve in line with the changing
markets and economic circumstances – planning permission for the
masterplan was granted consent in 2016. 
Policy Proposal 
E1, C1, I1 & P1 
Lead/ Partners 
Braehead and Renfrewshire Council. 
Progress and future actions 
A change in ownership and investment strategy has resulted in the
focus of investment at Braehead being on internal spaces. Delivery of
the masterplan is currently paused.

Page 42

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 16
Delivering the Centres Strategy
Action 10: Prepare and review Centre Visions, Strategies and Action Plans for Renfrewshire’s Network of Centres.
Policy/Proposal:  C1, I1, P1, ENV3 & ENV5 
Lead/ Partners: Renfrewshire Council, Community
Councils, Community Organisations, local residents
and businesses. 
Progress and future actions:  A new vision for Johnstone was published in May
2024 and is a strategic initiative aimed at revitalising the town centre. It focuses on
enhancing public spaces and supporting local businesses to create a more vibrant
and sustainable community. 
The vision seeks to promote economic growth, boost tourism, and enhance the
quality of life for residents by developing infrastructure, improving transport links,
and creating a sense of community pride. The initiative is part of broader efforts to
rejuvenate towns in the region, making them more attractive and liveable for future
generations. 
Another commission in Erskine is currently in progress  to develop proposals to
make public spaces and greenspaces more appealing as part of a review of the
Centre Strategy for Erskine and short, medium and long-term actions have been
identified. 
Officers are also looking to appoint a consultant to prepare landscape design
proposals which support the delivery of enhancements within an area of open space
to the south of Linwood town centre, known as ‘Linwood Lade’. 
Action 11:  Monitor and review Renfrew Town Centre Simplified Planning Zone (SPZ)
Policy/Proposal: C1, I1, P1, ENV3 & ENV5 
Lead/ Partners: Renfrewshire Council and Local
Businesses. 
Progress and future actions: The SPZ, which was adopted on 25 August 2015,
offers flexibility to help Renfrew town centre businesses to grow and adapt as well
as encouraging new business opportunities to locate in the town centre. There have
been 8 SPZ notifications received in the period since adoption. The Council will
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 43

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 17
Delivering the Centres Strategy
continue to monitor development activity within the SPZ and prepare a final report
on its impact once the SPZ period has ended (25 August 2025). 
Action 12: Identify opportunities and initiatives for housing development projects which would assist in increasing the number of people
living in and using Renfrewshire’s town centres
Policy/Proposal: C1, P1, I7 & ENV3
Lead/ Partners:  Renfrewshire Council, 
local businesses, Registered Social Landlords. 
Progress and future actions: Good progress has been made within Paisley Town
Centre encouraging more people to live and use the town centre.  The Link Group
have completed the fourth phase of the redevelopment of the former Arnott’s
department store site in Paisley providing 81 affordable flats. Thirty-four flats have
been developed by Nixon Blue at Bridge Street in Paisley. These projects alongside
the other 269 residential units that have been completed since 2016 are contributing
to the wider regeneration of Paisley town centre, adding to the tenure diversification
and increased residential provision within this key central location. Proposals
continue to be progressed to deliver new homes in and around town centres and will
continue to be considered and promoted through the preparation of Centre
Strategies and the delivery of the Strategic Housing Investment Plan. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 44

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 18
Delivering the Places Strategy
Dargavel Village Community Growth Area 
Action 13
Support the successful implementation of the Dargavel Village
Community Growth Area through a partnership approach.
Delivery of Dargavel Village is through a masterplanned approach
to remediate and re-develop the site.  Planning consents are in
place for a range of uses including 4,000 new homes, a woodland
park, education and health facilities, recreation and open space
facilities, retail provision and associated infrastructure including a
motorway junction.  
Timescales
Works commenced at the site in 2012 and development is forecast
to reach completion by 2037. 
Policy/Proposal 
E1, P1, P2, P3, P5, P6, P7, C1, I1, ENV2, ENV3 & ENV4
Lead/ Partners
BAE Systems, Renfrewshire Council, Transport Scotland,
Strathclyde Partnership for Transport, Forestry and Land Scotland,
local community organisations and various developers.
Funding
Funding secured through approved s75 agreement.

Page 45

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 19
Delivering the Places Strategy
Dargavel Village Community Growth Area 
Progress and future actions
Work is progressing well on site and has delivered: 
• Major road and drainage infrastructure, including a new
motorway junction;
• Extensive earthworks and remediation activity;
• Structural landscaping and new greenspaces including the
formation of a ‘village square’;
• Over 2500 new homes delivered, including 138 new Social
Rented homes
• Traffic management and environmental enhancements;
• Village retail centre with foodstore anchor, and new foodstore
under construction;
• New school and nursery complete, and additional primary school
proposed;
• First phase of park and ride facilities at Bishopton rail station,
with second phase scheduled for completion by June 2025;
• New local play areas and early phases of a new ‘Central Park’
serving the development;
• Initial phases of a 400 hectare community Woodland Park as a
key asset for the area; and,
• Satellite health centre currently under construction.
• Introduction of bus service between Dargavel and Braehead

Page 46

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 20
Delivering the Places Strategy
Strategic Housing Investment Plan Projects 
Action 14
Support the delivery of the Strategic Housing Investment Plan
(SHIP) projects.
The Strategic Housing Investment Plan sets out how investment in
affordable housing will be targeted to meet the objectives of
Renfrewshire’s Local Housing Strategy.
Projects within the Strategic Housing Investment Plan are prioritised
to reflect project deliverability in terms of local needs assessments,
site availability, strategic priorities and funding availability from both
a programme prospective and the housing developers’ own financial
capacity.  
Timescales
The SHIP is reviewed and updated annually and submitted to the
Scottish Government by 31 October each year. The SHIP contains
expected timescales for completion of projects subject to the
availability of grant funding.
Policy/Proposal
P1, P2 & P3
Lead/ Partners
Scottish Government, Registered Social Landlords and
Renfrewshire Council.

Page 47

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 21
Delivering the Places Strategy
Strategic Housing Investment Plan Projects 
Funding
The Scottish Government allocates grant funding to local
authority areas through the Affordable Housing Supply
Programme. Funding for financial year 2024/25 was lower than
originally anticipated, and there is uncertainty over future year’s
funding meaning delivery of the programme is likely to be
impacted.
Progress and future actions
The SHIP continues to provide funding to deliver a range of
affordable housing developments across Renfrewshire including
the delivery in 2023/24 of 101 new homes by the Council at
Ferguslie Park, Paisley, and 81 homes at Abbey Quarter in
Paisley and 14 homes at Woodend House in Houston, both
development by Link Group.
New affordable homes are being developed to the ensure they
are energy efficient to help tackle fuel poverty and the Council
and partners continue to develop options around the
achievement of low carbon, energy efficient homes that meet
our climate change aspirations through innovation and
technology.   
Throughout the lifetime of the SHIP the Council will continue to
explore options around innovative delivery mechanisms to
expand the supply of affordable housing focusing on the
regeneration of brownfield and previously used land.

Page 48

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 22
Delivering the Places Strategy
Action 15: Support local communities to prepare and deliver Place Plans for their area 
Policy/Proposal: P1, P5, P6, C1, I1, ENV2 & ENV7
Lead/ Partners: Local community groups, residents,
local businesses, Development Trusts, Renfrewshire
Council and Community Councils. 
Progress and future actions: A community led Pilot Local Place Plan for Foxbar
in Paisley was completed in 2018 with the assistance of the Scottish Government
‘Making Places’ initiative. 
The outcomes and principles emerging from this process informed the preparation
of a ‘How to Guide’ providing a template to support communities to deliver Local
Place Plans across Renfrewshire. 
In May 2023, an invitation was issued to communities across Renfrewshire to
prepare a Local Place Plan. Information sessions were held in March 2024, and
further information drop-in sessions were held in August and September 2024, as
well as one-to-one meetings with interested organisations. As at September 2024,
13 community organisations have expressed an interest in preparing a Local
Place Plan for their area. The Council will work to support local communities if
they decide to prepare a plan for their area. 
Action 16: Prepare Advice Note on how settlements across Renfrewshire can learn from the example of Dargavel Village in integrating
walking and cycling provision in new development
Policy/Proposal: C1, P1, P5, P6, P7, I1 & ENV2
Lead/Partners: Renfrewshire Council, 
Scottish Forestry, NatureScot, Local Outdoor Access
Forum, Land owners and public. 
Progress and future actions: Advice note to be prepared. This is not within the
current work programme. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 49

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 23
Delivering the Places Strategy
Action 17: Assist with the implementation of the Community Growth Area at Johnstone South West
Policy/Proposal: P1, P2, P3, P5, P6 I1,I3, I7 & ENV4 
Lead/ Partners: Renfrewshire Council, various house
builders and Registered Social Landlords. 
Progress and future actions: A masterplan was produced for the Johnstone
South West area in 2012 with a range of local residents, community
representatives and key stakeholders involved in a 'charrette' exercise supported
by the Scottish Government.  As at 2024, 222 houses have been developed on
sites identified in the masterplan, including 183 private houses either side of Beith
Road at Fordbank, and 39 houses by Renfrewshire Council at Auchengreoch
Road. A new early learning and childcare centre has also been delivered in the
area. 
The Howwood Road regeneration and renewal area sits within the Community
Growth Area. Two phases of new build housing are planned for this area, with a
planning application for the first phase of 70 houses submitted. Other housing
development opportunities have still to be brought forward. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 50

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 24
Delivering the Places Strategy
Action 18: Review social rented housing stock, undertake option appraisal and develop area-based strategies to ensure good
placemaking in Renfrewshire’s existing places
Policy/Proposal: P1, P3, P5, P6, I1 & I7
Lead/Partners: Renfrewshire Council, Local
Communities and Registered Social Landlords. 
Progress and future actions: The Housing-led Regeneration and Renewal
Programme is focused on eight regeneration areas within Renfrewshire
(Auchentorlie, Howard Street, Waverley Road, Ferguslie/Broomlands,
Springbank/Mossvale, Thrushcraig, all Paisley, Howwood Road in Johnstone, and
Moorpark in Renfrew). The programme will deliver modern, high quality, energy
efficient, affordable Council housing and contribute to the wider transformation of
communities across Renfrewshire. 
Within each area, there is a different scope of regeneration activity and
timescales, within a 10-year programme that commenced in 2022. Regeneration
activity involves a mix of investment in existing properties, demolition, new-build,
and environmental improvements. 
The programme involves a new approach to community neighbourhood renewal,
going beyond housing and taking account of broader issues such as health and
wellbeing, and access to open space, sustainable travel, and employment/training
opportunities. 
A detailed update setting out progress and future activity in each area was
reported to the 20 August 2024 Communities and Housing Policy Board. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 51

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 25
Delivering the Places Strategy
Action 19: Consider the need to identify new sites to meet the housing needs of key groups
Policy/Proposal: P1, P2, P3, P4, I3, I4 & ENV4
Lead/ Partners: Key housing groups, developers, Key
Agencies, Local Community Organisations, Registered
Social Landlords, adjoining Local Authorities and
Renfrewshire Council. 
Progress and future actions: Strategic Priority 5 of the Local Housing Strategy
2023-28 is that ‘people can live independently for as long as possible in their own
home and the different housing needs of people across Renfrewshire are being
met’. Whilst recognising a general need of housing for particular needs, the Local
Housing Strategy does not specify the need for specific sites for key groups. 
However, opportunities to deliver new homes for key groups are continually
investigated through the annual review of the Strategic Housing Investment
Programme. 
The Local Housing Strategy also sets a requirement for 10% of dwellings in new
residential proposals to be designed to be easily adaptable for wheelchair users,
and 5% to be designed to be wheelchair accessible. 
LDP2 provides a framework for the consideration of new small privately-owned
sites to accommodate Gypsies/Travellers and Travelling Showpeople, whether
transit or permanent. 
The requirement for the identification of land/sites for Gypsy/Traveller housing
needs is being considered as part of the new Local Development Plan (LDP3)
process. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 52

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 26
Delivering the Places Strategy
Action 20: Prepare development briefs to support the delivery of key sites including housing regeneration sites and Council owned sites
Policy/Proposal: P1, P2 & P3
Lead/ Partners: Renfrewshire Council.  Progress and future actions: Development briefs have been prepared for
eleven sites under LDP2 and will continue to be prepared as required.
Development briefs are available at
https://www.renfrewshire.gov.uk/article/12717/Site-development-briefs. 
Action 21: In partnership with local communities develop and implement local regeneration strategies for Johnstone Castle, Paisley West
End, and Ferguslie Park
Policy/Proposal: P1, P3, P5, P6 & I1
Lead/Partners: Renfrewshire Council, Local
Communities and Registered Social Landlords. 
Progress and future actions: 95 new energy efficient Council homes were
delivered as part of Phase I of the regeneration of Johnstone Castle, Johnstone
in April 2021. Link Group are now on site with Johnstone Castle Phase II which
will provide 68 new social rented homes, with these homes due to complete in
August 2026. 
101 new affordable homes were completed in the Tannahill regeneration area in
Ferguslie Park in July 2023. These 95 Council homes and 6 homes for shared
equity low-cost home ownership included a mix of 1 and 2 bed cottage flats and
bungalows and 2, 3 and 4 bedroom homes. 
To complement the housing development, the Council worked in partnership with
the local community to prepare ‘The Making of Ferguslie’, which sets out a vision
for the future of Ferguslie over 5-10 years from 2021. 
Sanctuary Scotland in partnership with the Council and Scottish Government are
progressing plans for the regeneration of Paisley West End. Phase 1 of the new
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 53

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 27
Delivering the Places Strategy
build programme will deliver 35 units for social rent at Sutherland Street, Paisley
with these new homes due to complete in February 2025. 
Plans are also progressing to deliver 120 additional new social rented homes in
the West End with significant demolition due to take place in late 2024 and early
2025 to facilitate delivery of the West End Regeneration Masterplan. 
Action 22: Update and refresh Renfrewshire’s Places Design Guidance 
Policy/Proposal:  P1, P2, P3, P5, P6, I1 & I7
Lead/ Partners: Renfrewshire Council. Progress and future actions: Renfrewshire’s Places Design Guidance sets out
the objectives of sustainable placemaking, design and achieving high-quality
design. The current guidance, dating from 2015, is still in use and many of the
principles it sets out are still relevant. An update of the guidance is not currently
within the work programme. 
Action 23: Work with local communities to support the delivery of community asset transfer projects
Policy/Proposal: P1, P5, P6 & ENV7
Lead/Partners: Renfrewshire Council, Local
Community/Voluntary Organisations and Development
Trusts. 
Progress and future actions: Renfrewshire Council is committed to building
strong, safe and resilient communities. In 2022 the Council created a dedicated
single point of contact for community asset transfer and reviewed our policy and
procedures. The result has been an increase in the number of asset transfer
requests, better support for community organisations and management of the
process through the Council and an increase in success. 
Since Part 5 of the Community Empowerment (Scotland) Act 2015 came into
force in 2017, Renfrewshire Council has processed 22 full CAT requests. 11 of
the applications were processed in the period 2017-22 of which 3 were refused
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 54

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 28
Delivering the Places Strategy
and 2 subsequently withdrawn. Of the 11 applications processed since 2022, 10
were approved and 1 refused. The time taken for asset transfer requests to be
determined and completed has also significantly reduced with fully validated
applications receiving a decision within 12 weeks. 
Future actions include a more strategic approach and integration with the
Council’s review of assets and development of a social value toolkit to aid in the
evaluation and assessment of applications and to measure community benefit
from asset transfer. 
Action 24: Develop a standard for affordable housing in Renfrewshire
Policy/Proposal: P1, P3 P5, P6, I1 & I7
Lead/Partners: Renfrewshire Council, Registered
Social Landlords. 
Progress and future actions: The preparation of the guidance was halted
owing to changing sustainability standards, and issues that other local authorities
were having in implementing similar guidance. The need for guidance will be
reviewed with Housing Services. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 55

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 29
Delivering the Infrastructure Strategy
Action 25: Support the delivery of major Infrastructure Projects: Clyde Waterfront and Renfrew Riverside (CWRR) and Glasgow Airport
Investment Area (GAIA).
Policy/Proposal: E1, E2, E5, I1, I2, I3, P1, ENV2, ENV3, ENV4 & ENV5
Lead/ Partners: Renfrewshire Council leading
delivery of projects and working with stakeholders
including Scottish Government, Scottish Enterprise,
Glasgow City Region, Strathclyde Partnership for
Transport (SPT), and land owners. 
Progress and future actions: GAIA Infrastructure project is complete. 
CWRR project commenced in 2022 and will complete in 2025.
AMIDS 
AMIDS South is expected to commence construction in 2025 and will provide a
new gateway route between AMIDS and Paisley Town Centre (enhance airport
route too). 
The Council are working with other local authorities and key stakeholders across
the city region to look at the feasibility of a Glasgow Metro scheme which would
look to improve public transport connectivity across the region and enhance access
to Glasgow Airport. 
Action 26: Promote enhanced public transport facilities at Braehead
Policy/Proposal: I1 & C1
Lead/ Partners: Renfrewshire Council, Strathclyde
Partnership for Transport.   
Progress and future actions: Improved public transport facilities and links to
Braehead will be investigated as part of the Clyde Metro proposal. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 56

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 30
Delivering the Infrastructure Strategy
Action 27: Support preparation and delivery of Flood Risk and Drainage Management Plans. 
Policy/Proposal: I3
Lead/ Partners: Renfrewshire Council, Scottish
Environment Protection Agency, Scottish Government
and adjoining local authorities. 
Progress and future actions: Renfrewshire Council continues to work in
partnership to support the delivery of the actions identified in the Clyde and Loch
Lomond Flood Risk Management Plan, the Scotland and Clyde Area River Basin
Management Plans as well as the Metropolitan Glasgow Strategic Drainage Plan. 
Action 28: Investigate feasibility to improve circulation and access to/from Paisley Town Centre
Policy/Proposal: I1, E3 & C1
Lead/ Partners: Renfrewshire Council.  Progress and future actions: Completion of renewal of urban traffic control
system plus upgrade of strategic signal junction equipment and controllers
expected to bring efficiencies to traffic management and control which should
smooth traffic flow in Paisley. AMIDS South project will provide a new gateway
between AMIDS and Paisley town centre. 
Action 29: Support preparation and implementation of Council’s Plan for Net Zero 
Policy/Proposal: I4, I7, P1 & ENV5
Lead/ Partners:  Renfrewshire Council, Community
Planning partners
local residents, communities, organisations and
businesses, private, public, key regional and national
stakeholder organisations,
Scottish Government 
Progress and future actions: Renfrewshire’s Plan for Net Zero was approved at
Planning and Climate Change Policy Board in August 2022, aiming to end
Renfrewshire’s contribution to climate change within a generation and committing
us to work towards net zero emissions by 2030 for Renfrewshire Council as an
organisation and the Renfrewshire Council area as a whole.  
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 57

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 31
Delivering the Infrastructure Strategy 
The most up to date reporting year (2023-24) has seen Renfrewshire Council’s
emissions reduce to 18,889t tCO2e – a reduction of 3.3% compared with the
previous year and an overall reduction of 64.6% against the baseline year of 2012-
13. 
Internally, projects which feed into the Plan for Net Zero continue to be delivered as
a Council across all 5 themes (clean energy, sustainable transport, circular
economy, connected communities and resilient place). Work is also progressing on
the preparation of priority projects which will build on the policy framework in the
Local Development Plan to provide a strategic framework to meet our climate
change targets. These projects will take into consideration the key plans and
policies to provide the direction and scale we need to work towards net zero
emissions. 
The Local Development Plan provides a spatial strategy and policy framework to
support Renfrewshire’s Plan for Net Zero, which will be kept under review, including
the preparation of additional planning guidance if required. 
Action 30: Investigate the potential for Low Carbon and Renewable Energy Developments
Policy/Proposal: I1, I4, I7, & ENV2
Lead/ Partners: Renfrewshire Council,  Progress and future actions: A renewable energy district heating system has
been installed at the Advanced Manufacturing and Innovation District Scotland
(AMIDS) site. The Council has published planning guidance on solar farm
developments. A number of solar farms and battery energy storage system
applications have been approved in Renfrewshire. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 58

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 32
Delivering the Infrastructure Strategy
Action 31: Work in partnership to increase accessibility to digital connectivity for all areas
Policy/Proposal: I1
Lead/ Partners: Renfrewshire Council, Scottish
Government and Digital Infrastructure Providers.
Progress and future actions: Enhanced wi-fi connectivity has been provided to
80% (at July 2024) of Council (including schools), One Ren, and HSCP buildings,
with free public wi-fi available across Johnstone, Paisley and Renfrew town centres.
There has been extensive and ongoing rollout of full fibre broadband across
Renfrewshire.   
Action 32: Investigate potential Heat Network opportunities across Renfrewshire
Policy/Proposal: I4
Lead/ Partners: Renfrewshire Council, Scottish
Environment Protection Agency, developers and local
businesses. 
Progress and future actions: Renfrewshire’s Local Heat and Energy Efficiency
Strategy (LHEES) and Delivery Plan (LHEEDP) were both approved and published
in 2024.  Renfrewshire also received funding to carry out feasibility studies across
the Renfrewshire area.  Following the conclusion of the studies funding has also
been secured from Scottish Government to progress two potential district heating
networks to Investment Grade Business Case.  Further work to be carried out to
identify opportunities for renewable and low carbon infrastructure and to explore
more innovative and collaborative delivery models across stakeholders, including
potential for joint ventures and partnership projects. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 59

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 33
Delivering the Infrastructure Strategy
Action 33: Monitor and Review Infrastructure Considerations Map to identify potential capacity constraints in Schools across Renfrewshire
Policy/Proposal: P2
Lead/ Partners: Renfrewshire Council.  Progress and future actions: There is ongoing liaison between the Planning
Service and Children’s Services on school capacity and school pupil projections
based on new housing development. Children’s Services has produced a School
Estate Management Plan (2024) and are developing a Learning Estate Strategy is
being developed. 
Action 34: Investigate potential measures to improve traffic flows on the Strategic Road Network
Policy/Proposal: I1, E1 & E2
Lead/ Partners: Renfrewshire Council, Transport
Scotland, and Strathclyde Partnership for Transport. 
Progress and future actions: A transport appraisal considering the strategic road
network will be prepared as part of the new LDP3. 
Action 35: Investigate health care provision capacity across Renfrewshire 
Policy/Proposal: P1, P2 & Illustrative Figure 11 – Infrastructure Considerations 
Lead/ Partners: NHS Greater Glasgow and Clyde,
Renfrewshire Health and Social Care Partnership,
Renfrewshire Council. 
Progress and future actions: Health care provision capacity is being investigated
as part of the new Local Development Plan (LDP3) process. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 60

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 34
Delivering the Infrastructure Strategy
Figure 1 – Infrastructure Considerations Map

Page 61

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 35
Delivering the Environment Strategy
Renfrewshire’s Growing Grounds Forum 
Action 36 
Renfrewshire’s Growing Grounds Forum work with local communities
to support local growing activities and to increase the quantity and
quality of community growing opportunities across the Council area. 
Part 9 of the Community Empowerment (Scotland) Act 2015
places duties on local authorities to support the provision of
allotments and other community growing opportunities. Managed
jointly by Renfrewshire Council and Renfrewshire Health and Social
Care Partnership, the Growing Grounds Forum provides a valuable
support and guidance network for local communities. 
Timescales 
Ongoing 
Policy Proposal: 
E3, P1, P5, P6, ENV2 & ENV7 
Lead/Partners: Renfrewshire Council, Renfrewshire Health and
Social Care Partnership, community groups and local residents.

Page 62

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 36
Delivering the Environment Strategy
Renfrewshire’s Growing Grounds Forum 
Progress and future actions: 
Renfrewshire’s Growing Grounds Forum works to support local
residents and community groups to increase the quantity and quality of
growing ground opportunities. 
The Forum has applied a collaborative and comprehensive approach
to community growing across Renfrewshire. This has supported the
reuse of vacant land, the creation of sustainable places and deliver of
community ambitions in line with the Spatial Strategy in the Local
Development Plan.   
The Forum has had a significant impact, with support and direction
provided to members. This has included assistance in securing leases,
funding advice and specialist growing guidance. A key element has
also been to encourage peer learning between members. The Forum
meets on a regular basis and continues to support growing
opportunities across Renfrewshire.

Page 63

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 37
Delivering the Environment Strategy
Renfrewshire’s Green Network Strategy  
Action 37 
Preparation and delivery of Green Network Strategy incorporating
access, open space and biodiversity to support the creation of
sustainable places. 
A Green Network Startegy is to be developed to identify greenspaces
across Renfrewshire and opportunities for their protection and
enhancement. 
Timescales: .TBC 
Policy Proposal: 
E4, C1, I1, P5, P6, ENV1, ENV2, ENV4, ENV6 & ENV7 
Lead/Partners: 
Renfrewshire Council, Glasgow and Clyde Valley Green Network
Partnership, Renfrewshire Growing Grounds Forum, Central Scotland
Green Network, Scottish Forestry, Scottish Environment Protection
Agency, Transport Scotland and local developers.

Page 64

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 38
Delivering the Environment Strategy
Renfrewshire’s Green Network Strategy 
Funding Details: 
It is anticipated that projects will be funded through a variety of
sources and organisations, such as national grant schemes as well as
those funding streams available to voluntary and third sector bodies. 
Progress and future actions: 
Several pieces of work that would inform a Green Network Strategy
have been completed or commenced. These include an updated Core
Paths Plan (2022) and Biodiversity Action Plan (2024). An open space
audit and work to identify a nature network is being undertaken to
inform LDP3. 
There is now a statutory requirement to prepare an Open Space
Strategy, although Regulations to inform tits preparation are still
awaited. It is likely that an Open Space Strategy could cover much of
the same content of a Green network Strategy. The preparation of a
separate Green Network Strategy is therefore not within the current
work programme and the need for a separate strategy will be kept
under review. inform future opportunities and actions across
Renfrewshire. 
The Green Network Strategy will be prepared and implemented in
consultation with key stakeholders, key agencies, businesses and
local residents across Renfrewshire.

Page 65

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 39
Delivering the Environment Strategy
Action 38: Review and deliver actions within Renfrewshire’s Biodiversity Action Plan 2018-2022
Policy/Proposal: P1, P5, P6, ENV1, ENV2, ENV3, ENV4, ENV5, ENV6 & ENV7
Lead/ Partners: Local Biodiversity Steering Group  Progress and future actions: The Renfrewshire Biodiversity Duty Report 2021-
2023 highlights the actions undertaken to support biodiversity over that period. 
A new Biodiversity Plan for Renfrewshire was approved on 28 May 2024. Some
actions identified within the plan are already underway including progress on the
restoration of more than 200 hectares of peatland at Clyde Muirshiel Regional
Park, a feasibility study considering potential enhancements to the Candren Burn
and a range of conservation activities developed by the Friends of Jenny’s Well
Local Nature Reserve. 
Progress on delivery of the Biodiversity Action Plan will be monitored by the
Council and its partners through the LBAP Steering Group, with updates reported
to the relevant Council Board. 
Action 39: Reviewing and working with partners to deliver actions within the Renfrewshire Vacant and Derelict Land Strategy
Policy/Proposal: E1, E3, E5, C1, C2, I1, I5, P1, P2, P5, P6, ENV5, ENV6 & ENV7
Lead/ Partners: Developers, local businesses land
owners, land owners, Scottish Government and
Renfrewshire Council. 
Progress and future actions:  The Vacant and Derelict Land Strategy was
updated in 2024. This reports a reduction in vacant and derelict land of 18.9%
since 2017, with a decrease in the amount of vacant and derelict land of 33.41
hectares since 2022. The Council will continue work on the actions set out in the
Vacant and Derelict Land Strategy. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 66

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 40
Delivering the Environment Strategy 
Action 40: Review of Sites of Importance for Nature Conservation (SINCs) and Local Nature Reserve (LNRs)
Policy/Proposal: E4, P5, ENV1, ENV2, ENV3, ENV4, ENV5 & ENV6
Lead/ Partners: Renfrewshire Council, NatureScot,
Scottish Forestry, landowners, land managers and local
residents.
.
Progress and future actions: There will be a review of SINCs as part of the
local development plan (LDP3) process. A review of Local Nature Reserves is
not within the current work programme. 
Action 41: Support delivery of access and biodiversity interests through Outdoor Access Forum and LBAP Steering Group.
Policy/Proposal:  P1, I1, P5, P6, ENV1, ENV2, ENV3, ENV4, ENV5 & ENV6
Lead/Partners: The Local Access Forum represents
land owners and managers, community groups, local or
national organisations and the general public. 
The Local Biodiversity Action Plan Steering Group
consists of a range of local/national organisations and
individuals with an interest and knowledge of
biodiversity. 
Progress and future actions:  The LBAP Steering Group meets quarterly and
supports work with statutory bodies, third sector and voluntary groups with an
interest biodiversity to deliver actions with the Renfrewshire Biodiversity Action
Plan. 
The Renfrewshire Local Outdoor Access Forum advise on access rights, rights of
way and core paths.The Forum has most recently supported a revision of the
Renfrewshire Core Paths Plan, approved by the Council in 2022. 
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 67

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 41
Delivering the Environment Strategy 
Action 42: Core Path Plan 
Policy/Proposal: C1, E4, P1, P5, P6, I1, ENV2
Lead/ Partners: Renfrewshire Council, Sustrans,
Forestry and Land Scotland, NatureScot, Local
Outdoor Access Forum, Land owners and public. 
Progress and future actions: 
Renfrewshire’s Core Paths Plan 2022 was adopted by the Council on 18th January
2022.   
The Plan sets out a strategic network of over 300 key access routes across
Renfrewshire which connect communities and provide opportunities for active
travel to schools, work and local amenities.   
The plan also identifies routes which connect people with areas of nature and
greenspace, promoting and encouraging healthy lifestyles.   
2021/22 2022/23 2023/24 2024/25 2025/26 Post 2026

Page 68

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 42
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF0907B LINWOOD ROAD
PHOENIX PARK PAISLEY
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 198 164 34 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF0989 FORMER BASF SITE 144
HAWKHEAD ROAD
PAISLEY (MILLER)
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 234 201 33 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0989A FORMER BASF SITE 144
HAWKHEAD ROAD
PAISLEY (TW)
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 209 187 22 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF1012 THE MILL HOUSE
BRIDGE ST PAISLEY
UNDER
CONSTRUCTION
PRIVATE  BROWNFIELD 34 16 18 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
YES
RFRF0988 PRINTERS PLACE
PAISLEY
UNDER
CONSTRUCTION 
PRIVATE BROWNFIELD 49 10 20 19 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF1042 MAIN BUILDING
CASTLEHEAD CHURCH
MAIN ROAD PAISLEY
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD
(CONVERSION)
7 0 7 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF0870 HAWKHEAD HOSPITAL
ACCORD PLACE PAISLEY
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 291 254 10 27 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF1058 17 GLASGOW ROAD
PAISLEY
UNDER
CONSTRUCTION 
PRIVATE BROWNFIELD
(CONVERSION)
4 0 4 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF1096 13A MOSS STREET
PAISLEY
UNDER
CONSTRUCTION 
PRIVATE BROWNFIELD
(CONVERSION)
4 0 4 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
YES
RFRF1049 3 COUNTY PLACE
PAISLEY
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD
(CONVERSION)
4 1 3 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
YES
RFRF1056 MAIN BUILDING
LIBERAL CLUB HIGH
STREET PAISLEY
CONSENT PRIVATE BROWNFIELD
(CONVERSION)
22 0 0 0 10 12 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
YES
RFRF1078 6-8 HIGH STREET
PAISLEY
CONSENT PRIVATE BROWNFIELD
(CONVERSION)
8 0 0 0 0 0 0 0 0 0 0 0 8 Planning permission
21/1479/PP granted
16/12/21. Pipeline site as
uncertainty over
implementation of
planning consent. Will be
kept under review in
preparing LDP3. 
YES
RFRF1080 2 LONEND PAISLEY CONSENT PRIVATE BROWNFIELD 67 0 0 20 20 27 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1084 IN SHOPS MANAGERS
OFFICE PAISLEY CENTRE
PAISLEY
CONSENT PRIVATE BROWNFIELD 80 0 0 0 0 0 0 0 0 30 30  20 0 21/1668/PP.  Site has
Planning Permission in
Principle and key
regeneration priority for
the Council. Programming
will be kept under review
in preparing LDP3.
YES
RFRF0971 PAISLEY SOUTH UWS
PAISLEY
CONSENT  PRIVATE BROWNFIELD 179 0 0 36 36 36 36 35 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0971A PAISLEY SOUTH
DYKEBAR PAISLEY
CONSENT PRIVATE BROWNFIELD 603 0 0 30 45 60 90 90 90 90 90 18 0 Programming agreed in
HLA 24.
NO
RFRF1082 7 CAUSEYSIDE STREET
PAISLEY
CONSENT PRIVATE  BROWNFIELD
(CONVERSION)
4 0 0 4 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
YES
RFRF1086 6 ORR SQUARE PAISLEY CONSENT PRIVATE BROWNFIELD
(CONVERSION)
4 0 0 0 4 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1033 57 AMOCHRIE ROAD
PAISLEY
CONSENT PRIVATE BROWNFIELD 4 0 0 0 0 0 0 0 0 0 0 0 4 18/0852/PP.  Uncertainty
over implementation of
planning consent. Will be
kept under review in
preparing LDP3.
NO
RFRF0706 THE INSTITUTE
MAXWELLTON STREET
PAISLEY
LDP2 SITE PRIVATE BROWNFIELD 40 0 0 0 0 0 0 0 0 15 15 10 0 24/0563/PP. New
application submitted,
delivery expected within
10 year period.
Programming will be kept
under review. Site capacity
will be updated if
application is approved.
NO
RFRF1028 WEST BRAE PAISLEY LDP2 SITE PRIVATE BROWNFIELD 4 0 0 0 0 0 0 0 0 0 0 0 4 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO

Page 69

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 43
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF0880 STATION ROAD PAISLEY LDP2 SITE PRIVATE BROWNFIELD 147 121 0 0 0 0 0 0 0 0 0 0 26 Uncertainty over
implementation of
planning consent. Will be
kept under review in
preparing LDP3.
NO
RFRF1048 PRIORY PARK NURSING
HOME 19-21 MAIN
ROAD PAISLEY
WINDFALL PRIVATE BROWNFIELD
(CONVERSION)
17 0 0 0 0 0 0 0 0 0 0 0 17 24/0316/PP. Planning
application still to be
determined. Will be kept
under review in preparing
LDP3.
NO
RFRF1001 HUNTER STREET
PAISLEY
LDP2 SITE PRIVATE BROWNFIELD 7 0 0 0 0 0 0 0 0 0 0 0 7 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1034 21 GORDON STREET
PAISLEY
LDP2 SITE PRIVATE BROWNFIELD
(CONVERSION)
15 0 0 0 0 0 0 0 0 0 0 0 15 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1044 SITE BETWEEN 2&8
STANELY CRESCENT
PAISELY
WINDFALL PRIVATE BROWNFIELD 24 0 0 0 0 0 0 0 0 0 0 0 24 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1014 BLACKHALL STREET
PAISLEY
LDP2 SITE PRIVATE  BROWNFIELD 59 0 0 0 0 0 0 0 0 0 0 0 59 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1040 LAND TO SOUTH OF ST
JAMES INTERCHANGE
BURNSIDE PLACE
PAISLEY
LDP2 SITE PRIVATE BROWNFIELD 180 0 0 0 0 0 0 0 0 0 0 0 180 22/0569/PP. Planning
application refused at
appeal. Pipeline site, will
be kept under review in
preparing LDP3
NO
RFRF0981 20 HIGH STREET PAISLEY LDP2 SITE PRIVATE BROWNFIELD
(CONVERSION)
6 0 0 0 0 0 0 0 0 0 0 0 6 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
YES
RFRF0851 CALSIDE FORMER RAH
PAISLEY
LDP2 SITE PRIVATE  BROWNFIELD
(CONVERSION)
81 0 0 0 0 20 30 31 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1007 FORMER TENNIS
COURTS GLENCOURSE
ROAD PAISLEY
LDP2 SITE PRIVATE BROWNFIELD 50 0 0 0 0 0 0 0 0 0 0 0 50 Constrained site. Pipeline
site, will be kept under
review in preparing LDP3.
NO
RFRF1050 LAND SW OF STANELY
PARK HOME STANELY
ROAD PAISLEY
WINDFALL PRIVATE  BROWNFIELD 31 0 0 0 0 0 0 0 0 10 10 11 0 19/0831/PP. Planning
consent granted following
completion of HLA24.
Programming will be
reviewed in HLA25.
NO
RFRF1081 41 GAUZE STREET
PAISLEY
CONSENT PRIVATE BROWNFIELD
(CONVERSION)
14 0 0 0 7 7 0 0 0 0 0 0 0 22/0747/PP. Programming
agreed in HLA 24.
YES
RFRF0711B SUTHERLAND STREET
PAISELY
UNDER
CONSTRUCTION
SOCIAL
RENTED
BROWNFIELD 35 0 35 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0950 CARTHA CRESCENT
PAISLEY 
UNDER
CONSTRUCTION
SOCIAL
RENTED
BROWNFIELD 33 0 12 21 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0870A HAWKHEAD HOSPITAL
ACCORD PLACE PAISLEY
UNDER
CONSTRUCTION 
SOCIAL
RENTED
BROWNFIELD 30 0 0 30 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF1077 EAST LANE PAISLEY UNDER
CONSTRUCTION
SOCIAL
RENTED
BROWNFIELD 48 0 48 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0671 DEE DRIVE PAISLEY LDP2 SITE SOCIAL
RENTED
BROWNFIELD 45 0 0 0 0 0 0 0 0 20 25 0 0 Site in SHIP and
programming reflects
expected funding
availability 
NO
RFRF0671A DON DRIVE PAISLEY LDP2 SITE SOCIAL
RENTED
BROWNFIELD 40 0 0 0 0 0 0 20 20 0 0 0 0 Programming agreed in
HLA 24. Site in SHIP and
programming reflects
expected funding
availability
NO

Page 70

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 44
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF0711 WEST BRAE OAKSHAW
PAISLEY (west end
regeneration phase 2)
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 120 0 0 0 0 20 30 30 40 0 0 0 0 Programming agreed in
HLA 24. Site in SHIP and
programming reflects
expected funding
availability. Planning
application 24/0078/PP. to
be determined.
NO
RFRF0773 ALMOND CRESCENT
PAISLEY
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 20 0 0 0 0 0 0 0 0 0 0 0 20 Pipeline site. Site not
currently in SHIP, review in
preparing LDP3.
NO
RFRF0839 HERIOT AVENUE
PAISLEY
LDP2 SITE SOCIAL
RENTED 
BROWNFIELD 35 0 0 0 0 0 0 0 0 0 0 0 35 Pipeline site. Site not
currently in SHIP, review in
preparing LDP3.
NO
RFRF0954 ARKLESTON ROAD
PAISLEY
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 65 0 0 0 30 35 0 0 0 0 0 0 0 Site in SHIP. Construction
expected to commence
next year. Programming
agreed in HLA 24.
NO
RFRF1004 NEW SNEDDON STREET
PAISLEY
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 30 0 0 0 0 0 0 0 0 0 0 0 30 Pipeline site. Site not
currently in SHIP, review in
preparing LDP3.
NO
RFRF1013 HIGH CALSIDE PAISLEY LDP2 SITE SOCIAL
RENTED
BROWNFIELD 20 0 0 0 0 0 0 0 0 0 0 0 20 Pipeline site. Site not
currently in SHIP, review in
preparing LDP3.
NO
RFRF0934 GARTHLAND LANE
PAISLEY
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 32 0 0 0 0 0 0 0 0 0 16 16 0 Site in SHIP and
programming reflects
expected funding
availability
NO
RFRF1071 STATION ROAD PAISLEY WINDFALL SOCIAL
RENTED
BROWNFIELD 45 0 0 0 0 0 0 0 0 0 0 0 45 Planning application
refused at appeal. Pipeline
site, will be kept under
review in preparing LDP3
NO
RFRF1072 WESTBURN
AVENUE/BLACKSTOUN
ROAD PAISLEY
WINDFALL SOCIAL
RENTED
BROWNFIELD 22 0 0 0 0 0 0 0 0 0 0 22 0 Site in SHIP and
programming reflects
expected funding
availability.
NO
RFRF1074 THRUSHCRAIGS
CRESCENT PAISLEY
WINDFALL SOCIAL
RENTED
BROWNFIELD 50 0 0 0 0 0 30 20 0 0 0 0 0 Programming agreed in
HLA 24.  Part of Council’s
regeneration programme.
Site in SHIP and
programming reflects
expected funding
availability
NO
RFRF1075  BROOMLANDS PAISLEY
(Location: Carbrook St)
(Location: Ferguslie
Main Road)
WINDFALL SOCIAL
RENTED
BROWNFIELD 43 0 0 0 0 0 0 0 43 0 0 0 0 Programming agreed in
HLA 24.  Part of Council’s
regeneration programme.
Site in SHIP and
programming reflects
expected funding
availability
NO
RFRF1076 SPRINGBANK ROAD
AREA PAISLEY
WINDFALL SOCIAL
RENTED
BROWNFIELD 100 0 0 0 0 65 0 0 35 0 0 0 0 Programming agreed in
HLA 24.  Part of Council’s
regeneration programme.
Site in SHIP and
programming reflects
expected funding
availability
NO
RFRF0952 GRAMPIAN
AVENUE/LOMOND
CRESCENT PAISLEY 
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 30 0 0 0 0 0 0 0 0 0 0 0 30 Pipeline site. Site not
currently in SHIP, review in
preparing LDP3.
NO
RFRF1043 WRIGHT STREET
RENFREW
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 39 37 2 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0864 KINGS INCH ROAD OLD
POWER STATION
RENFREW
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 248 129 49 63 7 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1083 LAYMOOR AVENUE
RENFREW
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 122 0 65 33 24 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1093 74 FULBAR STREET
RENFREW
CONSENT PRIVATE BROWNFIELD 8 0 0 8 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO

Page 71

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 45
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF1018 26 HIGH STREET
RENFREW
LDP2 SITE PRIVATE BROWNFIELD
(CONVERSION)
9 0 0 0 0 0 0 0 0 0 0 0 9 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
YES
RFRF1019 24 HIGH STREET
RENFREW
LDP2 SITE PRIVATE BROWNFIELD
(CONVERSION)
11 0 0 0 0 0 0 0 0 0 0 0 11 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
YES
RFRF0769B CLYDE WATERFRONT &
RENFREW RIVERSIDE
AREA 1
LDP2 SITE PRIVATE BROWNFIELD 142 0 0 0 0 0 0 0 0 50 50 42 0 Key regeneration priority.
Recent City Deal
investment delivering new
bridge crossing across
River Clyde and Renfrew
North development road
providing access to
Advanced Manufacturing
and Innovation District.
Programming to be
reviewed in preparing
LDP3 
NO
RFRF0860 INCHINNAN ROAD
BLYTHSWOOD
RENFREW
LDP2 SITE PRIVATE BROWNFIELD 85 0 0 0 0 0 0 0 0 0 0 0 85 Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF0994 CLYDE WATERFRONT &
RENFREW RIVERSIDE
AREA 2
LDP2 SITE PRIVATE BROWNFIELD 434 0 0 0 0 0 0 0 0 0 0 0 434 Key regeneration priority.
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1051A  ROW AVENUE
RENFREW
CONSENT SOCIAL
RENTED
BROWNFIELD 57 0 0 0 0 0 0 0 0 0 0 0 57 Site removed from SHIP. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1064
LDP2057
GOLF DRIVING RANGE
RANNOCH ROAD
JOHNSTONE
CONSENT PRIVATE GREENFIELD 88 0 0 0 20 25 23 20 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1025 CORSEFORD AVENUE
JOHNSTONE
CONSENT PRIVATE GREENFIELD 49 0 0 15 15 19 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1052 16 WALKINSHAW
STREET JOHNSTONE
WINDFALL PRIVATE BROWNFIELD 6 0 0 0 0 0 0 0 0 0 0 0 6 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1041 30 CAMPBELL STREET
JOHNSTONE
LDP2 SITE PRIVATE BROWNFIELD 7 0 0 0 0 0 0 0 0 0 0 0 7 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF0667 BARBUSH MILLVIEW
CRESCENT JOHNSTONE
LDP2 SITE PRIVATE BROWNFIELD 86 74 0 0 0 0 0 0 0 0 0 0 12 Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF0796A HIGH STREET PATON’S
MILL JOHNSTONE
LDP2 SITE PRIVATE BROWNFIELD 40 0 0 0 0 0 0 0 0 0 0 0 40 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF0940 BARBUSH FARM
JOHNSTONE
LDP2 SITE PRIVATE GREENFIELD 65 0 0 0 0 0 0 0 0 20 20 25 0 Developer has confirmed
intention to deliver this
site through the recent
Call for Ideas process. Will
be kept under review in
preparing LDP3
NO
RFRF1024  FORDBANK OFF BEITH
ROAD JOHNSTONE
LDP2 SITE PRIVATE  GREENFIELD 100 0 0 0 0 0 0 0 0 30 30 4 0 Allocated LDP2 site which
would continue recent
development in Beith
Road area of Johnstone.
Developer still to be
identified, will be kept
under review in preparing
LDP3.
NO
RFRF0912H MAPLE DRIVE
JOHNSTONE
UNDER
CONSTRUCTION
SOCIAL
RENTED
BROWNFIELD 68 0 20 30 18 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO

Page 72

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 46
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF0164_AH
LDP2057
GOLF DRIVING RANGE
RANNOCH ROAD
JOHNSTONE
CONSENT SOCIAL
RENTED
GREENFIELD 8 0 0 0 0 0 8 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0759 RYEFIELD AVENUE
JOHNSTONE
CONSENT SOCIAL
RENTED
BROWNFIELD 36 0 0 0 0 0 0 16 20 0 0 0 0 Programming agreed in
HLA 24. Consent for 31
units 21/1087/PP and
application 23/0482/PP
for a further 5 units still to
be determined. Site in
SHIP and programming
reflects expected funding
availability
NO
RFRF0972A MACDOWALL STREET
MILL BRAE JOHNSTONE
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 35 0 0 0 0 0 0 0 0 0 15 20 0 Site in SHIP and
programming reflects
expected funding
availability
NO
RFRF0819B NORTH ROAD EAST
GIBSON CRESCENT
JOHNSTONE
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 28 0 0 0 0 0 0 0 28 0 0 0 0 Programming agreed in
HLA 24.  Site in SHIP and
programming reflects
expected funding
availability.
NO
RFRF0912E HOWWOOD ROAD
JOHNSTONE
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 130 0 0 0 20 30 40 40 0 0 0 0 0 Programming agreed in
HLA 24.  Site in SHIP and
part of Council’s
regeneration programme.
Construction expected to
commence next year. 
NO
RFRF0911E DARGAVEL VILLAGE
TOWN CENTRE SITE
H4B, 4C, M2, H11, H32,
H29, 33. BISHOPTON-
DV
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 320 319 1 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1037 DARGAVEL VILLAGE
AREA H13&14
BISHOPTON-DV
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 249 169 50 30 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1047 DARGAVEL VILLAGE SITE
S1 &S3 BISHOPTON-DV
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 150 120 30 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1087 DARGAVEL VILLAGE SITE
H24 AREA W10 STATION
ROAD BISHOPTON-DV
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 172 67 50 30 25 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1088 DARGAVEL VILLAGE SITE
H24 STATION ROAD
AREA W BISHOPTON-DV
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 135 16 0 0 30 30 30 29 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1095 DARGAVEL SITE MC
BISHOPTON-DV
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 49 0 0 0 0 0 0 0 0 0 0 49 0 Programming agreed in
HLA 24.
NO
RFRF0911X REMAINING CAPACITY
BISHOPTON-DV
CONSENT PRIVATE BROWNFIELD 315 0 0 0 0 0 0 0 0 47 200 68 0 Programming agreed in
HLA 24.
NO
RFRF0911Y REMAINING CAPACITY
BISHOPTON-DV
CONSENT PRIVATE  BROWNFIELD 90 0 0 0 0 27 33 30 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0911Z REMAINING CAPACITY
BISHOPTON-DV
CONSENT PRIVATE BROWNFIELD 435 0 0 0 0 0 42 73 167 153 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1090 DARGAVEL VILLAGE SITE
N1 OFF CRAIGTON
DRIVE BISHOPTON-DV
CONSENT PRIVATE BROWNFIELD 213 0 0 40 20 40 40 40 33 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1091 DARGAVEL VILLAGE SITE
N2 BISHOPTON-DV
CONSENT PRIVATE BROWNFIELD 286 0 10 60 73 60 55 28 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0911J DARGAVEL VILLAGE
PHASE 3 BISHOPTON-
DV
CONSENT SOCIAL
RENTED
BROWNFIELD 62 0 0 0 30 32 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1090A DARGAVEL VILLAGE
PHASE 4A SITE N1 OFF
CRAIGTON DRIVE
BISHOPTON-DV
CONSENT SOCIAL
RENTED
BROWNFIELD 20 0 0 0 0 20 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1091A DARGAVEL VILLAGE
PHASE 4B SITE N2 OFF
CRAIGTON DRIVE
BISHOPTON-DV
CONSENT SOCIAL
RENTED
BROWNFIELD 23 0 0 0 0 23 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO

Page 73

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 47
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF1054 MAR HALL BISHOPTON CONSENT PRIVATE GREENFIELD 25 0 0 0 0 0 0 0 0 0 0 0 25 21/1022/PP. Current
planning consent,
however, uncertainty over
whether consent will be
implemented as
alternative development
has recently been
approved on the site.
Review in preparing LDP3
NO
RFRF0752 INGLISTON DRIVE
BISHOPTON
LDP2 SITE PRIVATE GREENFIELD 20 0 0 0 0 0 0 0 0 0 0 0 20 Pipeline site. Site not
currently being marketed
by the Council. Will review
in preparing LDP3.
NO
RFRF0979 STATION ROAD
BISHOPTON
LDP2 SITE PRIVATE BROWNFIELD 50 0 0 0 0 0 0 0 0 0 0 0 50 Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1053 TORR FARM HOUSE
TORR ROAD BRIDGE OF
WEIR
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD
(CONVERSION)
8 0 0 4 4 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1026  STATION ROAD BRIDGE
OF WEIR
CONSENT PRIVATE BROWNFIELD 39 0 0 0 0 0 0 0 0 0 0 0 39 19/0456/PP – Site has
planning consent but
currently constrained
which is impacting on
deliverability. Will be kept
under review in preparing
LDP3.
NO
RFRF1092 27 MAXWELL PLACE
BRIDGE OF WEIR
CONSENT PRIVATE BROWNFIELD 4 0 0 0 0 4 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1021 HOUSTON STATION
HOUSE BAROCHAN
ROAD BROOKFIELD
UNDER
CONSTRUCTION
PRIVATE GREENFIELD 24 16 8 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1032 3 WOODSIDE ROAD
BROOKFIELD
WINDFALL  PRIVATE BROWNFIELD 10 0 0 0 5 5 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1039 NAPIER STEET
LINWOOD
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 28 24 4 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1060 EAST FULTON FARM
DARLUITH ROAD
LINWOOD
CONSENT  PRIVATE  GREENFIELD 49 0 0 0 0 0 20 29 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1017 35 NAPIER STREET
LINWOOD
LDP2 SITE PRIVATE BROWNFIELD 12 0 0 0 0 0 0 0 0 0 0 0 12 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1039A NAPIER STREET
LINWOOD
UNDER
CONSTRUCTION
SOCIAL
RENTED
BROWNFIELD 51 23 28 0 0 0 0 0 0 0 0 0 0 SHIP site. Programming
agreed in HLA 24.
NO
RFRF0967A LAND SURROUNDING
ST BRENDAN’S SOCIAL
CLUB STIRLING DRIVE
LINWOOD
LDP2 SITE SOCIAL
RENTED
BROWNFIELD 65 0 0 0 0 32 33 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1061 LAND EAST OF NEWTON
COTTAGE AT ELDERSLIE
GOLF CLUB
CONSENT PRIVATE GREENFIELD 27 0 0 5 10 12 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1067
LDP2024
SOUTH OF WOODEND
HOUSE HOUSTON ROAD
HOUSTON
UNDER
CONSTRUCTION
PRIVATE GREENFIELD 43 27 16 0 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1094 CHAPEL FARM HOUSE
CHAPEL ROAD
HOUSTON
CONSENT PRIVATE BROWNFIELD
(CONVERSION /
NEWBUILD)
4 0 0 4 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1065
LDP2033
WEST OF BAROCHAN
ROAD HOUSTON
LDP2 SITE PRIVATE GREENFIELD 59 0 0 0 0 0 20 20 19 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0840 HILLFOOT DRIVE
CARSEWOOD HOUSE
HOWWOOD
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD 10 0 5 5 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0936 BLEACH WORKS 64
MIDTON ROAD
HOWWOOD
LDP2 SITE PRIVATE GREENFIELD 19 0 0 0 0 0 0 0 0 0 0 0 19 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3 
NO

Page 74

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 48
Estimated delivery of housing sites
LDP2
ref/HLA
ref
Site Address Planning
Status
Tenure Brownfield/
Greenfield
Capacity Past
Completions
Projected Delivery Comments/
constraints to
delivery
Town centre
site? 
Short term Medium term Long term Pipeline   
24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 Post 34  
RFRF1036 KILBARCHAN WEST
PARISH CHURCH
CHURCH STREET
KILBARCHAN
UNDER
CONSTRUCTION
PRIVATE BROWNFIELD
(CONVERSION)
18 0 0 0 0 0 0 0 0 0 0 0 18 Site has planning consent
but is being marketed
again for sale.  Pipeline
site, will be kept under
review in preparing LDP3
NO
RFRF1038 11 STEEPLE STREET
KILBARCHAN
LDP2 SITE PRIVATE BROWNFIELD 5 0 0 0 0 0 0 0 0 0 0 0 5 Planning consent expired. 
Pipeline site, will be kept
under review in preparing
LDP3
NO
RFRF1066
LDP2037
BARHILL CRESCENT,
KILBARCHAN
LDP2 SITE PRIVATE GREENFIELD 60 0 0 0 0 0 20 20 20 0 0 0 0 Programming agreed in
HLA 24. 
NO
RFRF1068
LDP2032
WEST OF BURNFOOT
ROAD LOCHWINNOCH
LDP2 SITE PRIVATE GREENFIELD 92 0 0 0 0 20 40 32 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1089 44 HIGH STREET
LOCHWINNOCH
WINDFALL PRIVATE  BROWNFIELD 10 0 0 0 0 10 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF0977 NORTHBARR ERSKINE UNDER
CONSTRUCTION
PRIVATE GREENFIELD 195 141 37 17 0 0 0 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1079 TORRANCE HOUSE
ERSKINE HARBOUR
ERSKINE
CONSENT PRIVATE BROWNFIELD 42 0 0 0 0 0 15 15 12 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1063
LDP2046
NORTHBAR PHASE 2
SITE BETWEEN
SANDIELAND WOOD
AND FLORISH ROAD
ERSKINE
CONSENT PRIVATE GREENFIELD 59 0 0 0 0 0 33 26 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1063A
LDP2046
NORTHBAR PHASE 2
SITE BETWEEN
SANDIELAND WOOD
AND FLORISH ROAD
ERSKINE
CONSENT SOCIAL
RENTED
GREENFIELD 24 0 0 0 0 0 24 0 0 0 0 0 0 Programming agreed in
HLA 24.
NO
RFRF1045 GREENHEAD NURSERY
OLD GREENOCK ROAD
INCHINNAN
WINDFALL PRIVATE BROWNFIELD 15 0 0 0 0 0 0 0 0 5 10 0 0 Planning consent has
expired but new planning
application is expected.
Will be kept under review
in preparing LDP3.
NO
RFRF1069
LDP2094
LAND AT BEARDMORE
COTTAGES INCHINNAN
LDP2 SITE PRIVATE GREENFIELD 10 0 0 0 0 0 0 0 0 0 0 0 10 Council not currently
marketing site. Will be
reviewed in preparing
LDP3.
NO

Page 75

Renfrewshire Local Development Plan – Delivery Programme | 2024 | 49
Appendix 1 – Housing Sites 