Page 1

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Report of Handling 
Reference No.   23/0112/PP
 
Agenda Item ( ) 
KEY  INFORMATION 
Ward: Ward 1 –
Renfrew North and
Braehead 
Applicant: Mr Brian
Lees 
Registered: 
07/03/2023 
 
RECOMMENDATION 
Grant subject to
conditions 
 
 
 
 
 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Erection of residential
development comprising of eight flats with associated
access, parking, bin store, boundary treatment and
landscaping 
LOCATION: 74 Fulbar Street, Renfrew, PA4 8PB 
APPLICATION FOR: Full Planning Permission 
© Crown Copyright and database right 2021. All rights reserved. Ordnance Survey Licence number 100023417. 
IDENTIFIED KEY ISSUES 
 The application site is covered by Policy P1 within
the adopted Local Development Plan. 
 There have been no objections from consultees. 
 There have been five letters of objection.
 
 
Alasdair Morrison
Head of Economy &
Development

Page 2

Renfrewshire Council Planning and Climate Change Policy Board 
Page 2
 
REPORT OF HANDLING FOR APPLICATION 23/0112/PP 
SITE ADDRESS  74 Fulbar Street, Renfrew, PA4 8PB
PROPOSAL  Erection of residential development comprising of eight flats with
associated access, parking, bin store, boundary treatment and
landscaping 
RECOMMENDATION Grant subject to conditions 
PROPOSALS This application seeks planning permission for the erection of a
residential development comprising of eight flats within a four storey
building with associated access, parking, bin storage, boundary
treatment and landscaping. 
The application site is located on a corner plot, and is bound by Fulbar
Street to the south west, Blysthwood Avenue to the north west, a two
storey end terrace residential property to the north east, and a row of
two storey terraced properties to the south east. 
The site is approx. 700 square metres in area. It is currently occupied
by a single storey building which is positioned to the south east
corner, with the remainder of the site finished in a hard surface. This
building was previously used as offices, however the applicant has
advised that it has been vacant since 2022. Boundary treatment
currently comprises of a brick wall. 
The proposed development comprises the demolition of the single
storey building and the erection of a four storey flatted block with a
square footprint of approx. 188 square metres. The flatted block will
be positioned in the north western half of the site. The south eastern
half of the site comprises the parking and manoeuvring areas, with 8
parking spaces delineated. 
The four storey block will be predominantly finished in facing brick,
with metal cladding panels above and below the window opening. The
roof will also be finished in profiled sheet metal. The layout provides
for a landscaped buffer around the edge of the block. There is also a
bin and cycle store and further landscaping positioned along the north
eastern boundary. 
It should be noted that the original description of development
included reference to a biomass boiler. However, this has now been
omitted from the proposed scheme. 
This report relates to an application that would normally fall within the
Council's scheme of delegation to be determined by an appointed
officer. However, a request has been submitted by three members,
within 21 days of the application appearing on the weekly list, that the
matter be removed from the scheme of delegation for determination
by the Board. It was considered that the potential impact of the
development on the local community and local environment required it

Page 3

Renfrewshire Council Planning and Climate Change Policy Board 
Page 3
 
to be fully considered prior to any decision being made.
SITE HISTORY None recorded. 
CONSULTATIONS Communities & Housing Services (Environmental Protection
Team) – No objections. Advisory note required with regard to potential
land contamination. 
Chief Executive’s Service (Roads Development) – No objection
subject to conditions relating to the resurfacing of the footway fronting
the site, formation of a pedestrian route into the main entrance, the
location of the bin collection point, and the design of the site access. 
NATS – No objections. 
Glasgow Airport Safeguarding – No objection subject to condition
relating to the submission of a bird hazard management plan.
Advisory note also required with regard to the possible use of a crane. 
Scottish Water – No objections. 
Children’s Services – No objections. 
REPRESENTATIONS  The Council has undertaken two rounds of neighbour notification. 
Seven letters of representation, which object to the proposed
development, were received. The points raised in these letters can be
summarised as follows: 
1 – Noise, disruption and inconvenience associated with the
construction process. 
2 – Loss of sunlight and overshadowing. 
3 – Noise and fumes associated with biomass boiler. 
4 – Loss of privacy. 
5 – Loss of property value. 
6 – Insufficient parking provision. 
7 – Height and scale of the building is out of keeping with the
surrounding area. 
8 – Drainage and flooding. 
9 – Notification of the application has not been undertaken. 
10 – A two storey build would be more suitable at this location.

Page 4

Renfrewshire Council Planning and Climate Change Policy Board 
Page 4
 
11 – It is disingenuous to use other buildings or previous industrial use
of the area to justify the scale of the development. There are no other
three or four storey buildings within the immediate vicinity of the site. 
12 – Car ownership in the area is high and public transport services
continue to be reduced. 
13 – The building will be higher than the existing at 80 Fulbar Street. 
14 – No garden space is provided for residents. 
15 – Loss of views and impact on outlook. 
16 – There is already an adequate supply of flats in the area.
DEVELOPMENT PLAN
POLICIES
Policy and Material Considerations 
Legislation requires planning decisions to be made in accordance with
the Development Plan unless material considerations indicate
otherwise. In this instance, the proposal must be assessed against the
following: 
Development Plan 
National Planning Framework 4 
NPF4: Policy 1 – Tackling the climate and nature crisis
NPF4: Policy 3 – Biodiversity
NPF4: Policy 9 – Brownfield land, vacant and derelict land, and empty
buildings
NPF4: Policy 13 – Sustainable transport
NPF4: Policy 14 – Design, quality, and place
NPF4: Policy 15 – Local living and 20 minute neighbourhoods
NPF4: Policy 16 – Quality Homes
NPF4: Policy 18 – Infrastructure first 
Renfrewshire Local Development Plan 
LDP 2021: Policy P1 – Renfrewshire’s Places
LDP 2021: Policy P3 – Housing Mix and Affordable Housing
LDP 2021: Policy I3 – Flooding and Drainage
LDP 2021: Policy I7 – Zero and Low Carbon Buildings
LDP 2021: Policy ENV2 – Natural Heritage 
Supplementary Guidance 
Delivering the Environment Strategy
Delivering the Infrastructure Strategy
Delivering the Economic Strategy 
Material Considerations

Page 5

Renfrewshire Council Planning and Climate Change Policy Board 
Page 5
 
Renfrewshire Councils Residential Design Guide 
Scottish Government publications on Designing Streets and Designing
Places 
PLANNING
ASSESSMENT
Policy P1 states that within uncoloured areas on the proposals maps
there will be a general presumption in favour of a continuance of the
built form. New development proposals within these areas should
make a positive contribution to the Place, and be compatible and
complementary to existing uses. 
Whilst the most recent use of the site was an office, the surrounding
area is predominantly characterised by residential use. The
redevelopment of the site for residential use would be compatible with
surrounding uses in principle. However detailed consideration of the
propped development against the provisions of the New Development
Supplementary Guidance and the Residential Design Guide is
required. 
These documents set out a range of considerations that form the
basis of good places design. Each consideration will be assessed in
turn. 
Context and Character 
The application site is located in a built up area approx. 250m from
Renfrew town centre to the south east. The predominant built form
immediately surrounding the site is a mix of two storey terraced
properties. It is noted that the built form steps down as you move
further away from the town centre. There are four storey tenement
properties on the edge of the town centre, and three storey flats
opposite Fulbar Lane approx. 50m to the south east of the site. 
While the built form surrounding the site is predominantly two storeys,
there is a mix of design, age, and finish of the buildings. The most
notable building within the streetscene is number 80 Fulbar Street
which is directly opposite the site to the north west. This building
incorporates traditional proportions, and is higher than the two storey
dwellinghouses in the area. It is also finished in red facing brick which
contrasts with the grey render and stone associated with other
properties. 
The concept for the proposed development is based on the building at
number 80, and has taken ques with regard to design, height and
materials. While the proposed development is four storeys, the eaves
and ridge line height are commensurate with the building at number
80. The proposed development also incorporates facing brick, and
vertically proportioned windows. 
It is noted that number 80 is a remnant of the areas previous industrial
heritage. The applicant has sought to justify the development partly
based on this historical industrial built form. However, the area is now
clearly established as a residential area, and this provides the context

Page 6

Renfrewshire Council Planning and Climate Change Policy Board 
Page 6
 
from which the development should be assessed.       
Access and Connectivity 
The application site is within walking distance of Renfrew town centre,
its associated amenities and public transport connections. Policy 15
advocates local living to encourage connected and compact
neighbourhoods where people can meet most daily needs within a
reasonable distance of their home. Policies 13 and I1 advocate good
accessibility and connectivity to walking, cycling and public transport. 
The application site is well located in this regard, with the town centre,
other amenities such as Robertson Park, Renfrew Health Centre,
Kirklandneuk Primary School and Trinity High School all within a 20
minute walk from the site. 
The Roads Development officer has offered no objections to the
development, and is satisfied with the parking provision being
proposed given the sustainable location of the site. The matters of
detailed design raised by the Roads Development officer can be
managed via condition where required, and it is noted that the site
plan has been amended to accommodate some of the requirements. 
Layout and Built Form 
The proposed split in the site layout, with the building occupying the
northwestern half and the parking to the south east, is considered to
be acceptable. The site is a prominent corner plot, and the position of
the building reflects the building line along Blysthwood Avenue. 
With regard to built form, it is acknowledged that the four storey height
would be as departure from the predominant two storey built form in
the immediate vicinity of the site. However, the building is
commensurate with the height of the building at number 80. The
building at number 80 makes a positive contribution to the character of
the area, and a design concept which seeks to reflect this should be
considered desirable in principle. 
On this basis a departure from the predominant built form is not
considered to be a reason in itself for the proposal to be considered
unacceptable. The form of the building will not be detrimental to the
character or appearance of the place, and it is considered that a
development of this scale can be accommodated within the
streetscene without appearing incongruous. 
It is also noted that the existing building on the site is vacant, and the
proposal will redevelop a brownfield site which is supported by policy
9. On balance, it is considered that the redevelopment of the site will
have a positive impact on the place.   
Environment and Community

Page 7

Renfrewshire Council Planning and Climate Change Policy Board 
Page 7
 
A key consideration in the assessment of the development is the
potential impact on the residential amenity of neighbouring properties.
While it is considered that a building of this scale is acceptable with
regard to the streetscene, it must be demonstrated that it is
compatible with neighbouring uses. 
The development is most likely to have a potential impact on the
neighbouring properties to the north east (2 Blysthwood Avenue) and
south east (68 a-d Fulbar Street) which directly bound the site, 2
Fulbar Avenue to the south west, and 3 – 5 Blysthwood Avenue to the
north west. 
Turning firstly to 2 Blysthwood Avenue, the fenestration on the north
eastern elevation of the building has been amended to reduce the
potential loss of privacy. This includes replacement of a dormer with a
rooflight, and incorporation of high level windows. There is no direct
window to window overlooking as the gable of number 2 does not
incorporate any habitable room windows. 
The applicant has provided sunlight calculations which show the
extent of shadow cast by the proposed building. These calculations
show that the minimum standard of at least 50% of garden ground
receiving at least 2 hours of sunshine on the 12th March (as set out
within the BRE 209 2022 guidance on Site Layout Planning for
Daylight and Sunlight: A Guide to Good Practice) are met. 
Turning to 68 a-d Fulbar Street, there is a separation distance of 19m
between these properties and the proposed building. This will ensure
that windows and garden ground associated with 68 a-d Fulbar Street
are not overlooked to an unacceptable degree, and that sufficient
levels of privacy will be maintained. Treatment along this and all other
boundaries will be controlled via condition. 
In terms of overshadowing, as these properties are directly to the east
of the application site they are not significantly impacted through loss
of sunlight. With regard to daylight, it is noted that removal of the
existing building (which is hard up against the eastern boundary) will
improve the outlook and levels of daylight received by 68a in
particular. It is noted that the proposed building is within the 25 degree
line when plotted from 68 a-d. However the orientation of the
properties will ensure that overall amenity is not significantly impacted. 
Number 2 Fulbar Avenue is to the south west of the site on the
opposite side of Fulbar Steet. Given the position of the property to the
south west it will not be impacted by any overshadowing. The
windows on the rear elevation of this property which fronts Fulbar
Street are in the public domain, and I am satisfied that privacy will not
be compromised further with respect to the development being
proposed. It is noted that the proposed building is also within the 25
degree line when plotted from number 2. However the orientation of
the properties will ensure that overall amenity is not significantly
impacted.

Page 8

Renfrewshire Council Planning and Climate Change Policy Board 
Page 8
 
Numbers 3 and 5 Blysthwood Avenue are 20m from the development
site, and do not directly face the proposed block of flats. They will not
be impacted regarding loss of privacy. Due to the orientation of the
properties the sunlight analysis shows that the development will
overshadow the front elevation of these properties resulting in a partial
loss of sunlight within the habitable rooms on the front elevation of the
properties. 
The analysis shows that the development will not result in a total loss
of sunlight. These properties will still receive some sunlight in the
afternoon. The partial loss is restricted to winter months only. It is not
considered that the impact on amenity that arises from the loss of
sunlight would be so significant as to justify refusal of the application.   
The potential impact on number 80 Fulbar Street is not likely to be
significant as this is a commercial property and not a dwellinghouse. 
In view of the above, it is considered that on balance the development
will not result in a significant loss of amenity for neighbouring
properties. 
The site plan includes an indicative landscaping strategy which will
provide a softer setting for the building and some amenity for
residents. It is noted above that public parks are also within walking
distance of the site. 
Whilst the planting plan is not detailed, it is likely that any landscaping
will improve biodiversity at this location given the site in its current
condition is fully covered with hard standing. The development would
meet the aims of policy 3 and ENV2 in this regard. 
The proposal includes a drainage strategy which would manage
surface water in a sustainable manner using filter trenches and a
soakaway system. A condition can be applied to ensure the strategy is
implemented on site and maintained thereafter in accordance with the
submitted documents. 
Finally, it is noted that while the site is on the edge of the coastal
potential flooding extent the flood risk area does not cover the
footprint of the building, the surrounding landscaping, the car parking
area, or the site access. The development is considered to comply
with Policy I3.   
Buildings and Design 
The design and finish of the proposed building is based on the brick
building at number 80 Fulbar Street. I am satisfied that the building is
of a suitable design and finish, and will make a positive contribution to
the place as required by policies 14, 16 and P1. 
The combined bin and bike store is also finished in brick, with a flat

Page 9

Renfrewshire Council Planning and Climate Change Policy Board 
Page 9
 
roof. Its position to the rear of the flats ensures it will not have a
significant impact on the streetscene. 
The applicant has advised that energy efficiency and carbon dioxide
reduction will be a key component of the development. The
development initially included a biomass boiler system. However this
has since been omitted from the scheme. It is considered that a
condition should be applied requiring the submission of an Energy
Design Analysis to demonstrate that predicted emissions from the
development are reduced by at least 15% below 2007 building
standards as required by Policy I7. 
In response to the points raised in the letters of representation,
matters relating to points 2, 4, 6, 7, 8, 13, and 14, namely the scale of
the development and the impact on amenity, drainage, landscaping,
and parking have been addressed in the above assessment. 
1 - A construction and environmental management plan will be
requested via condition to ensure the construction phase is managed
appropriately. 
3 - The biomass boiler has been omitted from the proposal. 
5 – Loss of property value is not a material consideration. 
9 – Notification of the application has been undertaken in accordance
with the requirements of the legislation. It is noted that a second round
of notification was undertaken following submission of amended
plans. 
10, 11, 16 – Although historical building patterns in the area are
acknowledged, the proposal has been assessed against the current
residential context. Existing supply of flats in the area or preference
for a lower density of build is not considered to be a reason to refuse
the development. Higher density and more compact development is
supported in principle by NPF4, particularly at locations such as this
where amenities are within a walkable distance of the site. The
development will contribute to the mix of houses and flats in this area
as promoted by Policy P3. 
12 – A higher density of development will contribute to the viability of
services and amenities. The Roads Development officer has offered
no objections to the development. 
15 – Loss of views is not a material consideration. Impact on outlook
has been considered in the above assessment. 
In conclusion, the proposed development will support delivery of two
of the overarching spatial principles set out in National Planning
Framework 4 – Local Living and Compact Urban Growth. The
application site is within a sustainable location, and its redevelopment

Page 10

Renfrewshire Council Planning and Climate Change Policy Board 
Page 10
 
in the manner proposed will contribute positively to the place.
Minimum standards relating to the amenity of neighbouring residential
properties will be met.   
In view of the above, it is considered that the proposal would accord
with the relevant provisions of the Development Plan. There are no
other material considerations. Planning permission should therefore
be granted. 
RECOMMENDATION Grant subject to conditions  
Reason for Decision 
The proposal accords with the provisions of the Development Plan and there were no
material considerations which outweighed the presumption in favour of development
according with the Development Plan. 
Conditions 
1. That prior to the occupation of any flat hereby approved, the developer shall
resurface the sections of footway which are commensurate with the site boundaries
fronting Fulbar Street and Blysthwood Avenue. The footway shall be resurfaced to
a standard that is structurally adequate and to the satisfaction of the Planning
Authority. 
Reason: To ensure the standard of footway fronting the site is sufficient to serve the
development. 
2. That prior to the commencement of development on site, the developer shall submit
for the written approval of the Planning Authority a plan showing the location of a
bin collection area from where bins can be safely presented for collection. The plan
shall include a specification for all works neccesary to form the bin collection area
including and hard surfacing or boundary treatments. The bin collection area
thereafter approved shall be implemented on site and made available for use prior
to the occupation of any of the flats. 
Reason: To ensure that bins associated with the development can be presented for
collection safely. 
3. That prior to the commencement of development on site, the developer shall
provide a strategy for the written approval of the Planning Authority which details
the drainage of surface water from all areas of hard standing. The strategy shall
ensure that surface water from any areas of hard standing shall not discharge onto
the public road. The approved strategy shall thereafter be implemented on site, and
maintained for the life of the development. 
Reason: To ensure that surface water is managed appropriately in the interests of
sustainable drainage. 
4. That the development hereby approved shall be undertaken in accordance with
approved drawings 1848/AL(0)007 rev E titled ‘Plans as Proposed’ and
1848/AL(0)11 rev E titled ‘Elevations as Proposed’. No alterations to these plans

Page 11

Renfrewshire Council Planning and Climate Change Policy Board 
Page 11
 
are to take place unless first submitted to and agreed in writing with the Planning
Authority. The combined bin and cycle store as shown in these drawings shall also
be constructed and made available for use prior to the occupation of any flat hereby
approved. 
Reason: To ensure the development is implemented in accordance with the
approved plans.   
5. Development shall not commence until a Bird Hazard Management Plan has been
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. The submitted plan shall include details of: 
 Management of any flat/ shallow pitched/green roofs on buildings within the site
which may be attractive to nesting, roosting and loafing birds. The management
plan shall comply with Advice Note 8 ‘Potential Bird Hazards from Building
Design’. 
The Bird Hazard Management Plan shall be implemented as approved on
completion of the development and shall remain in force for the life of the
development. No subsequent alterations to the plan are to take place unless first
submitted to and approved in writing by the Planning Authority in consultation with
Glasgow Airport. 
Reason: It is neccesary to manage the development in order to minimise its
attractiveness to birds which could endanger the safe movement of aircraft and the
operation of Glasgow Airport. 
6. That prior to the commencement of development on site, the developer shall
provide for the written approval of the Planning Authority a specification detailing
the colour and texture of all finishing materials to be used on the external walls of
the building hereby approved. This shall include windows and all rainwater goods.
Only the materials within the approved specification shall thereafter be used in the
development of the site. 
Reason: To ensure the external materials are suitable for use in the interests of
visual amenity. 
7. That prior to the commencement of development on site, full details of all soft and
water landscaping works shall be submitted as part of a landscape strategy for the
written approval of the Planning Authority. The landscape strategy shall include (but
not be limited to) provisions in respect of:
 all proposed trees, shrubs, hedgerows, areas of grass/wildflower seeding,
turfing including size, species, spacing and location.
 all areas of hard standing including location and materials.
 a plan showing proposed site levels. 
 all areas of surface water including ponds, and measures for the sustainable
management and drainage of surface water where applicable. 
 the implementation of all biodiversity and habitat enhancements.
 a timetable for the implementation of the landscape strategy.
 a strategy for the future management and maintenance of all landscaped
areas including provision for replacement of trees, shrubs, hedgerows and

Page 12

Renfrewshire Council Planning and Climate Change Policy Board 
Page 12
 
areas of grass/wildflower seeding and turfing if they were to become
diseased, die, become seriously damaged or are removed within 5 years of
being planted. 
The approved landscape strategy shall thereafter be implemented on site in
accordance with the approved timetable and shall be managed and maintained
thereafter for the life of the development. 
Reason: To ensure a robust landscaping strategy is implemented in the interests of
visual amenity, landscape character and biodiversity. 
8. That prior to the commencement of development on site, the developer shall
provide a specification for the written approval of the Planning Authority detailing
the location, design, materials and colour of all boundary fences, gates, walls, or
other method of enclosure to be installed at the site. Only the boundary fences,
gates, walls, or other methods of enclosure within the approved specification shall
thereafter be used in the development of the site. 
Reason: To ensure the methods of enclosure are of a suitable design in the
interests of visual amenity. 
9. That prior to the commencement of development, a Construction Environmental
Management Plan (CEMP) shall be submitted to and approved in writing by the
Planning Authority.  The CEMP shall include (but not be limited to) provisions in
respect of:
 mitigation measures for potential dust, noise, and vibration impacts on nearby
properties, 
 waste management, pollution control and mitigation, 
 a plan showing existing drainage pipes and other utilities within the site and
procedures for how they will be safeguarded during construction,
 surface water management,
 procedures for monitoring compliance and dealing with any breaches of the
approved management plan,
 the formation of access from the public road to accommodate construction
vehicles including geometry, surfacing, and sightlines
 the additional signage on both public roads where access will be taken to
inform drivers of the construction vehicles.
 details of proposed temporary site compound for storage of materials,
machinery, and designated car parking. 
The measures set out within the approved CEMP shall thereafter be implemented
on site during the construction phase 
Reason: To ensure environmental impacts are mitigated during the construction
phase, and that the construction phase is undertaken safely. 
10. That prior to the commencement of development on site, the developer shall submit
an Energy Design Analysis for the written approval of the Planning Authority
demonstrating the fabric performance of the building and the installation of
technology that provides low or no amounts of carbon dioxide emissions, to reduce
the predicted emissions from the building by at least 15% below 2007 building
standards. The building shall thereafter be developed in accordance with the

Page 13

Renfrewshire Council Planning and Climate Change Policy Board 
Page 13
 
approved Energy Design Analysis. 
Reason: To ensure the building is designed in a manner that reduces energy
requirements and carbon emissions.