Page 1

___________________________________________________________________ 
To: Planning and Climate Change Policy Board 
On: 7 November 2023
___________________________________________________________________ 
Report by: Chief Executive
___________________________________________________________________ 
Heading: Clyde Peatlands – Update 
___________________________________________________________________ 
1. Summary 
1.1 The Clyde Peatlands initiative has been developed as part of a wider response
to tackling climate change across Glasgow City Region.  The purpose of the
initiative is the restoration of degraded peatland bogs which deliver climate and
ecological benefits across the City Region, supporting Net Zero ambitions. 
1.2 The purpose of this report is to update members on the Clyde Peatlands
initiative and delivery within Renfrewshire.   
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Board: 
(i) Notes development of Clyde Peatlands and the role of the initiative in
contributing to the Council’s response to climate change; 
(ii) Notes the opportunity for development of the West Tandlemuir Farm
Restoration Project as part of Clyde Peatlands in Renfrewshire; 
(iii) Delegates authority to the Head of Economy and Development, in
consultation with the Convenor, to develop and progress implementation
of the West Tandlemuir Restoration Project, including the preparation of
bids for capital funding; 
(iv) Notes that further progress on delivery of the West Tandlemuir project
will be reported to the Board as appropriate. 
3. Background 
3.1. The Clyde Peatlands initiative was developed in 2022 as part of a wider
response to tackling climate change across the Glasgow City Region.

Page 2

The initiative has been led by the Glasgow and Clyde Valley Green Network
Partnership (GCVGNP), which includes the region’s eight local authorities and
key agencies such as NatureScot.   
3.2. The purpose of the initiative is to directly address the opportunities for peatland
restoration which deliver climate and ecological benefits across the Glasgow
City Region.  Peatland restoration supports the region’s Net Zero ambitions
through the storage of carbon, assists in reducing the impact of climate change
through storing surface water and provides ecological benefits by supporting
enhanced habitat networks.   
3.3. The initiative was endorsed by the Glasgow City Region Cabinet on 16 June
2022 with initial phases of the project funded by the NatureScot Peatland Action
programme.  The programme has set aside £250 million until 2030 to support
peatland restoration across Scotland and enabled a dedicated Clyde Peatlands
Officer to be appointed by GCVNP in April 2023.   
3.4. Renfrewshire Council declared a Climate Emergency on 27 June 2019.  A key
element of the Council’s approach to climate change is to achieve net zero
carbon emissions by 2030, and a Plan for Net Zero was approved by the
Planning and Climate Change Board on 23 August 2022.  The Clyde Peatlands
initiative supports delivery of the plan through storage of carbon and reduction
of emissions. 
4. Clyde Peatlands – West Tandlemuir Farm Restoration   
4.1 The Clyde Peatlands Project Officer has engaged with local authorities across
the City Region to consider the potential for ‘early win’ projects which
demonstrate the benefits of peatland restoration, maximise use of funding
available from NatureScot’s Peatland Action Programme and support the
restoration of peat bogs across the City Region. 
4.2 Early engagement with Council officers identified that the most significant
opportunity for peatland restoration within Renfrewshire lies within West
Tandlemuir Farm, Clyde Muirshiel Regional Park, Lochwinnoch, as shown on
the attached plan.   
4.3 In this context a specialist feasibility evaluation of peat reserves at West
Tandlemuir Farm was funded and commissioned by NatureScot’s Peatland
Action team.  The study concluded that an area of some 216ha of the farm was
suitable for restoration, with the potential to sequester 556 tonnes of CO2  per
year.  The area concerned represents less than 17% of the farm’s total extent
and is located on poorer quality grazing land.   
4.4 The works identified within the feasibility study include the construction of  ‘wave
dams’ with reprofiling of ditches and gullies.  The estimated cost of works, which
will require a specialist contractor to be appointed, is circa £210,000.  As with
the initial feasibility study, the opportunity exists for delivery to be 100% funded
through NatureScot’s Peatland Action programme.

Page 3

5. Next Steps 
5.1 Development of a detailed programme of restoration works at West Tandlemuir
Farm is being taken forward in partnership with the Clyde Peatlands officer
through a Working Group comprising of relevant officers from the Chief
Executive’s Service and Environment, Housing and Infrastructure Services.   
5.2 The area of land proposed for restoration is currently let to an agricultural tenant
and officers are working with the farmer to secure consent for the works and to
assist in seeking external funding for land management practices which protect
and enhance the natural heritage, improve water quality, manage flood risk,
and mitigate and adapt to climate change in the area of restored peatland. 
5.3 In tandem, over the coming months Council officers will work with the Clyde
Peatlands officer to secure the necessary statutory consents and approvals
(including planning permission), submit a formal application to the Peatland
Action Programme to secure NatureScot funding and procure an appropriate
specialist contractor to undertake works on the ground. 
6. Delivery and Reporting 
6.1 Subject to securing funding and necessary approvals, it is anticipated that
works could progress in autumn 2024.  Progress on delivery of the project and
any future phases of Clyde Peatlands will be reported to the Board as
appropriate.
___________________________________________________________________ 
Implications of the Report 
1. Financial – It is anticipated that the project will be fully funded by NatureScot’s
Peatland Action Programme.   
2. HR & Organisational Development – None. 
3. Community Planning – 
Creating a sustainable Renfrewshire for all to enjoy – Clyde Peatlands will
support the Council’s response to climate change and delivery of Renfrewshire’s
Plan for Net Zero and Renfrewshire Biodiversity Strategy 2018-2022 through the
storage of carbon emissions and works which support, enhance and connect
existing habitats. 
4. Legal – None. 
5. Property/Assets – None. 
6. Information Technology – None. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights.

Page 4

No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report.  If required following
implementation, the actual impact of the recommendations and the mitigating
actions will be reviewed and monitored, and the results of the assessment
will be published on the Council’s website.   
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – None. 
11. Privacy Impact – None. 
12. Cosla Policy Position – None. 
13. Climate Change – Implementation of the Clyde Peatlands within Renfrewshire
will support the Council’s Plan for Net Zero through storage of carbon and
reduction of emissions. 
________________________________________________________________ 
Appendices 
(a) Location Plan – West Tandlemuir Peatland Restoration Works 
___________________________________________________________________ 
Author: Euan Shearer, Regeneration and Place Manager
euan.shearer@renfrewshire.gov.uk Tel: 07483 136235

Page 5

1:32,951
Author:
Ordnance Survey Mapping - © Crown Copyright and database right 2023. All rights reserved. Ordnance Survey Licence number 100023417. 
Aerial Photography 2009 - Cities Revealed ® copyright by The Geoinformation ® Group, 2009 and Crown Copyright © All rights reserved.
Aerial Photography 2004/6 - © 2004 Getmapping plc © 2006 Getmapping plc
Aerial Photography 2001 - Cities Revealed ® copyright by The Geoinformation ® Group, 2009 and Crown Copyright © All rights reserved.
Historic Map Data - © Crown Copyright and Landmark Information Group Limited 2012. All rights reserved.
I
Date: 22/08/2023ALAN BURGESS
LOCATION / CONTEXT PLAN
WEST TANDLEMUIR
- PEATLAND RESTORATION WORKS
Legend
Clyde Muirshiel Regional Park - Boundary
SELECTED TREATMENT
AREA
WEST TANDLEMUIR
FARM BOUNDARY