5. Developer Contributions (Education) – new planning guidance - Report

Renfrewshire Council · 19 March 2024
Back to Planning and Climate Change Policy Board — 19 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________ 
To:  Planning and Climate Change Policy Board 
On:  19 March 2024
___________________________________________________________________ 
Report by: Chief Executive 
___________________________________________________________________ 
Title:  Developer Contributions (Education) – new planning guidance
___________________________________________________________________ 
1. Summary 
1.1 This report sets out proposed draft planning guidance on potential education
contributions from new housing development in Renfrewshire. 
1.2 The draft guidance supplements and aligns with the current relevant Local
Development Plan (LDP) policy I8 on Developer Contributions. 
1.3 Subject to approval of the draft guidance, the document will be published for a
period of stakeholder consultation before being brought back to Board for
formal approval as Council policy.
________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Board:
(i) Consider the new draft planning guidance on Developer Contributions
(Education) appended to this report;
(ii) Approve the draft planning guidance for stakeholder consultation for a 6-
week period;
(iii) Note that the outcomes of this consultation will be brought back to a
subsequent Board meeting for member consideration;
(iv) Delegate authority to the Convenor, in conjunction with the Head of
Economy and Development, to make any further incidental changes to the
draft document as may be relevant, to account for any changes made by
the Board and to ensure that the consultation document is as up to date
as possible at the time of publication;

Page 2

________________________________________________________________________________ 
3. Background 
3.1 Planning and Climate Change Policy Board considered and noted a report in
January 2024 that set out the reasons why new planning guidance for
developer contributions (education) is being brought forward by Renfrewshire
Council in 2024. It also explained the key metrics that the Council will rely on
in its proposed new planning guidance. 
3.2 It is considered, therefore, that there is no need to repeat that background
context here. 
3.3 One question that has been raised with officers since the January Board
meeting is whether an “Infrastructure Levy” or similar policy mechanism could
be introduced in Renfrewshire, rather than (or alongside) the approach being
proposed in the new draft planning guidance. 
3.4 The Planning (Scotland) Act 2019 makes provision at Section 54 for Scottish
Ministers to present regulations that would lead to local authorities having the
ability to introduce an infrastructure levy for their area. However, these
regulations have not yet been published and, as such, local authorities are not
able to move forward with defining an approach for any prospective
Infrastructure Levy. Should this context change then officers will update
members. The draft guidance has been prepared with consideration that such
a mechanism may become available to Renfrewshire Council at a later date. 
4 Draft planning guidance 
4.1 The principal aim of the new guidance is to introduce a degree of certainty for
all stakeholders concerned with education capacity in Renfrewshire. Linking
with the Council’s Learning Estate Management Plan, the guidance aims to
clarify how planned housing development and the pupils they generate will be
accommodated within Renfrewshire’s schools. 
4.2 Applicants for planning permission for residential development will be
expected to use the guidance in shaping their planning applications and to
allow them to make allowance for any financial or other contribution that may
be expected from that proposed development. 
4.3 As is common with this type of policy in Renfrewshire (and elsewhere) the
expectation is that the applicant is expected to mitigate the impact from their
proposed development. 
4.4 The draft guidance offers clarification on the Council’s proposed approach to: 
 Pupil product ratio (the number of school age pupils likely to be derived
from the new homes built);
 How identified housing land and existing planning consents will be
factored in to any calculations;

Page 3

 Planning applications for “windfall” (unidentified) housing sites;
 Dealing with the cumulative effect of multiple applications in the same
catchment;
 How the “operational capacity” of schools will be calculated;
 How the catchment of the denominational and non-denominational
primary and secondary schools will relate to the location of the planning
application site;
 Using individual school capacity statistics;
 Understanding the implications of planned school capital investment;
 New housing development requiring a new school to be provided;
 Developer contribution amounts to be negotiated for;
 Exceptions to the Council’s planning policy; 
5 Next Steps 
5.1 Subject to any changes Board wish to agree to make to the draft guidance,
the document will then be published for stakeholder consultation for a period
of 6 weeks in spring 2024. 
5.2 All representations made to the Council on their draft guidance will then be
brought back to the Planning and Climate Change Policy Board for their
consideration. The Board will then be asked to agree a final version of the
policy guidance which will be published on the Council’s website for use by
planning applicants for residential development in Renfrewshire. 
___________________________________________________________________ 
Implications of the Report 
1. Financial – Significant potential impact, depending on the successful
implementation of any new developer contributions policy.   
2. HR & Organisational Development – Examination going forward of the
additional resources required to negotiate planning obligations because of
submitted / approved planning application. 
3. Community/Council Planning – 
 Our Renfrewshire is thriving – The new developer contributions policy
can assist in supporting new or enhanced community infrastructure
(schools) in connection with new housing for pupils living in the local
area;
 Building strong, safe, and resilient communities: The policy can assist in
the forward planning of education capacity requirements across
Renfrewshire’s varied communities and achieve positive education
outcomes for our younger residents;

Page 4

4. Legal – Likelihood of additional resource demand being placed on Council’s
Legal Team in terms of negotiating and confirming planning obligations
(including Section 75 Agreements) for a larger number of planning
applications. 
5. Property/Assets – None. 
6. Information Technology – None. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report.  If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website.   
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – None. 
11. Privacy Impact – None. 
12. COSLA Policy Position - None. 
13. Climate Risk – None.
___________________________________________________________________ 
Authors: 
Alasdair Morrison, Head of Economy and Development;
Tel: 07979 700472; Email: Alasdair.morrison@renfrewshire.gov.uk 
David Love, Chief Planning Officer
Tel: 07483 410182; Email: david.love@renfrewshire.gov.uk

Page 5

RENFREWSHIRE COUNCIL 
Renfrewshire Local Development Plan 2021: Draft Planning Guidance
Developer Contributions (Education) Supplementary
Guidance
V.9.0
March 2024 
-------------------------------------------------------------------- 
CONTENTS 
1. Summary
2. Introduction
3. Background
4. Current Context
5. Calculating the Financial Contribution
6. Legal Agreements
7. Contact 
----------------------------------------------------------------------- 
1. Summary 
 The principal aim of the guidance is to set out new Renfrewshire Council
planning policy guidance on developer contributions towards education
capacity impacts from new housing development. The guidance aligns with
Policy I8 of the Renfrewshire Local Development Plan; 
 Once adopted this guidance will be used in the assessment of all planning
applications in Renfrewshire for residential development (subject to any
exceptions outlined in the policy); 
 The guidance has used information on the current and forecast school rolls
and capacity for all primary and secondary schools in Renfrewshire, taking
account of planned or proposed housing development that the Council is
aware of; 
 Renfrewshire continues to be a desirable location for new housing
development and will continue to face pressure to both identify additional
land and assess planning applications for this purpose. The guidance offers
details of the currently identified housing land supply in Renfrewshire; 
 The Council’s capital programme currently outlines investment plans for new
or replacement schools and planned extension of schools; 
 The guidance outlines the proposed pupil product ratio (average number of
pupils per new dwelling built) that has been generated from recent housing
developments in Renfrewshire.

Page 6

The Council will apply this average to future planning applications in
catchments of all denominational and non-denominational primary and
secondary schools; 
 Contributions will be sought for all housing developments which will result in
the relevant school’s operational capacity (85%) being met or breached by
the quantum of planned housing in the respective planning application is
factored to have generated the estimated number of pupils to the catchment; 
 The developer contribution negotiated for by the Council will be based on
estimated additional pupil impact from new homes granted planning
permission; 
 The specific developer contribution applied is based upon several sources
which are relevant to the current Renfrewshire context. The contribution rate
will apply across Renfrewshire on a uniform basis for all schools of that type; 
 Contributions will be confirmed through appropriate legal agreements
between the applicant/developer/landowner and Renfrewshire Council. New
housing development (as relevant) will not be built and occupied until such
agreements have been signed. Payment of contributions can, in certain
circumstances, be phased for a housing development; 
 Contributions will be sought from all planning applications for 10 or more new
dwellings on a site, except where that application site is located in a school
catchment where total identified land supply proposed will breach operational
capacity of the relevant schools. In such cases all new housing will require
to contribute, regardless of the scale of housing site proposed or timing of
the planning application; 
 Contributions will not apply to one-bedroom homes, to homes built
specifically for an older demographic resident or to student housing and will
be calculated at a lower rate of pupils per new home where flats / apartments
are proposed; 
===========================================================

Page 7

2. Introduction 
2.1  This Developer Contributions (Education) supplementary guidance
document forms part of Renfrewshire Council’s non-statutory planning guidance
and is a material consideration in the determination of planning applications. 
Applicants and other stakeholders should take account of the guidance when
preparing development proposals.   
2.2 This guidance details the Council’s approach to securing developer contributions
in respect of education provision and will be reflected in all such discussions with
applicants in relation to proposals for residential developments. 
2.3 The guidance covers a range of issues related to education impact from new
housing development, including current school capacity, proposed housing
development by catchment, estimated pupil product ratios from new housing and
links to Renfrewshire Council’s Learning Estate Management Plan. 
2.4 It makes clear the expected financial contributions from planning applications for
new housing developments in school catchments which (as a result of the new
housing being built) will meet or breach agreed operational capacity levels. 
Aims of the guidance 
2.5 The principal aim of this new guidance is to introduce a degree of certainty for all
stakeholders concerned with education capacity in Renfrewshire. Linking with
the Council’s Learning Estate Management Plan, it clarifies how housing
developments and the school pupils they generate will be accommodated within
Renfrewshire’s schools. 
2.6 Renfrewshire’s Planning Service actively encourage discussions with
prospective applicants for residential development at the earliest opportunity to
ensure that they are fully conversant with the implications of this (and other)
planning guidance before submitting applications for development.  Prospective
applicants are encouraged to submit a pre-application enquiry in the first instance
to dc@renfrewshire.gov.uk. 
Review 
2.7 This guidance will be reviewed at regular intervals to ensure that the education
and housing land supply data which informs it is as up to date as possible. 
3. Background 
Purpose of planning obligations 
3.1 Planning obligations seek to mitigate the impacts of a proposed development
and make it acceptable in planning terms. They can be used to secure financial
contributions to, or in-kind provision of, necessary new social and community
infrastructure to support new developments.

Page 8

3.2 Obligations are usually entered into in accordance with Section 75 of Town and
Country Planning (Scotland) Act 1997, as amended, and are commonly referred
to as Section 75 Agreements (S75).  They are often used where a planning
condition or another form of legal agreement would not be appropriate to address
the impact of the development in question. 
3.3 Planning obligations can be entered into between a person with an interest in the
land and the planning authority; or via a unilateral undertaking by a person with
an interest in the land. S75 agreements run with the land and the obligation
continues to be enforceable against any subsequent owner of the land until such
time as the details of the agreement are fully discharged by the local planning
authority. 
3.4 Scottish Government’s policy on Planning Obligations is expressed in Circular
3/2012 (Planning Obligations and Good Neighbour Agreements - Revised
2020). The Circular sets out five tests which must be met when seeking to secure
a planning obligation: 
 Necessary to make a proposal acceptable in planning terms (and overcome
a barrier to the approval of planning permission); 
 Serve a planning purpose where it is possible to identify infrastructure
provision requirements to advance, should relate to development plans; 
 Be related to the proposed development either as a direct consequence of
it or arising from the cumulative impact of development in an area; 
 Fairly and reasonably relate in scale and kind to the proposed development
(provide or contribute to the provision of infrastructure that would not be
necessary were it not for the development, on a proportionate pro-rata basis
as appropriate, but not to resolve existing deficiencies); and 
 Be reasonable in all other respects.  
3.5 A planning authority may utilise an alternative legal mechanism to secure
developer contributions in certain circumstances.  Section 69 of the Local
Government (Scotland) Act 1973 provides the Council with the power to enter
into an agreement with the developer with the discharge of any if its functions. 
Known, more widely, as Section 69 Agreements, they can include payment of
financial contributions and is normally used when a one-time payment of a
developer contribution is agreed, without the need for this agreement to be
binding on subsequent owners of the land.

Page 9

Renfrewshire’s Planning Policy Context 
3.6 Section 25 of the Town and Country Planning (Scotland) Act 1997, as amended,
requires that planning applications be determined in accordance with the
development plan, unless material considerations indicate otherwise. In the case
of Renfrewshire, the development plan currently consists of: 
 National Planning Framework 4 (NPF4; 2023); and 
 Renfrewshire Local Development Plan 2 (2021) 
3.7 Policy 18 of NPF4 (Infrastructure First) seeks to encourage, promote and
facilitate an infrastructure first approach to land use planning, which puts
infrastructure considerations at the heart of placemaking. The policy notes that
developments will be supported where they provide or contribute to infrastructure
in line with that identified as necessary in Local Development and Delivery
Programmes. 
3.8 In addition, Policy 18 notes that the impacts of development proposal on
infrastructure should be mitigated. The policy states that: 
Development proposals will only be supported where it can be demonstrated
that provision is made to address the impacts on infrastructure. Where planning
conditions, planning obligations, or other legal agreements are to be used, the
relevant tests will apply. 
3.9 Policy I8 of the Renfrewshire Local Development Plan (Developer
Contributions) sets the policy context for the outlined framework:   
Contributions will be sought for the following items to address infrastructure
deficits and/ or a shortfall in infrastructure capacity that arise as a direct result
of new development. Any contribution sought will be appropriate, proportionate,
necessary and relevant to the nature of the development, its scale and its
location: 
 Education – additional classrooms and associated school facilities
required to support the operation of a school, related to the number of
pupils generated by the development; 
 Healthcare Services and Facilities – where investment is required to
provide healthcare infrastructure to address increased demand generated
by the development; 
 Traffic Management and Active Travel – traffic signals, crossings,
measures required in relation to road safety and providing safer routes to
school, active travel connections and improvements to the road network
required to support the development; 
 Public Transport Infrastructure – where investment is required to
address increased demand associated with the development;

Page 10

 Open Space – where a contribution is required to enhance open space
provision off-site to support the development; 
 Blue/Green Infrastructure – where a contribution is required in relation
to the sustainable management of water and where mitigation including
on-site or offsite habitat creation or enhancements to watercourses are
required. 
Recent housing development in Renfrewshire 
3.10 Renfrewshire has been the subject of significant levels of housebuilding in recent
years.  The development of sites at Renfrew Riverside, Dargavel, Hawkhead
Road in Paisley and Johnstone South West (amongst others) have kept
completions at a relatively high level. 
3.11 The table below illustrates the annual total new build completions by year since
2012. Full analysis of Renfrewshire’s housing land supply on a site-by-site basis
is available in the annually published Housing Land Audit.  
YEAR OWNER
OCCUPIED
PRIVATE
RENTED
COMBINED
LA/SOCIAL
HOUSING
ANNUAL TOTAL
NEW HOUSING
COMPLETIONS 
2012-13 251 0 173 424
2013-14 313 0 210 532
2014-15 517 0 26 543
2015-16 577 0 101 678
2016-17 643 0 167 810
2017-18 601 0 107 708
2018-19 784 0 175 959
2019-21 1,383 0 324 1,707
2021-22 572 0 222 794
2022-23 422 0 195 617
Total 5,812 0 1,527 7,348
Annual average
(10 years)  581 0 153 734 
4. Current Context 
Renfrewshire school capacity 
4.1 Current school rolls at each of Renfrewshire’s 62 primary and secondary schools
are published by Renfrewshire Council on an annual basis. School rolls are
regularly updated by the Council and published online to allow for this policy to
reflect the latest circumstances in the assessment of planning applications.
Calculations of developer contributions will be based on the latest published
information of school rolls and capacity.

Page 11

4.2 Each residential property which is located within Renfrewshire has a ‘catchment’
for denominational and non-denominational primary and secondary school
assigned to it. This is determined by the geographical location of the property
and each school’s delineated catchment area in which the property is located. 
4.3 Although the Council aims to provide enough places for all children at the
preferred catchment primary and secondary school, living within the delineated
catchment area of a school does not guarantee a child a place at a catchment
school. 
Operational school capacity 
4.4 The “operational capacity” of a school is considered by Renfrewshire Council to
be reached when it is at 85% of its original design capacity. This is taken as the
same for all schools, regardless of denomination, location, and scale. The
rationale for 85% in the Renfrewshire context is that flexibility is required in each
school to plan accommodation across all year groups and allow for sufficient
communal and circulation space.   
4.5 The design capacity is used by Renfrewshire Council as the benchmark as, over
time, changes have been made to the operational configuration of schools which
may not align with the original design purpose of that space. For example, this
could have been to meet a short-term requirement for cohorts in a particular year
group. The calculation of capacity for the purposes of this policy will be made on
the original intended purpose of spaces rather than necessarily their current use.
Guidance will be sought from the Council’s Director of Children’s Services and
the school’s headteacher in this regard. 
4.6 Renfrewshire Council prepares 7-year rolling forecasts for the number of pupils
expected at each of its primary and secondary schools. This is based upon
anticipated pupil journeys through the school estate and also the range of
planned housebuilding expected to take place across Renfrewshire in this time
period. Renfrewshire Council have also utilised the expertise of external
consultants to advise on school roll forecasting. 
4.7 The 85% operational capacity, together with school roll forecasting, enables the
Council to produce a “RAG” (red / amber / green) status for each Renfrewshire
school in relation to planned new housing development as set out in the
published Housing Land Audit. It should be noted that the timescale for the
building of this identified housing supply is by no means certain or guaranteed.
These % capacities will therefore be kept under regular review by the local
authority. 
4.8 It should be borne in mind that the Council’s forecast school rolls do not account
for any “windfall” housing sites (see definition below) that may emerge during the
period. The Council reserve the opportunity to update these % capacity forecasts
for individual schools as new information on such windfall sites becomes
available.

Page 12

Windfall housing site (definition) – a site, which is granted planning
permission for housing development which, at the time of that decision, was
not identified as part of the housing land supply in either the Council’s Local
Development Plan or Housing Land Audit 
Insert link to online source of information on individual school capacities 
Currently planned school investment 
4.9 The Council’s Learning Estate Management Plan provides further details on
planned future investments in Renfrewshire schools. This Plan, in turn, will be
reflected in the Council’s Capital Programme which is published annually. 
4.10 At present the education school investment projects reflects the published
Capital Programme (for year 2024 / 25). The specific timing for the delivery of
each of these projects will be updated in each Capital Programme publication. 
4.11 Some of the school investments will be made in the knowledge that contributions
will be sought towards the total cost. Although the Council may be anticipating
making capital investment in its school estate, this will be in anticipation of
additional impacts from new housebuilding and therefore the expectation will be
that all such housebuilding, regardless of the specific context of the school and
its catchment, will be expected to meet the terms outlined in this guidance. 
Currently Planned Housing 
4.12 This guidance seeks to take account of all known housing sites within
Renfrewshire and as such the accompanying map indicates approximate
locations for residential sites (greater than 10 units) which are allocated within
the Local Development Plan, benefit from planning permission or appear in the
Council’s published annual Housing Land Audit. More details of each are
included in the listed documents which are available on the Council’s website. 
4.13 As outlined elsewhere in this guidance, the Council is unable to anticipate all
housing development. “Windfall” sites will occur.  The Council reserve the
opportunity to amend calculations within this guidance because of these
unknown sites emerging and being proposed for housing development. Should
they be granted planning permission they will be expected to contribute
financially in line with the approved guidance.

Page 13

5. Calculating the Financial Contribution 
Pupil Product Ratio 
5.1 The pupil product ratio (PPR) is a commonly used calculation to demonstrate the
number of pupils likely to be generated by new housing.  Most local authorities
in Scotland use a PPR in determining the level of education development
contribution for policies of this type. 
5.2 Renfrewshire Council has based its PPR (see below) on evidence from research
into housing developments over recent years (2010 -2023). 
5.3 Differentiation is drawn between flats and houses. This is because flats will
generally have fewer bedrooms and therefore less pupils likely to be living at
each address than compared to typical houses. 
Age group Type of school Pupil Product Ratio per new
home  
Houses Flats
Primary schools Denominational 0.090 0.018
Non-
Denominational
0.250 0.050
Total  0.340 0.068    
Secondary schools Denominational 0.052 0.018
Non-
Denominational
0.135 0.027
Total  0.187 0.045

Page 14

5.4 As illustrated in the example below, impact will be measured across all 4 principal
school types for each proposed residential development. This will occur at the
time of a planning application being considered by the Council. In any instances
where the pupils generated by the new housing would cause the operational
capacity threshold to be met or exceeded, a developer contribution will be sought
from that application. 
5.5 In applying such a policy, it should be borne in mind by applicants that a
contribution could be required to all 4 school types in a particular location, or as
few as 1 school type contribution, may be required depending on the current
capacities of these schools and the calculated number of additional pupils that 
particular development will generate (see also “cumulative effect in same
catchment” section of this guidance). 
5.6 The PPR values will be reviewed by the Council (and updated if necessary) every
2 years following the adoption of this revised policy. 
PPR - Worked example 
5.7 The table below illustrates the calculation of PPR for a planning application for
50 new homes, made up of 30 houses and 20 flats. 
5.8 These additional pupil numbers would then be assessed against the predicted
school rolls and capacities for the schools in the relevant catchment. 
Age group Type of school Estimated number of pupils
generated from new residential
development  
Houses (#30) Flats (#20)
Primary schools Denominational 2.70 0.36
Non-
Denominational
7.50 1.00    
Secondary schools Denominational 1.56 0.36
Non-
Denominational
4.05 0.54 
Cumulative effect of multiple applications in same catchment 
5.9 Each planning application will be assessed individually and on its own merits
against the context at the time that the application is submitted and validated by
the Council. 
5.10 In considering any planning application submitted, the baseline will be
considered as being all new homes consented at that time and all proposed
homes on allocated housing sites in that catchment.

Page 15

The Council will assume that all such homes consented and allocated will be built
as planned in the timescales estimated (as detailed in the Housing Land Audit).
Council officers responsible for monitoring housing land supply will be involved
in assessing cumulative impact, as will colleagues in Children’s Services in terms
of real time changes in school enrolments. 
5.11 The practical implication of this is that the school roll forecast will be updated
annually by the Council, and this will affect planning applications not yet
determined. Those making planning applications for residential development are
therefore encouraged to engage at an early stage in the process. 
5.12 The Council will be able to discuss the implications of this cumulative effect for
the calculation of an individual developer contribution with any prospective
applicant. 
Approach to assessing planning applications for new housing 
5.13 If 9 or less homes proposed then no developer contribution is required unless, in
combination with other identified housing sites in that catchment, the operational
capacity of the school in question would be increased above 85% by the delivery
of this development. 
5.14 If 10 or more homes proposed then: 
i. PPR calculated for that new housing development across all four school
types;
ii. Estimates (in discussion with housebuilders) on delivery timescale of homes
(by year);
iii. For each additional pupil generated (over and above the operational capacity
of schools in that catchment, taking into account the cumulative effect of all
proposed housing in that catchment), applicant will be expected to contribute
the per additional pupil amount set out in this guidance;
iv. Consideration given to whether physical extension may be required to
schools within the catchment because of the new housebuilding;
v. Consideration as to whether physical extension is achievable at schools
concerned;
vi. Calculation of cost of extension to school (based on recent Renfrewshire
examples) 
5.15 If number of proposed housing units is not defined in planning application [eg.
through an application for planning permission in principle] then: 
i. Estimate of numbers based on location, site characteristics and size of site;
ii. Average number of bedrooms per unit estimated to calculate predicted PPR;
iii. Process outlined above (depending on size of site) is followed;

Page 16

New school required because of new housing development 
5.16 The approach set out in this guidance does not preclude specific contexts where
large scale housing allocations may require new school provision as part of the
future community facilities planning for that location. If this is the case this will be
set out clearly in the Council’s LDP and its Learning Estate Management Plan in
advance of any planning application being considered for that site. 
5.17 The situation may arise in terms of future housing development, as it did recently
in Renfrewshire with the Dargavel Masterplan, where a new school needs to be
provided to meet the demand from additional pupils resulting from new housing
being built. The size of site required for a new school is very much dependent on
the proposed capacity of that school and therefore cannot be determined in
advance. 
5.18 The context for this, the policy approach and the expectations from the
developers involved (including land requirements and the respective values
attributed to that) will be set out in full in the Renfrewshire LDP and its associated
documents when they are published. 
Figure 1: Diagram showing the decision process once a planning application
is received.

Page 17

5.19 It should be noted that there will operational maximums for the number of pupils
any school will be able to accommodate, even with physical extension or
replacement by new school. This will be determined by Renfrewshire Council’s
Director of Children’s Services. 
Developer Contribution per pupil 
5.20 Renfrewshire Council has taken the approach to negotiate for requisite developer
contributions on a per additional pupil basis. The Council believe this is fairest
way to calculate any contribution, as opposed to using a per housing unit basis,
as it allows the Council to monitor contributions and estimates of capacity impact
against the number of pupils which eventually transpire for the relevant schools.   
5.21 The Council have utilised several sources to assist in calculating the proposed
developer contribution rate per pupil from new housing developments set out in
this guidance, including: 
 Recent new school developments in Renfrewshire – both new build and
extensions;
 Planned school investments in Renfrewshire;
 Scottish Futures Trust’s evidence base of school building costs; 
 Developer contributions sought by other Scottish local authorities in the most
up-to-date examples of such planning policies;
 Discussions with HubCo West on their data of school construction costs in
recent years; 
5.22 Based on these sources of evidence, the developer contributions which
Renfrewshire Council will be seeking from all new housing development (that
meet the terms of this guidance) and which trigger the capacity thresholds in the
relevant school catchments is as follows: 
School type Primary school Secondary school
Level of contribution per
pupil
£56,000 £56,000 
5.23 In terms of the level of contribution it should be noted by applicants this
contribution level is stated as at (insert month) 2024 and any required changes
to this amount will be indexed linked in line with BCIS costs at (insert quarter)
2024. 
5.24 The Council reserve the ability, depending on the scale of the residential
development proposed, to seek phased payments of the required contribution
linked to thresholds reached in terms of new housing units built over time. This
will be negotiated with the applicant at the time of the S75 being agreed.

Page 18

Where developer contributions will be used 
5.25 Developer contributions associated with this policy will be utilised to overcome
the impact in the specific catchment concerned from the increased number of
primary and secondary school pupils generated by new housing development. 
5.26 There may be school specific factors, such as space, and quality of ancillary
accommodation, which mean increasing capacity is not a practical solution. If it
is technically impossible to provide extra capacity, the Council may resolve the
issue using suspensive conditions to control the phasing of development or may
refuse planning permission. 
Exceptions to this policy 
5.27 All proposals relating to planning applications which result in new residential
units will be assessed against the policies outlined. 
5.28 Exceptions to the policy will be applied as follows: 
 Proposals for extending or altering existing residential dwellings; 
 Proposals which would not result in an increase in the number of residential
units; 
 Development proposals which involve nine residential units or less (unless,
in combination with other identified housing sites in that catchment, the
operational capacity of the school in question would be increased above
85% by the planned delivery of all proposed development); 
 Proposals involving one-bedroom dwellings; 
 Proposals for housing specifically aimed at an older demographic resident; 
 Proposals relating to student accommodation; 
 Proposals relating to sheltered accommodation, care homes or housing
designated for older age groups; and 
 Proposals where a Viability Assessment has been submitted and
independently verified and where Elected Members approve the
development. 
5.29 This list of exceptions will be kept under review by the Council and any changes
dealt with in future versions of the policy guidance.

Page 19

Viability Assessments 
5.30 Circular 3/2012 notes that the economic viability of proposals should be taken
into consideration when applying developer obligations and alternative solutions
should be considered including options of phasing or staging payments. 
5.31 The Council’s requirements from a viability assessment submitted by an
applicant for planning permission for residential is set out in Appendix 1. 
5.32 Please note this will only be applicable for planning applicants who wish to make
the case that the payment of a developer contribution would impact the financial
viability of the development in question. The applicant should bring this matter to
the attention of the Council’s Planning Team at the earliest opportunity. 
5.33 In all circumstances where a viability assessment has been undertaken,
determination of the application will be the responsibility of the Planning and
Climate Change Policy Board (or equivalent).   
6. Legal Agreements 
6.1 Developer contributions generally require applicants to enter into legally binding
contracts, or obligations with the local authority.  In line with this guidance,
planning permission will not be granted until the relevant legal agreement has
been concluded. The development should not commence until the decision
notice has been released for the relevant planning application by Renfrewshire
Council. 
Section 75 Agreements (S75) 
6.2 Following the Council’s decision to grant planning permission, planning officers,
together with legal colleagues, will finalise discussions in relation to seeking to
agree the terms of a S75 legal agreement. It is anticipated that the broad terms
of any agreement will have been discussed with the applicant before a decision
is reached. 
6.3 The S75 legal agreement requires to either be registered in the Land Register,
or acknowledgement has been received from the Keeper of the Register, prior to
the release of the Council’s application decision notice. 
6.4 In cases where the planning application relates to planning permission in
principle, depending on circumstances, the following process will be followed: 
 Where the planning permission in principle application outlines the number
of residential units, the application will be assessed, and any contributions
determined on the stated number of units.  The S.75 agreement will
thereafter secure the identified contribution noting the number of units
approved.

Page 20

 In circumstances where the planning permission in principle application
does not outline the number of residential units, the S.75 agreement will set
out the principles that will be applied to calculate the level of applicable
contribution in line with this guidance 
Section 69 Agreements 
6.5 In certain circumstances it may be appropriate for development contributions to
be secured via a Section 69 (S69) agreement.  This would be paid in full in one
instalment prior to planning permission being issued. There is no need to register
a S69 agreement as a burden against the land title. 
6.6 In the event that a contribution has been paid in respect of a S69 agreement, and
the proposed development does not go ahead, the Council will not return the
contribution if it has already been spent or committed for the purposes collected
within the timeframes agreed.  
Return of unused contributions 
6.7 All Section 75 agreements will be entered into in favour of the Council on the
expectation of having fifteen (15) years to expend the contribution received. 
Thereafter should contribution remain unspent, the contribution will be returned
to the applicant following a request from the applicant. This timescale reflects the
timescale taken to deliver larger housing sites and the resultant impacts on
school capacity that may be required. 
6.8 For developments involving phased payment of developer obligations the 15-
year period for spending contributions shall commence on the date that the final
phased payment is made to the Council. 
6.9 In the event of the contribution, or part of it, not being spent within this time period,
the contribution, or part of it, will be refunded to the applicant or their nominee
along with relative interest accrued. 
Contact 
7.1 For further information or to arrange a discussion in relation to developer
contributions, in the first instance please email dc@renfrewshire.gov.uk.

Page 21

APPENDIX 1 
Viability Assessments 
o Circular 3/2012 notes that the economic viability of proposals should be taken
into consideration when applying developer obligations and alternative
solutions should be considered alongside options of phasing or staging
payments. 
o The Planning Authority will give consideration to altering the levels or payment
structure of any planning obligations as part of financial contributions in the
interests of maintaining overall development viability.     
o In the event that the applicant considers that the payment of a developer
contribution would impact the financial viability of the development in question,
the applicant should bring this matter to the attention of the Planning Authority
at the earliest opportunity. 
o In such circumstances, the applicant will require to submit a Viability
Statement including ‘open book accounting’ of the proposed development. 
o The submitted Viability Statement will be evaluated and assessed by the
District Valuer in order to provide an independent view of the viability of the
proposed development. 
o The evaluation and assessment of any submitted Viability Statement will be
instructed by the Planning Authority; however, it should be noted that any
costs associated with undertaking the assessment will be recovered in full
from the applicant.   
o Thereafter the opinion of the District Valuer will form a material consideration
in the processing and determination of the planning application in question.   
o It should be noted that while Viability Statements will be treated as
confidential, full details of contributions, including an indication of the scale of
any agreed reductions will be reported to members of the Planning and
Climate Change Policy Board via the Report of Handling. 
o In all circumstances where a viability assessment has been undertaken,
determination of the application will be the responsibility of the Planning and
Climate Change Policy Board.