To: Leadership Board
On: 22 February 2023
Report by:  Chief Executive, Director of Finance and Resources, and Chief
Finance Officer Renfrewshire HSCP
Heading:  Revenue and Capital Budget Monitoring as at 11 November 2022 
1. Summary of Financial Position
1.1. The projected revenue outturn at 31 March 2023 for those services reporting to
the Leadership Board is an underspend position of £0.186m. 
1.2. The projected capital outturn at 31 March 2023 for projects reporting to the
Leadership Board is a breakeven position against the revised budget for the
year.
1.3. This is summarised in the table below and further analysis is provided in the
Appendices. 
Table 1: Revenue
Division
Revised
Annual
Budget
£000 
Projected
Annual
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance 
%
Adult Services 93,607 92,586 1,021 1.1%
Chief Executives 20,363 21,198 (835) (4.1%)
Total 113,970 113,784 186 0.2% 
Table 2: Capital
Division
Revised
Annual
Budget
£000
Projected
Annual
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance 
%
Chief Executives 44,808 44,808 0 0%
Leisure Services 2,386 2,386 0 0%
Total 47,194 47,194 0 0%

Page 2

2. Recommendations
2.1. Members are requested to:
(a) Note the projected Revenue outturn position detailed in Table 1 above; 
(b) Note the projected Capital outturn position detailed in Table 2 above;
and 
(c) Note the budget adjustments detailed at sections 4 and 6. 
3. Revenue
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual underspend of £0.186m (0.2% of total budget) for all services reporting
to this Board. Detailed division reports can be found in Appendix 2, along with
an explanation of each significant projected variance.
3.2. The projected outturn is based on information currently available, and
assumptions made by service budget holders.
3.3. The main reasons for the projected outturn position are indicated in the
appendices showing both the subjective analysis (what the budget is spent on)
and the objective analysis (which division is spending the budget).
3.4. The most significant areas to bring to member’s attention are outlined below: 
• OneRen continues to experience increased cost and reduced revenue
generation in the short to medium term as a result of both temporary and
more permanent behavioural changes as the recovery from COVID
progresses. In addition the level of pay award agreed for 2022/23 is in
excess of the level of budgetary provision made, resulting in an increased
forecast overspend. OneRen is also facing steeply increasing utilities costs
which are currently being managed within existing resources through close
financial management. The Board and management team of OneRen
continue to put measures in place to mitigate the level of financial support
required. 
• Within Adult Services, managed by Renfrewshire HSCP, the service
continues to take significant action in response to the pandemic, including
providing substantial levels of support to external care providers in order to
ensure their ongoing financial sustainability. 
At Period 8, the service estimates that costs of £3.12m will be incurred
specifically in relation to COVID-19 Adult Social Care services by the end of the
financial year; this includes costs related to financial sustainability payments to
private adult and elderly care providers. T

Page 3

The projected costs are however based on the current position and may change
depending on any further impact of COVID on internal and externally provided
services. The Scottish Government provided the HSCP with additional COVID-
19 funding in the final quarter of 2021/22, any uncommitted proportion of which
will require to be returned to the Scottish Government over the course of
2022/23. This funding has been held as an earmarked reserve and will be
utilised to fund COVID-19 costs incurred this financial year. In this context,
additional costs specifically relating to the COVID-19 response are not therefore
included within this report. 
The Scottish Government has confirmed additional funding for local
government to partly offset the overall financial impact of the pay settlement on
local government budgets. This additional funding has been provided to local
government as general grant and therefore each individual Council is free to
deploy these resources locally to reflect local financial requirements and
priorities. In this context, and reflecting the projected year end underspend for
Adult Services in 2022/23 as outlined in this report (which takes into account
the full year impact of the pay uplift for all Council employees), and the
significant in year projected overspend being reported by the Council, the IJB’s
financial allocation from the Council is not at this stage expected to be adjusted
in 2022/23 and the impact of the settled pay award will be managed within
existing resources. 
4. Revenue Budget Adjustments 
4.1. Members are asked to note from Appendix 1 that minor budget adjustments
have been processed since the previous report to board. 
5. Capital
5.1. The Capital Investment Programme 2022/23 to 2026/27 was approved by the
Council on 3 March 2022. 
5.2. For the Chief Executives Service, the approved capital spend for 2022/23 is
£44.808m (£44.981m approved Capital Plan). For Leisure Services, the
approved capital spend for 2022/23 is £2.386m (£0.754m approved Capital
Plan). 
5.3. Further detail, including reasons for significant variances, can be found at
Appendix 3.

Page 4

5.4. It is anticipated that due to both the impact of COVID-19 on the construction
industry through constrained supply chain capacity for all major building
materials, coupled with heightened demand across the globe as economies
emerge from pandemic lockdowns, there will be increasing financial pressures
and potential time impacts in several of the Council’s capital building projects.
In this context and as previously reported, it is anticipated that consequential
cost pressures arising from COVID-19 will require to be addressed from specific
earmarked reserve balances. 
6. Capital Budget Adjustments
6.1. Since the 2022/23 budget was approved in March, budget adjustments totalling
£1.459m have arisen. Within Chief Executives, £6.015m of these adjustments
have occurred since the previous board report as a result of: 
Budget carried forward into 2023/24 from 2022/23 (£6.015m) as result of
updated cash flows:
o Clyde Waterfront and Renfrew Riverside: (£5.353m);
o AMIDS: South (£0.662m).
___________________________________________________________________ 
Implications of this report 
1.  Financial – The projected budget outturn position for the revenue budget
reported to the Leadership Board is an underspend of £0.186m. Income
and expenditure will continue to be monitored closely for the rest of the
financial year and, where necessary, steps will be taken to mitigate any
overspend.   
The projected outturn position for capital budgets reported to the
Leadership Board is breakeven. The Capital programme will continue to be
monitored closely for the rest of the financial year. 
Any changes to current projections in either Revenue or Capital budgets
will be reported to the board as early as possible, along with an explanation
for the movement. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning- 
None directly arising from this report.

Page 5

4.  Legal 
None directly arising from this report. 
5.  Property/Assets 
Capital projects will result in new assets (City Deal) and refurbishment and
improvement to Cultural Infrastructure and Public Realm assets. 
6.  Information Technology 
None directly arising from this report.
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health and Safety
None directly arising from this report. 
9. Procurement 
None directly arising from this report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact
None directly arising from this report. 
12.  Cosla Policy Position 
N/a. 
13.  Climate Risk
None directly arising from this report. 
__________________________________________________________________ 
List of Background Papers 
The Capital Investment Programme 2022/23 to 2026/27 approved by the Council
on 3 March 2022
__________________________________________________________________ 
Authors: Revenue - Valerie Howie, Finance Business Partner

Page 6

Capital - Geoff Borland, Finance Manager

Page 7

Appendix 1   
Objective Summary
Approved
Annual Budget
at Period 6
Budget
Adjustments
Revised Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Adult Services 93,607 0 93,607 92,586 1,021 1.1% 971 50
Chief Executive's Service 20,349 14 20,363 21,198 (835) (4.1%) (278) (557)
NET EXPENDITURE 113,956 14 113,970 113,784 186 0.2% 693 (507)
Subjective Summary
Approved
Annual Budget
at Period 6
Budget
Adjustments
Revised Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 42,065 2,046 44,111 43,429 682 1.5% (9,048) 9,730
Premises Related 815 0 815 868 (53) (6.5%) (112) 59
Transport Related 836 1 837 488 349 41.7% 383 (34)
Supplies and Services 15,433 89 15,522 16,269 (747) (4.8%) (219) (528)
Third Party Payments 76,307 139 76,446 77,173 (727) (1.0%) 472 (1,199)
Transfer Payments 8,344 (1,914) 6,430 6,098 332 5.2% 90 242
Support Services 76 15 91 75 16 17.6% 3 13
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 143,876 376 144,252 144,400 (148) (0.1%) (8,431) 8,283
Income (29,920) (362) (30,282) (30,616) 334 1.1% 10,220 (9,886)
NET EXPENDITURE 113,956 14 113,970 113,784 186 0.2% 1,789 (1,603)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 11 November 2022
Budget Variance
(Adverse) or Favourable
Budget Variance
(Adverse) or Favourable
POLICY BOARD :  LEADERSHIP BOARD

Page 8

Appendix 2   
Objective Summary
Approved
Annual Budget
at Period 6
Budget
Adjustments
Revised Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Older People 60,563 (416) 60,147 60,993 (846) (1.4%) (521) (325)
Physical or Sensory Difficulties 7,500 36 7,536 7,338 198 2.6% 87 111
Learning Difficulties 20,969 282 21,251 20,011 1,240 5.8% 1,149 91
Mental Health Needs 3,825 45 3,870 3,433 437 11.3% 255 182
Addiction Services 750 53 803 811 (8) (1.0%) 1 (9)
NET EXPENDITURE 93,607                       0   93,607 92,586 1,021                1.1% 971                       50
Objective Heading
Older People
Physical or Sensory Difficulties
Learning Difficulties
Mental Health Needs
Key Reasons for Projected Variance
POLICY BOARD :  LEADERSHIP BOARD - ADULT SERVICES
Underspends in employee costs reflecting national recruitment issues facing all Health & Social Care. 
Underspends in employee costs reflecting national recruitment issues facing all Health & Social Care. 
Spend within care at home continues to increase as the service continues to support delayed discharges and demand.
Underspends in employee costs reflecting national recruitment issues facing all Health & Social Care offset with the
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 11 November 2022
Budget Variance
(Adverse) or Favourable

Page 9

Appendix 2   
Subjective Summary
Approved
Annual
Budget at
Period 6
Budget
Adjustments
Revised
Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 36,987 1,965 38,952 38,291 661 1.7% (1,016) 1,677
Premises Related 442 0 442 493 (51) (11.5%) (51) 0
Transport Related 835 1 836 487 349 41.7% 371 (22)
Supplies and Services 2,131 89 2,220 2,100 120 5.4% 73 47
Third Party Payments 76,181 139 76,320 77,047 (727) (1.0%) (1,082) 355
Transfer Payments 6,112 (1,847) 4,265 3,933 332 7.8% 1,258 (926)
Support Services 72 15 87 71 16 18.4% 3 13
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 122,760 362 123,122 122,422 700 0.6%                   (444) 1,144
Income (29,153) (362) (29,515) (29,836) 321 1.1% 1,415 (1,094)
NET EXPENDITURE 93,607 0 93,607 92,586 1,021 1.1% 971                        50
Budget Variance
(Adverse) or Favourable
1 April 2022 to 11 November 2022
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
POLICY BOARD :  LEADERSHIP BOARD - ADULT SERVICES

Page 10

Appendix 2   
Objective Summary
Approved
Annual Budget
at Period 6
Budget
Adjustments
Revised Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Chief Executive and Management 268 31 299 296 3 1.0% 1 2
Policy and Commissioning 4,576 51 4,627 4,616 11 0.2% 42 (31)
Marketing and Communications 3,771 (68) 3,703 3,694 9 0.2% 21 (12)
City Deal & Infrastructure 0 0 0 0 0 0.0% 0 0
Leisure Services (incl Renfrewshire Leisure) 11,734 0 11,734 12,592 (858) (7.3%) (342) (516)
NET EXPENDITURE 20,349 14 20,363 21,198 (835) (4.1%) (278) (557)
Objective Heading
Chief Executive and Management
Policy and Commissioning
Marketing and Communications
City Deal & Infrastructure
Leisure Services (incl Renfrewshire Leisure)
Key Reasons for Projected Variance
No significant projected year end variances to report.
REVENUE BUDGET MONITORING STATEMENT 2022/23
Budget Variance
(Adverse) or Favourable
1 April 2022 to 11 November 2022
RENFREWSHIRE COUNCIL
POLICY BOARD :  LEADERSHIP BOARD - CHIEF EXECUTIVE'S SERVICE
No significant projected year end variances to report.
The projected overspend position reflects the significant challenges OneRen continues to face following the pandemic and its
impact on commercial income, in addition to the higher level of pay award now agreed for 2022/23.
No significant projected year end variances to report.
No significant projected year end variances to report.

Page 11

Appendix 2   
Subjective Summary
Approved
Annual
Budget at
Period 6
Budget
Adjustments
Revised
Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 5,078 81 5,159 5,138 21 0.4% 72 (51)
Premises Related 373 0 373 375 (2) (0.5%) (2) 0
Transport Related 1 0 1 1 0 0.0% 0 0
Supplies and Services 13,302 0 13,302 14,169 (867) (6.5%) (359) (508)
Third Party Payments 126 0 126 126 0 0.0% 0 0
Transfer Payments 2,232 (67) 2,165 2,165 0 0.0% (2) 2
Support Services 4 0 4 4 0 0.0% 0 0
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 21,116 14 21,130 21,978 (848) (4.0%) (291) (557)
Income (767) 0 (767) (780) 13 1.7% 13 0
NET EXPENDITURE 20,349 14 20,363 21,198 (835) (4.1%) (278) (557)
Budget Variance
(Adverse) or Favourable
1 April 2022 to 11 November 2022
POLICY BOARD :  LEADERSHIP BOARD - CHIEF EXECUTIVE'S SERVICE
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23

Page 12

Appendix 3   
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
Include prior Project to 31/03/2022* 2022-23 in 2022-23 2022-23 2022-23 Budget Outurn
Project Title Code to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
LEISURE SERVICES
Leisure Investment Programme y LGL01 52,279 0 321 321 321 0 0% 52,600 52,600 0 0%
Grass Pitches & Changing Facilities y LU000GPTHCF 3,872 0 369 369 369 0 0% 4,241 4,241 0 0%
Community Halls Refurbishment y LGL02CMMRFB 1,710 754 942 1,696 1,696 0 0% 3,433 3,433 0 0%
Lagoon Internal Play Centre y LIPC 0 0 0 0 0 0 0% 1,000 1,000 0 0%
Total Leisure Services 57,861 754 1,632 2,386 2,386 0 0% 61,274 61,274 0 0%
CHIEF EXECUTIVES
City Deal Projects
Glasgow Airport Investment Area y DGD01GLARIA 38,662 2,314 1,934 4,248 4,248 0 0% 43,053 43,053 0 0%
Clyde Waterfront & Renfrew Riverside y DGD01CWRERV 21,821 37,714 -8,908 28,806 28,806 0 0% 117,748 117,748 0 0%
Airport Access y DGD01AIRACC 2,934 0 0 0 0 0 0% 141,991 141,991 0 0%
Economic Development
GAIA Regeneration y GAIA Regeneration 2,109 0 1,891 1,891 1,891 0 0% 5,500 5,500 0 0%
AMIDS: Public Realm Phase 1 Netheron Square y DGD11AMID01 246 2,726 962 3,688 3,688 0 0% 3,933 3,933 0 0%
AMIDS: District Heating Network y DGD11DISTHN 3,882 2,007 1,204 3,211 3,211 0 0% 7,093 7,093 0 0%
AMIDS: South y AMIDSSouth 415 220 2,744 2,964 2,964 0 0% 42,328 42,328 0 0%
Total Chief Executives 70,069 44,981 (173) 44,808 44,808 0 0% 361,646 361,646 0 0%
TOTAL LEADERSHIP BOARD 127,930 45,735 1,459 47,194 47,194 0 0% 422,920 422,920 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 11th November 2022
POLICY BOARD: LEADERSHIP
Current Year 2022-23 Full Programme - All years
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable