Notice of Meeting and Agenda
Planning and Climate Change Policy Board 
Date Time  Venue
Tuesday, 23 January
2024
13:00 Council Chambers (Renfrewshire),
Council Headquarters, Renfrewshire
House, Cotton Street, Paisley, PA1 1AN 
MARK CONAGHAN
Head of Corporate Governance 
Membership 
Councillor Jim Paterson (Convener):     Councillor Bruce MacFarlane (Depute
Convener):    
Councillor Jennifer Adam:  Councillor Alison  Ann-Dowling:  Councillor Andy Doig: 
Councillor Chris Gilmour:  Councillor Neill Graham:  Councillor Anne Hannigan: 
Councillor Kenny MacLaren:  Councillor Jamie McGuire:  Councillor Marie McGurk: 
Councillor John McNaughtan:  Councillor Iain Nicolson:  Councillor John Shaw: 
Councillor Ben Smith:   
Hybrid Meeting 
Please note that this meeting is scheduled to be held in the Council
Chambers.  However, it is a hybrid meeting and arrangements have been made for
members to join the meeting remotely should they wish. 
Further Information 
This is a meeting which is open to members of the public. 
A copy of the agenda and reports for this meeting will be available for inspection prior
to the meeting at the Customer Service Centre, Renfrewshire House, Cotton Street,
Paisley and online
at http://renfrewshire.cmis.uk.com/renfrewshire/CouncilandBoards.aspx
For further information, please email
democratic-services@renfrewshire.gov.uk

Page 2

Members of the Press and Public 
Members of the press and public wishing to attend the meeting should report to the
customer service centre where they will be met and directed to the meeting. 
Webcasting of Meeting 
This meeting will be filmed for live or subsequent broadcast via the Council’s internet
site – at the start of the meeting the Convener will confirm if all or part of the meeting
is being filmed.  To find the webcast please navigate to 
https://renfrewshire.public-i.tv/core/portal/home

Page 3

Apologies 
Apologies from members. 
Declarations of Interest and Transparency Statements 
Members are asked to declare an interest or make a
transparency statement in any item(s) on the agenda and to
provide a brief explanation of the nature of the interest or the
transparency statement. 
Finance 
1 Revenue and Capital Budget Monitoring Report 
Joint report by Chief Executive and Director of Finance &
Resources. 
1 - 6 
Climate Change 
2 Renfrewshire’s Local Heat and Energy Efficiency
Strategy 
Report by Director of Environment, Housing & Infrastructure.
(A suite of maps will be provided to accompany this report as
soon as possible) 
7 - 72 
Development Management 
3 Tree Preservation Order Requests 
Report by Chief Executive. 
73 - 78 
4 Developer Contributions (Education) - key metrics 
Report by Chief Executive. 
79 - 86  
Planning Applications 
Members must deal with planning applications in an objective
manner to ensure that they cannot be challenged with
accusations of bias or predetermination. Votes on planning

Page 4

applications must be seen to be impartial and not influenced by
party political issues. 
5 Planning Applications 
List of planning applications to be determined by the Board. 
87 - 88 
5(a)  23/0112/PP: Erection of residential development
comprising of eight flats with associated access,
parking, bin store, boundary treatment and
landscaping at 74 Fulbar Street, Renfrew, PA4 8PB by
Mr B Lees. 
Report by Chief Executive. 
89 - 106 
5(b)  23/0283/PP - Erection of a secondary school and
community campus with associated external amenities
including landscaping, access, parking and sports
pitches at 111-113 Renfrew Road, Paisley PA3 4 DY by
Renfrewshire Council. 
Report by Chief Executive. 
107 - 124 
5(c)  23/0504/LB - Installation of replacement windows and
door, solar panels, two ramps, railings, cladding and a
false floor.  Erection of extension; formation of window
and door openings; renewal of roof; stonework repairs;
internal alterations and landscaping works at S Block,
University of West of Scotland, Storie Street Paisley
PA1 2BX by the University of the West of Scotland. 
Report by Chief Executive. 
125 - 132 
5(d)  23/0505/PP - Installation of replacement windows and
door, solar panels, two ramps, railings, cladding and a
false floor.  Erection of extension; formation of window
and door openings; renewal of roof; stonework repairs;
internal alterations and landscaping works at S Block,
University of the West of Scotland, Storie Street,
Paisley PA1 2BXby the University of the West of
Scotland. 
Report by Chief Executive. 
133 - 140

Page 5

No embedded text on this page.

Page 6

No embedded text on this page.

Page 7

To: Planning and Climate Change Policy Board
On: 23 January 2024
Report by:  Chief Executive and Director of Finance and Resources
Heading:  Revenue and Capital Budget Monitoring as at 10 November 2023
1. Summary of Financial Position
1.1. The projected revenue outturn at 31 March 2024 for those services reporting
to the Planning and Climate Change Policy Board is an overspend position of
£0.035 million (5.6%). 
1.2. This is summarised in the table below and further analysis is provided in the
Appendices. 
1.3. There are no capital projects reporting to the Planning and Climate Change
Policy Board. 
2. Recommendations
2.1. Members are requested to:
(a) Note the projected revenue outturn position in Table 1 above; and  
(b) Note the budget adjustments detailed at section 4. 
3. Revenue
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
overspend of £0.035 million (5.6% of total budget) for all services reporting to
Table 1
Revised
Annual
Budget
£000
Projected
Annual
Outturn
£000
Budget
Variance
(Adv) / Fav
£000
Budget
Variance 
%
Planning Services 625 660 (35) (5.6)
Item 1
PACC230124 Page 1 of 140

Page 8

this Policy Board.  Detailed division service reports can also be found here,
together with an explanation of any significant projected variances.
3.2. The projected outturn is based on information currently available, and
assumptions made by service budget holders.  Any changes to these
projections will be detailed in future reports to the Board.
3.3. The main reasons for the projected outturn position are indicated below the
tables showing both the subjective analysis (what the budget is spent on) and
the objective analysis (which division is spending the budget).
3.4. The projected overspend position reflects the net effect of two main factors,
being a projected under-recovery in fee income (see 3.5), offset by a
projected underspend in employee costs due to the expected impact of staff
turnover over the course of the financial year. 
3.5. Due to the very demand-led nature of the income stream, which is impacted
by the economic and financial climate, the level of Planning and Building
Standards income can vary over the course of the financial year, which can
make it challenging to determine trends for income projection. The
projections, mid-way through the third quarter of the financial year, currently
indicate an expected over-recovery in Planning fees and an under-recovery in
Building Standards fees and reflect a reasonable forecast at this stage in the
financial year.
4. Revenue Budget Adjustments
4.1. No budget adjustments have been processed since the previous report to
board. 
__________________________________________________________________
Implications of this report 
1.  Financial – The projected budget outturn position for the revenue budget
reported to the Planning and Climate Change Board is an overspend of
£0.035 million. Income and expenditure will continue to be monitored
closely for the rest of the financial year and any changes to current
projections in Revenue budgets will be reported to the board as early as
possible, along with an explanation for the movement.
2.  HR and Organisational Development 
None directly arising from this report.
3. Community/Council Planning
None directly arising from this report.
4.  Legal 
None directly arising from this report.
Page 2 of 140

Page 9

5.  Property/Assets 
None directly arising from this report.
6.  Information Technology 
None directly arising from this report.
7.  Equality and Human Rights 
None directly arising from this report.
8. Health and Safety
None directly arising from this report.
9. Procurement 
None directly arising from this report.
10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors.
11. Privacy Impact
None directly arising from this report.
12. 
13.
Cosla Policy Position 
N/a.
Climate Risk
None directly arising from this report.
__________________________________________________________________
List of Background Papers: None
__________________________________________________________________ 
Author: Valerie Howie, Finance Business Partner
Page 3 of 140

Page 10

Appendix 1   
Objective Summary
Annual
Budget at
Period 6
Budget
Adjustments
Revised
Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Planning Strategy & Place 557 0 557 521 36 6.5% 12 24
Development Management 234 0 234 85 149 63.7% 136 13
Building Standards (166) 0 (166) 54 (220) (132.5%) (169) (51)
NET EXPENDITURE 625 0 625 660 (35) (5.6%) (21) (14)
Objective Heading Key Reasons for Projected Variance
Planning Strategy & Place
Development Management
Building Standards
No significant projected year end variances to report.
The projected underspend relates mainly to a projected over-recovery in Planning fee income (c. 11.5% of targeted
income).
The projected overspend relates mainly to a projected under-recovery in Building Standards fee income (c. 26.5% of
targeted income).
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 10 November 2023
Budget Variance
(Adverse) or Favourable
POLICY BOARD :  PLANNING SERVICES
Page 4 of 140

Page 11

Appendix 1   
Subjective Summary
Annual
Budget at
Period 6
Budget
Adjustments
Revised
Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 1,620 17 1,637 1,474 163 10.0% 101 62
Premises Related 1 0 1 1 0 0.0% 0 0
Transport Related 15 0 15 15 0 0.0% 0 0
Supplies and Services 180 0 180 182 (2) (1.1%) (2) 0
Transfer Payments 102 0 102 101 1 1.0% 0 1
Support Services 317 0 317 317 0 0.0% 0 0
GROSS EXPENDITURE 2,235 17 2,252 2,090 162 7.2% 99 63
Income (1,610) (17) (1,627) (1,430) (197) (12.1%) (120) (77)
NET EXPENDITURE 625 0 625 660 (35) (5.6%) (21) (14)
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 10 November 2023
POLICY BOARD :  PLANNING SERVICES
Page 5 of 140

Page 12

Page 6 of 140

Page 13

___________________________________________________________________
To:  Planning and Climate Change Policy Board 
On:  23 January 2024
___________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Renfrewshire’s Local Heat and Energy Efficiency Strategy
___________________________________________________________________    
1. Summary 
1.1 Reducing carbon emissions is one of the principle measures to address climate
change and is a key priority for all Local Authorities. Renfrewshire Council recognises
that climate change will have far reaching effects on Renfrewshire’s economy, its
people and its environment and is determined to lead by example in tackling the
causes of climate change. 
1.2 Renfrewshire Council declared a climate emergency in June 2019 and approved the
Plan for Net Zero in August 2022, which committed to working towards net zero by
2030 for both the Renfrewshire area as a whole and Renfrewshire Council as an
organisation. This challenging target covers all aspects of energy use within the
Renfrewshire wide area. Homeowners can help achieve these targets by ensuring
energy efficient homes. In doing so, there are many long-term benefits, such as
carbon savings, reducing energy bills and supporting the local economy. 
1.3 In 2022, the Scottish Parliament passed The Local Heat and Energy Efficiencies
(Scotland) Order 2022. This places a statutory duty on Local authorities to publish a
Local Heat and Energy Efficiency Strategy (LHEES) and Delivery Plan, and for these
to be updated at intervals of no more than 5 years. 
1.4 LHEES are designed to be local authority-led, however stakeholder engagement and
partnership working are key as the Strategy addresses all building stock at a local
authority wide level (Council, public, private, 3rd sector and all tenures of residents). 
1.5 Renfrewshire’s LHEES designates the most appropriate energy efficiency and heat
decarbonisation options on an authority-wide basis, broken down into area-based
schemes (or zones) with a focus on two key priorities of reducing carbon emissions
and alleviation of fuel poverty. 
1.6 Renfrewshire’s LHEES is evidence-driven, based on local data and local knowledge
and takes into account assets and infrastructure within each local area to ensure
potential solutions are tailored to the different issues, opportunities and needs across
Renfrewshire’s communities. 
Item 2
PACC230124 Page 7 of 140

Page 14

1.7 It is hoped that LHEES will also act as a prospectus for government funding and
external investment using a robust evidence base and place-based approach. 
1.8 Renfrewshire’s Local Heat and Energy Efficiency Strategy is being presented for
approval at the Infrastructure, Land and Environment Policy Board on 24th January
2024. As part of horizon scanning, Officers are highlighting this Strategy for Members
to note due to the clear links with climate change.
___________________________________________________________________
2.  Recommendations 
It is recommended that members of the Planning and Climate Change Policy Board: 
2.1 note the high-level information available at this time on Renfrewshire’s Local Heat
and Energy Efficiency Strategy; and 
2.2 note that updates will be provided to the relevant Policy Boards on the further
development of the Delivery Plans, outlining potential opportunities and proposed
projects, activities and interventions.
___________________________________________________________________    
3.  Background 
3.1 In addition to Scotland’s net zero targets, there are strategic national targets relating
to lowering emissions from our buildings through the decarbonisation of heat. These
targets are: 
• improving energy efficiency in domestic and non-domestic building stock; 
• removing poor energy efficiency as a driver for fuel poverty; 
• and in 2040, as far as reasonably practicable, no household is in fuel poverty. 
Clean Energy is one of the 5 focus areas as approved within Renfrewshire’s Plan for
Net Zero which aligns with these targets at a local level. 
3.2 LHEES are designed to be local authority-led – and buildings and assets owned by
the Council are key - but stakeholder engagement and partnership working are
critical as the Strategy addresses all building stock at a local authority wide level
(Council, public, private, 3rd sector and all tenures of residents). Engagement has
been undertaken throughout the development of Renfrewshire’s LHEES, as part of
the wider Plan for Net Zero engagement due to the links between the two key
strategies. 
3.3 ‘Place’ is a key aspect of LHEES. Renfrewshire’s LHEES designates the most
appropriate energy efficiency and heat decarbonisation options on an authority-wide
basis, broken down sufficiently into appropriate area-based schemes (or zones) with
a focus on two key priorities of reducing carbon emissions and alleviation of fuel
poverty. 
3.4 The LHEES is evidence-driven, based on local data and local knowledge and takes
into account assets and infrastructure within each local area, to ensure potential
solutions are tailored to reflect each local area and address the different issues,
opportunities and needs across Renfrewshire’s communities (e.g. urban and rural;
gas grid and off gas grid). 
Page 8 of 140

Page 15

3.5 Development of Renfrewshire’s LHEES (and the subsequent Delivery Plans)
includes identifying: 
• a range of projects and actions to be developed, with outline costs and
carbon savings associated with the proposed interventions
• the different drivers for fuel poverty across different local areas and within
communities
• key anchor loads for potential district heating networks (including public
buildings and buildings with a high heat demand) 
• an assessment of potential large-scale heat supply – not just looking at new
infrastructure but also using existing infrastructure and assets (such as water
sources) and innovative methods of waste heat recovery, such as those used
in the AMIDS district heating network in Renfrewshire
• opportunities for partnership working and engaging with all key stakeholders
throughout the process. 
4.  LHEES Outcomes 
4.1 The development of Local Heat and Energy Efficiency Strategies aims to: 
• ensure a clear and enhanced role for local authorities in shaping local energy
systems, highlighting the long-term direction of travel with a short-term focus,
• bring together stakeholders to identify opportunities based on targeted local
needs and potential for economies of scale – this includes identification and
optimisation of cross-border opportunities with neighbouring local authorities,
• develop a data-driven foundation for delivery programmes to meet fuel
poverty, energy efficiency and heat decarbonisation targets,
• focus on socio-economic benefits of solutions as well as project-specific
financial cases, and
• send clear investment signals to develop strong and sustainable supply chain
opportunities for local businesses, through a pipeline of infrastructure
projects. 
4.2 In addition, it is hoped that as well as helping to phase the area-based delivery
programmes, LHEES will act as a prospectus for government funding and external
investment using a robust evidence base and place-based approach. 
Implications of the Report 
1. Financial – No current implications as this report is for noting. Delivery of the LHEES
will have resource implications for the Council and includes a commitment to working
collaboratively to ensure best value for our approach. As noted in 2.1, as the full
extent of the resource implications for Renfrewshire Council emerge, reports will be
brought to the relevant future Policy Boards.  
2. HR & Organisational Development – No current implications. 
Page 9 of 140

Page 16

3. Community/Council Planning – No current implications as this report is for noting.
However, delivery of Renfrewshire’s LHEES will require engagement and
collaboration with local residents, businesses, partners and communities on the
climate emergency agenda and the Delivery Plan will highlight the continued
activities which support the key priorities set out in the Council and Community Plans
to tackle inequality and widen opportunity.   
4. Legal - No current implications as this report is for noting. However, future actions
may have some level of implication. 
5. Property/Assets - No current implications as this report is for noting. However,
delivery of Renfrewshire’s LHEES may have significant implications for property and
assets given the nature of the work involved. 
6. Information Technology – No current implications. 
7. Equality and Human Rights - The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights. No
negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in the
report because it is for noting only. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the Council’s
website.     
8. Health and Safety – No current implications. 
9.  Procurement – No current implications as this report is for noting. However, delivery
of Renfrewshire’s LHEES will have significant procurement implications given the
nature of the work involved. 
10. Risk – No current implications. 
11.  Privacy Impact – No current implications. 
12. COSLA Policy Position – Renfrewshire’s LHEES aligns with COSLA’s current work
alongside the Scottish Government in response to the climate emergency. 
13. Climate Risk – as noted in para 3.2, Renfrewshire’s LHEES aligns with
Renfrewshire’s Plan for Net Zero, specifically the Clean Energy theme.
___________________________________________________________________ 
List of Background Papers:
None
___________________________________________________________________ 
Author:   Roz Smith, Climate Emergency Lead Officer, Chief Executive’s Service
Page 10 of 140

Page 17

P a g e | 1
RENFREWSHIRE’S 
LOCAL HEAT & ENERGY EFFICIENCY STRATEGY (LHEES) 
Environment, Housing & Infrastructure 
Page 11 of 140

Page 18

P a g e | 2
Table of Contents
Executive Summary ............................................................................................................................................... 3
Introduction to Local Heat and Energy Efficiency Strategies (LHEES). ....................................................... 8
Renfrewshire’s Approach ................................................................................................... 12
National and Local Policy Drivers ..................................................................................... 14
Where are We Now? Energy Information and Statistics for Renfrewshire ................ 16
The 6 LHEES Stages ............................................................................................................. 19
LHEES Terminology – District Heating ............................................................................ 21
LHEES Terminology – Energy Efficiency Measures ....................................................... 24
Overview of Renfrewshire as a Whole: Fuel Poverty & Energy Efficiency. ................................................. 26
Fuel Poverty in Renfrewshire ............................................................................................. 28
Poor Building Energy Efficiency: What is Driving the Poor Energy Efficiency? ......... 32
Overview of the Opportunities for the Decarbonisation of Heat Across Renfrewshire – Potential for
Heat Networks  ................................................................................................................................................. 36
Overview of the Potential First Phase Priority Heat Network Zones ......................... 41
Overview of the Potential Second Phase Heat Network Zones.................................. 47
Additional Heat Decarbonisation Opportunities .......................................................... 51
Additional Considerations ................................................................................................. 54
Next Steps  ................................................................................................................................................. 56
Challenges and Opportunities .......................................................................................................................... 58
Appendices
Appendix 1 – Glossary of Terms ............................................................................................................................ 
Appendix 2 - National and Local Policy Drivers ................................................................................................. 
Appendix 3 – Energy Efficiency Maps (Larger Scale) ......................................................................................... 
Appendix 4 – Decarbonisation of Heat and Heat Network Maps (Larger Scale) ......................................... 
Appendix 5 – First Phase Priority Heat Network Zoning Maps (Larger Scale)    
Page 12 of 140

Page 19

P a g e | 3
Executive Summary 
From evidence and research, we know that human activities are the main cause of climate change. 
Many of our actions produce greenhouse gas emissions, raising the planet’s temperature and
causing our climate to change.  Greenhouse gas emissions from burning fossil fuels to heat homes
and buildings are a key contributor to global warming. In Renfrewshire, fuels for heating homes and
businesses make up 38% of the area’s total emissions. Decarbonisation of heat means reducing the
carbon emissions associated with our heating systems and switching to cleaner, more efficient
methods. Combined with improving energy efficiency to reduce energy demand, this will reduce
our emissions, ensure affordable warmth and help to alleviate fuel poverty. 
Scotland has ambitious plans to transform its buildings to ensure that by 2045 our homes and
buildings no longer contribute to climate change while also tackling fuel poverty. In 2022, the
Scottish Parliament passed The Local Heat and Energy Efficiencies (Scotland) Order 2022. This
places a statutory duty on local authorities to publish a Local Heat and Energy Efficiency Strategy
and Delivery Plan, to be updated at intervals of no more than 5 years. 
The Local Heat and Energy Efficiency Strategies (Scotland) Order 2022 defines that LHEES is a long-
term strategic framework for: 
• the improvement of the energy efficiency of buildings in the local authority’s area, and
• the reduction of greenhouse gas emissions resulting from the heating of such buildings. 
Renfrewshire Council has shown leadership at both strategic level and operational levels
to be adriver of change -declaring a climateemergency in June 2019
and committing to work towards net zero by 2030.
Our response to the climate emergency and a stable, managed energy transition alongside
improving energy efficiency to reduce demand, brings opportunities to transform our local
communities and economy.  It also brings opportunities to identify solutions to tackle inequalities
including those exacerbated by the current cost of living crisis, with 22% of households in
Renfrewshire currently in fuel poverty. 
Page 13 of 140

Page 20

P a g e | 4
Renfrewshire’s LHEES is ambitious and will require drive and collective local action. The Strategy is
Council-led but is for the whole Renfrewshire area and has been developed with local people and
key local, regional and national organisations, aligning with local and national policies as well as
targets within Renfrewshire’s Plan for Net Zero. 
Renfrewshire’s LHEES is built upon a robust evidence base of data and stakeholder engagement
and takes a place-based, locally led and tailored approach to set out a vision for improving energy
efficiency and heat decarbonisation. It breaks Renfrewshire down sufficiently into appropriate areas
(or zones) in order to consider local assets and issues and recognise local differences to identify
where projects can be delivered to make the biggest impact in our communities, making the best
use of assets and infrastructure to deliver net zero targets and affordable warmth. 
This strategic, area-based approach will ensure proposed solutions that reflect each local area and
take into account local distinctive needs, opportunities and priorities to encourage collaboration
and partnership working with all stakeholders within those areas: 
• People: engagement with all stakeholders at all stages to ensure the needs of all groups are
considered, with a focus on addressing inequalities, alleviating fuel poverty and ensuring
affordable warmth for all
• Places: solutions which reflect the local areas and take into account local assets and
infrastructure, developed with collaboration and partnership working so systems are developed
and tailored to local needs
• Infrastructure: ensuring resilient systems and security of supply, optimising existing
infrastructure and assets as well as new development, with a ‘whole system’ approach that
matches local demand with local supply where possible, taking an iterative approach to capture
new technologies and innovative solutions as well as scaling and replicating successful projects
• Investment: prioritising viable and replicable projects and identifying low regret options to
optimise low carbon investment opportunities - attracting private sector-led projects, public
sector exemplar opportunities, and external funding; coordinating and collaborating on joint
ventures; and identifying innovative delivery models to turn sectoral ambitions into investable
projects 
• Opportunities: inclusive growth with a role for community-led activity with all the local benefits
that brings, including regeneration of local areas; local job creation, upskilling and reskilling of
local workforce; and creating and developing local manufacturing and supply chains 
Page 14 of 140

Page 21

P a g e | 5
The development of Renfrewshire’s LHEES followed the national methodology, firstly reviewing
national and local policies, targets and strategies that are linked to, impact or could be impacted by
LHEES. A Data Library was then created, collating and verifying the most appropriate data to
support analysis for each stage of the LHEES process. 
Looking across buildings at a local authority wide level (Council, public, private and 3rd sector
buildings and all tenures of residents) enabled the development of strategic zones. These zones are
designed to set out the most appropriate energy efficiency and heat decarbonisation option,
including potential zones for heat networks, taking local priorities into account and framed around
the LHEES Considerations: 
- heat decarbonisation: heat decarbonisation of on-gas and off-gas buildings, including district
heating networks.
- energy efficiency: improving energy efficiency; removing poor energy efficiency as a driver for
fuel poverty; and mixed-tenure, mixed-use and historic buildings. 
Baselining the data looking at fuel poverty, energy efficiency and heat provided clarity on the
challenges; the key issues and activities to focus on; and the scale of action needed. Using mapping
with layers of data stacked spatially areas of focus were identified to be taken forward to the
Delivery Plan. High level findings showed: 
-Fuel Poverty: 12 of the 38 zones in Renfrewshire were above the national average fuel poverty of
24%, with the highest fuel poverty zone having 38% of households in fuel poverty. The 10 most
impacted areas are Paisley Ferguslie, Paisley Northwest, Linwood South, Paisley Gallowhill and
Hillington, Paisley North, Paisley Central, Paisley East, Johnstone Northwest, Paisley Foxbar and
Johnstone Northeast. 
The different factors that are driving fuel poverty – generally cost of energy; income; poor energy
efficiency; and/or use of energy will be analysed in greater detail in the Delivery Plans to ensure
tailored and targeted solutions. 
-Energy Efficiency: When looking at poor energy efficiency as a driver for fuel poverty, the top 10
most impacted areas was slightly different to the top 10 areas for fuel poverty. Paisley Central,
Paisley East, Paisley Northwest, Johnstone Northwest and Paisley North were in the top 10 for both
fuel poverty and for poor energy efficiency, suggesting that poor energy efficiency is one of the key
drivers for fuel poverty in these areas. 
Page 15 of 140

Page 22

P a g e | 6
More broadly, there were differences in energy efficiency across tenures (social housing, owner
occupier and private rented), with social housing having higher percentages of housing in the
higher bands of energy efficiency and the lowest percentages of housing in the lower bands of
energy efficiency. This highlighted areas and sectors where advice and support may be helpful. 
Properties that have poor energy efficiency are more likely to be eligible for targeted funding and
Delivery Plans will include an area-based energy efficiency focus outlining patterns and clusters to
assist funding bids.
-Potential Heat NetworkZones: district heating uses a single heat source to supply heating and hot
water to multiple buildings via a system of insulated, buried pipes. It is more efficient than
individual heating systems within each property and is likely to play a key role, including enabling
developers to capitalise on abundant sources of waste heat and divert to where it is required. 
Based on levels of heat demand, proximity to a heat source and presence of public buildings as
potential anchor loads for a network, 6 first phase heat network zones were identified in Central
Paisley, Shortroods and Laighpark, Lochfield and Charleston, Ferguslie Park, North Renfrew and
Moorpark and Newmains. A further 11 second phase heat network zones were also identified. All 17
will be explored further and details outlined in the Delivery Plans as well as additional opportunities
for areas with lower heat densities, including rural and smaller urban settlements in order to
identify the most beneficial heat solution for all our communities. 
Zoning across the area for viable large-scale and small-scale district heating and communal heating
networks will enable us to understand the scale and potential of these opportunities as part of the
Delivery Plans. 
-Additional Considerations: alternative heat solutions, including heat pumps, electricity and
biomass will be explored as well as impacts of conservation areas on energy efficiency measures to
ensure Delivery Plans include solutions for all residents and businesses, and all building types. 
The Delivery Plans will be developed in collaboration with residents, communities and all key
organisations to highlight opportunities for action for local communities, residents, businesses,
developers and wider stakeholders. 
Page 16 of 140

Page 23

P a g e | 7
There are challenges to be overcome, including financial; capacity; and skills gaps. However, by
identifying these challenges and setting out a pipeline of projects working alongside our
communities and partners we can link with skills transition and local employment opportunities
and identify skills gaps, shortages and requirements ahead of time to optimise local opportunities
as well as linking with funding opportunities and financial support schemes. 
It is hopedthat, as well as zoning helping to phasethe area-based deliveryprogrammes,
LHEES will act as a prospectus for government funding and external investment
and where these should be targeted.
Page 17 of 140

Page 24

P a g e | 8
Introduction To Local Heat & Energy Efficiency Strategies(LHEES)
LHEES sets out a long-term planwith an initial near-term focus looking at area-based interventions
for energy efficiency and decarbonisation of heat on a local authority-wide basis. 
In 2022, the Scottish Parliament passed The Local Heat and Energy Efficiencies (Scotland) Order
2022. This places a statutory duty on Local authorities to publish a Local Heat and Energy Efficiency
Strategy and Delivery Plan, and for these to be updated at intervals of no more than 5 years. 
The Local Heat and Energy Efficiency Strategies (Scotland) Order 2022 defines that a LHEES is a
long-term strategic framework for: 
• the improvement of the energy efficiency of buildings in the local authority’s area, and
• the reduction of greenhouse gas emissions resulting from the heating of such buildings. 
A Local Heat and Energy Efficiency Delivery Plan sets out how Renfrewshire proposes to support
implementation of its strategy. 
The guidance requires Local Heat and Energy Efficiency Strategies (LHEES) to be evidence based
and cover a local authority’s full building stock as far as reasonably possible. They should be
developed in collaboration with stakeholders and use extensive consultation and future updates
should be linked to any previous iteration to show progress achieved against outcomes and to carry
forward outstanding actions. In addition, the LHEES should demonstrate how it supports equality
and addresses inequality; be forward looking and delivery focused, working towards local and
national targets; and be open and transparent regarding data used, its associated limitations in
terms of scope, accuracy, and coverage, and be continuously reviewed with progress monitored. 
LHEES are at the heart of a place based, locally led and tailored approach to energy efficiency and
the heat transition. These local Strategies will underpin an area-based approach to heat and energy
efficiency planning and delivery. LHEES Strategies will set out the long-term plan for decarbonising
heat in all buildings and improving their energy efficiency across the Renfrewshire area. 
Page 18 of 140

Page 25

P a g e | 9
Local Heat and Energy Efficiency Strategies are primarily driven by Scotland’s statutory targets for
greenhouse gas emissions reduction and fuel poverty, but at a local level it is key Renfrewshire’s
LHEES to align with targets within Renfrewshire’s Plan for Net Zero as the strategy will play a crucial
role in working towards net zero by 2030 for the Renfrewshire area:
Key national targets include:
• Net zero emissions by 2045, 90% reduction by 2040 and 75% reduction by 2030
• In 2040, as far as reasonably possible, no household in Scotland is in fuel poverty
Key local targets withinRenfrewshire’s Plan for Net Zero which link with LHEES include:
• ensuring 100% of Council buildings heating requirements are carbon neutral by 2030.
• implementing measures in Council housing stock aiming to reduce carbon emissions by 68%
(from 2020 levels) and working towards ensuring all Council housing stock has an EPC of B by
2030 where feasible. 
The primary purpose of LHEES is to address energy and heat-related challenges while
promoting sustainability and reducing environmental impacts.
LHEES sets out a long term (20 year) with an initial near term (5 year) focus. For Renfrewshire, the
plan will: 
• set out how each segment of the building stock needs to change to meet national and local
objectives, including achieving zero greenhouse gas emissions in the building sector, and the
removal of poor energy efficiency as a driver of fuel poverty; 
• identify strategic heat decarbonisation zones, and set out the principal measures for reducing
buildings emissions within each zone; and  
• prioritise areas for delivery, against national and local priorities. 
LHEES will break the local authority area down sufficiently into appropriate local areas (or zones) in
order to consider local assets and issues and recognise the local differences (i.e., between rural vs
urban; gas grid vs off gas grid) so that proposed solutions reflect each local area and take into
account local distinctive needs, opportunities and priorities.  This will also encourage collaboration
and partnership working with all stakeholders within those areas so that solutions can be
community led. 
Page 19 of 140

Page 26

P a g e | 10
LHEES are framed around six ‘Considerations’ outlined in Table 1, below. For each Consideration,
spatial zones are to be generated to identify potential pathways to decarbonise the building stock
at local authority level (Strategic Zones) and then at delivery level (Delivery Areas). This will help to
guide the design of policy levers, such as advice, funding programmes and regulation, which will
give further direction and clarity to delivery routes and timescales. 
No. LHEES Consideration Description
1 Off-gas grid buildings Transitioning from heating oil
and LPG in off-gas areas
Heat decarbonisation 2  On-gas grid buildings On-gas grid heat
decarbonisation 
3 Heat networks Decarbonisation with heat
networks
4 Poor building energy
efficiency Poor building energy efficiency
Energy efficiency and
other outcomes 5
Poor building energy
efficiency as a driver for fuel
poverty
Poor building energy efficiency
as a driver for fuel poverty
6
Mixed-tenure, mixed-use and
historic buildings
Mixed-tenure, mixed-use
buildings, listed buildings, and
buildings in conservation areas
Table 1: LHEES Considerations 
Benefits and opportunities of Local Heat and Energy Efficiency Strategies include: 
• ensuring a clear and enhanced role for local authorities and local stakeholders in shaping
local energy systems. 
• bringing together all stakeholders to optimise opportunities based on targeted local needs,
potential for economies of scale.
• highlighting the long term direction of travel with a short term focus.
Page 20 of 140

Page 27

P a g e | 11
• sending clear investment signals to develop strong and sustainable supply chain
opportunities for Scottish businesses.
• focusing on socio-economic benefits of solutions and prioritises investment based on
weightings as well as project-specific financial cases.
• the potential to assist with large-scale funding bids, as well as to signpost residents and
businesses to impartial advice and support, including financial support schemes.
• a solid foundation for delivery programmes to meet fuel poverty, energy efficiency and heat
decarbonisation targets. 
A 5-year LHEES Delivery Plan, sufficiently broken down into specific areas, will be developed in
Phase 2 in partnership with key stakeholders to outline how the key outputs of the LHEES will be
achieved and to highlight opportunities for action for local communities, residents, businesses,
developers and wider stakeholders on an area-by-area basis and targeted interventions, projects
and early, low-regrets measures. 
Page 21 of 140

Page 28

P a g e | 12
Renfrewshire’s Approach
Arobust evidence base looking on an area-by-areabasis across Renfrewshire, combined with
engagement withkey stakeholders formed the foundation of the LHEES development. 
Developing Renfrewshire’s LHEES required a robust evidence base combining relevant data and
technical modelling and enhancing with local knowledge and engagement and input from local
stakeholders to optimise the strategy and ensure local needs are being met. There is a dual focus
on energy efficiency and heat decarbonisation – to make our homes and buildings warmer, greener
and more efficient – and recognition that it is key to remove poor energy efficiency as a driver for
fuel poverty. 
Renfrewshire Council worked in collaboration with external technical consultants Sweco UK Ltd as
well as our key stakeholders to ensure a structured approach that considers the unique
characteristics and needs of each of our communities in order to identify and tailor area-based
building energy efficiencies and low or zero carbon heating schemes (including potential heat
networks) across the Local Authority area. Due to the close links and crossovers between the two
key strategies, the engagement and consultations for Renfrewshire’s LHEES was carried out jointly
with engagement for Renfrewshire’s Plan for Net Zero and this joint approach will continue as the
strategies progress into the action and delivery phase. 
An internal Officers Working Group from across all key Service areas met regularly to discuss each
stage of the LHEES and ensure that policies, strategies, projects and programmes from across the
Council were being considered at each stage and opportunities to link, optimise or coordinate work
programmes were identified. 
Initial Stakeholder Engagement:
- CommunityClimate Conversation: the engagement process was designed for the community
voices to be heard first – listening to community priorities and project ideas, what people would
like to see in their local areas and barriers and challenges in order to find solutions. This
included the Clean Energy theme of the Plan for Net Zero and discussions linked to LHEES,
including decarbonisation of heat; improving energy efficiency; alleviation of fuel poverty and
removing poor energy efficiency as a driver for fuel poverty. A key theme that came through in
community engagement was that people were unsure where to start, help that is available and
what makes the biggest impact. Reducing the cost of energy, alleviating fuel poverty and
identifying community energy opportunities scored highly for energy priorities. 
Page 22 of 140

Page 29

P a g e | 13
- Key Stakeholder Organisation Event: with key local, regional and national organisations
including community planning partners; local housing associations; Scottish Power; Scottish
Gas; Scottish Water; and all 8 neighbouring authorities (57 attendees in total). This event built
on the community priorities and was designed to understand the key stakeholders’ influence
and their role in progressing to net zero as well as partnership working opportunities, including
potential for links across LHEES. This event helped us to: 
• gain an understanding of high-level projects being progressed across Renfrewshire and
wider Glasgow City Region
• bring partners together to identify and scope out new actions to move towards net zero.
• identify and target the challenges/problems collectively that we are all trying to solve. 
- Internal workshop: 70 Officers from across all Council Services looking at theme-specific project
examples, based on ideas from the community and stakeholder organisation events; and
projects from across Scotland. Groups scored against strategic fit, based on key outcomes (e.g.,
alleviation of fuel poverty; improving energy efficiency; reducing energy demand; renewable
energy generation, etc.); deliverability – incl. resources (pounds and people) and revenue
generating or cost saving potential; and additional opportunities looking at economic,
environmental and social impacts. Thinking not just of the carbon benefits of projects but all
the social benefits and opportunities as well as identifying challenges such as resources, risk
and skills gaps. 
Additional engagement includes with Scottish Government on LHEES development; engagement
with all 32 Local Authorities via a fortnightly LHEES Forum; and working with strategic partners such
as Scottish Futures Trust, Energy Savings Trust and Zero Waste Scotland to enhance each stage of
the process as the strategy was being developed. 
Engagement is an iterative process and will continue into the next phase of LHEES to build on
existing activities and identify new opportunities to accelerate change. Two-way communication
channels will remain in place as projects and activities are implemented to ensure everyone is
informed of progress and can provide feedback on our collective journey, with tailored engagement
and consultation at a local level on the proposed LHEES delivery plans.
Page 23 of 140

Page 30

P a g e | 14
National and Local Policy Drivers
The overarching legislation nationally is the Climate Change (Emissions Reduction Targets)
(Scotland) Act2019 which amended theClimate Change (Scotland) Act 2009. 
The overarching legislation nationally is the Climate Change (Emissions Reduction Targets)
(Scotland) Act 2019, which amended the Climate Change (Scotland) Act 2009.  This increased the
ambition to commit to net zero by 2045, with updated annual emissions targets and embeds the
principles of a just transition. 
Key national and local policies, targets and strategies that are linked to, impact, or could be impacted
by LHEES were identified and will be kept updated as legislation, policies, strategies and/or targets
emerge. The full list can be found in Appendix 2but includes: 
Key NationalPolicies:
Fuel Poverty (Targets, Definition and
Strategy) (Scotland) Act 2019
Sets targets relating to the eradication of fuel
poverty; to define fuel poverty; to require the
production of a fuel poverty strategy.
Housing to 2040
Sets out a vision for housing in Scotland to
2040 and a route map to get there.
Heat Networks (Scotland) Act 2021
Regulates heat networks, supporting
objectives in the Heat in Building Strategy to
grow heat network opportunities.
Climate Change (Emissions Reduction Targets)
(Scotland) Act 2019
Sets a 2045 net zero emissions target and
interim targets: 75% by 2030; and 90% by 2040.
Page 24 of 140

Page 31

P a g e | 15
Key Local Policies:
Renfrewshire Local Housing Strategy 2023-
2028
Sets out the strategic approach of the Council
and its partners to delivering high quality
housing and housing related services.
What is fuel poverty? In the Fuel Poverty (Targets, Definition and Strategy) (Scotland) Act
2019 a household is in fuel poverty if more than 10% of the household’s net income is
required to pay for their reasonable fuel needs to maintain an acceptable standard of
living after housing costs have been deducted. 
What is extreme fuel poverty? Where more than 20% of the income after housing costs is
spent on required fuel costs and there is insufficient residual income to maintain an
acceptable standard of living. 
The Scottish Government recognises 4 main drivers of fuel poverty: 
 energy prices
 income
 energy efficiency of the home
 how energy is used in the home 
The overarchingtarget in Scotland is that in the year 2040, asfar as reasonably
practicable, no household is in fuel poverty.
Renfrewshire Local Development Plan
Sets out the spatial strategy and proposals for
Renfrewshire over 
the next 10 years.
Council Plan – 2022-2027
The Council Plan sets out how the Council will
collaborate with partners, communities, and
business to progress our five strategic
outcomes.
Renfrewshire’s Plan for Net Zero
Developed in collaboration with all our
stakeholders, we are committed to working
towards net zero by 2030.
Page 25 of 140

Page 32

P a g e | 16
Where are we now? EnergyInformation & Statistics for Renfrewshire
In order to workcollectively to achieve the ambitions within Renfrewshire’s LHEES, it is important
toknow where we are starting from as an evidence base. 
The majority of Renfrewshire’s homes and businesses, including the Council estate and Council
housing stock, are currently heated and powered by fossil fuels which contribute to climate change. 
Many homes and buildings are also older and/or less well insulated, making them harder and more
expensive to heat, which increases carbon emissions and exacerbates issues with fuel poverty.   
It is vital that we cutemissions from Renfrewshire’s homes andbusinesses, in a way that ends fuel
poverty, ensures warm homes and buildings and develops a thriving, wellbeing economy.
Renfrewshire’s energy consumption makes up more than half (58%) of the area’s total emissions: 
• electricity to power homes and businesses totals 20% of our total
emissions (7% residential and 13% commercial and industry)
• gas and other fuels for heating homes and businesses total 38% of our
total emissions (22% residential and 16% commercial and industry)
• Latest figures show that22% of households in Renfrewshire are in fuel
poverty1  
• 89% of Renfrewshire’s homes use mains gas as their primary source of heat (higher than the
Scottish average of 79%)
• Council housing stock currently makes up nearly 15% of the overall housing in Renfrewshire
• the average carbon emissions per household in Renfrewshire is 3.6tCO2e per year (below the
Scottish average Scottish average of 4.3tCO2e per year)
• the average energy usage per household per year in Renfrewshire is 19,485kWh (below the
Scottish average Scottish average of 22,751kWh per year) 
1 Fuel poverty is defined as any household spending more than 10% of their income on energy after housing costs have been deducted. 
The Scottish average is 24%.
Page 26 of 140

Page 33

P a g e | 17
When developing Renfrewshire’s LHEES and the Delivery Plans which will be outlined in Phase 2,
the energy hierarchy has been taken into consideration and will be followed where possible. The
first step is to reduce energy waste, followed by improving poor energy efficiency and removing
poor energy efficiency as a driver for fuel poverty. This is followed by identifying renewable,
sustainable and low carbon sources of heat supply to meet the demand where possible. However,
the scale and pace of change required may mean that in some instances a low carbon heat supply
is identified and implemented which benefits residents, communities or businesses ahead of all
suitable energy efficiency measures being installed.  
It will not be technically or financially feasible in every instance to make the changes required to all
building stock for net zero emissions, whether that be energy efficiency measures or
decarbonisation of heat supply. In some instances, conventional sources may require to be used as a last
resort, with local carbon offsetting to compensate.     
This approach links with the Clean Energy theme in Renfrewshire’s Plan for Net Zero, which aims to
minimise energy demand, maximise energy efficiency and transform our energy systems to deliver
clean, affordable energy for all. 
Renfrewshire’s Plan for Net Zero Clean Energy Priority Areas
Page 27 of 140

Page 34

P a g e | 18
Mapping strategically across Renfrewshire to identify tailored, local energy efficiency and
decarbonised local heat solutions, will reduce reliance on fossil fuels; accelerate deployment of
local energy systems where local supply meets local demand; support the growth of net zero local
economies and quality, sustainable jobs; and tackle climate change while addressing specific
energy issues faced locally within our communities, including alleviation of fuel poverty. This will
ensure energy security, affordability and resilience while keeping the benefits of local energy
systems within our communities. 
Page 28 of 140

Page 35

P a g e | 19
The6 LHEES Stages
Renfrewshire’s LHEES is evidence-driven-using a wide range ofdata ateach stage, combined with
stakeholder engagement, in order to develop the strategy andtake into account a range ofkey
priorities to tailor local solutions specific to localareas.
Stage 1: Review -  involved a review of national and local policies, targets and strategies that are
linked to, impact, or could be impacted by LHEES. This stage provided the opportunity to consider
how national policy can be linked to local circumstances and strategies, helping to identify the key
priorities for LHEES and also relevant local targets and indicators. 
Stage 2: DataCollation and Verification – creating a Data and Tools Library to identify the most
appropriate data and information to support analysis in the subsequent stages of the LHEES
process. 
Based upon the national and local key policies anddiscussions regardingthekey challenges in
Renfrewshire, two key priorities were set for Renfrewshire’s LHEES, both of which align with key
drivers at a national and local level: fuel poverty alleviation;and carbon emissions reduction.
In addition to these key priorities, it was agreed that we would also consider other indicators set out
in the LHEES criteria as the policy review indicated that these would be relevant to the Renfrewshire
area: 
Indicator What does this illustrate?
1. Households in fuel poverty Homes that may need prioritised to alleviate
fuel poverty
2. Local Development Plan (LDP) Strategic areas to include for future heat
demands/heat loads
3. Potential anchor load buildings (public
buildings, high heat demands, hotels, etc.)
Potential heat demands to make a heat
network viable
4. Existing Heat Networks Potential for expansion to existing heat
networks
5. On gas /off gas grid Ease of transferring to a low carbon technology
6. Waste heat/energy Potential existing heat sources
7. Poor Energy Performance Certificates
(EPCs)
Buildings likely to need energy efficiency
improvements
Table 2: LHEES Indicators
Page 29 of 140

Page 36

P a g e | 20
These indicators were considered at each stage of the LHEES to provide a high-level understanding
of the current fuel poverty and building performance across Renfrewshire’s 38 intermediate zones.
Datazones are stable, small geographical areas that do not often change. Intermediate
zones are made up of aggregated data zones (2,500-6,000 residents) and sit between data
zones and Council areasfor granularity, or detail, ofdata.
Stage 3: Strategic Zones and Pathways – using the information from Stages 1 and 2 to understand
the current energy efficiency and heat decarbonisation performance of all building stock at a local
authority wide level (Council, public, private, 3rd sector and all tenures of residents) and designates
zones setting out the most appropriate energy efficiency and heat decarbonisation options for the
area. 
Stage 4: Generation of Initial Delivery Areas and Potential Zones for Heat Networks - place-based
analysis at a higher level of detail, identifying specific locations/clusters for potential Delivery Areas
within a Strategic Zone. 
Stage 5: Energy Efficiency and Heat Decarbonisation Pathways - establishing in more detail the types
of interventions required to decarbonise buildings and identified opportunities and challenges for
heat decarbonisation, including outline costs and carbon savings. 
Stage 6: Finalisation of Delivery Areas – identifying a range of projects and actions to be developed in
the LHEES Delivery Plan, highlighting the long-term direction of travel as well as near term
opportunities. 
Page 30 of 140

Page 37

P a g e | 21
LHEES Terminology –District Heating
A district heating network is the distribution of heat from a central energy source to multiple
customers through a system ofinsulated pipes.
District heating uses a central heat source to supply heating and hot water to
multiple residential and/or commercial buildings via a system of insulated pipes
that are generally buried underground. Although referred to as district ‘heating’,
these networks can provide both heating and cooling demand. 
Communal heating is similar to district heating, but in this case, the central heat
source supplies heating and hot water to multiple users within one building, e.g., 
blocks of flats. 
A central source for heat is more efficient than each building having its own
individual, carbon intense system and brings significant opportunities for this heat
to be delivered using low carbon sources direct to radiators. This reduces our
reliance on fossil fuels, reduces heat losses from inefficient boiler systems and
brings savings on service and maintenance. 
District heating systemsusing low carbon and renewable heat sources can help to alleviatefuel
poverty, increase energysecurity and resilience, reduce energy demand and canprotect users from
energy market volatility and spikes in prices.
There are examples of both communal heating and district heating networks in Renfrewshire,
including the first of a kind in Scotland AMIDS District Heating Network - provides low carbon heating,
cooling and hot water via a district heating network to businesses at the Advanced Manufacturing
Innovation District site in Paisley, with a carbon reduction of over 95% over the 40 years lifecycle of
the project and potential to connect other buildings locally. 
When identifying potential district heating networks, the most common approach is to identify
anchor loads for the network, assess the heat density (or heat demand) of the area and to identify a
heat source.  
Page 31 of 140

Page 38

P a g e | 22
• anchor loads - are buildings with significant heat demands in an area which help increase
network viability and are often the first buildings to be connectedto a network:
o public buildings are generally good anchor loads, providing higher levels of certainty for
developers due to predictability and consistency of building use
o buildings with high heat demand and/or diversity of use are key, e.g. hotels/leisure centres
have significant heating and hot water demand 24/7, 365 days a year; a school will require
heat during the day, whereas homes generally require their heating at night. These ranges
of heat demand help to balance a network. 
● assessing the heat demand of the area - this determines the size of energy centre required to
provide heat for buildings on a network, as well as the length and diameter of pipes required to
supply the heat:
o public buildings can again be key when assessing heat demand as this data is generally
reliable and easily accessible in order for analysis in the first instance. 
● identifying a heat source -the heat source which will supply all the buildingson anetwork is key:
o developing a district heating network does not necessarily mean using only new
infrastructure. In the development of Renfrewshire’s LHEES, opportunities to use existing
infrastructure and assets are also being explored. This includes opportunities to use waste
heat recovery, i.e., existing potential heat sources such as our rivers which in the past
powered mills; reservoirs; factories and manufacturing processes which produce high
levels of waste heat; and waste heat recovery from the wastewater treatment process.   
● minimising heat losses–increases viability of network:
o heat networks are generally more efficient than individual heating systems within each
property but the further the heat has to travel, the higher the likelihood that heat may be
lost. 
o a measurement called linear heat density is used to identify where networks may be more
viable, based on heat demand and the length of the network to calculate and minimise
potential heat losses. The accepted industry standard linear heat density for a viable
network is 4MWh/metre. However, all options will be explored, in order to include areas
within Renfrewshire which have lower heat densities, including rural areas and smaller
urban settlements in order to identify the most beneficial heat solution for communities.  
Page 32 of 140

Page 39

P a g e | 23
Additional duties came into force in May 2023 requiring owners of public sector non-domestic
buildings to submit a Buildings Assessment Report to their local authority. These public sector
buildings have the potential to be key anchor loads, and this will help assess potential anchor load
suitability and/or network connection opportunities.  
Zoning across Renfrewshirefor viable large-scale and small scaledistrict heating and
communal heating networks will enable us to understand the scale and potential
of these opportunities.
Page 33 of 140

Page 40

P a g e | 24
LHEESTerminology -EnergyEfficiency Measures
Energy efficiency means using less energy to get the same job done. Energy efficient homes and
buildings use less energy to heat and cool, which leads to cutting energy bills and reducing carbon
emissions.
The first steps in the energy hierarchy are to reduce energy waste and improve energy efficiency,
including removing poor energy efficiency as a driver for fuel poverty. Most homes and buildings lose
heat through walls, roof, windows and doors due to warm air travelling to cold spaces. Improving
energy efficiency is one of the main ways to reduce draughts, heat loss and carbon emissions. This
leads to lower energy bills, warmer homes and buildings and improved mental health and wellbeing.
It also improves the fabric of homes and buildings by reducing potential for damp and mould, which
can also affect the health of building occupants. 
Many homes and buildings in Renfrewshire are older and/or lesswell insulated, making them
harder and more expensive toheat, which increases carbonemissions and
exacerbates issueswith fuelpoverty.
There are a number of measures that can be taken to improve energy efficiency, which have been
explored in the development of Renfrewshire’s LHEES and which will be further developed in the
Phase 2 area-based Delivery Plans. 
Draught Proofing: draught proofing is one of the cheapest and most effective ways to stop heat loss,
helping to keep homes and buildings warm and reducing energy bills. This involves blocking
unwanted spaces and gaps that let cold air in and let heat escape out and there are simple ways that
this can be done without the need to call in professionals, but care must be taken not to seal off
ventilation which is specifically designed for air flow. Simple DIY methods include draught-proofing
strips for windows; draught excluders; keeping doors closed leading to rooms that you don’t normally
heat, e.g., spare room; and using a letterbox flap or brush. Warm air rises and so blocking off draughts
around loft hatches and attic doors can also reduce the amount of heat needed to keep warm.
Insulation: in an uninsulated home roughly a third of heat loss is through the walls and around 25%
of heat is lost through the roof, attic or loft spaces. Generally, homes built from 1990 onwards have
good levels of wall insulation, but older homes may require action to properly insulate.
Page 34 of 140

Page 41

P a g e | 25
● Cavity Wall Insulation: Cavity walls are made of 2 layers, with a small gap between them.
Insulation involves injecting insulation material into this gap (or cavity) and requires a
professional, but generally has minimal disruption as it can often be done in a couple of
hours. 
● Solid Wall Insulation: homes which were built before the 1920s general have solid external
walls with no cavity but can be insulated from either the inside or the outside. This is more
costly than cavity wall insulation but can also bring greater savings in bills.
● Loft and Roof Insulation: if your loft is easily accessed then loft insulation is often easy to
carry out, and it is possible to do yourself. Harder to access loft spaces require a professional
to complete the required works. 
Windows andDoors: energy efficiency can be improved by upgrading to double or triple glazing glass
or applying secondary glazing. Not only does this keep heat in, but it can also reduce noise from the
outside. Another effective way to keep heat in and reduce noise travelling is through heavy lined
curtains and closing curtains and blinds at night. If you live in a conservation area or a listed building
then you should check with Renfrewshire Council’s planning team as there may be restrictions on
work that is allowed, or special permissions may need to be obtained.
Hot Water Tanks and Radiators: insulating behind radiators on external walls using radiator reflector
panels is an effective, low cost option to reduce heat loss. They act by reflecting the heat from the
radiator back into the room instead of letting the heat escape through the external wall. Insulating
your water tank using a hot water cylinder jacket or lagging is also a quick and easy way to keep water
hotter for longer and reduce energy bills.
One of the ways Renfrewshire Council is helping our tenants is through our Housing Regeneration &
Renewal Programme: a £100M ten year programme delivering high qualityandenergy efficient
Council housing throughoutRenfrewshire-creating nicer places to live,bringing down energy bills
and alleviating fuelpoverty, with associated health and wellbeing benefits.
For free, impartial advice on energy efficiency for your home as well as financial support schemes,
grants and loans visit Home Energy Scotland. Interest free loans for small and medium sized
businesses, not-for-profit organisations and charities are also available through 
Business Energy Scotland.
Page 35 of 140

Page 42

P a g e | 26
Overview of Renfrewshire as aWhole: Fuel Poverty & Energy Efficiency
This section of Renfrewshire’s looks at the area-wide picture relating to fuel poverty and energy
efficiency for Renfrewshire, setting out the challenges and opportunities and potential areas of
focus. 
All potential proposals will then be further developed and enhanced during Phase 2, the action and
delivery phase, when detailed Delivery Plans, broken down sufficiently by area will be co-developed
with our local communities and other key stakeholders. 
The census high level results for Renfrewshire
released by the National Records of Scotland
showed that Renfrewshire’s population has
increased again and now stands at 183,800 - an
increase of 8,892 (5%) from 2011. This links with a
7.2% increase in the number of households
between 2011 and 2022, with 91,685 domestic
properties being analysed as part of
Renfrewshire’s LHEES. 
Where new homes and buildings have to meet certain
standards of energy efficiency, those older homes and
buildings need work to bring up to standard.
Undertaking energy efficiency measures such as
insulation in existing properties is called retrofitting.
Improving energy efficiency reduces the amount of
heat needed to keep hom
es and buildings warm and so leads to reduced energy
bills. 
Generally, houses built from the 1990s onwards have good levels of insulation. Analysis of
Renfrewshire households found that 75% of households in Renfrewshire were built pre-1992, but
many have since been retrofitted with insulation improvements such as insulation and double
glazing. 
Key Fuel Poverty and Energy Efficiency
Stats for Renfrewshire
% of homes in fuel poverty:22%
% of homes in extreme fuel poverty: 7.4%
% of homes on gas grid:94%
% of homes with single/partial glazing:5%
% of homes with double glazing:92%
% of homes with triple glazing:3%
% of homes with wall insulation:42%
Renfrewshire DomesticProperties by Age
Page 36 of 140

Page 43

P a g e | 27
An Energy Performance Certificate (EPC) gives information on how
energy efficient a building is and how it could be improved. EPCs are
valid for 10 years and need updated on expiry and also at all points
when a building is sold or let to a new tenant. EPCs can also be
updated following improvements to a building. 
An EPC’s energy efficiency rating estimates how much fuel bills may
be and also the environmental impact rating in terms of estimated
carbon emissions. EPC ratings are banded on a scale from A to G,
with A being the best. A recommendations report is included which
outlines improvements and what the potential EPC rating could be if
these were carried out. 
Analysis of Domestic EPCs in Renfrewshire found that 10% were in the top bands of A-B; 42% were in
Band C; 36% were in Band D; 9% were in Band E; and 3% were in the lowest bands F-G. However,
EPCs were often found to vary by tenure as outlined in the ‘Fuel Poverty’ section which follows. You
can find out the EPC for your property on the Scottish EPC register. 
To remove poor energy efficiency as a driver for fuelpoverty,targets ata national levelhave been
set to improve theenergy efficiency standards to the equivalent of EPC Band B for households in
fuel poverty.
Through Scotland’s Heat in Buildings Strategy, regulations requiring that all residential properties
achieve the equivalent to EPC Band C by 2033 where technically and legally feasible and cost-
effective is to be introduced. 
The social housing sector is expected to go further, with all social housing meeting EPC Band B or as
energy efficient as practically possible by the end of 2032 (within the limits of cost, technology and
necessary consent). 
Standards for the private rented sector are also being introduced to ensure measures are
implemented to prevent private tenants from being at increased risk from fuel poverty. 
Domestic EPCs inRenfrewshire
Page 37 of 140

Page 44

P a g e | 28
Fuel Poverty in Renfrewshire
A household is defined as in fuel poverty if more than 10% of
the household’s net income is required to pay for reasonable
fuel needs to maintain an acceptable standard of living after
housing costs have been deducted. Extreme fuel poverty is
where more than 20% of the household’s net income is
required for reasonable fuel costs after housing costs have
been deducted. 
Fuel Poverty in Renfrewshire
There are four maindrivers of fuelpoverty:energy prices; income;energy efficiency of the home;
and how energy is used inthe home.
Recent market volatility and spikes in energy prices have had severe impacts on households and
contributed to the cost-of-living crisis, including rising levels of all forms of poverty and people having
to choose between heating their homes and eating. This has led to many not using heating at all or
severely reducing their heating to reduce energy bills to as low
a level as possible. This has knock on effects on mental health
and wellbeing as well as having negative impacts on building
fabric such as increased damp and mould, bringing further
potential negative health impacts. Those who are in off gas grid
areas can often face higher energy prices and so higher levels
of fuel poverty due to a lack of fuel choice. Generally, off gas
grid areas are more commonly found in rural locations, but in
Renfrewshire there are also concentrated clusters of off gas
grid properties in urban areas. 
Household income is also a contributor to fuel poverty – particularly if household incomes are not
increasing at the same rate as energy and other household costs. Residents on a fixed income, such
as those who are unable to work and those over pensionable age are at particular risk of income
not keeping up with inflation of other requirements. Residents in Renfrewshire who are aged 65 or
over make up 19.5% of the total population. 
% of off gas grid levels in
Renfrewshire: where darkershades
indicate higher levelsof off gas grid
Page 38 of 140

Page 45

P a g e | 29
Poor energy efficiency is another key driver of fuel poverty – poorly insulated homes are difficult to
heat and keep warm, with heat loss through various areas of the home. This leads to the household
needing to use increased levels of heat to keep the home to a reasonable standard of warmth, and
so increases energy bills. 
The need to remove poor energy efficiency as a driver for fuel poverty is a focus area for
Renfrewshire’s LHEES. A way to identify poor energy efficiency can be through the household
Energy Performance Certificate (EPC). EPCs outline the energy efficiency of a building, and so are
indicative of potential energy costs, and are scaled from Band A to Band G, with A being the highest. 
Analysis of Domestic EPCs in Renfrewshire found that 10% were in the top bands of A-B; 42% were
in Band C; 36% were in Band D; 9% were in Band E; and 3% were in the lowest bands F-G. However,
EPCs were found to vary widely by tenure as can be seen below: 
The social housing sector has lower levels of EPC Bands D, E and F-G; and higher levels of properties
in Band C. EPC Bands A-B were fairly similar across all housing tenures. So, in cases where the
houses were energy efficient, then it appears that other factors are driving fuel poverty. In
developing the LHEES, EPCs were also mapped across the area to identify areas of focus for energy
efficiency interventions for LHEES Delivery Plans – this map can be found in Appendix 3. This data
confirmed areas which ranked as a low priority for energy efficiency measures, but which had high
fuel poverty, indicating that poor energy efficiency was not the driver for fuel poverty in these areas.  
EPCs in Housing Associations EPCs in Council Housing Stock  EPCs in Owner Occupied Homes  EPCs in Private Rented Homes
Page 39 of 140

Page 46

P a g e | 30
Scottish Index of Multiple Deprivation (SIMD) is a tool used to
identify areas where people are experiencing disadvantage across
different aspects of their lives. Renfrewshire’s SIMD profile is on a
scale, with SIMD 1 areas in red (most deprived) through to SIMD 5 in
green (least deprived), with 2 being orange, 3 being yellow and 4
being blue. 
SIMD data is at data zone level, looking at small geographical
populations (500 to 1,000 residents). Aspects used to calculate SIMD
ratings are income; employment; health; education and skills;
housing; geographic access; and crime. Not all of these factors
directly contribute to fuel poverty and so additional datasets were
combined to identify fuel poverty focus areas. 
Engaging with the most vulnerable members of our society whose voices are keyto ensure social
justice isdelivered. Innovative engagement methods andtargetedengagement withtraditionally
under-represented groups will be used toensure all demographics are reached.
Children Living in Low Income Families data
focuses on child poverty (and does not include
households with no children) but is another
indicator of households potentially at increased
risk of fuel poverty. This data shows significant
increases in child poverty from 2015 to 2022 and
sharp rises over the last few years, likely  related
to the pandemic and the cost-of-living crisis.
This highlights vulnerable sections of our
society that may not be captured, or may be
masked, in other dataset’s factors. For example,
because SIMD includes a scoring for
geographical access, urban areas with good
access to services and transport may receive a
better overall scoring, masking other issues
within the community. 
Renfrewshire’s SIMD Profile 
Children living in relative and absolute low
income households before housing costs
Page 40 of 140

Page 47

P a g e | 31
Data indicates the highest concentration of child poverty is within urban areas in Paisley, but is also
found in significant levels in other areas, highlighting further areas, in addition to those highlighted
using SIMD, for in-depth analysis and focus. 
Home Analytics data looks at key housing stock characteristics such as levels of insulation and
glazing. When cross-referencing Home Analytics energy efficiency data with fuel poverty, the 10
intermediate zones with the highest probability of fuel poverty being driven by poor energy efficiency
were different to the top 10 SIMD areas. In this analysis, areas most at risk of fuel poverty being driven
by poor energy efficiency were: 
• Paisley Central.
• Paisley North East.
• Bridge of Weir.
• Kilbarchan.
• Paisley East.
• Paisley North West.
• Johnstone North West.
• Erskine West.
• Paisley North; and
• Renfrew South. 
In Phase 2 Delivery Plans, there will be a specific focus on these areas to look at interventions and
work programmes that will help to remove poor energy efficiency as a driver for fuel poverty, as well
as a focus on what interventions can help with fuel poverty and extreme fuel poverty which are being
driven by other factors. The Children in Low Income Family and the Poor Energy Efficiency as a Driver
for Fuel Poverty maps are set out at intermediate zone level (2,500-6,000 residents) and so the areas
are not broken down as much as SIMD data mapping. 
Delivery Plans will further analyse all of these datasets and breakdown sufficiently to enable
identification of appropriate interventions and workprogrammes and to identify where support
and advice may be needed most.
Poor energy efficiency as a driver for fuel poverty
Page 41 of 140

Page 48

P a g e | 32
Poor Building Energy Efficiency: What isDrivingPoorEnergy Efficiency?
Larger versions of allmaps from this section can be found in Appendix 3
Data analysed during the development of Renfrewshire’s LHEES included 6,641 non-domestic
properties but due to the limitations of energy efficiency data for non-public sector non-domestic
buildings, this section concentrates on domestic properties only. However, there will be many non-
domestic buildings that will require interventions, such as wall and roof insulation, and
replacement glazing. Strategies for these will be explored in future updates of the LHEES as more
data is gathered for non-domestic buildings. 
There is more certainty with the non-domestic data when looking at potential for anchor loads
and/or heat demand for connecting to a district heating network as these benchmark calculations
take into account floor area, fuel type and use of building. As such, for non-domestic properties the
focus was on analysing potential as anchor loads and/or for connection to district heating networks
(covered in more detail in the ‘Heat Networks’ section later in the document). 
The energy efficiency performance of domestic properties across Renfrewshire is a mixed picture,
with 48% of properties estimated to have an EPC in the lowest bands of D-G. The EPC ratings are
slightly better than the national average, with Renfrewshire having an estimated 12% of properties
with an EPC of E-G (compared to a national average of 13%, according to the Scottish House
Condition Survey 2021). 
Properties that have a lower EPC rating are more likely to be
eligible for targeted funding to improve energy efficiency.
When analysing the EPCs at an intermediate zone level (2,500
to 6,000 residents), it appears that there are several zones that
have a higher percentage of domestic properties with poor
energy efficiency performance. 
Paisley Ralston has the highest percentage of poor energy
efficiency, with 87% of domestic homes having an EPC of D to
G, followed by Bishopton (77%) and Paisley South West
(71%). 31% of properties in Paisley Ralston have an EPC E-G
which is significantly higher than the next intermediate zone,
Bridge of Weir (20%). 
Map EE1: EPC D-G at intermediate
zone level
Page 42 of 140

Page 49

P a g e | 33
Intermediate zones (IZ) provide a score over a larger area to give an
overall view of poor EPCs across Renfrewshire. By considering data
at a more detailed data zone level (500 to 1,000 residents), we gain
a better understanding of more detailed patterns where clusters of
properties with poor energy efficiency are found. Analysis showed
that there were some areas that have low EPC scores but, because
IZ levels are large, they were averaged out and are not so obvious
until analysed at data zone level, for example Langbank. The focus
for energy efficiency in the area-based Delivery Plans will be at data
zone level for this reason. 
What are the main factors for Renfrewshire relating to poor energy efficiency?
Analysis was carried out on the 91,685 domestic properties across Renfrewshire to identify patterns
in poor energy efficiency in order to tailor interventions in the Delivery Plans and ensure targeted
advice where needed. 
Wall Insulation: 44,235 of 91,685 domestic properties in
Renfrewshire have cavity wall construction (48.2%); 24,721 have
solid brick or stone wall construction (27.0%); 15,238 timber frame
wall construction (16.6%); and 7,491 system-built wall construction
(8.2%). Overall, 58% of all homes are estimated to have some form
of wall insulation. 
Timber frames are the most likely wall construction to have insulation, with only 17.7% of these
properties being uninsulated, but this also links with property age – with 81% of these properties
being constructed post 1992 when higher levels of insulation are more common. 
When looking across differenttenures we can see that 74% of all social housing properties (Council
housing stock and Housing Association) have wall insulation; compared with 55% wall insulation
for owner occupiers and 42% wall insulation for private rentedproperties.
Taking the most common wall construction in Renfrewshire (cavity wall), 35% of these types of
homes are uninsulated (15,839 properties). Broken down by tenure: 
● social housing makes up 17.9% of all cavity wall construction domestic properties in
Renfrewshire (but 9% of the uninsulated cavity wall properties) 
Map EE2: EPC D-G at data zone
level
Wall Insulation (All Properties)
Page 43 of 140

Page 50

P a g e | 34
● 73.5% of cavity wall domestic properties are owner occupied (but these properties make
up 79.9% of uninsulated cavity wall properties) 
● private rented properties make up 8.6% of cavity wall domestic properties (but 11.1% of
uninsulated cavity wall properties) 
Glazing: Differences between different tenures can also be seen in glazing
types. Overall, in Renfrewshire, 92% of all domestic properties have
double glazing; 3% have triple glazing; and 5% have single or partial
glazing. Broken down by tenure:
- social housing and owner occupiers have higher levels of double
glazing (94% and 93% respectively) and triple glazing (3% and 2%
respectively) than private rented properties (89% double glazing and
1% triple glazing)
- 3% of social housing properties have single or partial glazing. This
rises to 5% for owner occupiers and rises again to 10% for private
rented properties. 
Private rented properties make up 11% of all homes in Renfrewshire but make up 21% of properties
with single or partial glazing; and 15% of all uninsulated properties. This highlights an area where
advice and support for this sector, including signposting to financial support schemes and upcoming
changes to legislation, may be helpful. This would help to alleviate fuel poverty and reduce bills while
improving warmth for tenants and would also help with the fabric of the building and maintenance,
decreasing the likelihood of problems such as damp and mould. 
Not all homes have lofts but, for those that do, this is another area where
energy efficiency improvements have significant impacts. Owner
occupier properties have the highest percentage of lofts at 72% (this
drops to 53% and 52% for social housing and private rented
respectively). The depth of loft insulation recommended by Energy
Saving Trust Scotland and current buildings regulations is 270mm, with
most new build homes having between 270-300mm insulation. As well
as higher likelihood of a loft, owner occupiers had the highest levels of
250mm+ insulation at 42%, with social housing having 27% and private
rented 21% at this level.   
Glazing Type (All
Properties) 
Loft Insulation (All
Properties)
Page 44 of 140

Page 51

P a g e | 35
Next Steps-Energy Efficiency Focus for Delivery Plans: 
Of the 43,754 domestic properties with an EPC in the lowest bands (D-G), and
therefore more likely to be e ligible for targeted funding:
- 3,500 properties (8%) had single glazing
- 27,306 properties (62.4%) had uninsulated walls, and
- 2,792 properties (6.4%) had both single glazing and uninsulated walls 
This poor energy efficiency is likely to be an exacerbating factor in fuel poverty
for these households. The area-based Delivery Plans will have a focus on these
properties to identify clusters where targeted support and interventions can
help to remove poor energy efficiency as a driver for fuel poverty and provide
support across all tenures, including signposting for landlords where relevant. 
Support and advice for those properties in fuel poverty where poor energy
efficiency is not the key driver will also be developed in collaboration with
partner organisations to ensure that all households who may be vulnerable to
fuel poverty are reached and supported. 
Links to impartial advice and support will also be promoted for those looking
to make energy efficiency improvements who have higher band EPCs. And for
all households, opportunities for the decarbonisation of heat and supply of
efficient, low carbon heat will be explored to deliver clean, affordable warmth
to all. 
Renfrewshire Council are implementing energy efficiency improvements in housing stock and,
where possible,will work with homeowners within mixedtenure blocks to help them to participate,
as well as working with theprivate rented sector to share learnings and identify opportunities to
reduce costs through economies of scale.
EPC D-G: Uninsulated
Walls
EPC D-G: Uninsulated
Walls AND single
glazing
EPC D-G: Single Glazing
Page 45 of 140

Page 52

P a g e | 36
Overview of theOpportunities for the Decarbonisation of Heat acrossRenfrewshire:
Potential for Heat Networks
Larger versions of allmaps from this section can be found in Appendix4
In addition to improving energy efficiency, another key driver in affordable warmth is the provision
of heat and how that is supplied. This section looks at the area-wide picture relating to the
decarbonisation of heat for Renfrewshire, setting out the challenges and opportunities and
potential areas of focus. 
All potential proposals will then be further developed and enhanced during Phase 2, the action and
delivery phase, when detailed Delivery Plans, broken down sufficiently by area will be co-developed
with our local communities and other key stakeholders. 
Decarbonisation of heat means reducing the carbon emissions associated with our heating systems
and switching to cleaner and moreefficient systems to heat our homes and buildings.
Key Heat Stats for Renfrewshire
Size of Area: 262sq. kilometre
Population density: 703 residents/sq. km
(Scottish average: 70; Glasgow has 3,555)
% of homes in fuel poverty:22%
% of homes in extreme fuel poverty: 7.4%
Average heat demand per household:11,521kWhper year
% of homes on gas grid:94%
homes with mains gas as main source of heat: 82,667 (90.2%) 
homes with electricity as main source of heat: 7,017 (7.7%) 
homes with heat pumps as main heating system: 499 (0.5%)
homes with communal heating: 1,093 (1.2%)
Page 46 of 140

Page 53

P a g e | 37
Key Factors in the PotentialDecarbonisation of Heat through District Heating Networks:
Data across the whole of Renfrewshire was analysed in order to identify potential opportunities for
district heating networks, to enable the provision of efficient, low carbon heat to homes and
businesses. A number of factors were taken into account to identify the first phase of potential
opportunities. Population density links with heat demand and linear heat density (and the length of
pipework that would be required for a network). 
Overall, Renfrewshire has a population density of 703 residents per square kilometre (10% more
dense than the national average of 70, but significantly less densely populated than Glasgow at 3,555
residents per square kilometre). This population density varies significantly in different areas of
Renfrewshire and the potential for communal or district heating will be explored further for all areas,
not just those with the highest population densities. There are many small-scale operational
examples of district heating across Scotland in areas of low population densities which have the
potential to be scaled and replicated – and which have had significant impacts on both carbon
emissions and fuel poverty following implementation. Other factors include: 
1. On Gas andOffGas Grid Locations (Map H1):
The majority of homes and businesses in Renfrewshire are on gas
grid, but those in off gas grid areas often face higher instances of
fuel poverty due to a lack of fuel choice and higher bills. This has
been particularly true in recent years with high electricity prices
per kWh compared with that of gas. Higher fuel costs can also
impact viability of businesses in these areas. Even with lower
population and heat densities in some off gas grid areas, heat
networks can be viable on a smaller scale as heat can often be
supplied at lower costs to the consumer than the traditional
source of heating (electricity, oil, LPG), so helping to alleviate fuel
poverty.  
Map H1: % on gas grid in
Renfrewshire
Page 47 of 140

Page 54

P a g e | 38
2. Potential Anchor Loads for District Heating Networks (Map H2):
Anchor loads are buildings with significant heat, cooling and hot
water demand, helping network viability. Potential anchor loads
were identified across Renfrewshire. Green dots signify Council
buildings, with orange dots signifying other public buildings. Blue
dots signify additional potential anchor loads with high heat
demands and a range of uses to diversify and balance heat
demand across seasons and throughout the day and night, to
optimise any potential networks. Cross-border opportunities with
neighbouring local authorities will also be explored further in
Delivery Plans – including any potential partnership projects or
potential for cross-border heat supply. 
Potential Heat Sources for District Heating Networks: Heat Networks generally have a purpose-built
energy centre to supply heat to all the buildings connected to the network. However, the heat source
for the energy centre can take different forms and does not always require new infrastructure and
assets. Analysis for Renfrewshire’s LHEES included identifying existing infrastructure and assets that
can be harnessed to supply heat. There are many existing potential large-scale heat sources, such as
rivers and aquifers, green spaces and geothermal opportunities. 
Opportunities to capture waste heat – similar to the waste heat
recovery used in the AMIDS district heating network will be
further developed in the Delivery Plans. Potential waste heat
sources include wastewater treatment plants; data centres;
factories, industry and manufacturing processes; hospitals;
supermarkets; leisure centres; and energy from waste. All of
these provide opportunities for low regret heat decarbonisation,
using existing infrastructure. 
There will also be a need for new development and purpose-built energy centres with low carbon
heat supply, and opportunities to site energy centres on Council-owned land will be identified, in
addition to extending and expanding existing heat networks. 
Map H2: Potential anchor
loads in Renfrewshire 
Wastewater Treatment
Opportunities
Page 48 of 140

Page 55

P a g e | 39
Housing Tenure (Map H3):
Renfrewshire Council has a target of implementing measures in
housing stock to reduce carbon emissions by 68% (from 2020
levels). Provision of low carbon heat in addition to energy efficiency
improvements will play a key role in this. Clusters of social housing
(both Council and Housing Association) provide opportunities for
both the tenants and for the viability of district heating networks as
a whole, due to work programmes such as boiler replacements
which are programmed and known in advance. Engagement with
tenants is also ongoing and so any potential heating schemes can
be set out and discussed fully in advance, with benefits including
affordable warmth being outlined and the opportunities for tenants’ questions to be asked. This then
also builds a solid base for the scheme to connect surrounding properties, whether owner occupier,
private rented or commercial.   
Existing Heat Networks:
Existing large heat networks in Renfrewshire include the AMIDS district heating network and the
University of the West of Scotland’s Paisley Campus. It is hoped collaboration and partnership
working will lead to the identification of opportunities for the potential for expansion and extension
of existing networks (again optimising these existing assets) and also a chance for knowledge gained
being applied to scale and replicate projects in other areas. 
Local Development Plan (Map H4):
Renfrewshire’s Local Development Plan (LDP) sets out the
spatial strategy over the next 10 years and aligns with
National Planning Framework 4, outlining development
and infrastructure in line with national principles,
priorities and policies. 
Knowing where potential developments are taking place,
and what these developments entail (e.g., housing or
industrial) helps to future-proof Delivery Plans when
looking at potential heat networks and any future connections. Horizon scanning also enables early
discussions to take place with developers and mitigate against potential heat network opportunities
being missed; connections to be optimised; energy centres and pipe networks to be suitably sized
and future-proofed, as well as potential for cost savings for heat network development by installing
pipe network at times when other civils works are being carried out (civils being one of the main costs
in installing a district heating network). 
Map H3: Social housing clusters
in Renfrewshire 
Map H4: Renfrewshire Local
Development Plan areas
Page 49 of 140

Page 56

P a g e | 40
All of these considerations were analysed and taken into account when looking at heat
decarbonisation opportunities across Renfrewshire, and thepotential for supplyof heat through
district heating networks.
Page 50 of 140

Page 57

P a g e | 41
Overview of thePotential First Phase Priority Heat NetworkZones
The initial areas for exploration were identifiedthrough having high heat demand,being close to an
energy sourceand thepresence of public buildings as potential anchor loads.
Larger versions of allmaps from this section can be found in Appendix5.
In order to prioritise the initial priority heat networks for further exploration, heat clusters were
identified across Renfrewshire. 12 heat clusters were identified in Paisley, with 33 heat clusters
identified in the rest of Renfrewshire. 
The heat clusters are mainly in urban and more densely populated areas,
but heat networks can also work on a smaller scale for rural areas. All
options will be explored on an area-by-area basis in the development of
Delivery Plans and in future iterations, based on scalability and
replicability of projects that can be tailored to these areas, and exploring
operational projects that have worked in similar areas across Scotland.  
Linear heat density is a measure of heat load per metre of district heating
pipework and identifies if a heat network is likely to be financially viable
based on likely revenue generation for a given capital cost of installation
of infrastructure: 
• Higher heat density (16,000kWh/year/metre) was used in Paisley
centre as laying pipework in town centres and under busy roads is
more costly and disruptive. These clusters needed 5 or more
anchor loads.
• Lower heat density (4,000kWh/year/metre) was used in more
suburban and rural areas, where anchor loads may be more
dispersed but where there may be more opportunities to install
pipework in soft-dig areas, which lowers pipework costs per metre
to ensure lower heat density networks are still viable. These
clusters needed 2 or more anchor loads.   
Renfrewshire Heat
Clusters 
Anchor Loads in high
linear heat density
clusters
Page 51 of 140

Page 58

P a g e | 42
The anchor loads and linear heat densities were then plotted to highlight clusters viable. To further
enhance the mapping analysis, heat sources, opportunities and constraints (such as railway tracks)
were added alongside looking at areas of Council land ownership, development sites in the Local
Development Plan and areas of concentrated social housing, as well as existing heat networks. This
helped to finalise the initial proposed heat network zones, e.g., zones were split where railway tracks
would need to be crossed; and zones were extended to capture additional opportunities identified
as part of the internal Officers Working Group. Input was received from across all key Service areas as
well as identification of opportunities to link, optimise or coordinate work programmes. 
Although the standard linear heat density for a network to be viable is 4MWh/metre, all options will
be explored in order to include those areas with lower heat densities, including rural and smaller
urban settlementsin orderto identify the most beneficial heat solution forall our communities.
First Phase Potential Heat Network Zones:
1.Central Paisley Potential Heat Network Zone:
 an area of 212 hectares
 an estimated heat demand of 167GWh2/year
 49 identified potential anchor loads (30+ public
buildings), 40 with a predicted heat demand above
500 MWh3/year.
 2,552 domestic properties that could potentially
connect to a network. 
Potential local energy sources include the White Cart
Water, an aquifer and areas of open space. There are also
multiple sources of potential waste heat as well as the existing district heating network at the
University of the West of Scotland campus, all of which fall within a 750 m radius. 
In addition to the potential for expansion of the existing UWS district heating network, there are
opportunities to add resilience through linking existing and new networks, with multiple energy
centres bringing security of supply at times of planned and unplanned maintenance. 
2 A gigawatt hour (GWh) is equivalent to 1 million kilowatt hours (kWh)
3 A megawatt hour (MWh) is equivalent to 1 thousand kilowatt hours (kWh)
Map DHN1: Central Paisley
Page 52 of 140

Page 59

P a g e | 43
This zone has areas of densely populated flatted properties, and large clusters of social housing to
the east and west. There are also large numbers of public buildings which could potentially connect
to a network. When looking at potential solutions, consideration must be taken of the large portion
of this zone which is a conservation area, with a number of listed buildings. 
2. Shortroods and Laighpark Potential Heat Network
Zone:
 an area of 284 hectares
 an estimated heat demand of 124GWh/year
 22 identified anchor loads (10 public buildings),
with 17 having a predicted heat demand above
500MWh/year.
 1,553 domestic properties within the zone that
could have the potential to connect to a network. 
Potential local energy sources include the White Cart Water as well as two wastewater treatment
sites. The AMIDS district heating network, which has capacity for extension and expansion also falls
within this zone, to the north. This also brings opportunities to link networks to increase resilience.
These are all within a 750 m radius.
This zone includes an economic investment zone within the Local Development Plan, and there are
several sites earmarked for housing supply. There are large clusters of social housing to the south and
west of the zone, with public building potential anchor loads distributed throughout the zone (as well
as potential for linking with a Phase 2 zone in Gallowhill to the east, which has significant social
housing and some public building anchor loads. 
3. Lochfield and Charleston Potential Heat Network Zone:
 an area of 33 hectares
 an estimated heat demand of 12GWh/year
 5 identified anchor loads (4 public buildings), 2 of
which have a predicted heat demand above 500
MWh/year.
 533 domestic properties within the zone that could
have the potential to connect to a network.
Map DHN2: Shortroods and Laighpark 
Map DHN3: Lochfield and Charleston
Page 53 of 140

Page 60

P a g e | 44
Potential local energy sources include open space which may have potential for ground source heat
pumps, or to site an energy centre. The 4 anchor loads are at the 4 corners of the zone, with significant
clusters of social housing in the centre.   
There are also 3 sites earmarked for housing supply within the Local Development Plan within or
bordering this zone, enhancing future opportunities. 
4. Ferguslie Park Potential Heat Network Zone:
 an area of 52 hectares
 an estimated heat demand of 14GWh/year 
 7 identified anchor loads (all public buildings), 2 of
which have a predicted heat demand above
500MWh/year.
 500 domestic properties within the zone that could
have the potential to connect to a network.  
Potential local energy sources include an aquifer as well as open spaces which may have potential
for ground source heat pumps, or as a site for an energy centre. The anchor loads are all in the centre
of the zone, surrounded by significant clusters of social housing on all sides. 
There are also Local Development Plan sites marked for housing supply as well as development
opportunity sites within and on the border of this potential heat zone, and potential to extend into
further areas of social housing. 
5. North RenfrewPotential Heat Network Zone:
 an area of 223 hectares
 an estimated heat demand of 79GWh/year
 16 anchor loads (13 public buildings), 8 of which
have a predicted heat demand above 500
MWh/year.
 1,694 domestic properties within the zone that
could have the potential to connect to a network.  
Map DHN4: Ferguslie Park 
Map DHN5: North Renfrew
Page 54 of 140

Page 61

P a g e | 45
Potential local energy sources include the River Clyde or White Cart Water for water source heat
pumps, similar to the Queens Quay heat network opposite. This also brings opportunities to explore
cross-border collaborations and partnership working through discussions with operators on future
plans to extend or expand to supply heat to this network zone, or to link networks to increase
resilience. 
There is also a moderately productive aquifer in this zone which could be used as a heat source, as
well as large areas of open space which may have potential for ground source heat pumps, or as a
site for an energy centre. 
Within the Local Development Plan, this zone contains a core town centre, as well as a large transition
area; development opportunity sites; and a number of sites earmarked for housing supply
throughout the zone. There are large clusters of social housing throughout the centre and lower half
of the zone from west to east, with the anchor loads also forming a belt across the middle of the zone. 
6. Moorpark and Newmains Potential Heat Network
Zone:
 an area of 198 hectares 
 an estimated heat demand of 73GWh/year
 12 anchor loads (9 public buildings), 6 of which
have a predicted heat demand above
500MWh/year. 
 1,892 domestic properties within the zone that
could have the potential to connect to a network.
Potential local energy sources include the White Cart
Water. 
There is a moderately productive aquifer in this area which could be used as a heat source, as well as
significant areas of open space which may have potential for ground source heat pumps, or as a site
for an energy centre. 
Within the Local Development Plan, this zone contains a strategic economic investment location, as
well as transition areas development opportunity sites; and 2 sites earmarked for housing supply.
There are large clusters of social housing throughout the centre and the north of the zone, with the
anchor loads dispersed throughout the zone. 
Map DHN6: Moorpark and Newmains
Page 55 of 140

Page 62

P a g e | 46
Next Steps–Heat Network Zones Focus for Delivery Plans:
When developing the Delivery Plans, each of these 6 first phase heat network zones will be explored
further, including verifying heat demand data; exploring the potential heat sources; engaging with
the potential non-Council anchor loads; and investigating the outline costs of installation and
potential savings (carbon and cost savings) associated with a potential heat network.
This engagement will include discussions with relevant Housing Associations to look at potential for
coordination of capital replacement work programmes, such as boiler replacements to identify key
timescales to improve viability of a heat network. Community engagement will also be key across all
tenures and property ownership, including local businesses and 3rd sector organisations, in order to
build knowledge and understanding of district heating and the benefits it can bring if implemented
locally.
Those areas not currently within afirst or second phase heat network zone will be looked at in
closer detail to identify opportunities for smaller scale networks or communal heat sources.
Page 56 of 140

Page 63

P a g e | 47
Overview of the Potential SecondPhase Heat Network Zones
These second phaseareas have lower heat demand and fewer potential anchor loads within each
zone.
7. Hawkhead and Dykebar Potential Heat Network Zone:
 an area of 57 hectares 
 estimated heat demand of 11GWh/year
 3 anchor loads (all public buildings), all of which are estimated
to have a heat demand above 500MWh/year.
 very low levels of social housing, but Local Development Plan
has 2 housing sites within and bordering this zone.
 299 domestic properties within the zone that could have the
potential to connect to a network.
 potential local energy sources: the White Cart Water; a
productive aquifer; or open space which may have potential for
ground source heat pumps, or as a site for an energy centre.
8. Millarston Potential Heat Network Zone:
 an area of 24 hectares 
 estimated heat demand of 6.4GWh/year
 3 anchor loads (no public buildings), 2 of which are estimated to
have a heat demand above 500MWh/year.
 low levels of social housing, but Local Development Plan has 2
housing sites bordering this zone.
 125 domestic properties within the zone that could have the
potential to connect to a network.
 potential local energy sources: a productive aquifer or open space
which may have potential for ground source heat pumps, or as a
site for an energy centre. 
Map DHN7: Hawkhead and
Dykebar 
Map DHN8: Millarston
Page 57 of 140

Page 64

9. East Ferguslie Heat Network Zone:
 an area of 151 hectares 
 estimated heat demand of 60 GWh/year
 6 anchor loads (no public buildings), 5 of which are estimated to have a
heat demand above 500MWh/year.
 mainly commercial and industrial - low levels of social housing, but
Local Development Plan has 5 housing sites bordering this zone.
 208 domestic properties within the zone that could have the potential
to connect to a network.
 potential local energy sources: wastewater treatment works or open
space which may have potential for ground source heat pumps, or as a site for an energy
centre. 
10. Linwood Heat Network Zone:
 an area of 270 hectares 
 estimated heat demand of 70 GWh/year
 15 anchor loads (2 public buildings), 10 of which are estimated to have
a heat demand above 500MWh/year.
 high levels of social housing, and Local Development Plan has 6
housing sites within this zone.
 2,110 domestic properties within the zone that could have the potential
to connect to a network.
 potential local energy sources: the Black Cart Water; Linwood Moss
former landfill site; Household Waste Recycling Centre; Scottish Water pumping station; or
open space which may have potential for ground source heat pumps, or as a site for an energy
centre. 
11. Gallowhill Heat Network Zone:
 an area of 98 hectares 
 estimated heat demand of 34 GWh/year
 7 anchor loads (no public buildings), 1 of which are estimated to have a
heat demand above 500MWh/year.
 high levels of social housing, but Local Development Plan has 2 housing
sites within this zone.
 1,832 domestic properties within the zone that could have the potential
to connect to a network.
Map DHN9: East
Ferguslie Park
Map DHN10: Linwood 
Map DHN11: Gallowhill
Page 58 of 140

Page 65

 potential energy sources: open space which may have potential for ground source heat
pumps, or as a site for an energy centre; potential to link networks with Shortroods and
Laighpark heat network zone to the west. 
12. Johnstone South Heat Network Zone:
 an area of 82 hectares 
 estimated heat demand of 19 GWh/year
 4 anchor loads (no public buildings), 2 of which are estimated to have a
heat demand above 500MWh/year.
 high levels of social housing, but Local Development Plan has 2 housing
sites within this zone and 2 housing sites bordering this zone.
 853 domestic properties within the zone that could have the potential
to connect to a network.
 potential local energy sources: open space which may have potential for
ground source heat pumps, or as a site for an energy centre. 
13. Johnstone North Heat Network Zone:
 an area of 30 hectares 
 estimated heat demand of 10 GWh/year
 2 anchor loads (1 public building), 1 of which are estimated to have a
heat demand above 500MWh/year.
 low levels of social housing, but Local Development Plan has 1 housing
sites within this zone.
 380 domestic properties within the zone that could have the potential
to connect to a network.
 potential local energy sources: the Black Cart Water; wastewater
treatment works; or open space which may have potential for ground
source heat pumps, or as a site for an energy centre. 
14. Johnstone East Heat Network Zone:
 an area of 80 hectares 
 estimated heat demand of 39 GWh/year
 16 anchor loads (4 public buildings), 8 of which are estimated to have a
heat demand above 500MWh/year.
 high levels of social housing, but Local Development Plan has 3
housing sites within this zone and 5 housing sites bordering this
zone. 
Map DHN12:
Johnstone South 
Map DHN13: Johnstone
North
Map DHN14: Johnstone
East
Page 59 of 140

Page 66

 816 domestic properties within the zone that could have the potential to connect to a
network.
 potential local energy sources: the Black Cart Water or open space which may have potential
for ground source heat pumps, or as a site for an energy centre. 
15. Brediland Heat Network Zone:
 an area of 67 hectares 
 estimated heat demand of 15 GWh/year
 9 anchor loads (1 public building), 3 of which are estimated to have a
heat demand above 500MWh/year.
 clusters of social housing, but Local Development Plan has 2 housing
sites within this zone and 4 housing sites bordering this zone.
 637 domestic properties within the zone that could have the potential
to connect to a network.
 potential local energy sources: Staneley reservoir or open space which may have potential
for ground source heat pumps, or as a site for an energy centre. 
16. Glenburn Heat Network Zone:
 an area of 29 hectares 
 estimated heat demand of 11 GWh/year
 5 anchor loads (1 public building), 3 of which are estimated to have a
heat demand above 500MWh/year.
 clusters of social housing, and Local Development Plan has 1 housing
site within this zone and 1 housing site bordering this zone.
 321 domestic properties within the zone that could have the potential
to connect to a network.
 potential local energy sources: Staneley reservoir or open space which may have potential for
ground source heat pumps, or as a site for an energy centre. 
17. Hillington West Heat Network Zone:
 an area of 192 hectares 
 estimated heat demand of 93 GWh/year
 18 anchor loads (1 public building), 17 of which are estimated to have a
heat demand above 500MWh/year.
 no social housing – commercial and industrial area.
 7 domestic properties within the zone that could have the potential to
connect to a network.
 local energy sources include waste heat recovery from industrial processes.
Map DHN15: Brediland
Map DHN16: Glenburn 
Map DHN17: Hillington
West
Page 60 of 140

Page 67

P a g e | 51
AdditionalHeat DecarbonisationOpportunities:
Foron-gas and off-gas grid properties, a variety of indicators were used to assess the most
appropriate heat decarbonisationpathway for eachproperty across Renfrewshire. 
Not all buildings may be suitable to connect to a district heating network; not all owners may wish to
connect to a network; and not all areas may be suitable to implement a district heating network.
Alternatives were explored to identify alternative suitable options for low carbon heat, in particular
heat pumps, biomass and electrical heating. 
Heat pumps are suitable for most buildings–capturing heat from outside and moving it into the
building using electricity.The heat energy delivered is more thanthe electricalenergy usedto
power the system.
A standard heat pump doesn’t provide hot water on demand - storage is required for hot water, and
so space is needed for a hot water cylinder which may not be available in all properties.
Air Source Heat Pumps (ASHPs): the most common type of domestic heat pump which transfers heat
from the outside air to water and then heats rooms via radiators or underfloor heating. Hot water is
stored in a cylinder for hot taps, showers, etc. Space is required outside the property for the unit. 
Ground Source Heat Pumps (GSHPs): transfer heat from the ground outside the building to water to
heat your radiators or underfloor heating. Hot water is stored in a cylinder for hot taps, showers, etc.
Land near the building which is suitable for digging boreholes is required as well as space inside your
home for the indoor heat pump unit. 
Scottish homeowners can apply for a grant of between £7,500 and £9,000 towards installing a heat
pump. 
When looking at potential for heat pumps across Renfrewshire, categories were used to indicate the
most straightforward or already in place (Category 0) up to the most challenging properties, where
significant alterations would be required to be heat pump ready (Category 3):  
Page 61 of 140

Page 68

Category Description
Category 0 Already have low or zero emissions heating systems, e.g. heat
pumps, biomass or connected to communal or district heating
Category 1 Considered highly suitable for heat pump retrofit, i.e. well
insulated properties with a wet central heating system
Category 2 Would require moderate fabric and/or heating system upgrades
to be heat pump retrofit ready
Category 3
Would require significant fabric and/or heating system upgrades
to be heat pump retrofit ready or properties that are not suitable
for heat pump retrofit
Table 3: Heat PumpReady Categories of Domestic Properties
There were no large hot spot clusters of Category 1 and 2 properties identified at intermediate zone
level for off-gas grid properties - most Category 1 and 2 were found in Lochwinnoch, Renfrew,
Castlehead and Johnstone with most properties sparsely distributed across Renfrewshire. In on-gas
grid areas, there were clusters of Category 1 properties in Gallowhill, Shortroods, Renfrew, Loanhead,
Ferguslie, Brediland, Howwood, and Spateston. 
Some of these clusters overlap with areas which were identified as having potential for heat network
zones. Delivery Plans will explore and prioritise the most suitable, cost effective and efficient heat
solution opportunities in each area, ensuring solutions are tailored to each community to bring the
greatest benefits.     
For Category 3 properties which are not suitable for heat pump retrofit, electrical heating (storage or
direct) or biomass heating are likely to be the most viable decarbonisation technologies. In off-gas
grid areas, the large numbers of Category 3 homes deemed suitable for electric heating suggests that
these properties do not currently have wet heating systems (e.g. oil-fired or LPG heating) or that
energy efficiency improvements required would be too costly to install, meaning that heat pump
operation would be too expensive. 
Considerations as part of the Delivery Plans:
o heat pumps use electricity and are more efficient than gas boilers, but good insulation levels
are required to ensure warm homes that don’t unnecessarily increase electricity costs beyond
what is affordable.
o initial analysis does not include consideration of electricity grid impacts or costs of grid
upgrades to accommodate heat pumps. Engagement with SPEN on grid constraints across
all solutions is ongoing.
Page 62 of 140

Page 69

o electrical and biomass were included in the analysis for alternative heat solutions in order to
not restrict fuel choice further for those areas at higher risk of fuel poverty (i.e., those in off-
gas grid areas).
Page 63 of 140

Page 70

P a g e | 54
Additional Considerations:
Many areas inRenfrewshireface additional challenges, including mixed use; mixed tenure; and
conservation areas and listed buildings. 
Renfrewshire, as with many areas across Scotland, has large concentrations and clusters of buildings
which bring additional challenges when identifying solutions for energy efficiency and
decarbonisation of heat. Mixed-tenure and mixed-use buildings can include a mixture of owner
occupied, private rented and social housing, and non-domestic uses, or simply multiple ownership
within the same tenure. Historic buildings include the buildings that are within conservation areas or
those that are listed buildings. 
These categories can be more challenging and may require established alternative approaches and
regulation for the installation of low carbon heat and energy efficiency solutions alongside specific
advice and support relating to the installation of these solutions. This cross-referencing of data will
help to inform the Delivery Plans in Phase 2, taken in consideration of the wider strategy context. 
The data was analysed initially at Ward level and will be explored in more detail in the Delivery Plans,
with the following results for consideration4:   
4 Some clusters cross Ward boundaries and have been counted in each Ward
Mixed Tenure: residential development which has a range of tenures, including owner occupier;
private rented; and social housing.
Mixed Use: a building that has residential, commercial, industrial and/or entertainment uses in
one space. This includes buildings with commercial premises on the ground floor and residential
properties above.
Conservation Areas: areas of special architectural or historic interest, the character or appearance
of which it is desirable to preserve or enhance.
Listed Building: listing is the process by which buildings of special architectural or historic interest
are protected.
Page 64 of 140

Page 71

Category Wards in which categoryis Found No. of
Clusters
Domestic Properties in
Conservation Areas
Johnstone North, Kilbarchan, Howwood and
Lochwinnoch  3 small
Paisley Northeast and Ralston 2 small
Paisley East and Central 3 small
Paisley Northwest 1 small
Domestic Listed Property
Areas
Bishopton, Bridge of Weir and Langbank 1 small
Paisley East and Central  7 small
Paisley Northwest 5 small
Paisley Southeast 2 small
Table 4:DomesticConservation and Listed Properties 
Domestic and Non-Domestic Mixed-Use Areas are found in all
Wards, with Renfrew North and Braehead; Renfrew South and
Gallowhill; Paisley Southeast; Paisley East and Central; and
Paisley Northwest having the highest levels (all with 10+
small/medium clusters). This is followed by Johnstone North,
Kilbarchan, Howwood and Lochwinnoch and Paisley
Southwest with 10 small clusters and Houston, Crosslee and
Linwood with 6 small clusters. 
There are also clusters of non-domestic properties in
conservation areas in Paisley East and Central; Lochwinnoch;
Kilbarchan; Houston and Bridge of Weir. 
Further considerations:
As well as strategic consideration of these more challenging aspects of energy efficiency
improvements and potential for connection to district heating networks, the Delivery Plans will focus
on gathering information on public buildings and other stakeholders on areas such as capital
replacement programmes for boilers and radiators in order to coordinate and future proof potential
networks and ensuring low temperature networks where viable. 
Domestic & Non-Domestic
Mixed Use
Page 65 of 140

Page 72

P a g e | 56
Next Steps:
We will continueto engage with all stakeholders in Phase 2 of Renfrewshire’s LHEES, building on
existingactivities and identifying new opportunities collectively to accelerate change. 
Delivery of Renfrewshire’s LHEES will be a result of collaborative work - led by the Council, but co-
designed with residents, public, private and community organisations and with all stakeholders
working together on an area-wide effort to bring about the pace and scale of change required for
area-wide energy efficiency improvements and decarbonisation of heat, leading to affordable
warmth, increased energy security and resilient communities, alleviation of fuel poverty and
reducing carbon emissions through reducing our reliance on fossil fuels. 
The good news is that we’re not starting from scratch – a solid foundation has been created and
we’re building on existing activities, expertise and knowledge across all partners in order to ensure
we’ll have cleaner air; warm homes; and be supporting sustainable jobs, with a managed stable
energy transition that that creates resilient communities and a better place for us all to live, work
and spend time in. 
Given the significant impact on emissions of energy use within Renfrewshire area, developing
projects with our communities and partners that have a publicengagement focus,will be vital if we
are to work towards net zero by 2030.
Our 5 key focus areas for Phase 2 are: 
1.Development of Costed Area-Based Delivery Plans:we will look strategically and holistically
across the whole Renfrewshire area to identify and explore strategically important (large-scale) as
well as local (small scale) opportunities.  These projects, interventions and activities will be outlined
over 20 years, but with an initial 5 year focus - aligning with Renfrewshire’s Plan for Net Zero and
prioritised based on agreed weightings in line with national and local priorities and targets.   
2. Stakeholder Engagement andConsultation:this is essential across all phases inthe design and
delivery of Renfrewshire’s LHEES. Two-way communication channels will remain in place as
projects and activities are implemented to ensure everyone is informed of progress and can provide
feedback on opportunities in their local areas and on our collective journey to net zero, and the
managed energy transition that will play a key role in this. This engagement will ensure that areas of
focus respond to and are tailored to meet the specific local needs of different communities’ social
and environmental issues.
Page 66 of 140

Page 73

3. Socio-economic Assessments:implementingRenfrewshire’s LHEES willdeliver multiple
outcomes simultaneously. Not all impacts and outcomes can be monetised (e.g., fuel poverty
alleviation, local job creation or carbon emissions reduction). When quantifying projects within the
Delivery Plans, we will undertake area-based socio-economic impact assessments to identify and
evaluate direct and indirect impacts and benefits of the proposed interventions and projects to be
implemented through Renfrewshire’s LHEES.  Viable and replicable projects and low regret options
will be prioritised, and appropriate zones for priority area-based delivery programmes will be
designated across the Renfrewshire area.  
4.Development ofStrategically Important Energy Opportunities with Partners:collaboration and
partnership working are key to deliver change at the pace and scale required. Using an area-based
data approach to identify potential large-scale energy projects and engaging all stakeholders to
maximise these opportunities, we will ensure economies of scale and best value. This includes
exploring a range of delivery models, including joint ventures, community ownership and public-
private collaborations to develop solutions and play to the strengths and knowledge of all
stakeholders. 
5. A Stable, Managed Energy Transition:ensuring an integrated ‘whole system’view. Equal
consideration of supply and demand and promoting local energy solutions planned with
community involvement will ensure investment in infrastructure that brings direct benefits to all our
communities, including energy cost savings; resilience and security of supply; and positive impacts
on fuel poverty (including removal of energy efficiency as a driver for fuel poverty. Producing
pipeline of major infrastructure projects will link with skills transition and local employment
opportunities and identify skills gaps, shortages and requirements ahead of time and will
encourage investment in local areas; enable local supply chain and manufacturing opportunities to
be identified; de-risk private sector investment; and assist the regeneration of local areas. 
It is recognised that support and advice will be key through the implementation of
Renfrewshire’s LHEES and at all stages we will signpost to funding and ensure that
impartial advice and support is in place in advance of change.
Page 67 of 140

Page 74

P a g e | 58
Challenges and Opportunities:
Thechallenge to improve energy efficiency and decarbonise heat on an area-wide basis cannot be
underestimated –but a stable, managed energy transition brings significant opportunities to design
better systems to distribute benefits fairly. 
The journey to net zero and the energy transition will transform our communities. Significant
progress has been made, providing a solid foundation but change at the scale and pace required
brings challenges. These challenges also present huge opportunities – growing our economy,
community wealth building and local job creation, improving health and wellbeing while reducing
fuel poverty and ensuring resilient, sustainable communities: 
CHALLENGES & ISSUES OPPORTUNITIES & BENEFITS
High levels of fuel poverty - across
Renfrewshire Council, 22% of households
are in fuel poverty, and 7.4% are in extreme
fuel poverty)
Improved energy efficiency will remove poor
energy efficiency as a driver for fuel poverty as well
as reducing energy demand and reducing energy
costs and improving health and wellbeing, incl.
mental health through targeted, large-scale energy
efficiency programmes and the provision of
affordable warmth via low carbon energy to all
communities
High levels of pre-1990s housingstock
(~75%) which generally has lower levels of
energy efficiency and the challenges
associated with retrofitting energy
efficiency measures and renewable
technologies onto existing buildings,
particularly listed and historic buildings,
with not all buildings being suitable for
retrofitting due to cost and/or viability
Local job creation and upskilling of local workers in
energy transition industry, incl. supply chain and
manufacturing opportunities with the pipeline of
projects and work programmes giving confidence
to these industries, enabling investment and
funding to be aligned with programmes of work
Grid constraints and/or geographical
constraintsmaking energy projects difficult
to install. Areas with lower population
density to make district heating networks
viable - a mix of urban and rural, with
clusters of off gas grid and population
Community benefits with local energy generation
infrastructure solutions tailored to fit distinct local
areas and needs alongside opportunities to
decentralise energy will end reliance on fossil fuels,
reducing carbon emissions and building resilience
Page 68 of 140

Page 75

density of 702.9 residents per square
kilometre (Glasgow: 3,555/sq. kilometre)
and security of supplywhile piloting innovative
technology and solutions to solve common barriers
Populationandhousing growth
infrastructure impacting on carbon
emissions – 7.2% increase in the number of
households in 11 years (2011-2022 census
data)
Matching local demand with local supply-
opportunities for local low carbon and renewable
energy generation to meet the increased heat
demands, with new developments having
significant potential for infrastructure to be
implemented bringing opportunities for
sustainable, resilient communities
Gaps indata:traditionally issues around
commercial data being shared, leaving
gaps in baselines, monitoring and progress
and leading to potential missed project
opportunities
Low cost, low carbon energy will assist businesses
in all areas but in particular rural areas, where
higher energy costs can prevent them setting
up/remaining viable – this also has a positive
impact on local employment 
The delivery and implementation of Renfrewshire’s LHEES also has some specific challenges, namely: 
1. Finance and Funding: significant capital investment at a time ofconstraints for many
Challenge: The Council would be unable to solely deliver or fund all of the projects and
interventions required, and collaboration and commitment from all stakeholders alongside long-
term financial resources and large-scale investment are needed. It will require government at all
levels to redirect and, in some cases, reprioritise finance to support the scale of change required.
Lower carbon options are often less expensive long term, but upfront costs can be a barrier and
tenants often have a lack of control over measures to reduce energy costs.   
Opportunity: The transition brings opportunities to identify more innovative and collaborative
ways to finance action across stakeholders, including new business models; joint ventures and
partnership projects.  There are also opportunities for knowledge sharing and collaboration
across stakeholders, to understand different approaches, solutions and best practice. This
increased partnership working at all levels of government will help to signpost residents and
businesses to advice, grants and financial support and maximise opportunities for programmes
that prioritise those least able to pay who would benefit most from interventions. 
Page 69 of 140

Page 76

2. Resources and Skills:
Challenge: The scale of transformation may result in bottlenecks in delivery due to skills
gaps/shortages and supply chain issues in key areas. 
Opportunity: Setting out pipelines of projects enables manufacturers and supply chain
businesses to identify opportunities and potential for local businesses to exploit gaps. For local
workforce and training providers, investment in the upskilling of our citizens in areas of skills gaps
or demand offers sustainable career paths and ensures local communities’ benefit from
infrastructure delivery. This approach will ensure community wealth buildings and local job
creation across all aspects – installation, manufacturing, construction, maintenance, repairs and
circular economy waste reprocessing. 
Throughout stakeholder engagement, challenges were identified which must be addressedto
mitigatethe impact on the successful delivery ofRenfrewshire’s LHEES. Short term actions include
working collaboratively to find solutions to these challenges.
Page 70 of 140

Page 77

P a g e | 61
Environment, Housing & Infrastructure
Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA1 1BR
Page 71 of 140

Page 78

Page 72 of 140

Page 79

___________________________________________________________________ 
To:  Planning and Climate Change Policy Board 
On:  23 January 2024
___________________________________________________________________ 
Report by: Chief Executive 
___________________________________________________________________ 
Title:  Tree Preservation Order Requests
___________________________________________________________________ 
1. Summary 
1.1 This report seeks to provide an update to the Tree Preservation Order (TPO)
requests which were considered at previous meetings of the Planning and
Climate Change Policy Board. 
1.2 The requests submitted are considered in line with the relevant legislation,
namely, Section 160 of The Town and Country Planning (Scotland) Act 1997
as amended by the Planning etc (Scotland) Act 2006, and within the
procedures set out in the Town and Country Planning (Tree Preservation
Order and Trees in Conservation Areas) (Scotland) Regulations 2011. 
1.3 The report recommends that the tree preservation orders are confirmed in
respect of the following sites:
 Land to the south of Stanely Reservoir, Paisley
 Trees at Potterhill Avenue, Paisley
 Trees at St. Marks Church, Paisley 
1.4 The report also notes that the 28 day consultation period in relation to the
TPO at Inchinnan Road, Renfrew is currently ongoing and a report will be
returned to the March meeting of the Planning and Climate Change Policy
Board for confirmation or otherwise of the order.   
________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Board:
Item 3
PACC230124 Page 73 of 140

Page 80

(i) Confirm the tree preservation orders in respect of the sites known as Land
to the south of Stanely Reservoir, Paisley, Trees at Potterhill Avenue,
Paisley and Trees at St. Marks Church, Paisley and agreed that officers
make the orders public and register them with the Land Registry for
Scotland. 
(ii) Note that the TPO designation agreed at the meeting of the Planning and
Climate Change Policy board in November 2023 in respect of the site at
Inchinnan Road, Renfrew is currently subject to a period of public
consultation. 
(iii) Note that the TPO designation in relation to the site at Inchinnan Road,
Renfrew will be returned to a future meeting of the Planning and Climate
Change Policy Board for confirmation or otherwise of the order.
___________________________________________________________________ 
3. TPO Requests Previously Considered 
3.1 At the meeting of the Planning and Climate Change Policy Board in August
2023, it was agreed that TPO designations would be placed on the following
sites: 
 Land to the south of Stanely Reservoir, Paisley
 Trees at Potterhill Avenue, Paisley
 Trees at St. Marks Church, Paisley 
3.2 In respect of the sites noted above and in line with the Renfrewshire Planning
and Development Tree Policy 2022, and the relevant legislation relating to
Tree Preservation Orders, Officers have, undertaken the following: 
 Prepared the relevant orders and made them available online for review;
 Served the orders on relevant parties including landowners;
 Published public notices in the local press advising of the orders; and
 Provided an opportunity for comments to be made by any interested party
in relation to either of the orders. 
3.3 The 28 day consultation period has now concluded in respect of the three
aforementioned sites with comments being received in relation to each site. 
The comments are summarised as follows. 
Land to the South of Stanely Reservoir, Paisley 
3.4 The owners of the site have advised that they have been in discussion with
Scottish Water in relation to the development of a site utilising renewable
energy and sustainable building materials.  The owners have noted that the
intended plans for the site include: 
 Development of 20 homes with renewable energy solutions, commonly
known as ‘green homes’ with support of Scottish Water;
 Formation of dog walkers path around the perimeter of the reservoir;
Page 74 of 140

Page 81

 Development of access to the site for walkers and bird watching;
 Removal of drug paraphernalia, rubbish and the impact of flytipping;
 Development of a public amenity area to the eastern fringes of the site
including children’s play area/picnic site. 
3.5 In addition the owners also comment, as follows, on the assessment
undertaken in relation to the trees in question: 
 The report does not take into consideration the impact of financial value
from an owners perspective;
 The survey is limited in its interpretation of amenity as it does not consider
the widescale and obvious signs of anti-social behaviour related to the
immediate area (drug use/fires/large group gatherings) 
3.6 An objection has also been received in respect to the TPO noting that Scottish
Water are currently being approached to investigate the potential for the
optimisation of development, maximising power generation for the wider
Foxbar  area, (potentially including RAH Paisley), and rather than a blanket
protection, the Council and their arboricultural specialists should be supporting
and encouraging this beneficial additional work- (all in support of NPF4 and
the adopted local plan). 
3.7 Support is offered to the TPO from Cllr Lorraine Cameron who notes that the
area is popular with locals and has become a habitat for wildlife including bats
which are a protected species.  In addition, Cllr Cameron notes that according
to ancient maps, there may be a standing stone, yet to be discovered,
adjacent, or in, the area in question. 
3.8 The above comments, both in support and against the TPO, are noted and it
is acknowledged that the owners are potentially seeking to progress plans for
alternative development on the site.   
3.9 In all regards, the independent arboriculturist, who undertook the survey of the
trees, concluded that the site is of significant landscape importance that
definitely merits a TPO designation.  The comments received as part of the
consultation process are noted however they do not raise any matters which
would give reason not to apply a TPO.  Should development on the site come
forward in future, the developer will require to take account of the TPO
designation and how trees could be protected and managed appropriately.  It
is considered that such matters could be considered and controlled via any
planning permission granted. 
3.10 It is recommended that the TPO in respect of Land to the south of Stanely
Reservoir, Paisley is confirmed. 
Trees at Potterhill Avenue, Paisley 
3.11 No objections were received in respect of the trees at Potterhill Avenue,
Paisley however comments were received which sought clarification on the
ownership and the ongoing maintenance of the trees.
Page 75 of 140

Page 82

3.12 In light of the comments received, it should be noted that the trees forming
part of the TPO are within private ownership and in this regard the
responsibility of the ongoing maintenance of the trees in question is a matter
for the respective owners. 
3.13 It is recommended that the TPO in respect of Trees at Potterhill Avenue,
Paisley is confirmed. 
Trees at St. Marks Church, Paisley 
3.14 Correspondence was received from the Church in question in respect of the
TPO at St. Marks Church, Paisley which sought clarification on the TPO
process and details of the survey undertaken. 
3.15 Clarification was provided to the church official and a copy of the independent
arboriculturist report was provided for their reference and records. 
3.16 It is recommended that the TPO in respect of Trees at St. Marks Church,
Paisley is confirmed. 
Trees at Inchinnan Road, Renfrew 
3.17 At the meeting of the Planning and Climate Change Policy Board in November
2023, it was agreed that TPO designations would be placed on trees at
Inchinnan Road, Renfrew. 
3.18 In respect of the sites noted above and in line with the Renfrewshire Planning
and Development Tree Policy 2022, and the relevant legislation relating to
Tree Preservation Orders, Officers have, undertaken the following: 
 Prepared the relevant orders and made them available online for review;
 Served the orders on relevant parties including landowners;
 Published public notices in the local press advising of the orders; and
 Provided an opportunity for comments to be made by any interested party
in relation to either of the orders. 
3.19 The 28 day consultation period is currently ongoing in respect of the trees at
Inchinnan Road, Renfrew.  Following the conclusion of the consultation
period, any comments received will be considered and a further report brought
back to the Planning and Climate Change Policy Board for consideration and
determination. 
4 Next Steps 
4.1 The TPO orders in respect of the sites known as Land to the south of Stanely
Reservoir, Paisley, Trees at Potterhill Avenue, Paisley and Trees at St. Marks
Church, Paisley are confirmed, made public and registered with the Land
Registry for Scotland. 
Page 76 of 140

Page 83

4.2 Following conclusion of the public consultation in respect of the TPO at
Inchinnan Road, Renfrew, the TPO will be returned to a future meeting of the
Planning and Climate Change Policy Board to take account of any comments
received and to confirm, or otherwise the order.
___________________________________________________________________ 
Implications of the Report 
1. Financial – None.   
2. HR & Organisational Development – None. 
3. Community/Council Planning – 
4. Legal – The recommendations in the report would require tree preservation
orders to made in relation to the sites in question.  Should the orders be
confirmed they would require to be lodged with the Land Register of Scotland. 
5. Property/Assets – None. 
6. Information Technology – None. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report.  If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website.   
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – None. 
11. Privacy Impact – None. 
12. COSLA Policy Position - None. 
13. Climate Risk – None.
___________________________________________________________________ 
Author: David Love, Chief Planning Officer
Tel: 07483410182; Email: david.love@renfrewshire.gov.uk
Page 77 of 140

Page 84

Page 78 of 140

Page 85

___________________________________________________________________ 
To:  Planning and Climate Change Policy Board 
On:  23 January 2024
___________________________________________________________________ 
Report by: Chief Executive 
___________________________________________________________________ 
Title:  Developer Contributions (Education) – key metrics
___________________________________________________________________ 
1. Summary 
1.1 This report seeks to provide an update to members on progress in preparing a
new developer contributions policy for education requirements arising from
new housing development in Renfrewshire. 
1.2 The draft policy is expected to be brought to the Planning and Climate
Change Policy Board in the near future. In the meantime, this report presents
an outline of the key metrics which are required to support such a new policy.
This report seeks members consideration of these key metrics ahead of
presentation of the new policy to a future Board. 
________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Board:
(i) Consider the key metrics outlined in this report and their implications for
any future policy to be applied to applicable planning applications;
(ii) Note the key metrics as indicated within this report as being an indicative
basis on which to prepare a draft Developer Contributions (Education)
policy for Renfrewshire Council; 
________________________________________________________________________________ 
3. Background 
3.1 Developers (and other applicants for planning permission) are often expected
to offset the impact of their proposed development by making contributions
(including in kind and financial) to necessary social infrastructure in a local
area or other local services. 
Item 4
PACC230124 Page 79 of 140

Page 86

These can include a range of contributions including financial sums to assist
in meeting the increased number of school-age pupils which could be
generated by building new housing in a particular community. 
3.2 Another term for these contributions is “planning obligations” and they are
usually entered into in accordance with Section 75 of Town and Country
Planning (Scotland) Act 1997, as amended, and are commonly referred to as
S75 Agreements.  They are often used where a planning condition or another
form of legal agreement would not be appropriate to address the impact of the
development in question. 
3.3 The principle of such planning obligations is guided by legislation which sets
out that such agreements must meet a series of tests to be enforceable
against the landowner – these include being necessary to make a proposal
acceptable and reasonable in terms of scale in relation to the proposal in
question. These tests are set out in Scottish Planning Circular 3/2012. 
3.4 In Renfrewshire, the adopted Local Development Plan (LDP2; 2021) sets out
a policy (policy I8) for developer contributions. This states:
Contributions will be sought for the following items to address infrastructure
deficits and/ or a shortfall in infrastructure capacity that arise as a direct result of
new development. Any contribution sought will be appropriate, proportionate,
necessary and relevant to the nature of the development, its scale, and its
location:
 Education – additional classrooms and associated school facilities required 
to  support  the  operation  of  a  school,  related  to  the  number  of  pupils 
generated by the development; 
3.5 Renfrewshire Council now intend to develop a more detailed set of policy
guidance for planning applicants of new residential development. This new
policy intends to offer specific guidance for all future housing development in
the area that is yet to receive planning permission. This will be linked to
individual school catchments and to individual housing sites already identified
in LDP2 / Housing Land Audit and those yet to be identified. 
3.6 It should be borne in mind that such a policy will make clear that contributions
are intended to offset the impact of the new housing development and not to
overcome other existing deficiencies that may exist in terms of school
provision locally. 
3.7 Subsequent policy guidance will be prepared for other developer contributions
towards others community infrastructure. This current report deals with
education contributions only. 
4 Key metrics for new policy 
4.1 In preparing a new policy of this type there are several key metrics that need
to be agreed as the basis for any developer contributions. 
Page 80 of 140

Page 87

These include:  
 How many pupils are likely to be generated by new housing sites in
Renfrewshire;
 How much capacity exists in each school / by catchment;
 Where will the additional housing demand come from (the identified
supply);
 What would be a reasonable level of contribution to negotiate for each
additional pupil generated by the new housing (above capacity
thresholds);
 The scale of residential development site at which the developer
contribution policy becomes applicable; 
4.2 This report will examine each of these key metrics in turn and seek member
consideration of the approach being followed by officers in the preparation of
the draft policy regarding each. 
Pupil Product Ratio (PPR) 
4.3 To determine how many new pupils may arise from housing development in
Renfrewshire officers have traced back over the last 10+ years of built
housing and calculated the average number of pupils that attend local schools
from these developments. This can be broken down to denominational and
non-denominational schools and differentiated between primary and
secondary education. 
4.4 It is accepted that this assessment looks at the position as is (i.e. in 2023) as
opposed to what it may have been when the housing was first occupied.
Some households may have moved home, others will have moved into the
area. However, this calculation is the most accurate available to estimate the
likely pupils generated from a new housing development in Renfrewshire. 
4.5 The draft policy will detail the results of the above research for Renfrewshire
by school type.  The intention is that these figures will be updated annually
and reviewed to ensure they reflect the reality of the situation from new
housing developments once occupied. 
4.6 Consultants (Edge Analytics) are currently undertaking a piece of work for the
Council looking at roll projections across the whole school estate. The
outcomes of this analysis will feature in the new policy presented to Board in
due course. 
4.7 The pupil product ratios will show the average primary and secondary age
children that would be expected to be generated for each new house or flat
built in Renfrewshire. Although this may vary by specific location and
development, officers consider it more expedient to have one ratio for flats in
Renfrewshire by school type and one for houses by school type. The ratio for
flats will be lower than that for houses. 
Page 81 of 140

Page 88

4.8 Each planning application submitted is assessed on its individual components.
In some case the number and mix of housing types will be known at the
submission stage, in others this will be indicative only. By applying a pupil per
housing unit approach, we can ensure flexibility as circumstances of individual
developments change or are varied at the detailed design stage. 
Existing school capacity 
4.9 In an ideal world housing development would take place where sufficient
capacity exists to accommodate the predicted increase in pupil numbers at
the local schools. However, this is unlikely to always be the case as school
location tends to be relatively fixed, while new housing development depends
on land availability, local demand, suitability for that purpose and deliverability. 
4.10 The importance of identifying individual school capacity by catchment is that
housing development in locations where sufficient capacity exists to
accommodate the new pupils would not normally be expected to contribute
financially to addressing this impact, as the capacity is already there.  This
equation changes when the capacity of a school will be breached following the
development of the new housing. 
4.11 The current school roll and capacity for each Renfrewshire school will be
published online and updated annually. These figures will be available for the
publication of a new policy on developer contributions and used as the agreed
basis for the consideration of any planning application for residential
development going forward. 
4.12 The “notional capacity” of a typical Renfrewshire school is taken as 85% of its
operating capacity. This 85% threshold is broadly consistent with other
Scottish local authorities with similar policies. This is to allow for flexibility
across the age groups of the additional pupils expected to be accommodated
and to allow for requirements for general purpose rooms and ancillary space
as the roll changes. 
4.13 Each primary and secondary school in Renfrewshire will be placed into one of
3 categories based on its existing remaining capacity.  This categorisation will
allow all stakeholders to gain an appreciation of the current position for their
school catchment. It is intended that this will be utilised for the purposes of the
new developer contributions policy.
eg.
 85% or more 
 75% to 84% 
 74% or less 
Identified housing land supply 
4.14 The existing school capacities will be affected by planned housing
development. The Council’s Housing Land Audit (published annually) list all
know housing sites, either under construction or with or without planning
permission and includes all LDP2 allocated sites.
Page 82 of 140

Page 89

4.15 Using this information it is possible to predict potential changes in school
capacities in future years, assuming housing is subsequently developed in
expected format and timescale. In doing so it is important to realise that not all
housing will be built in the same school year and that not all homes will
immediately generate school age pupils. The identified housing land supply
will form an integral part of any new policy for developer contributions in
Renfrewshire. 
Developer contribution levels 
4.16 The new policy will set out the level of contribution sought in those cases
where the notional capacity of the school will be breached by completion of
the new housing. 
4.17 Examining current practice across Scotland, some local authorities apply a
per new housing unit calculation, some use an amount of contribution per
additional pupil predicted in that school catchment. Renfrewshire’s proposal is
to use the latter, as this relates the specifics of the new pupils generated to
the expected capacity available at the school concerned. 
4.18 In calculating what the contribution should be (per new pupil generated) there
are several factors to consider, including:
 Whether land is available to extend an existing school, or build a new
school as required to meet demand;
 Evidence of recently built or planned schools in Renfrewshire and the
construction costs associated with these;
 The impact of construction inflation on any set amount within a policy
over time;
 The policies and approaches of other Scottish local authorities in this
respect;
 Available information from other national sources of school construction
costs; 
4.19 In drafting the proposed new policy officers have sought evidence from
several sources, including Scottish Futures Trust (SFT), HubCo (who are
engaged on behalf of SFT in many new school projects across Scotland),
other local authorities with similar policies. Examples have been drawn from
other Scottish local authorities, however, very few of these have been
approved in the last 2 or 3 years and therefore could be considered to be out-
of-date. 
4.20 The local context is best exemplified by the estimated gross costs for the new
Paisley Grammar School construction, which is the most recent example we
have in Renfrewshire. This predicts an approximate cost per pupil of more
than £55,000. This can be compared with the current SFT metric which is
below £30,000 per pupil for new school development. 
Page 83 of 140

Page 90

4.21 Many Councils negotiate for a different level of contribution for secondary and
primary schools (due to the difference in space requirements and layouts of
both types of school) and it is likely that Renfrewshire will follow a similar
approach. 
4.22 Officer would suggest to members that contribution rates (whatever level is
agreed in the new Renfrewshire policy) will need to be kept under regular
review to allow for their revision as required. The contribution level itself would
be subject to any changes in the BCI rates that are published on a regular
basis. Construction inflation in recent years have demonstrated that costs can
be extremely unpredictable for one year to the next. In the context of house
building and enhanced school capacity these changes can be planned to be
delivered some years in advance and therefore the scope for movement in
predicted costs is greater the longer the timescale involved. 
Scale of site 
4.23 Another factor to be considered for the new policy is whether developer
contributions should be sought from every planning application for new
housing (where capacity threshold will be breached) or only for those above a
certain scale. For example, some other Councils apply a threshold below
which they do not expect contributions to be sought. 
4.24 Based on existing pupil product ratios, a development of 5 new houses would
generate approximately 2 new school pupils and a development of 10 homes
would result in about 5 additional school age pupils. Clearly the policy
approach taken could aim to apply this to even the smallest of housing sites.
However, there are a few factors to be considered in reaching this decision:
 Renfrewshire does not get a large number of planning applications for
sites of less than 10 dwellings and even fewer of less than 5 new
homes (see Table 1);
 If the Council are to seek to negotiate a Section 75 Agreement for
smaller sites this will place an additional resource burden on officer
time for smaller potential contributions; 
Table 1: Renfrewshire Housing Land Audit; 2022 
Number of sites
with capacity of
11 or more
dwellings
Number of sites
with capacity of 
6-10 dwellings
Number of sites
with capacity of 
5 or less dwellings
Under construction  33 1 0
With planning permission 28 8 3
Allocated for housing
(without permission to date)
46 4 5
Total 107 13 8 
4.25 When considering smaller sites and any applicable threshold for a new policy,
the issue of cumulative impact needs to be examined. Officers’ current
thinking is to suggest a threshold of 10 dwellings and above for the
negotiation of developer contributions to mitigate education impact. However,
this threshold would be caveated by an assessment of the cumulative impact
of all identified housing land supply in that school catchment. 
Page 84 of 140

Page 91

If the school’s notional capacity (85%) is estimated to be breached
(cumulatively) by all planned housing then contributions will be sought from all
housing development in that catchment, regardless of the proposed number of
dwellings or scale of the site.  This is considered reasonable given that it will
not be possible to specifically attribute the remaining school capacity to one
planned housing development and will avoid cases of the last applicant having
to meet a disproportionate share of any impact in that catchment. 
5 Next Steps 
5.1 Subject to members views on the suggested metrics outlined above, officers
will prepare a draft new policy and bring this to Planning and Climate Change
Policy Board for endorsement. The draft policy will then be published for a
period of stakeholder consultation and the views expressed will be reported
back to elected members. 
______________________________________________________ 
Implications of the Report 
1. Financial – Significant potential impact depending on the successful
implementation of any new developer contributions policy.   
2. HR & Organisational Development – Examination going forward of the
additional resources required to negotiate planning obligations as a result of
submitted / approved planning application. 
3. Community/Council Planning – 
 Our Renfrewshire is thriving – The new developer contributions policy
can assist in supporting new or enhanced community infrastructure
(schools) in connection with new housing for pupils living in the local
area;
 Building strong, safe, and resilient communities: The policy can assist in
the forward planning of education capacity requirements across
Renfrewshire’s varied communities and achieve positive education
outcomes for our younger residents; 
4. Legal – Likelihood of additional resource demand being placed on Council’s
Legal Team in terms of negotiating and confirming planning obligations for a
larger number of planning applications. 
5. Property/Assets – None. 
6. Information Technology – None. 
Page 85 of 140

Page 92

7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report.  If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website.   
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – None. 
11. Privacy Impact – None. 
12. COSLA Policy Position - None. 
13. Climate Risk – None.
___________________________________________________________________ 
Authors: 
Alasdair Morrison, Head of Economy and Development;
Tel: 07979 700472; Email: Alasdair.morrison@renfrewshire.gov.uk 
David Love, Chief Planning Officer
Tel: 07483410182; Email: david.love@renfrewshire.gov.uk
Page 86 of 140

Page 93

SUMMARY OF APPLICATIONS TO BE CONSIDERED BY
THE PLANNING AND CLIMATE CHANGE POLICY BOARD
ON 23/01/2024
RENFREWSHIRE COUNCIL
Item No.PROPOSAL:LOCATION:APPLICANT: WARD:
APPN. NO:
23/0112/PP Mr Brian Lees
Ardeen
Toward
Dunoon
PA23 7UA
74 Fulbar Street
Renfrew
PA4 8PB
Erection of residential
development comprising of eight
flats with associated access,
parking, bin store, boundary
treatment and landscaping
Ward 1
RECOMMENDATION: Grant subject to conditions
A
23/0283/PP Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA3 9UW
111 - 113 Renfrew
Road
Paisley
PA3 4DY
Erection of a secondary school
and community campus with
associated external amenities
including landscaping, access,
parking and sports pitches.
Ward 2
RECOMMENDATION: Grant subject to conditions
B
23/0504/LB The University of the
West of Scotland
Paisley Campus
High Street
Paisley
PA1 2BE
S Block
University Of The
West Of Scotland
Storie Street
Paisley
PA1 2BX
Installation of replacement
windows and doors, solar panels,
two ramps, railings, cladding and
a false floor. Erection of
extension; formation of window
and door openings; renewal of
roof; stonework repairs; internal
alterations and landscaping works
Ward 4
RECOMMENDATION: Grant subject to conditions
C
23/0505/PP The University of the
West of Scotland
Paisley Campus
High Street
Paisley
PA1 2BE
S Block
University Of The
West Of Scotland
Storie Street
Paisley
PA1 2BX
Installation of replacement
windows and doors, solar panels,
two ramps, railings, cladding and
a false floor. Erection of
extension; formation of window
and door openings; renewal of
roof; stonework repairs; and
landscaping works
Ward 4
RECOMMENDATION: Grant subject to conditions
D
Total Number of Applications to be considered =  4
Item 5
PACC230124 Page 87 of 140

Page 94

Page 88 of 140

Page 95

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Supplementary Report
Reference No.    23/0112/PP       
Agenda Item 
KEY INFORMATION 
Ward: (1) Renfrew
North and Braehead 
Applicant:
Mr Brian Lees 
Registered: 
07/03/2023 
RECOMMENDATION 
Grant subject to
conditions 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Erection of residential
development comprising of eight flats with associated
access, parking, bin store, boundary treatment and
landscaping 
LOCATION: 74 Fulbar Street Renfrew PA4 8PB 
APPLICATION FOR: Full Planning Permission 
This supplementary report should be read together with
the original report of handling considered by the
Planning and Climate Change Policy Board on 7th
November 2023.  Appendix 1 details the original report
of handling.   
BACKGROUND 
The Planning and Climate Change Policy Board at its
meeting on 7th November 2023 considered the attached
report of handling and decided to continue the consideration
of the report to allow a site visit to take place. The detailed
assessment of the proposed development is included in the
attached report of handling.   
SITE VISIT 
A site visit took place on the 10th January 2024 and those
members attending viewed the application site and its
surroundings. 
The site visit was conducted in accordance with the Protocol
for Site Visits (22 May 2018) and members attending did not
discuss the merits of the proposal. 
RECOMMENDATION 
As detailed in the report of handling which was considered
by the Planning and Climate Change Policy Board on 7th
November 2023, the application is recommended for
approval subject to conditions.   
 
 
Alasdair Morrison
Head of Economy &
Development
Item 5(a)
PACC230124 Page 89 of 140

Page 96

Renfrewshire Council Planning and Climate Change Policy Board Page 2 
Reason for Decision 
The proposal accords with the provisions of the Development Plan and there were no
material considerations which outweighed the presumption in favour of development
according with the Development Plan. 
Conditions 
1. That prior to the occupation of any flat hereby approved, the developer shall
resurface the sections of footway which are commensurate with the site boundaries
fronting Fulbar Street and Blysthwood Avenue. The footway shall be resurfaced to
a standard that is structurally adequate and to the satisfaction of the Planning
Authority. 
Reason: To ensure the standard of footway fronting the site is sufficient to serve the
development. 
2. That prior to the commencement of development on site, the developer shall submit
for the written approval of the Planning Authority a plan showing the location of a
bin collection area from where bins can be safely presented for collection. The plan
shall include a specification for all works neccesary to form the bin collection area
including and hard surfacing or boundary treatments. The bin collection area
thereafter approved shall be implemented on site and made available for use prior
to the occupation of any of the flats. 
Reason: To ensure that bins associated with the development can be presented for
collection safely. 
3. That prior to the commencement of development on site, the developer shall
provide a strategy for the written approval of the Planning Authority which details
the drainage of surface water from all areas of hard standing. The strategy shall
ensure that surface water from any areas of hard standing shall not discharge onto
the public road. The approved strategy shall thereafter be implemented on site, and
maintained for the life of the development. 
Reason: To ensure that surface water is managed appropriately in the interests of
sustainable drainage. 
4. That the development hereby approved shall be undertaken in accordance with
approved drawings 1848/AL(0)007 rev E titled ‘Plans as Proposed’ and
1848/AL(0)11 rev E titled ‘Elevations as Proposed’. No alterations to these plans
are to take place unless first submitted to and agreed in writing with the Planning
Authority. The combined bin and cycle store as shown in these drawings shall also
be constructed and made available for use prior to the occupation of any flat hereby
approved. 
Reason: To ensure the development is implemented in accordance with the
approved plans.   
5. Development shall not commence until a Bird Hazard Management Plan has been
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. The submitted plan shall include details of: 
 Management of any flat/ shallow pitched/green roofs on buildings within the site
which may be attractive to nesting, roosting and loafing birds. The management
Page 90 of 140

Page 97

Renfrewshire Council Planning and Climate Change Policy Board Page 3
plan shall comply with Advice Note 8 ‘Potential Bird Hazards from Building
Design’. 
The Bird Hazard Management Plan shall be implemented as approved on
completion of the development and shall remain in force for the life of the
development. No subsequent alterations to the plan are to take place unless first
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. 
Reason: It is neccesary to manage the development in order to minimise its
attractiveness to birds which could endanger the safe movement of aircraft and the
operation of Glasgow Airport. 
6. That prior to the commencement of development on site, the developer shall
provide for the written approval of the Planning Authority a specification detailing
the colour and texture of all finishing materials to be used on the external walls of
the building hereby approved. This shall include windows and all rainwater goods.
Only the materials within the approved specification shall thereafter be used in the
development of the site. 
Reason: To ensure the external materials are suitable for use in the interests of
visual amenity. 
7. That prior to the commencement of development on site, full details of all soft and
water landscaping works shall be submitted as part of a landscape strategy for the
written approval of the Planning Authority. The landscape strategy shall include (but
not be limited to) provisions in respect of:
 all proposed trees, shrubs, hedgerows, areas of grass/wildflower seeding,
turfing including size, species, spacing and location.
 all areas of hard standing including location and materials.
 a plan showing proposed site levels. 
 all areas of surface water including ponds, and measures for the sustainable
management and drainage of surface water where applicable. 
 the implementation of all biodiversity and habitat enhancements.
 a timetable for the implementation of the landscape strategy.
 a strategy for the future management and maintenance of all landscaped
areas including provision for replacement of trees, shrubs, hedgerows and
areas of grass/wildflower seeding and turfing if they were to become
diseased, die, become seriously damaged or are removed within 5 years of
being planted. 
The approved landscape strategy shall thereafter be implemented on site in
accordance with the approved timetable and shall be managed and maintained
thereafter for the life of the development. 
Reason: To ensure a robust landscaping strategy is implemented in the interests of
visual amenity, landscape character and biodiversity. 
8. That prior to the commencement of development on site, the developer shall
provide a specification for the written approval of the Planning Authority detailing
the location, design, materials and colour of all boundary fences, gates, walls, or
other method of enclosure to be installed at the site. Only the boundary fences,
gates, walls, or other methods of enclosure within the approved specification shall
thereafter be used in the development of the site. 
Page 91 of 140

Page 98

Renfrewshire Council Planning and Climate Change Policy Board Page 4 
Reason: To ensure the methods of enclosure are of a suitable design in the
interests of visual amenity. 
9. That prior to the commencement of development, a Construction Environmental
Management Plan (CEMP) shall be submitted to and approved in writing by the
Planning Authority.  The CEMP shall include (but not be limited to) provisions in
respect of:
 mitigation measures for potential dust, noise, and vibration impacts on nearby
properties, 
 waste management, pollution control and mitigation, 
 a plan showing existing drainage pipes and other utilities within the site and
procedures for how they will be safeguarded during construction,
 surface water management,
 procedures for monitoring compliance and dealing with any breaches of the
approved management plan,
 the formation of access from the public road to accommodate construction
vehicles including geometry, surfacing, and sightlines
 the additional signage on both public roads where access will be taken to
inform drivers of the construction vehicles.
 details of proposed temporary site compound for storage of materials,
machinery, and designated car parking. 
The measures set out within the approved CEMP shall thereafter be implemented
on site during the construction phase 
Reason: To ensure environmental impacts are mitigated during the construction
phase, and that the construction phase is undertaken safely. 
10. That prior to the commencement of development on site, the developer shall submit
an Energy Design Analysis for the written approval of the Planning Authority
demonstrating the fabric performance of the building and the installation of
technology that provides low or no amounts of carbon dioxide emissions, to reduce
the predicted emissions from the building by at least 15% below 2007 building
standards. The building shall thereafter be developed in accordance with the
approved Energy Design Analysis. 
Reason: To ensure the building is designed in a manner that reduces energy
requirements and carbon emissions.   
Local Government (Access to Information) Act 1985 - Background Papers
For further information or to inspect any letters of objection and other background papers,
please contact James Weir on 07483370666
Page 92 of 140

Page 99

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Report of Handling 
Reference No.   23/0112/PP
 
Agenda Item ( ) 
KEY  INFORMATION 
Ward: Ward 1 –
Renfrew North and
Braehead 
Applicant: Mr Brian
Lees 
Registered: 
07/03/2023 
 
RECOMMENDATION 
Grant subject to
conditions 
 
 
 
 
 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Erection of residential
development comprising of eight flats with associated
access, parking, bin store, boundary treatment and
landscaping 
LOCATION: 74 Fulbar Street, Renfrew, PA4 8PB 
APPLICATION FOR: Full Planning Permission 
© Crown Copyright and database right 2021. All rights reserved. Ordnance Survey Licence number 100023417. 
IDENTIFIED KEY ISSUES 
 The application site is covered by Policy P1 within
the adopted Local Development Plan. 
 There have been no objections from consultees. 
 There have been five letters of objection.
 
 
Alasdair Morrison
Head of Economy &
Development
Page 93 of 140

Page 100

Renfrewshire Council Planning and Climate Change Policy Board 
Page 2
 
REPORT OF HANDLING FOR APPLICATION 23/0112/PP 
SITE ADDRESS  74 Fulbar Street, Renfrew, PA4 8PB
PROPOSAL  Erection of residential development comprising of eight flats with
associated access, parking, bin store, boundary treatment and
landscaping 
RECOMMENDATION Grant subject to conditions 
PROPOSALS This application seeks planning permission for the erection of a
residential development comprising of eight flats within a four storey
building with associated access, parking, bin storage, boundary
treatment and landscaping. 
The application site is located on a corner plot, and is bound by Fulbar
Street to the south west, Blysthwood Avenue to the north west, a two
storey end terrace residential property to the north east, and a row of
two storey terraced properties to the south east. 
The site is approx. 700 square metres in area. It is currently occupied
by a single storey building which is positioned to the south east
corner, with the remainder of the site finished in a hard surface. This
building was previously used as offices, however the applicant has
advised that it has been vacant since 2022. Boundary treatment
currently comprises of a brick wall. 
The proposed development comprises the demolition of the single
storey building and the erection of a four storey flatted block with a
square footprint of approx. 188 square metres. The flatted block will
be positioned in the north western half of the site. The south eastern
half of the site comprises the parking and manoeuvring areas, with 8
parking spaces delineated. 
The four storey block will be predominantly finished in facing brick,
with metal cladding panels above and below the window opening. The
roof will also be finished in profiled sheet metal. The layout provides
for a landscaped buffer around the edge of the block. There is also a
bin and cycle store and further landscaping positioned along the north
eastern boundary. 
It should be noted that the original description of development
included reference to a biomass boiler. However, this has now been
omitted from the proposed scheme. 
This report relates to an application that would normally fall within the
Council's scheme of delegation to be determined by an appointed
officer. However, a request has been submitted by three members,
within 21 days of the application appearing on the weekly list, that the
matter be removed from the scheme of delegation for determination
by the Board. It was considered that the potential impact of the
development on the local community and local environment required it
Page 94 of 140

Page 101

Renfrewshire Council Planning and Climate Change Policy Board 
Page 3
 
to be fully considered prior to any decision being made.
SITE HISTORY None recorded. 
CONSULTATIONS Communities & Housing Services (Environmental Protection
Team) – No objections. Advisory note required with regard to potential
land contamination. 
Chief Executive’s Service (Roads Development) – No objection
subject to conditions relating to the resurfacing of the footway fronting
the site, formation of a pedestrian route into the main entrance, the
location of the bin collection point, and the design of the site access. 
NATS – No objections. 
Glasgow Airport Safeguarding – No objection subject to condition
relating to the submission of a bird hazard management plan.
Advisory note also required with regard to the possible use of a crane. 
Scottish Water – No objections. 
Children’s Services – No objections. 
REPRESENTATIONS  The Council has undertaken two rounds of neighbour notification. 
Seven letters of representation, which object to the proposed
development, were received. The points raised in these letters can be
summarised as follows: 
1 – Noise, disruption and inconvenience associated with the
construction process. 
2 – Loss of sunlight and overshadowing. 
3 – Noise and fumes associated with biomass boiler. 
4 – Loss of privacy. 
5 – Loss of property value. 
6 – Insufficient parking provision. 
7 – Height and scale of the building is out of keeping with the
surrounding area. 
8 – Drainage and flooding. 
9 – Notification of the application has not been undertaken. 
10 – A two storey build would be more suitable at this location.
Page 95 of 140

Page 102

Renfrewshire Council Planning and Climate Change Policy Board 
Page 4
 
11 – It is disingenuous to use other buildings or previous industrial use
of the area to justify the scale of the development. There are no other
three or four storey buildings within the immediate vicinity of the site. 
12 – Car ownership in the area is high and public transport services
continue to be reduced. 
13 – The building will be higher than the existing at 80 Fulbar Street. 
14 – No garden space is provided for residents. 
15 – Loss of views and impact on outlook. 
16 – There is already an adequate supply of flats in the area.
DEVELOPMENT PLAN
POLICIES
Policy and Material Considerations 
Legislation requires planning decisions to be made in accordance with
the Development Plan unless material considerations indicate
otherwise. In this instance, the proposal must be assessed against the
following: 
Development Plan 
National Planning Framework 4 
NPF4: Policy 1 – Tackling the climate and nature crisis
NPF4: Policy 3 – Biodiversity
NPF4: Policy 9 – Brownfield land, vacant and derelict land, and empty
buildings
NPF4: Policy 13 – Sustainable transport
NPF4: Policy 14 – Design, quality, and place
NPF4: Policy 15 – Local living and 20 minute neighbourhoods
NPF4: Policy 16 – Quality Homes
NPF4: Policy 18 – Infrastructure first 
Renfrewshire Local Development Plan 
LDP 2021: Policy P1 – Renfrewshire’s Places
LDP 2021: Policy P3 – Housing Mix and Affordable Housing
LDP 2021: Policy I3 – Flooding and Drainage
LDP 2021: Policy I7 – Zero and Low Carbon Buildings
LDP 2021: Policy ENV2 – Natural Heritage 
Supplementary Guidance 
Delivering the Environment Strategy
Delivering the Infrastructure Strategy
Delivering the Economic Strategy 
Material Considerations 
Page 96 of 140

Page 103

Renfrewshire Council Planning and Climate Change Policy Board 
Page 5
 
Renfrewshire Councils Residential Design Guide 
Scottish Government publications on Designing Streets and Designing
Places 
PLANNING
ASSESSMENT
Policy P1 states that within uncoloured areas on the proposals maps
there will be a general presumption in favour of a continuance of the
built form. New development proposals within these areas should
make a positive contribution to the Place, and be compatible and
complementary to existing uses. 
Whilst the most recent use of the site was an office, the surrounding
area is predominantly characterised by residential use. The
redevelopment of the site for residential use would be compatible with
surrounding uses in principle. However detailed consideration of the
propped development against the provisions of the New Development
Supplementary Guidance and the Residential Design Guide is
required. 
These documents set out a range of considerations that form the
basis of good places design. Each consideration will be assessed in
turn. 
Context and Character 
The application site is located in a built up area approx. 250m from
Renfrew town centre to the south east. The predominant built form
immediately surrounding the site is a mix of two storey terraced
properties. It is noted that the built form steps down as you move
further away from the town centre. There are four storey tenement
properties on the edge of the town centre, and three storey flats
opposite Fulbar Lane approx. 50m to the south east of the site. 
While the built form surrounding the site is predominantly two storeys,
there is a mix of design, age, and finish of the buildings. The most
notable building within the streetscene is number 80 Fulbar Street
which is directly opposite the site to the north west. This building
incorporates traditional proportions, and is higher than the two storey
dwellinghouses in the area. It is also finished in red facing brick which
contrasts with the grey render and stone associated with other
properties. 
The concept for the proposed development is based on the building at
number 80, and has taken ques with regard to design, height and
materials. While the proposed development is four storeys, the eaves
and ridge line height are commensurate with the building at number
80. The proposed development also incorporates facing brick, and
vertically proportioned windows. 
It is noted that number 80 is a remnant of the areas previous industrial
heritage. The applicant has sought to justify the development partly
based on this historical industrial built form. However, the area is now
clearly established as a residential area, and this provides the context
Page 97 of 140

Page 104

Renfrewshire Council Planning and Climate Change Policy Board 
Page 6
 
from which the development should be assessed.       
Access and Connectivity 
The application site is within walking distance of Renfrew town centre,
its associated amenities and public transport connections. Policy 15
advocates local living to encourage connected and compact
neighbourhoods where people can meet most daily needs within a
reasonable distance of their home. Policies 13 and I1 advocate good
accessibility and connectivity to walking, cycling and public transport. 
The application site is well located in this regard, with the town centre,
other amenities such as Robertson Park, Renfrew Health Centre,
Kirklandneuk Primary School and Trinity High School all within a 20
minute walk from the site. 
The Roads Development officer has offered no objections to the
development, and is satisfied with the parking provision being
proposed given the sustainable location of the site. The matters of
detailed design raised by the Roads Development officer can be
managed via condition where required, and it is noted that the site
plan has been amended to accommodate some of the requirements. 
Layout and Built Form 
The proposed split in the site layout, with the building occupying the
northwestern half and the parking to the south east, is considered to
be acceptable. The site is a prominent corner plot, and the position of
the building reflects the building line along Blysthwood Avenue. 
With regard to built form, it is acknowledged that the four storey height
would be as departure from the predominant two storey built form in
the immediate vicinity of the site. However, the building is
commensurate with the height of the building at number 80. The
building at number 80 makes a positive contribution to the character of
the area, and a design concept which seeks to reflect this should be
considered desirable in principle. 
On this basis a departure from the predominant built form is not
considered to be a reason in itself for the proposal to be considered
unacceptable. The form of the building will not be detrimental to the
character or appearance of the place, and it is considered that a
development of this scale can be accommodated within the
streetscene without appearing incongruous. 
It is also noted that the existing building on the site is vacant, and the
proposal will redevelop a brownfield site which is supported by policy
9. On balance, it is considered that the redevelopment of the site will
have a positive impact on the place.   
Environment and Community 
Page 98 of 140

Page 105

Renfrewshire Council Planning and Climate Change Policy Board 
Page 7
 
A key consideration in the assessment of the development is the
potential impact on the residential amenity of neighbouring properties.
While it is considered that a building of this scale is acceptable with
regard to the streetscene, it must be demonstrated that it is
compatible with neighbouring uses. 
The development is most likely to have a potential impact on the
neighbouring properties to the north east (2 Blysthwood Avenue) and
south east (68 a-d Fulbar Street) which directly bound the site, 2
Fulbar Avenue to the south west, and 3 – 5 Blysthwood Avenue to the
north west. 
Turning firstly to 2 Blysthwood Avenue, the fenestration on the north
eastern elevation of the building has been amended to reduce the
potential loss of privacy. This includes replacement of a dormer with a
rooflight, and incorporation of high level windows. There is no direct
window to window overlooking as the gable of number 2 does not
incorporate any habitable room windows. 
The applicant has provided sunlight calculations which show the
extent of shadow cast by the proposed building. These calculations
show that the minimum standard of at least 50% of garden ground
receiving at least 2 hours of sunshine on the 12th March (as set out
within the BRE 209 2022 guidance on Site Layout Planning for
Daylight and Sunlight: A Guide to Good Practice) are met. 
Turning to 68 a-d Fulbar Street, there is a separation distance of 19m
between these properties and the proposed building. This will ensure
that windows and garden ground associated with 68 a-d Fulbar Street
are not overlooked to an unacceptable degree, and that sufficient
levels of privacy will be maintained. Treatment along this and all other
boundaries will be controlled via condition. 
In terms of overshadowing, as these properties are directly to the east
of the application site they are not significantly impacted through loss
of sunlight. With regard to daylight, it is noted that removal of the
existing building (which is hard up against the eastern boundary) will
improve the outlook and levels of daylight received by 68a in
particular. It is noted that the proposed building is within the 25 degree
line when plotted from 68 a-d. However the orientation of the
properties will ensure that overall amenity is not significantly impacted. 
Number 2 Fulbar Avenue is to the south west of the site on the
opposite side of Fulbar Steet. Given the position of the property to the
south west it will not be impacted by any overshadowing. The
windows on the rear elevation of this property which fronts Fulbar
Street are in the public domain, and I am satisfied that privacy will not
be compromised further with respect to the development being
proposed. It is noted that the proposed building is also within the 25
degree line when plotted from number 2. However the orientation of
the properties will ensure that overall amenity is not significantly
impacted. 
Page 99 of 140

Page 106

Renfrewshire Council Planning and Climate Change Policy Board 
Page 8
 
Numbers 3 and 5 Blysthwood Avenue are 20m from the development
site, and do not directly face the proposed block of flats. They will not
be impacted regarding loss of privacy. Due to the orientation of the
properties the sunlight analysis shows that the development will
overshadow the front elevation of these properties resulting in a partial
loss of sunlight within the habitable rooms on the front elevation of the
properties. 
The analysis shows that the development will not result in a total loss
of sunlight. These properties will still receive some sunlight in the
afternoon. The partial loss is restricted to winter months only. It is not
considered that the impact on amenity that arises from the loss of
sunlight would be so significant as to justify refusal of the application.   
The potential impact on number 80 Fulbar Street is not likely to be
significant as this is a commercial property and not a dwellinghouse. 
In view of the above, it is considered that on balance the development
will not result in a significant loss of amenity for neighbouring
properties. 
The site plan includes an indicative landscaping strategy which will
provide a softer setting for the building and some amenity for
residents. It is noted above that public parks are also within walking
distance of the site. 
Whilst the planting plan is not detailed, it is likely that any landscaping
will improve biodiversity at this location given the site in its current
condition is fully covered with hard standing. The development would
meet the aims of policy 3 and ENV2 in this regard. 
The proposal includes a drainage strategy which would manage
surface water in a sustainable manner using filter trenches and a
soakaway system. A condition can be applied to ensure the strategy is
implemented on site and maintained thereafter in accordance with the
submitted documents. 
Finally, it is noted that while the site is on the edge of the coastal
potential flooding extent the flood risk area does not cover the
footprint of the building, the surrounding landscaping, the car parking
area, or the site access. The development is considered to comply
with Policy I3.   
Buildings and Design 
The design and finish of the proposed building is based on the brick
building at number 80 Fulbar Street. I am satisfied that the building is
of a suitable design and finish, and will make a positive contribution to
the place as required by policies 14, 16 and P1. 
The combined bin and bike store is also finished in brick, with a flat
Page 100 of 140

Page 107

Renfrewshire Council Planning and Climate Change Policy Board 
Page 9
 
roof. Its position to the rear of the flats ensures it will not have a
significant impact on the streetscene. 
The applicant has advised that energy efficiency and carbon dioxide
reduction will be a key component of the development. The
development initially included a biomass boiler system. However this
has since been omitted from the scheme. It is considered that a
condition should be applied requiring the submission of an Energy
Design Analysis to demonstrate that predicted emissions from the
development are reduced by at least 15% below 2007 building
standards as required by Policy I7. 
In response to the points raised in the letters of representation,
matters relating to points 2, 4, 6, 7, 8, 13, and 14, namely the scale of
the development and the impact on amenity, drainage, landscaping,
and parking have been addressed in the above assessment. 
1 - A construction and environmental management plan will be
requested via condition to ensure the construction phase is managed
appropriately. 
3 - The biomass boiler has been omitted from the proposal. 
5 – Loss of property value is not a material consideration. 
9 – Notification of the application has been undertaken in accordance
with the requirements of the legislation. It is noted that a second round
of notification was undertaken following submission of amended
plans. 
10, 11, 16 – Although historical building patterns in the area are
acknowledged, the proposal has been assessed against the current
residential context. Existing supply of flats in the area or preference
for a lower density of build is not considered to be a reason to refuse
the development. Higher density and more compact development is
supported in principle by NPF4, particularly at locations such as this
where amenities are within a walkable distance of the site. The
development will contribute to the mix of houses and flats in this area
as promoted by Policy P3. 
12 – A higher density of development will contribute to the viability of
services and amenities. The Roads Development officer has offered
no objections to the development. 
15 – Loss of views is not a material consideration. Impact on outlook
has been considered in the above assessment. 
In conclusion, the proposed development will support delivery of two
of the overarching spatial principles set out in National Planning
Framework 4 – Local Living and Compact Urban Growth. The
application site is within a sustainable location, and its redevelopment
Page 101 of 140

Page 108

Renfrewshire Council Planning and Climate Change Policy Board 
Page 10
 
in the manner proposed will contribute positively to the place.
Minimum standards relating to the amenity of neighbouring residential
properties will be met.   
In view of the above, it is considered that the proposal would accord
with the relevant provisions of the Development Plan. There are no
other material considerations. Planning permission should therefore
be granted. 
RECOMMENDATION Grant subject to conditions  
Reason for Decision 
The proposal accords with the provisions of the Development Plan and there were no
material considerations which outweighed the presumption in favour of development
according with the Development Plan. 
Conditions 
1. That prior to the occupation of any flat hereby approved, the developer shall
resurface the sections of footway which are commensurate with the site boundaries
fronting Fulbar Street and Blysthwood Avenue. The footway shall be resurfaced to
a standard that is structurally adequate and to the satisfaction of the Planning
Authority. 
Reason: To ensure the standard of footway fronting the site is sufficient to serve the
development. 
2. That prior to the commencement of development on site, the developer shall submit
for the written approval of the Planning Authority a plan showing the location of a
bin collection area from where bins can be safely presented for collection. The plan
shall include a specification for all works neccesary to form the bin collection area
including and hard surfacing or boundary treatments. The bin collection area
thereafter approved shall be implemented on site and made available for use prior
to the occupation of any of the flats. 
Reason: To ensure that bins associated with the development can be presented for
collection safely. 
3. That prior to the commencement of development on site, the developer shall
provide a strategy for the written approval of the Planning Authority which details
the drainage of surface water from all areas of hard standing. The strategy shall
ensure that surface water from any areas of hard standing shall not discharge onto
the public road. The approved strategy shall thereafter be implemented on site, and
maintained for the life of the development. 
Reason: To ensure that surface water is managed appropriately in the interests of
sustainable drainage. 
4. That the development hereby approved shall be undertaken in accordance with
approved drawings 1848/AL(0)007 rev E titled ‘Plans as Proposed’ and
1848/AL(0)11 rev E titled ‘Elevations as Proposed’. No alterations to these plans
Page 102 of 140

Page 109

Renfrewshire Council Planning and Climate Change Policy Board 
Page 11
 
are to take place unless first submitted to and agreed in writing with the Planning
Authority. The combined bin and cycle store as shown in these drawings shall also
be constructed and made available for use prior to the occupation of any flat hereby
approved. 
Reason: To ensure the development is implemented in accordance with the
approved plans.   
5. Development shall not commence until a Bird Hazard Management Plan has been
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. The submitted plan shall include details of: 
 Management of any flat/ shallow pitched/green roofs on buildings within the site
which may be attractive to nesting, roosting and loafing birds. The management
plan shall comply with Advice Note 8 ‘Potential Bird Hazards from Building
Design’. 
The Bird Hazard Management Plan shall be implemented as approved on
completion of the development and shall remain in force for the life of the
development. No subsequent alterations to the plan are to take place unless first
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. 
Reason: It is neccesary to manage the development in order to minimise its
attractiveness to birds which could endanger the safe movement of aircraft and the
operation of Glasgow Airport. 
6. That prior to the commencement of development on site, the developer shall
provide for the written approval of the Planning Authority a specification detailing
the colour and texture of all finishing materials to be used on the external walls of
the building hereby approved. This shall include windows and all rainwater goods.
Only the materials within the approved specification shall thereafter be used in the
development of the site. 
Reason: To ensure the external materials are suitable for use in the interests of
visual amenity. 
7. That prior to the commencement of development on site, full details of all soft and
water landscaping works shall be submitted as part of a landscape strategy for the
written approval of the Planning Authority. The landscape strategy shall include (but
not be limited to) provisions in respect of:
 all proposed trees, shrubs, hedgerows, areas of grass/wildflower seeding,
turfing including size, species, spacing and location.
 all areas of hard standing including location and materials.
 a plan showing proposed site levels. 
 all areas of surface water including ponds, and measures for the sustainable
management and drainage of surface water where applicable. 
 the implementation of all biodiversity and habitat enhancements.
 a timetable for the implementation of the landscape strategy.
 a strategy for the future management and maintenance of all landscaped
areas including provision for replacement of trees, shrubs, hedgerows and
Page 103 of 140

Page 110

Renfrewshire Council Planning and Climate Change Policy Board 
Page 12
 
areas of grass/wildflower seeding and turfing if they were to become
diseased, die, become seriously damaged or are removed within 5 years of
being planted. 
The approved landscape strategy shall thereafter be implemented on site in
accordance with the approved timetable and shall be managed and maintained
thereafter for the life of the development. 
Reason: To ensure a robust landscaping strategy is implemented in the interests of
visual amenity, landscape character and biodiversity. 
8. That prior to the commencement of development on site, the developer shall
provide a specification for the written approval of the Planning Authority detailing
the location, design, materials and colour of all boundary fences, gates, walls, or
other method of enclosure to be installed at the site. Only the boundary fences,
gates, walls, or other methods of enclosure within the approved specification shall
thereafter be used in the development of the site. 
Reason: To ensure the methods of enclosure are of a suitable design in the
interests of visual amenity. 
9. That prior to the commencement of development, a Construction Environmental
Management Plan (CEMP) shall be submitted to and approved in writing by the
Planning Authority.  The CEMP shall include (but not be limited to) provisions in
respect of:
 mitigation measures for potential dust, noise, and vibration impacts on nearby
properties, 
 waste management, pollution control and mitigation, 
 a plan showing existing drainage pipes and other utilities within the site and
procedures for how they will be safeguarded during construction,
 surface water management,
 procedures for monitoring compliance and dealing with any breaches of the
approved management plan,
 the formation of access from the public road to accommodate construction
vehicles including geometry, surfacing, and sightlines
 the additional signage on both public roads where access will be taken to
inform drivers of the construction vehicles.
 details of proposed temporary site compound for storage of materials,
machinery, and designated car parking. 
The measures set out within the approved CEMP shall thereafter be implemented
on site during the construction phase 
Reason: To ensure environmental impacts are mitigated during the construction
phase, and that the construction phase is undertaken safely. 
10. That prior to the commencement of development on site, the developer shall submit
an Energy Design Analysis for the written approval of the Planning Authority
demonstrating the fabric performance of the building and the installation of
technology that provides low or no amounts of carbon dioxide emissions, to reduce
the predicted emissions from the building by at least 15% below 2007 building
standards. The building shall thereafter be developed in accordance with the
Page 104 of 140

Page 111

Renfrewshire Council Planning and Climate Change Policy Board 
Page 13
 
approved Energy Design Analysis. 
Reason: To ensure the building is designed in a manner that reduces energy
requirements and carbon emissions.   
 
 
 
Page 105 of 140

Page 112

Page 106 of 140

Page 113

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Report of Handling 
Reference No.   23/0283/PP
 
Agenda Item ( ) 
KEY  INFORMATION 
Ward: 2 Renfrew South
and Gallowhill 
Applicant:
Renfrewshire Council 
Registered: 29/05/2023 
 
RECOMMENDATION 
Approve subject to
conditions 
 
 
 
 
 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Erection of a secondary
school and community campus with associated external
amenities including landscaping, access, parking, and sports
pitches. 
LOCATION: 111 - 113 Renfrew Road, Paisley, PA3 4DY 
APPLICATION FOR: Full Planning Permission 
© Crown Copyright and database right 2021. All rights reserved. Ordnance Survey Licence number 100023417. 
IDENTIFIED KEY ISSUES 
 The application site is located within the Paisley
Town Centre North Transition Area as defined by
Policy E1 of the Adopted Local Development Plan.
 The Local Development Plan New Development
Supplementary Guidance on Delivering the
Economic Strategy states that educational facilities
are an acceptable use within the Paisley Town
Centre North Transition Area
 There have been no objections from consultees.
 There have been no representations. 
 
 
Alasdair Morrison
Head of Economy &
Development
Item 5(b)
PACC230124 Page 107 of 140

Page 114

Renfrewshire Council Planning and Climate Change Policy Board 
Page 2
 
REPORT OF HANDLING FOR APPLICATION 23/0283/PP 
SITE ADDRESS  111 - 113 Renfrew Road, Paisley, PA3 4DY 
PROPOSAL  Erection of a secondary school and community campus with
associated external amenities including landscaping, access, parking
and sports pitches. 
RECOMMENDATION Grant subject to conditions
 
PROPOSALS This application seeks planning permission for the erection of a
secondary school and community campus with associated external
amenities including landscaping, access, parking, and sports pitches
on the site of the former Chivas premises at 111-113 Renfrew Road,
Paisley. 
The proposed development will facilitate the relocation of Paisley
Grammar School from its current location on Glasgow Road. 
The application site is approx. 6 hectares in area. The warehouses
associated with the Chivas premises have been cleared, and the site
is now vacant with the exception of buildings along the Renfrew Road
frontage which have been retained. The retained buildings are outwith
the application site boundary and are not related to the development
proposal. The site itself is flat with no significant level changes.
However, it sits down below the level of Renfrew Road to the east.   
The site is split from Renfrew Road by a row of office buildings, one of
which is B listed. To the north the site is bound by an industrial
building that is currently occupied by Scottish Leather Group, to the
south by the West College Scotland Paisley campus, and to the west
by Abercorn Street which features a mix of industrial and commercial
premises. 
The proposed secondary school is positioned in the southern half of
the development site. It comprises of a flat roofed part two storey/part
three storey building with an irregular shaped footprint, and floor area
of approx. 14,675 square metres. The proposed secondary school has
a capacity for 1380 pupils. The external walls will be finished in
aluminium cladding which is a mix of bronze and champagne colours.
Outdoor play areas including all weather pitches are located in the
northern half of the site. 
The submitted plans identify the access to the site from a new
east/west link road which forms part of the Advanced Manufacturing
and Innovation District Scotland (AMIDS) South infrastructure
upgrades. These upgrades are intended to improve access to the
Advanced Manufacturing and Innovation District at Glasgow Airport,
and were approved under planning application 22/0363/PP.  The
east/west link includes a new junction onto Renfrew Road.
Page 108 of 140

Page 115

Renfrewshire Council Planning and Climate Change Policy Board 
Page 3
 
There are two access points from the east/west link road, one at the
western end which provides access to a drop of zone for buses, and
one at the eastern end which functions as the principal access for
pedestrians and private vehicles entering the school grounds. There
are six disabled spaces adjacent to the main entrance, with 103
parking spaces towards the north east corner of the site. 
The front elevation of the school is set back 36m from the east/west
link. The space between the school and the road comprises of a
drainage basin, various informal social spaces, and associated
landscaping. Boundary treatment around the site perimeter comprises
of a 2.4m high welded mash fence.     
SITE HISTORY Application No: 23/0087/PN
Description: A new secondary school and community campus with
associated external amenities including landscaping, parking and
sports pitches
Status; Accepted 
Application No: 23/0507/HZR
Description: Revoke hazardous substance consent 8803/H3788
Status; Revoked 
Application No: 22/0363/PP
Description: Formation of 2 lane road, including a bridge crossing over
the White Cart Water, road and footpath upgrades and other
associated works.
Status; Granted subject to conditions 
Application No: 20/0756/DD
Description: Prior notification for demolition of buildings
Status; Prior Approval not Required 
Application No: 14/0267/PP
Description: Erection of single storey gatehouse
Status; Granted 
Application No: 14/0721/PP
Description: Siting of modular building.
Status; Granted subject to conditions 
Application No: 13/0679/PP
Description: Erection of single storey gatehouse.
Status; Granted 
Application No: 13/0078/PP
Description: Erection of a loading canopy
Status; Granted 
Application No: 13/0549/PP
Description: Erection of compactor building
Page 109 of 140

Page 116

Renfrewshire Council Planning and Climate Change Policy Board 
Page 4
 
Status; Granted 
Application No: 12/0420/PP
Description: Overcladding of part of building and external alterations
Status; Granted 
Application No: 11/0772/PP
Description: Construction of extension to form loading dock
Status; Granted subject to conditions 
Application No: 10/0554/PP
Description: Erection of store building
Status; Granted subject to conditions 
Application No: 07/0811/AD
Description: Display of externally illuminated signs.
Status; Granted subject to conditions 
Application No: 07/0359/PP
Description: Formation of concrete hardstanding with lighting to
accommodate articulated trailers with 3m high chainlink perimeter
fence.
Status; Granted subject to conditions 
Application No: 07/0820/PP
Description: Erection of a compactor building and pallet park.
Status; Granted subject to conditions 
Application No: 00/1100/HZ
Description: Claim for deemed hazardous substances consent in
respect of the storage of liquid ethenol (UN 3065 Alcoholic Beverage).
Status; Deemed consent 
Application No: 05/0062/PP
Description: Erection of distribution building with loading docks and
lean-to structure and reconstruction of existing service road.
Status; Granted subject to conditions 
Application No: 95/0917/AD
Description: Formation of sign.
Status; Granted subject to conditions 
Application No: 94/0982/PP
Description: Siting of one temporary portacabin.
Status; Granted subject to conditions 
Application No: 93/0314/PP
Description: Erection of extension to existing loading bay.
Status; Granted subject to conditions 
Application No: 93/1069/AD
Description: Erection of a fixed sign.
Page 110 of 140

Page 117

Renfrewshire Council Planning and Climate Change Policy Board 
Page 5
 
Status; Granted subject to conditions 
Application No: 93/0057/PP
Description: Siting of two temporary portable buildings.
Status; Granted subject to conditions 
CONSULTATIONS Communities & Housing Services (Environmental Protection
Team) – An air quality assessment is required prior to
commencement of development, and any mitigations within the
assessment shall be implemented. Conditions are required with
respect to land contamination, noise, and lighting. 
Environment, Housing and Infrastructure – no objection subject to
the attached roads related conditions. 
Children’s Services – No objections. 
Scottish Water – No objections. 
Glasgow Airport Safeguarding – No objection subject to conditions
requiring the submission of a bird hazard management plan, and
further details of all soft and water landscaping works. 
NATS – No objections. 
SEPA – No objections. 
Health and Safety Executive – do not advise against the granting of
planning permission. 
REPRESENTATIONS  None received. 
DEVELOPMENT PLAN
POLICIES
Policy and Material Considerations 
Legislation requires planning decisions to be made in accordance with
the Development Plan unless material considerations indicate
otherwise. In this instance, the proposal must be assessed against the
following: 
Development Plan 
National Planning Framework 4 
NPF4: Policy 1 – Tackling the climate and nature crisis
NPF4: Policy 2 – Climate mitigation and adaptation
NPF4: Policy 3 – Biodiversity
NPF4: Policy 7 – Historic Assets and Places
NPF4: Policy 9 – Brownfield land, vacant and derelict land, and empty
buildings
NPF4: Policy 13 – Sustainable transport
NPF4: Policy 14 – Design, quality, and place
NPF4: Policy 18 – Infrastructure first
Page 111 of 140

Page 118

Renfrewshire Council Planning and Climate Change Policy Board 
Page 6
 
NPF4: Policy 22 – Flood risk and water management
NPF4: Policy 27 – City, town, local and commercial centres 
Renfrewshire Local Development Plan 
LDP 2021: Policy E3 – Transition Area
LDP 2021: Policy I1 – Connecting Places
LDP 2021: Policy I3 – Flooding and Drainage
LDP 2021: Policy I7 – Zero and Low carbon Buildings
LDP 2021: Policy ENV2 – Natural Heritage
LDP 2021: Policy ENV3 – Built and Cultural Heritage
LDP 2021: Policy ENV5 – Air Quality 
Supplementary Guidance 
Delivering the Economic Strategy
Delivering the Infrastructure Strategy
Delivering the Environment Strategy
Delivering the Places Strategy 
ENVIRONMENTAL
IMPACT
ASSESSMENT
The development has been assessed against the Town and Country
Planning (Environmental Impact Assessment) (Scotland) Regulations
2017 to determine if it should be accompanied by an Environmental
Impact Assessment (EIA). 
The development does not meet any of the descriptions of
development as set out within Schedule 1 of the regulations for which
an EIA is always required. 
The development does meet one of the descriptions of development
within schedule 2 of the regulations on the basis that it constitutes an
urban development project where the site area exceeds 0.5 hectares.
An EIA is required for schedule 2 development only when it is likely to
have significant effects on the environment by virtue of factors such as
its nature, size, or location. 
In view of the above an EIA screening checklist for the development
has been undertaken. The checklist has concluded that the
development is not likely to have a significant environmental impact
which would necessitate the undertaking of an EIA. Potential impacts
noted in the supporting information accompanying the planning
application can be addressed via the planning process. 
An EIA is not therefore required to accompany the planning
application.     
PLANNING
ASSESSMENT
Policy E3 of the local development plan (LDP) states that transition
areas aim to support a mix of uses. Development proposals within
transition areas require to be able to co-exist with existing uses,
having no significant effect on the character and amenity of the
surrounding area. 
Page 112 of 140

Page 119

Renfrewshire Council Planning and Climate Change Policy Board 
Page 7
 
The application site is within the Paisley Town Centre North transition
area. The supplementary guidance states that educational facilities
are an acceptable use within this transition area. 
Proposals must thereafter be assessed against the transition areas
development criteria. 
In this instance the proposed development is appropriate for the site
and compatible with the wider surrounding area. 
There have been no objections from consultees. Matters relating to
noise, air quality and lighting can be managed via conditions. 
Policy 14 of NPF4 seeks to encourage, promote, and facilitate well
designed development that makes successful places by taking a
design led approach which promotes quality places, spaces, and
environments. 
The proposed development will contribute positively to the place and
the environment within the Paisley Town Centre North transition area.
The building is of a good quality design and finish. It will also be
accompanied by structural landscaping and open space which create
an attractive natural setting for the building.       
The development will also contribute to the regeneration of the
transition area. The previous use on the site has ceased, and the site
is now vacant. The proposal also therefore complies with Policy 9 of
NPF4 which seeks to encourage, promote, and facilitate the reuse of
brownfield, vacant and derelict land. 
Policy 9 states that the biodiversity value of brownfield land which has
naturalised should be taken into account. 
In this instance the site has only recently been cleared and has very
little existing ecological value or natural heritage assets. 
The development of the site includes areas of grassland, soft
landscaping, ornamental planting, hedges, trees, and a drainage
basin. The development will therefore enhance the ecological value of
the site and improve its biodiversity in accordance with Policy 3 of
NPF4 and Policy ENV2 of LDP. A detailed landscape specification
which includes species, number and spacing of all planting will be
requested by condition. 
There will be no adverse effect on the integrity of any Natura 2000
site. 
Policy 27 of NPF4 states that development proposals which are
outwith the defined centre of a city/town, and which will generate
significant footfall, should be subject of a Town Centre First
Assessment. This includes education and community facilities
however the policy states that the assessment should be applied
Page 113 of 140

Page 120

Renfrewshire Council Planning and Climate Change Policy Board 
Page 8
 
flexibly so that the facility is easily accessible to the communities it is
intended to serve. 
While it is noted that the existing Paisley Grammar School catchment
area does include part of Paisley town centre, there are no sites within
the town centre that can accommodate the scale of development
proposed. A site selection process has been undertaken, and the
former Chivas site was identified as the preferred option. 
The application site is within a 20 minute walk of the town centre. It is
accessible by walking, cycling and public transport, and there are a
range of transport options available to accommodate the footfall
associated with the school. The proposal is considered to comply with
Policy 27. 
Further to the accessibility noted above, Policy 13 of NPF4 seeks to
encourage, promote, and facilitate developments that prioritise
walking, wheeling, cycling and public transport, and that transport
requirements generated by a development proposal are considered in
line with the sustainable travel and investment hierarchies. 
Policy I1 of LDP also seeks to promote good accessibility and
connectivity to walking, cycling and public transport to support modal
shift, and all development proposals require to ensure appropriate
provision and accessibility including the ability to connect to active
travel and public transport networks. 
The site has been laid out to prioritise sustainable modes of travel.
There are two pedestrian gates providing access from the east/west
link road, with the front of the school characterised by open space and
landscaping to create an attractive pedestrian environment and
prioritise pedestrian and cycle access into the school. 
The layout includes an area for cycle parking. The final location and
design of the cycle parking can be managed via condition. 
While there are six disabled parking spaces adjacent to the main
entrance, the main car park is further removed from the main entrance
in a secondary location towards the north east corner of the site. The
layout includes a bus drop off bay which can accommodate eight
buses. 
The site layout prioritises space for pedestrians over private vehicles,
and this will support journeys to the school by walking and cycling as
required by Policy 27 of NPF4 and Policy I1 of LDP. 
The secondary school will be accessed from the east/west road link
approved under planning application 22/0363/PP. While the final
design of the road link is still to be approved by condition, the outline
design includes sufficient space to accommodate pedestrian and
cycle journeys. 
Page 114 of 140

Page 121

Renfrewshire Council Planning and Climate Change Policy Board 
Page 9
 
The east/west link will connect the site with the new Paisley to
Renfrew core path to the west, and the existing public transport and
pedestrian network on Renfrew Road to the east. The connection to
the core path is important to facilitate journeys by walking and cycling,
and a condition will be recommended to ensure a link to the core path
is in place prior to the school becoming operational. 
The infrastructure approved under planning application 22/0363/PP
also includes a new bridge link over the White Cart water which will
improve connections between the school and Shortroods and
Gockston. The core path will improve connections between the site
and Gallowhill, Whitehaugh and Glasgow Road. 
The east/west road link includes a new junction onto Renfrew Road.
The outline design for the junction includes provision for pedestrian
crossing, and final details will be submitted via condition to ensure the
crossing facilities are suitable. 
In addition to the above it is also considered neccesary to undertake a
safety and accessibility review of Renfrew Road to identify barriers to
active travel and potential road safety hazards, and to promote
mitigation measures to improve connectivity for pedestrians and
cyclists (particularly between the site and Gallowhill and the East End
of Paisley) and promote walking and cycling to the school. The review
can be submitted via condition. 
Additionally, it is noted that while Policy I1 states priority should be
given to sustainable modes of travel it also states that developments
should have no significant impact on the safe and efficient operation
of the local road network. While the principle of a new junction onto
Renfrew Road has been established, the design of the new junction
and other mitigation measures to enhance active travel will need to be
balanced with the operation of Renfrew Road noting its function as a
key connection between Paisley and the M8 motorway. 
The service yard is located adjacent to the bus drop of area. This area
will be able to accommodate service vehicles outwith pick up and drop
of times. 
The primary focus of this application, in conjunction with application
22/0363/PP, is delivery of infrastructure to connect the school to the
existing transport network. This can be managed via conditions
attached to this application and already attached to application
22/0363/PP. This will also ensure that the proposal complies with
Policy 18 of NPF4 which states that infrastructure considerations are
integral to development planning.         
The site is located outwith a functional flood plain as set out within the
SEPA flood risk maps. A detailed surface water drainage strategy can
be requested via condition to ensure surface water is managed in a
sustainable manner in accordance with Policy 22 of NPF4 and Policy
I3 of the LDP.  
Page 115 of 140

Page 122

Renfrewshire Council Planning and Climate Change Policy Board 
Page 10
 
An Energy Design Analysis can be requested via condition to ensure
the building incorporates technology to reduce predicted carbon
dioxide emissions by at least 15% below 2007 building standards in
accordance with Policy I7 of the LDP. 
With respect to Policies 1 and 2 of NPF4, it is noted above that
provision will be made to reduce predicted emissions from the
building. Additionally, the development is on a brown field site which is
sustainably located within the existing urban area and includes
provision for soft landscaping and biodiversity gain. The development
therefore accords with the principles of climate mitigation and
adaptation advocated by Policies 1 and 2 of NPF4. 
Policy 7 of NPF4 states that development proposals affecting the
setting of a listed building should preserve its character, and its
special architectural or historic interest. Policy ENV3 of the LDP also
states that development proposals within the vicinity of built heritage
assets will be required to demonstrate that there is no negative impact
to their setting. 
The application site is to the west of 121 Renfrew Road (one of a row
of buildings that comprise the Mirren Court Business Centre) which is
a category B listed building, and 111-113 Renfrew Road (former
Chivas administration building) which is a category C listed building. 
The proposed secondary school is to the rear of number 121 and 111-
113. It is also at a lower ground level. Previous development patterns
have included large buildings to the rear of 121 and 111-113. Views of
the principal eastern elevation of the buildings will be largely
unaffected by the development. While the secondary school may be
visible from the east in the gaps between the buildings, it will not
overdominate the buildings or have a detrimental impact on its setting. 
Policy ENV5 of the LDP states that development proposals should
not have a significant adverse effect on air quality particularly within or
adjacent to Renfrewshire’s Air Quality Management Areas. 
The applicant has submitted a desk top air quality assessment which
confirms that a full air quality assessment is required. The
Environmental Protection team have advised that the air quality
assessment can be submitted via condition, and that any mitigations
within the assessment shall be implemented thereafter. 
In view of the above, it is considered that the proposal would accord
with the relevant provisions of the Development Plan. There are no
other material considerations. Planning permission should therefore
be granted. 
RECOMMENDATION Grant subject to conditions 
 
Page 116 of 140

Page 123

Renfrewshire Council Planning and Climate Change Policy Board 
Page 11
 
Reason for Decision 
1. The proposal accords with the provisions of the Development Plan and there were
no material considerations which outweighed the presumption in favour of
development according with the Development Plan. 
Conditions/Reasons 
 
1. That prior to the commencement of any works on site, the developer shall submit,
for the written approval of the Planning Authority, a phasing plan which shall include
the following:
a) Details of all enabling works which shall take place on site before construction
works on the development approved commences; and
b) Details of the phasing of the construction works which shall take place on site. 
Thereafter works shall proceed in accordance with the approved phasing plan. 
Reason: To ensure all works are undertaken in a phased manner with respect to
controlling the development of the site. 
2. That prior to the commencement of any works on site, either enabling works or
construction works, the following shall be submitted for the written approval of the
Planning Authority:
a) a Site Investigation report (characterising the nature and extent of any soil,
water and gas contamination within the site); and, if remedial works are
recommended therein
b) a Remediation Strategy and Implementation Plan setting out the proposed
methods for implementing all remedial recommendations contained with the
site investigation report prepared in accordance with current authoritative
technical guidance, has been provided by the Planning Authority. 
Reason: To ensure that the site will be made suitable for its proposed use. 
3. That prior to the occupation of the secondary school, a Verification Report
confirming completion of the works specified within the approved Remediation
Strategy and Implementation Plan and also confirming that imported materials are
suitable for use shall be submitted for the written approval of the Planning Authority. 
Reason: To demonstrate that works required to make the site suitable for use have
been completed. 
4. That prior to the commencement of any works on site, either enabling works or
construction works, a Construction Environmental Management Plan (CEMP) shall
be submitted to and approved in writing by the Planning Authority.  The CEMP shall
include (but not be limited to) provisions in respect of:
 mitigation measures for potential dust, noise, and vibration impacts on nearby
properties, 
 waste management, pollution control and mitigation, 
 a plan showing existing drainage pipes and other utilities within the site and
procedures for how they will be safeguarded during construction,
 surface water management,
Page 117 of 140

Page 124

Renfrewshire Council Planning and Climate Change Policy Board 
Page 12
 
 procedures for monitoring compliance and dealing with any breaches of the
approved management plan,
 the formation of access from the public road to accommodate construction
vehicles including geometry, surfacing, and sightlines
 the additional signage on both public roads where access will be taken to
inform drivers of the construction vehicles.
 details of proposed temporary site compound for storage of materials,
machinery, and designated car parking.
 a timetable for the construction phase including confirmation of site operating
times on each day of the week. 
The measures set out within the approved CEMP shall thereafter be implemented
on site during the construction phase. 
Reason: To ensure environmental impacts are mitigated during the construction
phase, and that the construction phase is undertaken safely. 
5. That prior to the commencement of any construction works on site, as defined in
the phasing plan approved in respect of condition 1, a road safety and accessibility
review shall be submitted for the written approval of the Planning Authority.  The
review shall comprise a study of the Renfrew Road corridor (between the junction
of Renfrew Road and Weir Street and Renfrew Road and Paisley Road) and shall
include the following:
a) Review of the existing road network to accommodate journeys to the application
site by pedestrians and cyclists;
b) Identification of existing barriers to movement along the corridor;
c) Identification of potential road safety hazards; and
d) Identification of detailed mitigation measures in respect of issues identified as
part of a, b and c above. 
Reason: To promote sustainable travel modes and to ensure safe accessibility for
pedestrians and cyclists. 
6. That concurrent with condition 5 above, all measures identified in the review to
improve road safety and enhance accessibility for sustainable modes of travel shall
be implemented prior to the secondary school being brought into use unless
otherwise agreed in writing with the Planning Authority.   
Reason: To ensure all measures to improve accessibility and safety are
implemented prior to the secondary school being brought into use. 
7. That prior to the commencement of any construction works on site, as defined in
the phasing plan approved under the terms of condition 1, a specification of the
final design and layout of the proposed access onto Renfrew Road to serve the
secondary school, shall be submitted for the written approval of the Planning
Authority.  The design shall include the associated pedestrian crossing points.  The
approved access thereafter, shall be implemented in full and made available for
use, to the satisfaction of the Planning Authority, prior to the secondary school
being brought into use, unless otherwise agreed in writing with the Planning
Authority. 
Reason: To ensure the site is accessed safely.
Page 118 of 140

Page 125

Renfrewshire Council Planning and Climate Change Policy Board 
Page 13
 
8. That concurrent with condition 7 above, should the developer require to bring the
secondary school into use prior to the access onto Renfrew Road being completed,
the developer shall submit a plan for the written approval of the Planning Authority
detailing  interim access arrangements for the site which would be put in place until
the final access is completed. The plan would also specify the duration within which
the interim access arrangement would be required. The interim access
arrangement would thereafter be implemented prior to the secondary school being
brought into use and retained for the duration specified in the plan approved. 
Reason: To ensure the site can be accessed safely. 
9. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, a plan identifying key
walking and cycling routes to the secondary school shall be submitted for the
written approval of the Planning Authority in conjunction with Childrens Services.   
Thereafter a review shall be undertaken of the routes in question which shall
identify any such deficiencies and enhancements which are required in order to
ensure the routes in question fully promote, support and encourage travel to the
secondary school by walking or cycling.  The results of the review undertaken shall
be submitted for the written approval of the Planning Authority.  Thereafter the
approved plan shall be completed and brought into use prior to the occupation of
the secondary school unless otherwise agreed in writing by the Planning Authority. 
Reason: To encourage sustainable means of travel. 
10. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, a Bird Hazard Management
Plan shall be submitted for the written approval of the Planning Authority in
consultation with Glasgow Airport.  The submitted plan shall include details of: 
Management of any flat/shallow pitched/green roofs on buildings within the site
which may be attractive to nesting, roosting and loafing birds.  The management
plan shall comply with Advice Note 8 ‘Potential Bird Hazards from Building Design’. 
The Bird Hazard Management Plan shall be implemented as approved, on
completion of the development and shall remain in force for the life of the
development.  No subsequent alterations to the plan are to take place unless first
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. 
Reason: It is necessary to manage the development in order to minimise its
attractiveness to birds which could endanger the safe movement of aircraft and the
operation of Glasgow Airport. 
11. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, full details of soft and water
landscaping works shall be submitted to and approved in writing by the Planning
Authority.  The details must comply with Advice Note 3 ‘Potential Bird Hazards from
Amenity Landscaping and Building Design’, and shall include:
 Details of any existing trees or hedgerows and methods for their protection
Page 119 of 140

Page 126

Renfrewshire Council Planning and Climate Change Policy Board 
Page 14
 
during the construction phase.
 The species, number and spacing of all proposed trees, shrubs, hedgerows,
areas of grass/wildflower seeding, and turfing.
 Drainage details including SUDS – Such schemes must comply with Advice
Note 6 ‘Potential Bird Hazards from Sustainable Urban Drainage Schemes.
 All areas of hard standing including location and materials.
 All areas of surface water including ponds, and measures for the sustainable
management and drainage of surface water where applicable. 
 All biodiversity and habitat enhancements.
 A timetable for the implementation of the soft and water landscaping works.
 A strategy for the future management and maintenance of all landscaped areas
including provision for replacement of trees, shrubs, hedgerows and areas of
grass/wildflower seeding and turfing if they were to become diseased, die,
become seriously damaged or are removed within 5 years of being planted.
The scheme shall thereafter be implemented as approved. No subsequent
alterations to the approved landscaping scheme are to take place unless submitted
to and approved in writing by the Planning Authority in consultation with Glasgow
Airport.
Reason: To avoid endangering the safe movement of aircraft and the operation of
Glasgow Airport through the attraction of birds and an increase in the bird hazard
risk of the application site.
12. The design, installation and operation of any plant, machinery or equipment shall
be such that noise associated with the development does not exceed Noise Rating
Curve NR25 between the hours of 2300 to 0700 hours and NR 35 at all other times,
when measured within any dwelling in the vicinity of the development. Structure
borne vibration from the proposed development shall be imperceptible within any
dwelling in the vicinity of the development.  For an explanation of noise rating
curves, refer to BS 8233:2014 Sound insulation and noise reduction in buildings-
code of practice, Annex B. 
Reason: To mitigate noise impact on neighbouring properties in the interests of
amenity. 
13. That prior to the development hereby approved being brought into use, the
applicant shall undertake a survey to determine the impact of floodlighting from the
proposed development using the principles set out in British Standard BS EN
12193:2018 (Incorporating corrigendum February 2019) Light & Lighting - Sports
Lighting, or a method agreed by the Planning Authority.  The survey shall be
submitted to and approved in writing by the Planning Authority and shall include
details of: 
 a description of the proposed lighting units including height, type, shape and
luminous flux of the floodlights. 
 the luminance levels, both horizontal and vertical, on the illuminated part of the
Page 120 of 140

Page 127

Renfrewshire Council Planning and Climate Change Policy Board 
Page 15
 
site to demonstrate that obtrusive light and glare does not adversely affect
neighbouring properties. 
 the direction and aiming angle of each floodlight and the upward waste light
ratio for each light. 
 the Environmental Zone, as defined in the Institution of Lighting Engineers
Publication – Guidance Notes for the Reduction of Obtrusive Light, within which
the site falls. 
The works which form part of the approved lighting scheme shall thereafter be
implemented on site before the development becomes operational, and maintained
thereafter for the life of the development, unless otherwise agreed in writing with
the Planning Authority. 
Reason: To mitigate light impact on neighbouring properties in the interests of
amenity. 
14. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, the developer shall submit
for the written approval of the Planning Authority a report which satisfies the
Planning Authority that the Local Air Quality Management Objectives for the
pollutants specified in the relevant Air Quality Regulations, made under Part IV of
the Environment Act 1995, shall not be exceeded at any location at or in the vicinity
of the development where “relevant exposure” is liable to occur. In addition, the
overall significance of the air quality impacts from the development shall be
assessed and clearly defined within the report with mitigation proposed where
required. The survey and report shall adhere to the methods and principles set out
in the Scottish Government publication “Local Air Quality Management Technical
Guidance LAQM.TG(09) and LAQM.TG(16)” and the EPUK guidance document
“Land-Use Planning & Development Control: Planning for Air Quality (Jan 2017)” or
a method that has been agreed with the Planning Authority. If the report concludes
that Local Air Quality Management Objectives will be exceeded, it shall include
appropriate recommendations (and a timetable for the implementation of the
recommendations) to ensure that the impact of exceeding the objectives is
mitigated. The recommendations shall thereafter be implemented in accordance
with the timetable unless otherwise agreed in writing with the Planning Authority. 
Reason: To ensure Local Air Quality Management Objectives are managed in the
interests of public health. 
15. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, the developer shall submit
an Energy Design Analysis for the written approval of the Planning Authority
demonstrating the fabric performance of the building and the installation of
technology that provides low or no amounts of carbon dioxide emissions, to reduce
the predicted emissions from the building by at least 15% below 2007 building
standards. The building shall thereafter be developed in accordance with the
approved Energy Design Analysis. 
Reason: To ensure the building is designed in a manner that reduces energy
requirements and carbon emissions.   
16. That prior to the commencement of any construction works, as defined in the
Page 121 of 140

Page 128

Renfrewshire Council Planning and Climate Change Policy Board 
Page 16
 
phasing plan approved under the terms of condition 1, the developer shall provide a
specification for the written approval of the Planning Authority detailing the location,
design, materials and colour of all boundary fences, gates, walls (including
retaining walls), or other method of enclosure to be installed at the site. Only the
boundary fences, gates, walls, or other methods of enclosure within the approved
specification shall thereafter be used in the development of the site. 
Reason: To ensure the methods of enclosure are of a suitable design in the
interests of visual amenity. 
17. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, the developer shall provide
for the written approval of the Planning Authority a specification detailing the colour
and texture of all finishing materials to be used on the external walls of the
development hereby approved. This shall include windows and all rainwater goods.
Only the materials within the approved specification shall thereafter be used in the
development of the site. 
Reason: To ensure the external materials are suitable for use in the interests of
visual amenity. 
18. That prior to the commencement of any construction works, as defined in the
phasing plan approved under the terms of condition 1, the developer shall submit
for the written approval of the Planning Authority a strategy for the sustainable
drainage of surface water. Only the approved strategy shall thereafter be
implemented on site. 
Reason: To ensure surface water is managed appropriately in the interests of
sustainable drainage. 
19. That prior to the occupation of the secondary school hereby approved, the
developer shall submit a specification detailing the final location and design of all
bike stores. The specification shall also include a timetable for the installation of the
bike stores. The approved stores shall thereafter be installed on site in accordance
with the approved timetable. 
Reason: To ensure suitable provision for bike storage at the development in the
interests of supporting sustainable transport. 
20. That prior to the secondary school hereby approved being brought into use, the
developer shall provide a plan and specification for the written approval of the
Planning Authority detailing how the secondary school shall be connected to the
Paisley/Renfrew core path located to the west of the site. The connection detailed
in the approved plan and specification shall thereafter be implemented on site and
made available for use prior to the secondary school being brought into use, and
shall be maintained thereafter for the life of the secondary school unless otherwise
agreed in writing with the Planning Authority. 
Reason: To ensure the site is connected to the core path prior to the school being
brought into use to encourage journeys to the school by walking and cycling. 
21. That within a period of 12 months immediately following the secondary school
Page 122 of 140

Page 129

Renfrewshire Council Planning and Climate Change Policy Board 
Page 17
 
hereby approved being brought into use the developer shall submit a school travel
plan for the written approval of the Planning Authority. The travel plan shall include
a review of current travel patterns to the secondary school, identify any barriers
associated with travel to the secondary school by sustainable modes (active travel
and public transport) and shall thereafter set out measures to promote and
encourage travel to the site by sustainable modes and to reduce travel by single
occupancy private vehicle. The travel plan shall include targets for travel by
sustainable modes, associated measures to achieve these targets, when these
measures would be undertaken, and a scheme for regular monitoring and review
whereby the measures will be continued, or new measures will be identified to
ensure targets are met. The measures within the travel plan shall thereafter be
implemented and reviewed accordingly. 
Reason: To encourage travel to the school by sustainable modes and reduce
demand for single occupancy private car trips.   
 
 
 
Page 123 of 140

Page 130

Page 124 of 140

Page 131

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Report of Handling 
Reference No.   23/0504/LB
 
Agenda Item ( ) 
KEY  INFORMATION 
Ward: 4 – Paisley
Northwest 
Applicant: The
University of the West of
Scotland 
Registered: 
22/09/2023 
 
RECOMMENDATION
Grant, subject to
conditions 
 
 
 
 
 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Installation of replacement
windows and doors, solar panels, two ramps, railings,
cladding and a false floor. Erection of extension; formation of
window and door openings; renewal of roof; stonework
repairs; internal alterations and landscaping works 
LOCATION: University of the West of Scotland, Storie
Street, Paisley, PA1 2BX 
APPLICATION FOR: Full Planning Permission 
© Crown Copyright and database right 2021. All rights reserved. Ordnance Survey Licence number 100023417. 
IDENTIFIED KEY ISSUES 
 The building is B listed and is located within both
Paisley Town Centre and its Conservation Area. 
 Historic Environment Scotland have not objected to
the proposal. 
 The proposal accords with the relevant provisions of
National Planning Framework 4, the Renfrewshire
Local Development Plan and Historic Environment
Scotland’s guidance. 
Alasdair Morrison
Head of Economy &
Development
Item 5(c)
PACC230124 Page 125 of 140

Page 132

Renfrewshire Council Planning and Climate Change Policy Board 
Page 2
 
REPORT OF HANDLING FOR APPLICATION 23/0504/LB 
SITE ADDRESS  University of the West of Scotland, Storie Street, Paisley, PA1 2BX 
PROPOSAL  Installation of replacement windows and doors, solar panels, two
ramps, railings, cladding and a false floor. Erection of extension;
formation of window and door openings; renewal of roof; stonework
repairs; internal alterations and landscaping works 
RECOMMENDATION Grant, subject to conditions 
PROPOSALS This application seeks listed building consent for the extension of, and
alterations to, a detached building on Storie Street, Paisley. 
The building, which is located within the University of the West of
Scotland campus, fronts a road to the east and is bound by a mixture
of commercial and residential properties. The building is B listed and
sits within both Paisley Town Centre and its Conservation Area. 
The two storey sandstone property has a dual pitched slate roof and
timber framed windows. A single storey red brick rotunda projects
from the rear. 
Several structures that sit between the main two storey building and
the rotunda would be removed and a small, flat roofed extension
would be constructed. Alterations would be made to the internal layout
of the building and aluminium cladding would be installed along part of
the northern elevation of the rotunda. 
Replacement windows and doors would be installed across the
building while two new window openings (with decorative aluminium
shutters) would be formed on the southern elevation of the main
building. 
The ramp that provides access to the rotunda roof from the first floor
of the main building would be removed and a new ramp, false floor
and railings would be installed on the rotunda roof to create useable
outdoor space. In association with the installation of the new ramp,
two first floor window openings on the rear elevation of the main
building would be converted to a door and an existing door opening
would be infilled to create a window. 
Several sections of stonework would be either cleaned or repaired
while the slate roof would be renewed and solar panels would be
installed on the rear roof plane. 
An access ramp would be installed to the south of the property and
decorative railings would be installed along the southern site
boundary. 
Finally, areas of both hard and soft landscaping would be formed
Page 126 of 140

Page 133

Renfrewshire Council Planning and Climate Change Policy Board 
Page 3
 
across the application site. 
In light of the minimal removal of some of the existing building, and in
line with the Scheme of Delegation the application is being referred to
Board for consideration and determination.   
SITE HISTORY Application No: 23/0505/PP
Description: Installation of replacement windows and doors, solar
panels, two ramps, railings, cladding and a false floor. Erection of
extension; formation of window and door openings; renewal of roof;
stonework repairs; and landscaping works
Decision: This application is also being presented to Board today for
determination.
 
CONSULTATIONS Historic Environment Scotland - No objection. 
REPRESENTATIONS  None received. 
DEVELOPMENT PLAN
POLICIES
Policy and Material Considerations
Legislation requires planning decisions to be made in accordance with
the Development Plan unless material considerations indicate
otherwise. In this instance, the proposal must be assessed against the
following: 
National Planning Framework 4
Policy 7 - Historic assets and places
 
Renfrewshire Local Development Plan 
Policy ENV3 - Built and Cultural Heritage
 
New Development Supplementary Guidance
Delivering the Environment Strategy
 
Material Considerations
Historic Environment Scotland: Managing Change in the Historic
Environment Guidance
 
PLANNING
ASSESSMENT
The Town and Country Planning (Listed Buildings and Conservation
Areas) (Scotland) Act 1997 states that in considering whether to grant
listed building consent special regard must be had to the desirability of
preserving the listed building and its setting as well as any features of
special architectural or historic merit. 
In terms of Development Plan policy, Policy 7 of NPF4 and Policy
ENV3 of the LDP are similar in that they both require works to listed
buildings to respect their character. The relevant supplementary
guidance, as well as Historic Environment Scotland’s guidance notes,
requires alterations to be carefully considered but also recognises that
the continued occupation of listed buildings is the best way to secure
their long term future. The following matters therefore require
consideration. 
Page 127 of 140

Page 134

Renfrewshire Council Planning and Climate Change Policy Board 
Page 4
 
Extension, cladding and internal alterations
The construction of the extension would require the removal of several
small structures that sit between the main building and the rotunda.
These are poor quality, piecemeal additions that contribute little to the
architectural importance of the building. The removal of these
structures is therefore considered acceptable. 
The extension has been designed to fill the gap between the rear of
the main building and rotunda without dominating the space. The
extension would not be highly visible from the street and would not
affect the principal elevation. 
The extension would be finished in aluminium cladding, in contrast
with the sandstone main building and red brick rotunda. Such a finish
is acceptable as it would allow the extension to be identified as a later
addition and would link the structure to the more modern buildings
found elsewhere on campus. 
The aluminium cladding used on the extension would continue along
part of the northern side elevation of the rotunda. This is acceptable
as this elevation is not integral to the architectural merit of the building
and the original red brick finish has already been removed in this
location. 
The associated internal alterations would have minimal impact on the
character of the listed building and the original subdivision of space
would remain evident. 
Replacement windows and new window openings
While guidance from Historic Environment Scotland encourages the
retention and repair of existing windows and doors, it also
acknowledges that in some circumstances it is necessary to replace
them. In this instance, the existing single glazed frames have reached
the end of their working life. 
The replacement windows and doors would be timber framed, double
glazed units that closely mirror the style, opening mechanism and
colour of the existing frames. This work would therefore have no
impact on the character of the building and would help protect its
fabric. 
The windows that would be formed on the southern elevation would
be of an appropriate size for the location, would help activate what is
currently a windowless gable elevation and would add to the character
of the area. The aluminium frames and shuttering are also considered
acceptable and would not be detrimental to the architectural merit of
the building. 
Rotunda roof access
Access arrangements onto the rotunda roof do not comply with
current accessibility standards. The existing ramp would therefore be
removed and a new ramp installed, emerging from the centre of the
Page 128 of 140

Page 135

Renfrewshire Council Planning and Climate Change Policy Board 
Page 5
 
rear elevation of the main building at first floor level. A false floor
would be formed on the rotunda roof to allow the pitch of the ramp to
be reduced while new, taller, railings would protect those using the
roof as an outdoor space. 
Repositioning the ramp so that it sits centrally and the associated
alterations to first floor window and door openings would improve the
symmetry of the rear elevation and would be more in keeping with
how the building would have originally looked. 
The new ramp and railings would have a negligible impact on the
character of the listed building as they would replace existing
structures of a similar design while the false floor would not be highly
visible. 
No details have been provided on how the structure or fabric of the
listed building at first floor level will be made good following the
alterations. To protect the listed building it is therefore considered
appropriate to add a condition, should consent be granted, requesting
that details of the materials to be used are submitted to, and approved
by, the Planning Authority before any work begins. 
Access ramp, railings and landscaping
The access ramp to be installed to the south of the building would
allow step free access into the building and would be of a standard
size and design. 
Initially, it was proposed that 4.3 metre high aluminium curtain walling
would be installed along the southern site boundary. However,
following discussions between planning and the applicant this was
reduced to a 2.5 metre high decorative railing so that the rotunda
remains visible to those entering the campus from Storie Street. The
railing would be of a similar design to those installed on the ramps and
rotunda roof, minimising the material palette used on the listed
building and protecting its integrity. 
The areas of hard and soft landscaping to be formed across the
application site would complete the development and improve the
setting of the building. A condition can be added to ensure the quality
is appropriate for the setting of a listed building. 
Roof, solar panels and stonework
The roof would be stripped back and renewed, with the slate that is in
the best condition retained and used on the principal elevation. The
use of original slate on the main elevation, which is of greatest
architectural significance, is welcome and a condition can be added to
ensure the slate used on the rear elevation is appropriate for use on a
listed building. 
The solar panels would be installed on the rear roof plane so would
not affect the main principal elevation. 
Page 129 of 140

Page 136

Renfrewshire Council Planning and Climate Change Policy Board 
Page 6
 
The stonework cleaning and repairs would be carried out in a
sensitive, non invasive manner. It would not attempt to make the
building look new but would instead address defects such as cracking,
decay and areas of water ingress. This work would therefore help
improve the general appearance of the building and would help
protect its fabric and long term future. 
Overall, it is therefore considered the proposal complies with Policy 7
of NPF4, Policy ENV3 of the LDP, the new development
supplementary guidance and Historic Environment Scotland’s
guidance notes as the development would respectfully alter the
building to allow it to meet the needs of the applicant while protecting
the integrity of the listed building. 
The proposal represents the positive management of the building and
would help it return to active use. The works would protect the fabric
of the building and make it more suitable for modern use while
respecting its character and architectural qualities. Historic
Environment Scotland has echoed the above assessment by offering
no objection to the proposal. Listed building consent should therefore
be granted subject to conditions. 
RECOMMENDATION Grant, subject to conditions 
Reason for Decision 
1. The proposal accords with the provisions of the Development Plan and there were
no material considerations which outweighed the presumption in favour of
development according with the Development Plan. 
Conditions/Reasons 
1. Prior to the commencement of development hereby approved, full details of the
finishing materials to be used for the extension shall be submitted to, and approved
by, the Planning Authority.  Thereafter only the approved materials shall be used.   
Reason:  To safeguard the special interest of the building. 
2.  Prior to the commencement of development hereby approved, full details of the
design of and finish to the aluminium framed windows and their shutters as well as
all ramps, railings and the false floor on the rotunda roof shall be submitted to, and
approved by, the Planning Authority. Thereafter only the approved materials shall
be used.   
Reason:  To safeguard the special interest of the building. 
3. Prior to the alteration of openings at first floor level necessary for the removal of the
existing ramp and installation of the new ramp approved, details of the materials
that will be used to repair the fabric of the property in this location shall be
submitted to, and approved by, the Planning Authority. Thereafter only the
approved materials shall be used.
Page 130 of 140

Page 137

Renfrewshire Council Planning and Climate Change Policy Board 
Page 7
   
Reason:  To safeguard the special interest of the building. 
4. Prior to the commencement of development hereby approved, full details of any
new slate to be used shall be submitted to, and approved by, the Planning
Authority.  Thereafter only the approved slate shall be used. 
Reason:  To safeguard the special interest of the building. 
5. For the avoidance of doubt, any slate vents shall be installed on the rear elevation
only.   
Reason:  To safeguard the special interest of the building. 
6. Prior to the commencement of development hereby approved, a scheme of
landscaping shall be submitted for the written approval of the Planning Authority.
The scheme shall include (a) details of any earth moulding; (b) full details of the
finish to any areas of hard landscaping; (c) a scheme of tree and shrub planting,
incorporating details of the number, species, size and spacing of trees and shrubs
to be planted; and (d) details of the phasing of all works.   
The approved landscaping scheme shall thereafter be implemented in accordance
with the phasing plan.   
Reason: In the interests of visual amenity. 
Local Government (Access to Information) Act 1985 - Background Papers
For further information or to inspect any letters of objection and other background papers,
please contact James McCafferty on 0141 487 1366 
 
 
 
Page 131 of 140

Page 138

Page 132 of 140

Page 139

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Report of Handling 
Reference No.   23/0505/PP
 
Agenda Item ( ) 
KEY  INFORMATION 
Ward: 4 – Paisley
Northwest 
Applicant: The
University of the West of
Scotland 
Registered: 
22/09/2023 
 
RECOMMENDATION
Grant, subject to
conditions 
 
 
 
 
 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Installation of replacement
windows and doors, solar panels, two ramps, railings,
cladding and a false floor. Erection of extension; formation of
window and door openings; renewal of roof; stonework
repairs; and landscaping works 
LOCATION: University of the West of Scotland, Storie
Street, Paisley, PA1 2BX 
APPLICATION FOR: Full Planning Permission 
© Crown Copyright and database right 2021. All rights reserved. Ordnance Survey Licence number 100023417. 
IDENTIFIED KEY ISSUES 
 The building is B listed and is located within both
Paisley Town Centre and its Conservation Area. 
 No representations were received. 
 The proposal accords with the relevant provisions of
both National Planning Framework 4 and the
Renfrewshire Local Development Plan. 
Alasdair Morrison
Head of Economy &
Development
Item 5(d)
PACC230124 Page 133 of 140

Page 140

Renfrewshire Council Planning and Climate Change Policy Board 
Page 2
 
REPORT OF HANDLING FOR APPLICATION 23/0505/PP 
SITE ADDRESS  University of the West of Scotland, Storie Street, Paisley, PA1 2BX 
PROPOSAL  Installation of replacement windows and doors, solar panels, two
ramps, railings, cladding and a false floor. Erection of extension;
formation of window and door openings; renewal of roof; stonework
repairs; and landscaping works 
RECOMMENDATION Grant, subject to conditions 
PROPOSALS This application seeks planning permission for the extension of, and
alterations to, a detached building on Storie Street, Paisley. 
The vacant building, which is located within the University of the West
of Scotland campus, fronts a road to the east and is bound by a
mixture of commercial and residential properties. The building is B
listed and sits within both Paisley Town Centre and its Conservation
Area. 
The two storey sandstone property has a dual pitched slate roof and
timber framed windows. A single storey red brick rotunda projects
from the rear. 
Several structures that sit between the main two storey building and
the rotunda would be removed and a small, flat roofed extension
would be constructed. Aluminium cladding would be installed along
part of the northern elevation of the rotunda. 
Replacement windows and doors would be installed across the
property while two new window openings (with decorative aluminium
shutters) would be formed on the southern elevation of the main
building. 
The ramp that provides access to the rotunda roof from the first floor
of the main building would be removed and a new ramp, false floor
and railings would be installed on the rotunda roof to create useable
outdoor space. In association with the installation of the new ramp,
two first floor window openings on the rear elevation of the main
building would be converted to a door and an existing door opening
would be infilled to create a window. 
Several sections of stonework would be either cleaned or repaired
while the slate roof would be renewed and solar panels would be
installed on the rear roof plane. 
An access ramp would be installed to the south of the property and
decorative railings would be installed along the southern site
boundary. A tree would be felled to accommodate the access ramp. 
Finally, areas of both hard and soft landscaping would be formed
Page 134 of 140

Page 141

Renfrewshire Council Planning and Climate Change Policy Board 
Page 3
 
across the application site. 
In light of the minimal removal of some of the existing building, and in
line with the Scheme of Delegation the application is being referred to
Board for consideration and determination.   
SITE HISTORY Application No: 23/0504/LB
Description: Installation of replacement windows and doors, solar
panels, two ramps, railings, cladding and a false floor. Erection of
extension; formation of window and door openings; renewal of roof;
stonework repairs; internal alterations and landscaping works
Decision: This application is also being presented to Board today for
determination.
 
CONSULTATIONS Communities & Housing Services (Environmental Protection
Team) – has no comments to make on the proposals. 
REPRESENTATIONS  None received. 
DEVELOPMENT PLAN
POLICIES
Policy and Material Considerations
Legislation requires planning decisions to be made in accordance with
the Development Plan unless material considerations indicate
otherwise. In this instance, the proposal must be assessed against the
following: 
National Planning Framework 4
Policy 1 - Tackling the climate and nature crises
Policy 2 - Climate mitigation and adaptation
Policy 7 - Historic assets and places
Policy 9 - Brownfield, vacant and derelict land and empty buildings
Policy 11 - Energy
Policy 27 - City, town, local and commercial centres
 
Renfrewshire Local Development Plan 
Policy C1 - Renfrewshire's Network of Centres
Policy ENV3 - Built and Cultural Heritage
Policy I4 - Renewable and Low Carbon Energy Developments
 
New Development Supplementary Guidance
Delivering the Centres Strategy
Delivering the Environment Strategy
 
Material Considerations
A Guide to Development in Conservation Areas 2022
Historic Environment Scotland: Managing Change in the Historic
Environment Guidance
 
PLANNING
ASSESSMENT
The main issues that must be assessed in this report are the impact
the development would have on Paisley Town Centre and on the
Conservation Area. The impact on the building's listed building status
will be assessed in the associated listed building consent application
(23/0504/LB) which is also being presented to Board today.
Page 135 of 140

Page 142

Renfrewshire Council Planning and Climate Change Policy Board 
Page 4
 
In respect of the impact on the Town Centre, Policy 27 of NPF4 and
Policy C1 of the LDP both support development that will strengthen
and enhance Town Centres as long as the proposal is compatible with
surrounding land uses. The New Development Supplementary
Guidance recognises Paisley Town Centre's role as a learning hub. 
The application site sits within the University of the West of Scotland
campus, with numerous educational buildings found nearby. The
proposal would improve access to, as well as the layout and fabric of,
this vacant building, allowing it to be brought back into use for
educational related purposes. The proposal therefore complies with
Policy 27 of NPF4 and Policy C1 of the LDP. 
Furthermore, as the proposal would result in the reuse of a vacant
listed building it is also considered to comply with Policy 7 and Policy
9 of NPF4 in this regard. 
In respect of the impact on the Conservation Area, Policy 7 of NPF4
and Policy ENV3 of the LDP both support the safeguarding of
Conservation Areas. Furthermore, Renfrewshire’s New Development
Supplementary Guidance, as well as Historic Environment Scotland's
guidance notes, require proposals to preserve the character of the
Conservation Area. The following matters therefore require further
consideration, 
Extension and cladding
The construction of the extension would require the removal of several
small structures that sit between the main building and the rotunda.
These are poor quality, piecemeal additions that contribute little to the
Conservation Area. The removal of these structures is therefore
considered acceptable. 
The extension has been designed to fill the gap between the rear of
the main building and rotunda without dominating the space. The
extension would not be highly visible from the street and raises no
overlooking or overshadowing concerns. 
The extension would be finished in aluminium cladding, in contrast
with the sandstone main building and red brick rotunda. Such a finish
is acceptable as it would allow the extension to be identified as a later
addition and would link the structure to the more modern buildings
found elsewhere on campus. 
The aluminium cladding used on the extension would continue along
part of the northern side elevation of the rotunda. This is acceptable
as this elevation is not highly visible from elsewhere within the
Conservation Area and the original red brick finish has already been
removed in this location. 
Replacement windows and new window openings
While guidance from Historic Environment Scotland encourages the
Page 136 of 140

Page 143

Renfrewshire Council Planning and Climate Change Policy Board 
Page 5
 
retention and repair of existing windows and doors, it also
acknowledges that in some circumstances it is necessary to replace
them. In this instance, the existing single glazed frames have reached
the end of their working life. 
The replacement windows and door would be timber framed, double
glazed units that closely mirror the style, opening mechanism and
colour of the existing frames. This work would therefore have minimal
impact on the character  of the Conservation Area. 
Replacing single glazed windows with double glazed windows would
also comply with Policy 1 and Policy 2 of NPF4 in that their
installation would improve the energy efficiency of the building. 
The windows that would be formed on the southern elevation would
be of an appropriate size for the location, would help activate what is
currently a windowless gable elevation and would add to the character
of the area. The aluminium frames and shuttering are also considered
acceptable and would not be detrimental to the character of the
Conservation Area. 
Rotunda roof access
Access arrangements onto the rotunda roof do not comply with
current accessibility standards. The existing ramp would therefore be
removed and a new ramp installed, emerging from the centre of the
rear elevation of the main building at first floor level. A false floor
would be formed on the rotunda roof to allow the pitch of the ramp to
be reduced while new, taller, railings would be installed to protect
those using the roof as an outdoor space. 
Repositioning the ramp so that it sits centrally and the associated
alterations to first floor window and door openings would improve the
symmetry of the rear elevation and would be more in keeping with
how the building would have originally looked. 
The new ramp and railings would have a negligible impact on the
quality of the Conservation Area as they would replace existing
structures of a similar design while the false floor would not be highly
visible. 
No details have been provided on how the external appearance of the
building will be made good following the alterations to the window and
door openings. To protect the Conservation Area it is therefore
considered appropriate to add a condition, should consent be granted,
requesting that details of the materials to be used are submitted to,
and approved by, the Planning Authority before any work begins. 
Access ramp, railings and landscaping
The access ramp to be installed to the south of the building would
allow step free access into the building and would be of a standard
size and design. 
Page 137 of 140

Page 144

Renfrewshire Council Planning and Climate Change Policy Board 
Page 6
 
Initially, it was proposed that 4.3 metre high aluminium curtain walling
would be installed along the southern site boundary. However,
following discussions between planning and the applicant this was
reduced to a 2.5 metre high decorative railing so that the rotunda
remains visible to those entering the campus from Storie Street. The
railing would be of a similar design to those installed on the ramps and
rotunda roof, minimising the material palette used for the development
and therefore its impact on the Conservation Area. 
The areas of hard and soft landscaping to be formed across the
application site would complete the development and improve the
setting of the building. The landscaping works and railings would also
help create a more welcoming environment at the Storie Street
campus entrance. A condition can be added to ensure the quality of
the landscaping is appropriate for a Conservation Area. 
Roof, solar panels and stonework
The roof would be stripped back and renewed, with the slate that is in
the best condition retained and used on the principal elevation. The
use of the original slate on the main elevation, which is of greatest
architectural significance, is welcome and a condition can be added to
ensure the slate used on the rear elevation is appropriate for the
location. 
The solar panels would be installed on the rear roof plane so they
would not affect the principal elevation and would not be highly visible
from the Conservation Area. As the panels would generate renewable
energy for the property this element of the proposal would also comply
with Policy I4 of the LDP as well as Policy 1, Policy 2 and Policy 11
of NPF4. 
The stonework cleaning and repairs would be carried out in a
sensitive, non invasive manner. It would not attempt to make the
building look new but would instead address defects such as cracking,
decay and areas of water ingress. This work would therefore improve
the quality of the building and the contribution it makes to the
Conservation Area. 
Overall, it is therefore considered the proposal complies with Policy 7
of NPF4, Policy ENV3 of the LDP and the associated supplementary
guidance as the development would respectfully alter the building to
allow it to meet the needs of the applicant while protecting the
contribution it makes to the wider Conservation Area. 
In view of the above, it is considered that the proposal would accord
with the relevant provisions of the Development Plan. There are no
other material considerations. Planning permission should therefore
be granted subject to conditions. 
RECOMMENDATION Grant, subject to conditions 
Page 138 of 140

Page 145

Renfrewshire Council Planning and Climate Change Policy Board 
Page 7
 
Reason for Decision 
1. The proposal accords with the provisions of the Development Plan and there were
no material considerations which outweighed the presumption in favour of
development according with the Development Plan. 
Conditions/Reasons 
1. Prior to the commencement of development hereby approved, full details of the
finishing materials to be used for the extension shall be submitted to, and approved
by, the Planning Authority.  Thereafter only the approved materials shall be used.   
Reason:  To safeguard the character of the Conservation Area. 
2. Prior to the commencement of development hereby approved, full details of the
design of and finish to the aluminium framed windows and their shutters as well as
all ramps, railings and the false floor on the rotunda roof shall be submitted to, and
approved by, the Planning Authority. Thereafter only the approved materials shall
be used.   
Reason:  To safeguard the character of the Conservation Area. 
3. Prior to the alteration of openings at first floor level necessary for the removal of the
existing ramp and installation of the new ramp approved, details of the materials
that will be used to repair the external appearance of the property in this location
shall be submitted to, and approved by, the Planning Authority. Thereafter only the
approved materials shall be used.   
Reason:  To safeguard the character of the Conservation Area. 
4. Prior to the commencement of development hereby approved, full details of any
new slate to be used shall be submitted to, and approved by, the Planning
Authority.  Thereafter only the approved slate shall be used. 
Reason:  To safeguard the character of the Conservation Area. 
5. For the avoidance of doubt, any slate vents shall be installed on the rear elevation
only.   
Reason:  To safeguard the character of the Conservation Area. 
6. Prior to the commencement of development hereby approved, a scheme of
landscaping shall be submitted for the written approval of the Planning Authority.
The scheme shall include (a) details of any earth moulding; (b) full details of the
finish to any areas of hard landscaping; (c) a scheme of tree and shrub planting,
incorporating details of the number, species, size and spacing of trees and shrubs
to be planted; and (d) details of the phasing of all works.   
The approved landscaping scheme shall thereafter be implemented in accordance
with the phasing plan.   
Reason: In the interests of visual amenity.
Page 139 of 140

Page 146

Renfrewshire Council Planning and Climate Change Policy Board 
Page 8
 
Local Government (Access to Information) Act 1985 - Background Papers
For further information or to inspect any letters of objection and other background papers,
please contact James McCafferty on 0141 487 1366 
 
 
 