Minute of Meeting
Planning and Climate Change Policy Board 
Date Time Venue
Tuesday, 29 August 2023 13:00 Council Chambers (Renfrewshire), Council
Headquarters, Renfrewshire House, Cotton
Street, Paisley, PA1 1AN 
Present: Councillor Jennifer Adam, Councillor Alison  Ann-Dowling, Councillor Andy Doig,
Councillor Chris Gilmour, Councillor Neill Graham, Councillor Bruce MacFarlane, Councillor
Kenny MacLaren, Councillor Jamie McGuire, Councillor Marie McGurk, Councillor John
McNaughtan, Councillor Iain Nicolson, Councillor Jim Paterson, Councillor John Shaw,
Councillor Ben Smith 
Chair
Councillor Paterson, Convener, presided. 
In Attendance
A Morrison, Head of Economy & Development; L Mahon, Head of Marketing &
Communications; D Love, Chief Planning Officer, G McCracken, Development Standards
Manager, K Dalrymple, Development Plans & Housing Strategy Team Leader, P Moss,
Strategy, Policy & Insight Manager, R Smith, Climate Emergency Lead Officer, L Adamson,
Communications & Public Affairs Manager and G Crawford, Senior Communications
Officer (all Chief Executive’s); G Hannah, Head of Climate, Public Protection & Roads
(Environment, Housing & Infrastructure); M Conaghan, Head of Corporate Governance, N
Young, Managing Solicitor (Litigation & Advice), V Howie, Finance Business Partner, R
Devine and C MacDonald, both Senior Committee Services Officers, D Cunningham,
Committee Services & Licensing Officer and R McCallum, Licensing & Committee
Assistant (all Finance & Resources). 
Webcasting of Meeting
Prior to the commencement of the meeting the Convener intimated that this meeting of the
Policy Board would be filmed for live or subsequent broadcast via the Council's internet
site. 
Apology
Councillor Hannigan.

Page 2

Declarations of Interest and Transparency Statements
There were no declarations of interest or transparency statements intimated prior to
the commencement of the meeting. 
1 Revenue & Capital Budget Monitoring Report
There was submitted a Revenue and Capital Budget Monitoring report by the Director
of Finance & Resources for the period 1 April to 23 June 2023. 
The report stated that the projected outturn as at 31 March 2024 for all services
reporting to this Policy Board was an overspend position of £0.006 million. It was
noted that there were no capital budget projects reporting to this Policy Board.
Summaries were provided over the relevant services in the tables within the report,
together with further analysis. It was noted that the projected outturn was based on
current available information and assumptions made by service budget holders. It was
also highlighted that budget adjustments totalling £0.006 million had been processed
since approval of the budget at the meeting of Council held on 2 March 2023. Full
details of these adjustments were outlined within the report. 
DECIDED: That the projected Revenue outturn position, detailed in Table1 of the
report, and the budget adjustments, detailed in section 4 of the report, be noted.  
Sederunt
Councillor Ann-Dowling entered the meeting during consideration of the following item
of business. 
2 Implications of a Separate Carbon Neutral Plan for Renfrewshire
Under reference to item 2 of the Minute of the meeting of this Policy Board held on 24
January 2023 there was submitted a report by the Director of Environment, Housing &
Infrastructure relative to the implications of a separate Carbon Neutral Plan for
Renfrewshire. 
Renfrewshire’s Plan for Net Zero was approved at the meeting of this Policy Board
held on 23 August 2022, committing to working towards net zero by 2030 for both the
Renfrewshire area as a whole and Renfrewshire Council as an organisation. The
target placed Renfrewshire 15 years ahead of the national target, as set out in the
Climate Change (Emissions Reduction Targets) (Scotland) Act 2019, which
committed Scotland to become net zero by 2045 and 20 years ahead of the UK
Government target of net zero by 2050. At the meeting of this Policy Board held on 24
January 2023, it had been agreed that a report be submitted relating to a ‘Carbon
Neutral by 2025’ Plan. It was highlighted that the Carbon Neutral Plan would be
distinct from the approved Plan for Net Zero, focusing on the applicability of external
carbon offsetting and how this could be used to offset the emissions produced by
Renfrewshire. The report outlined the implications associated with external carbon
offsetting if applied to the Renfrewshire context; and the appropriate steps should an

Page 3

additional Carbon Neutral Plan, with a target date of 2025, be adopted in addition to
the existing Plan for Net Zero with a target date of 2030. It was also noted that while
there was significant commitment and focus within the Council and across
Renfrewshire to tackle the climate emergency, the report indicated that the resource
and financial capacity required to deliver two distinct Plans with different target dates
and different methodologies was unlikely to be feasible or bring best value. In addition
to the potentially significant financial impact for the Council on an ongoing annual
basis, there was also a risk around confusion of the messaging, communication and
engagement, which had been a key strength of Renfrewshire’s response to date. The
report acknowledged that within the Plan for Net Zero offsetting would have a role to
play to deal with residual emissions. The detailed phased road map and costed
delivery plans which were currently being developed would highlight the levels of
offsetting required to reach net zero for both the Council as an organisation and the
whole Renfrewshire area. The development of an offsetting strategy, looking at both
local offsetting and external offsetting, which aligned to the phased road map would
be a valuable tool to support Renfrewshire’s net zero activities. However, based on
the information currently available, it was recommended that the Council's focus
remained on continuing to work with partners towards the current 2030 targets and
actions within the approved Plan for Net Zero. 
DECIDED: 
(a) That the implications, particularly the financial implications, of having a distinct and
separate Carbon Neutral Plan which focused on external carbon offsetting in addition
to the approved actions and targets within the existing Plan for Net Zero be noted; 
(b) That it be noted that the existing Plan for Net Zero and the approved targets and
actions, including those currently relating to carbon offsetting, should remain the focus
and continue to be progressed as a priority by all partners in Renfrewshire; and 
(c) That, following phase 2 of Renfrewshire’s Plan for Net Zero, the development of an
offsetting strategy aligning with the phased road map and costed delivery plans to
identify and maximise opportunities associated with offsetting be agreed. 
3 Circular Economy (Scotland) Bill: Stage 1
There was submitted a report by the Director of Environment, Housing &
Infrastructure relative to the Circular Economy (Scotland) Bill. 
The report stated that the Circular Economy (Scotland) Bill had been introduced in 
Parliament on 13 June 2023 with the objective of introducing measures as part of the
transition to a circular economy that required primary legislation. The aim of the Bill
was to set out how modernising Scotland’s waste and recycling services could help
tackle the climate and nature crises and how, by introducing a circular economy
strategy and associated targets, progress towards reaching a circular economy would
be monitored. Measures included giving Ministers powers to set local recycling rates,
setting statutory targets for delivery of a circular economy to measure progress in
reducing waste; banning the disposal of unsold consumer goods to prevent good
products ending up in landfill; and placing charges on single use items such as coffee
cups to encourage the move to reusable alternatives. Key areas within the Bill which
would potentially have future impacts for the Council were highlighted within the
report.

Page 4

DECIDED: That the high-level information available at this time on the Circular
Economy (Scotland) Bill be noted; and that it be further noted that updates would be
submitted to the relevant Policy Boards on the further development of the Bill as it
progressed, along with impacts on local service delivery and statutory obligations. 
4 Dargavel – Planning Update
Under reference to Item 3(b) of the Minute of the meeting of Council held on 22 June
2023 there was submitted a report by the Chief Executive relative to site allocations
within the Dargavel Masterplan (Community Growth Area) site following negotiations
between BAE Systems and the Council; the total number of housing units granted
planning permission to date; and proposed changes to the Section 75 legal
agreement between BAE Systems and the Council. 
The report outlined three proposed changes to the currently approved Dargavel
Masterplan to allow for additional education capacity to be delivered to serve the
residents of Dargavel Village. The sites involved were identified in plans appended to
the report, together with a summary of the proposal.  In addition, the report stated that
the Council had been working on the premise that the total number of homes with
planning permission was approximately 4,300 units and while this broadly concurred
with the position being progressed by BAE Systems, Council officers had identified
potential uncertainties in relation to the interpretation of the total housing units
approved as part of the planning applications determined. BAE’s legal interpretation of
the planning permissions granted differed from the Council’s view, stating that they
had consent for 4,322 homes in total and their list of relevant planning permissions
was set out within Appendix 1 of the report. In terms of working towards an agreement
to find a solution to the current education capacity issues at Dargavel, the Council had
agreed to work to an explicitly clarified total of 4,322 homes. This figure had been
used by the Council in commissioning the Edge Analytics work on school roll
forecasting for the catchment area. 
As a result of negotiations that had taken place between the Council and BAE
Systems in recent months, and in reaching agreement on the land transfers outlined
in the report to be considered at the meeting of the Infrastructure, Land &
Infrastructure Policy Board to be held on 30 August 2023, there were also several
proposed changes to the existing Section 75 Agreement that applied to the Dargavel
Masterplan. It was highlighted that the Section 75 Agreement was a legal document
that set out the obligations placed upon BAE Systems, as co-signatories with
Renfrewshire Council, and subsequent landowners of the Dargavel development.
Proposed revisions to the October 2018 Section 75 Agreement, which would be
formalised in a Minute of Variation, were detailed within the report. 
The report highlighted that the revised site allocations and proposed changes to the
Section 75 legal agreement would only be enacted when the Council reached
agreement with BAE Systems on the transfer of land within the Dargavel Masterplan
for education purposes. 
DECIDED: 
(a) That the proposed changes to the Dargavel Masterplan, as currently approved and
illustrated in the adopted Local Development Plan, be noted;

Page 5

(b) That the proposed changes to the existing Dargavel Section 75 Agreement be
agreed; 
(c) That the confirmed housing capacity of the Dargavel Masterplan site, given
planning permissions granted, be noted; and 
(d) That it be noted that the above changes would only be enacted when the Council
reached agreement with BAE Systems on the transfer of land for education purposes
within the Dargavel Masterplan. 
5 Tree Preservation Order Requests
There was submitted a report by the Chief Executive relative to requests to apply a
Tree Preservation Order (TPO) designation to sites across Renfrewshire. 
The report advised that the TPO requests submitted had been considered in terms of
the relevant legislation, namely, Section 160 of The Town and Country Planning
(Scotland) Act 1997 as amended by the Planning etc (Scotland) Act 2006, and within
the procedures set out in the Town and Country Planning (Tree Preservation Order
and Trees in Conservation Areas) (Scotland) Regulations 2011. The report referred to
requests received for the designation of TPOs in respect of sites at (i) Potterhill
Avenue, Paisley; (ii) the south of Stanely Reservoir; (iii) St Mark's Church, Paisley; (iv)
Station Road, Bridge of Weir; (v) Edzell Drive, Elderslie; and (vi) Barrochan Road,
Brookfield, and advised that an assessment had been undertaken in respect of each
requested site, details of which were provided within the report,  together with
recommendations whether a TPO should be made and considerations. 
DECIDED: 
(a) That the need for a Tree Preservation Order be approved in respect of a site at
Potterhill Avenue, Paisley, trees to the south of Stanely Reservoir and trees at St
Mark's Church, Paisley and that it be agreed that officers proceed to prepare the
Orders, serve them on relevant parties and make the Orders available to the public
and seek representations; and 
(b) That it be agreed that Tree Preservation Orders not be progressed at Station
Road, Bridge of Weir; Edzell Drive, Elderslie; and Barrochan Road, Brookfield. 
6 Developer Contributions – Annual Report
There was submitted an annual report by the Chief Executive relative to monies held
by the Council which had been received in relation to developer contributions
associated with approved planning applications. 
The report detailed the current status, sums of monies involved and purpose of the
developer contributions received in terms of various Section 50, Section 69 and
Section 75 agreements relating to (i) planning application 90/0661/PP, known as the
Station Rise development; (ii) planning application 02/0660/PP at Kings Inch
Road/Ferry Road/Meadowside Street/Neil Street, Renfrew; (iii) a number of planning
applications for developments at Kings Inch Road and Ferry Village, Renfrew where a

Page 6

financial contribution towards the bus rapid transit system, known as Fastlink, had
been agreed; (iv) planning application 16/0878/PP at Abbotsinch Retail Park; (v) the
Ferry Village, Renfrew development; and (vi) Dargavel Village. 
DECIDED: 
(a) That the Annual Report in respect of developer contributions be noted; and 
(b) That the developer contributions currently held by the Council be noted. 
7 Developer Contributions – Education - Update
There was submitted a report by the Chief Executive relative to progress in
developing new supplementary planning guidance on developer contributions for
education. 
The report advised that Renfrewshire Council’s adopted Local Development Plan
included policy I8 which made it clear that the local authority would seek proportionate
and necessary contributions from new housing development towards shortfalls in
education capacity resulting from the impact of the development. This was a standard
planning policy approach used by most Scottish local authorities and had been used
in Renfrewshire for several years in respect of relevant new housing developments.
Education contributions were normally achieved via a planning obligation, namely a
Section 75 Agreement, between the local authority and the applicant(s). It was
highlighted that such an obligation applied to the land concerned, regardless of
subsequent changes in ownership. The report stated that, in Renfrewshire, Section 75
Agreements were identified early during pre-application discussion with applicants
and the headlines from any such agreement identified in appropriate Board reports
with the detailed wording and signing of the documentation delegated to senior
officers within the Council. 
The report indicated that it was the intention, in Renfrewshire, to progress towards
preparing draft supplementary planning guidance on developer contributions for
education to supplement policy I8 of the adopted Local Development Plan. The
rationale for adopting such a policy and the factors to be considered to ensure that the
policy achieved its aims were outlined.  The report advised that the aim was to
develop and submit a framework for how a revised education contributions policy
would be applied in the Renfrewshire area to the next meeting of this Policy Board
with a revised draft policy being submitted for consideration to the next meeting of this
Policy Board and then be subject to a public consultation exercise prior to being
finalised and submitted to the Policy Board for approval. 
DECIDED: That the update on progress towards new supplementary planning
guidance on developer contributions for education be noted and that it also be noted
that the draft guidance would be submitted to a future meeting of this Policy Board for
approval in due course.

Page 7

8  Renfrewshire Planning Performance Framework 2022/23
There was submitted a report by the Chief Executive relative to Renfrewshire’s
Planning Performance Framework 2022/23, a copy of which was appended to the
report. 
The report stated that a system of performance management for planning had been
established by local authorities and the Scottish Government, which required all
planning authorities to produce an annual Planning Performance Framework. The
Framework had been developed by the Heads of Planning in Scotland to capture and
highlight a balanced measurement of planning performance, showing commitment to
speed of decision making; qualitative analysis, delivery and implementation of good
quality development and design; project management and communication
consultation, and engagement with communities and stakeholders. The Renfrewshire
Planning Performance Framework 2022/23 demonstrated that the Council was
committed to continuous improvement in the service it provided in its role as a local
planning authority. It was noted that the Framework demonstrated how the planning
performance feedback received from the Scottish Government in 2022 had been
considered, provided case studies and examples of strategies and projects where
Planning had led or been a partner in implementing or supporting the delivery of
Council priorities and highlighted the ongoing changes and adaptations made to
planning processes and procedures over the previous year. The Renfrewshire
Planning Performance Framework also included statistical indicators. 
DECIDED: That the Renfrewshire Planning Performance Framework 2022/23 be
noted. 
9 Renfrewshire Local Development Plan - Development Plan Scheme
2023
There was submitted a report by the Chief Executive relative to the annual
Renfrewshire Development Plan Scheme 2023. 
The report indicated that the next Local Development Plan (LDP) for Renfrewshire
would be informed by National Planning Framework 4 and any local place plans
prepared by local communities across Renfrewshire. The Development Plan Scheme
detailed the work required to prepare, engage and consult on the Local Development
Plan. A key element of the development plan scheme was the participation statement
which outlined when, how and with whom consultation would take place during the
plan preparation process. The draft participation statement had been subject to a four-
week consultation, commencing on 11 July 2023, to gather the views of local
communities and other key stakeholders on how the Council should engage with them
during the plan preparation process and had resulted in 81 responses being received
from a wide range of participants including local residents, community groups,
development trusts, key agencies, local businesses, landowners and developers. It
was highlighted within the report that approximately 90% of the respondents
supported the draft participation statement and that all comments received had been
considered when finalising the Renfrewshire Development Plan Scheme 2023. 
DECIDED: That the Renfrewshire Development Plan Scheme 2023 be approved.

Page 8

10  Planning Application
There was submitted a report by the Chief Executive relative to the following
application for planning permission that required to be determined by the Board. 
10(a) 23/0148/PP: Erection of extension to height of golf range netting at
Gleddoch Resort and golf course by Gleddoch Resorts Limited. 
G McCracken, Development Standards Manager, provided a presentation relative to
the application. 
In terms of Standing Order 59 Councillor Paterson, moved that the application be
granted subject to the conditions and reasons detailed within the report. This was
agreed unanimously. 
DECIDED: That the application be granted subject to the conditions and reasons
detailed within the report.