Housing Emergency Update

Argyll and Bute Council · 13 August 2025
Back to Oban Lorn & the Isles Area Community Planning Group — 13 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Community Planning
Partnership 
OLI Area Community Planning Group 
13th August 2025 
Housing Emergency Update 
Summary 
In June 2023 the Council declared a Housing Emergency. There was a stake
holders’ event in November 2023 which resulted in a Housing Emergency
Action Plan being agreed in June 2024. The Community Planning Partnership
is key to bringing forward many of the actions within the Plan. The
Community Planning Partnership Outcomes Improvement Plan has
highlighted housing as 1 main issue to be addressed through the Plan. This
report will highlight housing activity in Argyll and Bute to address the Housing
Emergency and also focus on the actions within the Action Plan of particular
relevance to the Community Planning Partnership. 
1. Purpose    
The purpose of this report is to provide CPG Members with a high
level synopsis of the considerable volume of wide-ranging activity,
which is underway, often well in advance of houses being completed
and handed over, such is the long term nature of development.  This
synopsis is a snapshot of activity in the housing system in the last six
months.     
2. Recommendations    
CPG members are asked to consider the content of the report   
3. Background    
Contained in the Full Report 
4. Detail    
Contained in the Full Report

Page 2

5. Conclusions    
Contained in the Full Report 
6. CPP Outcomes    
Does your report relate to any of the following:    
Outcome Tick as appropriate (🗸)
Community Wellbeing 
Housing  🗸
Transport Infrastructure 
For further information please contact:   
Fergus Murray – Head of Development and Economic Growth
fergus.murray@argyll.bute.gov.uk 
Matt Mulderrig –   Development Policy and Housing Manager 
matt.mulderrig@argyll-bute.gov.uk 
Douglas Whyte – Team Lead – Housing Strategy                      
douglas.whyte@argyll-bute.gov.uk

Page 3

ARGYLL AND BUTE COUNCIL      OLI CPG
DEVELOPMENT AND ECONOMIC 
GROWTH    13th AUGUST 2025  
HOUSING EMERGENCY UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 In June 2023 the Council’s Environment, Development and Infrastructure (EDI)
Committee declared a Housing Emergency due to a consistent reduction in the
supply of housing, a steady increase in demand for housing across all tenures
and increasing levels of un-affordability. 
1.2 In November 2024, Council agreed an update to the Local Housing Strategy,
incorporating the Housing Emergency Action Plan, and a set of Housing
Emergency Progress Metrics.  It was agreed these would all be reported to
Council annually in November.   
1.3 The purpose of this report is to provide CPG Members with a high level synopsis
of the considerable volume of wide ranging activity which is underway, often well
in advance of houses being completed and handed over, such is the long term
nature of development.  This synopsis is a snapshot of activity in the housing
system in the last six months.   
1.4 Activity includes: engaging directly with Scottish Government; developing
Strategic Development Frameworks to facilitate long-term delivery, securing
national funding investment into housing projects in the area; working towards
delivery of worker housing on Mull,  engaging with infrastructure providers to
provide worker housing; and partnering with RSL’s and community housing
groups to facilitate housing developments. 
RECOMMENDATION 
CPG members are asked to consider the content of the report.

Page 4

ARGYLL AND BUTE COUNCIL      OLI CPG
DEVELOPMENT AND ECONOMIC     
GROWTH    13th AUGUST 2025     
HOUSING EMERGENCY UPDATE 
2.0 INTRODUCTION 
2.1 The purpose of this report is to inform Members on progress made in terms of
the Council tackling the Housing Emergency in Argyll and Bute.  The last
report on this issue was to Council in November 2024 Nov 2024 LHS Update
and Housing Emergency Report .  This report focuses on progress since that
date.   
3.0 RECOMMENDATION 
3.1 CPG members are asked to consider the content of the report. 
4.0 DETAIL 
4.1 In November 2024, Council agreed an update to the Local Housing Strategy
Incorporating the Housing Emergency Action Plan, and a set of Housing
Emergency Progress Metrics.  It was agreed these would all be reported to
Council annually in November.  The purpose of this report is to provide CPG
members with a high level synopsis of the considerable volume of wide ranging
activity which is underway, often well in advance of houses being completed and
handed over, such is the long term nature of development.  This synopsis is a
snapshot of activity in the housing system in the last six months.

Page 5

Homes Consented
4.2 From the declaration of the Housing Emergency in June 2023 until the end of
February 2025 the Council granted planning consent for 860 residential units. 
Scottish Government Engagement 
4.3 In November 2024, Members of the Scottish Government, Local Government,
Housing and Planning Committee, visited Oban.  They met with the Council’s
leader Jim Lynch, CEO Pippa Milne, other senior council officials, and
representatives from the Link Housing Group together with a representative
from the Colonsay Community Development Company. The day also included
a visit to the Dunbeg Corridor housing development.  The Scottish
Government has produced a report of the visit which can be accessed here: 
Scottish Govt Report on Housing Emergency Visit to Argyll and Bute .  A
number of requests and suggestions for Scottish Government were made at the
meeting and these are summarised in appendix 1 to this report. 
Preparing Strategic Development Frameworks
4.4 In January 2025 consultants were engaged, to develop the Strategic
Development Frameworks for Oban (OSDF) and Helensburgh (HSDF).  Both
these are intended to identify long-term 20-40 years strategic development
opportunities.  By doing this we will set a long term framework that can be used
to direct infrastructure investment and create a pipeline of deliverable
development land, particularly housing supply but also other related community,
public service and economic development land.  Initial desk-top and baseline
surveys have been ongoing and the development of preliminary options for

Page 6

assessment.  Early engagement with community representatives, members, and
key stakeholders are planned over the summer months.  These pieces of work
will ultimately feed in to LDP3. 
Securing External Housing Funding Investment
4.5 The Council has continued to develop Business Cases for the proposals for a
worker accommodation pilot on Mull, and market housing for principal home
occupation on Islay.  In addition to the £3m Rural Growth Deal investment
allocated to these projects, the Community Regeneration Fund has potentially
been identified to provide up to a further £5m investment to enabling housing
projects. 
Delivering Tobermory Worker Housing
4.6 The Council has employed local contractors and is working with MICT to deliver
worker housing in Tobermory, on-site infrastructure is currently being installed
and will be complete by July 2025.  Work is underway to procure tender costs
for construction of the worker housing which will provide 12 units.  There is an
anticipated site start for building construction of Spring 2026.

Page 7

Improving Home Energy Efficiency and Fuel Poverty
4.7 A Local Heat and Energy Efficiency Strategy was approved by Council in
November.  This sets out a policy framework that assists in reducing fuel poverty
in the long term.  Officers will now work to identify deliverable projects, and use
the LHEES to support funding applications.
4.8 The HEEPS:ABS Programme allows homeowners and private rented tenants
to reduce their energy bills, assists with the cost-of-living crisis and reduces
energy consumption contributing to a reduction in climate change   The
Council fully utilised it HEEPS:ABS funding of £1,979,827 for 24/25.  Looking at
the full history of HEEPS:ABS Programmes, from 2013 to Sept 2024,there have
been 4,161 energy improvement measure installations in Argyll and Bute. 
There has been a focus on external and internal wall insulation.  Most of the
properties are owner occupied, many built between 1950 and 1983.  A
significant proportion are in the most deprived areas of Argyll and Bute. Most
properties experience a benefit in their EPC ratings meaning warmer and more
efficient homes. 
Worker Accommodation from Infrastructure Providers
4.9 Officers continue to work with SSEN to deliver their worker housing strategy in
association with the delivery of the overhead power line projects they have
ongoing.  Principle activity has seen the development of dedicated worker
accommodation being provided at Kilmory Industrial Estate and other locations. 
The effect of this is to significantly reduce the impact on the local housing
market, but also to provide servicing and infrastructure investment in the Kilmory
Industrial Estate.  There is ongoing engagement with SSEN at a Senior

Page 8

Management level.  One priority begin explored is the potential for further
investment by SSEN in legacy housing, and options are still being explored. 
Empty Homes for Workers
4.10 Our Empty Homes Officer project, working with the HSCP solely to assist empty
homes owners to bring back properties in to use for HSCP staff has received
national recognition through an award from the Empty Homes Network.  This
project is directly supporting the retention and recruitment of the key workforce
required to sustain essential services and making the best use of existing stock. 
The role has directly enabled homes and bed spaces for use by HSCP workers
on Coll, Tiree, Islay and in Connel.

Page 9

RSL Housing Provision & Pipeline 
4.11 ACHA is exploring site acquisition options on Tiree which could deliver 10 units,
but subject to ACHA satisfaction on local housing demand. 
4.12 West Highland are exploring the feasibility of a 4 unit re-development in
Campbell Street, Oban with Scottish Government and the Council.  The re-
development would be a key regeneration opportunity in the town as well as
valuable affordable housing supply.

Page 10

4.13 West Highland has acquired land at Shillinghill, Tobermory, have achieved
planning consent for 10 units, and are in the process of agreeing a grant request
with Scottish Government. 
4.14 West Highland is developing a planning application for 16 social rent units at
Dalmally subject to site acquisition negotiations.

Page 11

4.15 West Highland is in the process of acquiring Dalmally Police House & Station
subject to achieving planning and funding. 
4.16 West Highland is working with the Council to design infrastructure works which
will facilitate the development of the Old Hospital Site on Ganavan Road, Oban
which would deliver 50 units.
4.17 West Highland is in negotiations with the contractor for Cruachan refurbishment
project which is going ahead.  The contractor will potentially utilise the West
Highland’s Loch Awe site, facilitating construction of a road access and services
which will later help to enable housing construction.

Page 12

4.18 In February 2025, LINK Group submitted four planning applications for phase 4
Dunbeg, which will deliver a Distributor Road Network including a trunk road
roundabout, a phased commercial area, and 433 homes including:
• Social Rent - 150
• Mid- Market Rent (MMR) – 48 
• New Supply Shared Equity (NSSE) – 40
• Elderly Living – 31 (16 NSSE & 15 Rent)
• Student Accommodation – 31
• Private Housing – 133

Page 13

4.19 At the same time, the Scottish Government has also agreed a ten year
extension to the Council’s Lorn Arc TIF scheme.  These are both major
milestones in progressing to the start of construction for this significant
investment in the Oban area, projected to add £179m in Net Present Value to
the local area. 
Community Housing Projects
4.20 Tiree Community Development Trust has completed a purchase of land for
housing development and have gained Rural and Islands Feasibility Funding.
4.21 The Hynish Trust on Tiree has been granted Strategic Housing Fund grants to
bring back 6 properties back in to use, and they are exploring Rural and Islands
Housing Fund to bring a further 6 properties back in to use.
4.22 Luing Community Trust has worked with second home owners to bring
properties back into long term let rent for workers on the island.   They are
exploring new build opportunities.
4.23 South West Mull and Iona Development Trust is exploring housing opportunities
in Bunessan and the Ross of Mull.

Page 14

4.24 On Kerrera, the MacDougall of Dunollie Preservation Trust is exploring options
to refurbish the Ferry House on Kerrera for affordable housing.
4.25 Mull and Iona Community Trust (MICT) has set up an Iona Housing Steering
group to look at delivering affordable housing on the island and bringing existing
buildings on the island back in to use.  The Iona Community is exploring
redevelopment options of the MacLeod Building and are in discussion with MICT
and the Council.
4.26 MICT is pursuing two open market housing acquisitions on Mull, in Dervaig and
Craignure. They are looking to purchase land in Fishnish for delivery of new
build affordable housing.  
4.27 On Lismore the Lismore Community Trust are looking to deliver 2 affordable
homes on the island with assistance of feasibility funding from the Council.
4.28 Dalavich Improvement group is working with the Council, using the Community
Housing Assessment Toolkit to assess local housing needs and demand. 
5.0 Argyll and Bute Outcomes Improvement Plan 2024 -2034
5.1 The Community Planning Partnership has been actively engaged with other
partners in trying to find ways to tackle the Housing Emergency in Argyll and
Bute. The Housing Emergency Action Plan identified several actions which the
CPP can assist with delivering:-
• Freedom to use Scottish Government housing funding more flexibly and
as an allocation within local administrative control
• Create funding mechanisms for Community Housing Trusts to finance
feasibility studies, professional fees and approval processes
• Deliver seasonal and temporary workforce accommodation using short
term occupancy agreements
• Develop a strategic approach to evidencing the need for workforce
housing in the public sector
• Deliver emergency workforce housing options including the use of
modular, temporary and tiny homes
• Identify and map public sector land and buildings which could provide
workforce housing via repurposing and change of use
• Develop a better range if housing options for older people to encourage
movement in existing housing stock
5.2 The Outcomes Improvement Plan produced by the Community Planning
Partnership has Housing as one of the main 3 outcomes which the Partnership
will focus on for the duration of the Plan.
5.3 There will be a CPP Development Day later this year with a focus on housing
and how the Partners can continue to work together to deliver on the actions
within the Housing Emergency and also how Partners can meaningfully deliver

Page 15

on the fact that housing is one of the 3 main topics within the Outcomes
Improvement Plan. 
6.0  CONCLUSION
6.1 The Housing Emergency was declared due to a whole housing system failure and
addressing the issues behind the failure will take time to address and require a
partnership approach. Members requested periodic update in activity addressing
the Housing Emergency.  This report demonstrates the wide range of actions that
are being taken forward within the context of reduced resources for the delivery
of new homes at a national level.  That said, the council continues to work with
the Government, key agencies and our housing delivery partners to make
progress including exploring new methods and solutions to tackle housing
shortages across the local authority area, but many of these will take time to come
to fruition. 
7.0 IMPLICATIONS 
7.1 Policy - the ongoing activity is consistent with current Council priorities and the
Local Housing Strategy vision and outcomes which are directly aligned with
the overarching objectives of the Outcome Improvement Plan – outcome 2:
Housing.  
7.2 Financial - none directly arising from this report but future housing delivery
actions will require additional funding at some stage from the Council and our
partners if delivery is to be accelerated
7.3  Legal – None. 
7.4  HR – None.
7.5 Customer Service – None.  
7.6 Risk - there is a risk of depopulation, damage to the economy a risk to
delivering essential services in the local authority area if partners cannot
effectively tackle the Housing Emergency.
7.7 Climate Change – new housing in the right location helps reduce carbon
outputs when delivered using renewable energy and other measures. Making
best use of existing stock by delivering energy efficiency measures helps
towards achieving climate change targets. 
7.8  Fairer Scotland Duty – Socio-economic Duty – the delivery of housing across
Argyll and Bute facilitates socio-economic opportunities for all. The housing
plans in the report link to the Child Poverty Strategy

Page 16

7.9 Equalities - protected characteristics - the activity outlined in the report is
consistent with the aims and objectives set out in the Local Housing Strategy
which is subject to an EQIA. There are targets within the housing plans to
deliver housing which meet the needs of specialist groups
7.10 Consumer Duty – none
7.11 Island Communities – many of the housing projects detailed in the report are
being delivered on islands which will provide many benefits such as
employment and the continued delivery of essential services to island
communities.
7.12 Children’s Rights and Wellbeing – the delivery of more housing will enable
more children to have a safe secure environment. The housing plans also
have clear links to the Child Poverty Strategy.   
Kirsty Flanagan
Executive Director with responsibility for Development and Economic Growth
Councillor Jim Lynch Council Leader and Policy Lead for Housing
August 2025                                                  
For further information contact: 
Fergus Murray – Head of Development and Economic Growth
fergus.murray@argyll.bute.gov.uk 
Matt Mulderrig –   Development Policy and Housing Manager 
matt.mulderrig@argyll-bute.gov.uk 
Douglas Whyte – Team Lead – Housing Strategy                      
douglas.whyte@argyll-bute.gov.uk

Page 17

Appendix 1 
Actions suggested for Scottish Government during meeting with Scottish
Government Local Government, Planning and Housing Committee (Nov 2024) 
Actions suggested for the Scottish Government: 
• Market failure needs intervention and radical thinking, and there needs to be a long-
term and continuous approach to housing. 
• More funding flexibility is required, such as with the housing infrastructure fund (HIF).
Devolution of funding to councils could be considered. 
• The council would like to be able to accrue funds from underspend in the Affordable
Homes Supply Programme (AHSP). 
• There needs to be advance investment in critical infrastructure (such as a new access
road to Dunbeg in Oban). 
• The AHSP Grant Benchmark threshold is too low to buy back properties – there needs
to be a higher % of funding. 
• Community housing trusts are looking to deliver housing, but without expertise in
development they need support and seed funding. 
• Key worker housing is important, and the council needs to be able to provide shorter
tenures and dispose of sites. However, funding through the AHSP and other funds will
not allow this. 
• A pilot of shorter tenures is taking place in Mull, which the council would like to fund
through Resource Planning Assumptions. 
• Regulations on housing and planning need to be more joined-up in order to tackle a
complex system, considering the impact of regulation on the whole system (such as a
possible cladding levy negatively impacting on housing supply). 
• For example, currently an increase in council tax for second homes can be avoided by
property owners registering their main residence in another authority (which is not
charging increased council tax) as their second property; a combined approach across
authorities may therefore be needed.  
• Consideration of a new Planning Use class for ‘non-principal homes’ would augment
provisions for increased council tax, short-term let licensing and planning control areas. 
• Need for compulsory sales orders and for a land and property tax, which could lead to
less people likely to ‘sit’ on land and property. 
The need for flexibility in funding and regulations: 
• With the Rural and Islands Housing Fund completions need to take place pre-election,
which limits the feasibility studies that can be carried out now (as any project is unlikely
to be completed pre-election). This demonstrates the need for long term certainty of
funding, and the hope is that the fund will be reinstated post election. 
• There need to be more flexible grant conditions in the Affordable Housing Supply
Programme and other funds. 
• Important to avoid unintended impacts of legislation e.g.: 
o Infrastructure levy would have negative impact on builds 
o Cladding levy – would be unfair for local developers who haven’t used cladding 
o Passivhaus standard – there are few contractors available, and they would not
go to remote builds. Something instead ‘near’ Passivhaus would be sufficient and
more cost effective.

Page 18

• Investment in renewals and transmission to the national grid could have an impact on
housing – local distribution of renewable energy is needed.