City Deal and AMIDS Projects Update

Renfrewshire Council · 30 November 2022
Back to Leadership Board — 30 November 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Leadership Board
On: 30 November 2022
___________________________________________________________________
Report by: Chief Executive and Director of Finance and Resources
___________________________________________________________________
Heading: City Deal and AMIDS Projects Update
___________________________________________________________________
1. Summary 
1.1 This report is to update the Board on the progress of Renfrewshire Council’s Glasgow
City Region City Deal and Advanced Manufacturing Innovation District Scotland
(AMIDS) projects being undertaken by the Council’s City Deal and Infrastructure Team. 
1.2 Renfrewshire Council is delivering an ambitious regeneration agenda, focused on
creating the infrastructure and business environment that will generate economic
growth and jobs whilst promoting active travel and green opportunities ensuring that
the area is a fairer, more inclusive place where all our people, communities, visitors
and businesses thrive. As a partner in the Glasgow City Region City Deal, signed in
2014, Renfrewshire Council along with the Scottish Government, the UK Government
and the other Member Authorities is tasked with growing the economy through the
delivery of £1.13bn of infrastructure projects and supporting economic development
activity. 
1.3 Since the City Deal projects were approved in 2014, the scale of the economic shock
we have since experienced from global events such as the pandemic and war in
Ukraine has been unforeseeable. Renfrewshire continues to invest and build on the
enabling infrastructure provided by the City Deal to deliver its ambitious Advanced
Manufacturing Innovation District Scotland (AMIDS) and the Levelling Up funded
AMIDS South project as completion of these projects are central to the recovery and
inclusive growth of the Renfrewshire economy. 
________________________________________________________________________ 
2. Recommendations 
2.1 The Leadership Board is asked to: 
i) Note the scale of ambition and progress of the City Deal and AMIDS projects as
outlined in this paper.

Page 2

________________________________________________________________________ 
3.  Project Updates 
At the commencement of the City Deal programme in 2014, the Glasgow Airport Investment
Area (GAIA) project and the Clyde Waterfront and Renfrew Riverside (CWRR) project were
viewed as complementary. Whilst each project individually contributed to economic growth, it
was accepted, that the combined social and economic outcomes from both would be greater
than the sum of the two individual parts, and that the absolute maximum potential of AMIDS
would be achieved with the construction of CWRR. It was also recognised that the
development opportunities provided by CWRR will gain increased investor attention as a result
of AMIDS. 
Glasgow Airport Investment Area Project 
The Glasgow Airport Investment Area project provides the enabling infrastructure for the
Advanced Manufacturing Innovation District Scotland. This project has now reached
construction completion and is now in an extended (5 year) defects and maintenance period. 
The project has realigned a section of Abbotsinch Road between a point north of Arran Avenue
and the existing A8 Inchinnan Road to the west of the existing Bascule Bridge. This has
created a new road called Netherton Avenue which has wide shared active travel footways
and high-quality lighting and landscaping to ensure the vision for the manufacturing district is
achieved. A new vehicular bridge (the Barnwell Street Bridge) across the White Cart links the
industrial and commercial sites at the bottom of Wright St including Westway Park with the
realigned Abbotsinch Road and a new pedestrian and active travel bridge across the Black
Cart which links to the cycling and walking improvements on Greenock Road (Inchinnan) land
onwards to Inchinnan Business Park and beyond. 
Clyde Waterfront Renfrew Riverside Project 
The Clyde Waterfront and Renfrew Riverside (CWRR) project consists of a new opening road
bridge at Meadowside Street, Renfrew linked to a new road network which links to Dock Street
on the north side of the River Clyde and a new road connecting the bridge to AMIDS. The road
will run between Meadowside Street, and Argyll Avenue, Renfrew to link with Inchinnan Road
and onwards to AMIDS. The roads and bridge include provision for walking and cycling and
will enable improved public transport links. 
CWRR provides an alternative route around Renfrew Town centre (for traffic travelling from
and to locations out with the area) by delivering the North Renfrew Development Road. This
has a consequential improvement in air quality and public transport reliability, within Renfrew
town centre. 
The project also provides access to development opportunities along Meadowside Street,
increases the potential to reinvigorate Blythswood Retail Park and improves access for the
communities on both sides of the River Clyde to facilities and employers on the other side
such as the Queen Elizabeth University Hospital; NHS Golden Jubilee; West College
Scotland’s Clydebank campus and Yoker train station. The project also increases the
employee catchment area for businesses planning to locate at AMIDS, while improving links
to suppliers and customers. 
Early site works including ground remediation, updated habitat and invasive species surveys
commenced 31st January 2022 and the contractor Graham Construction is now fully
established on site with works progressing. Accommodation works for adjacent landowners,
agreed as part of the project consent process are now underway. Detailed design work for the
bridge is underway as is liaison with key stakeholders including Peel Ports and Glasgow
Airport. The construction is due to complete during 2025

Page 3

The economic outcomes from the project remain the most significant within the whole of the
City Deal infrastructure programme, providing the opportunity and environment to attract an
estimated £230million of private sector investment over 25 years into the project area. Value
for money checks on the project reveal a healthy benefit to cost ratio of 10.2 for public sector
spend and 3.1 for the combined public and private sector spend, following investment in
development and business creation. These indicators demonstrate a solid, evidence based,
justification for the project. 
As an outcome of the CWRR Project, 1,440 permanent jobs and 950 temporary construction
roles could follow from the estimated £230million in private sector investment attracted to both
sides of the Clyde. Around 700 jobs will support the project construction. Included in these
additional jobs resulting from construction of the CWRR project, there will be a minimum of 17
new entrant job opportunities and 25 work experience opportunities.  Contractor Grahams
have already employed 13 new entrants and 10 work experience personnel. Career
awareness events and site visits have also been managed with clients from Invest in
Renfrewshire employability team and schools in Renfrewshire including: Park Mains High,
Trinity High and Renfrew High. This project is also sustaining a significant number of existing
jobs in the construction industry. 
The Construction Contract for the CWRR project requires that subcontract and supplier
opportunities over a value of £10,000 are advertised through the PCS Tender portal. This
requirement ensures that as the large-scale project is broken into smaller work parcels, local
companies and SME’s have the opportunity to bid for packages of work. To date 13 works
packages have been advertised, five awarded, three of which to companies within the City
Region. Additionally, a commitment of a minimum of 12 days will be spent by the Contractor
undertaking supply chain development, to encourage and coach, local organisations and
SME’s how to prepare to enable access to this and therefore other public sector work
opportunities. Thus far five sessions of training have been held. 
Advanced Manufacturing Innovation District Scotland (AMIDS)
The establishment of the Advanced Manufacturing Innovation District Scotland (AMIDS) has
only been possible as a consequence of the catalyst provided by the City Deal Glasgow Airport
Investment Area (GAIA) project. 
The delivery of AMIDS is progressing well with the Medicines Manufacturing Innovation Centre
now operational and the National Manufacturing Institute Scotland (NMIS) due to become
operational early next year. Now that the GAIA contract is complete the City Deal and
Infrastructure team are now focusing on securing further investment which will bring
employment, skills development and economic growth to Renfrewshire. This context is
recognised within the Renfrewshire Economic Strategy 2020-2030 where AMIDS is noted as
a key component.
AMIDS Development Partner 
To ensure the progressive and effective delivery of AMIDS, the City Deal and Infrastructure
Team are working with specialist commercial property and legal advisers to procure a
development partner who shares the vision for AMIDS and who will finance and drive the
investment and delivery of the AMIDS site for future occupiers. As part of the requirements
the successful Development Partner will design and construct a speculative first phase
development on the site aimed at providing space and support for small scale innovative
organisations such as university spin off companies. This will enable organisations to tap into
the expertise provided by NMIS on site, develop and expand, providing more high quality jobs. 
The procurement process is progressing well with negotiated dialogue underway. It is
anticipated an outcome of the procurement process will be complete in early 2023.

Page 4

AMIDS District Heating Network 
The City Deal and Infrastructure Team have delivered a £7million award-winning innovative
fifth generation district heating network for the AMIDS site, the first of its kind in Scotland. This
enhances the sustainable credentials of AMIDS in line with the Council’s ambition for carbon
reduction and long-term sustainability and provides an additional attraction for employers we
would wish to locate at AMIDS. The initial off-takers are NMIS and the Medicines Centre who
will utilise the system in the coming weeks for heating and hot water.
AMIDS Netherton Square 
Netherton Square, which will be the arrival and focal point of AMIDS Netherton, is currently
under construction and due to complete early in 2023. The City Deal and Infrastructure Team
have worked with specialist designers to develop a high-quality public realm design for the
whole of Netherton with Netherton Square being the first phase. The contractor RJ Mcleod
are making excellent progress and the initial phase focusses on the area immediately adjacent
to the two flagship facilities. 
AMIDS Strategic Advisory Group 
The innovation eco-system that is being created at AMIDS has also resulted in the Lightweight
Manufacturing Centre (LMC) and a research and development initiative by Boeing, locating at
Westway.  It is estimated that around £185million of investment has already been made so far
at AMIDS, with more to come.  None of this would have been possible without the City Deal
infrastructure and investment by the Council. 
The Council also organises and Co-Chairs with Scottish Enterprise, a Strategic Advisory
Group (SAG) with our partners to ensure the AMIDS vision, as a key development location in
Scotland for national and international investors, is delivered. The group is currently working
closely to identify and target markets for potential development at AMIDS and are preparing
marketing materials to enable discussions to take place with some of the specialist Advisory
Group members including Scottish Enterprise, NMIS, the Medicines Centre and the University
of Strathclyde. SAG members are recruiting an AMIDS director who will be based within the
NMIS building and lead these specialist conversations.
AMIDS South Levelling Up Fund project 
The City Deal and Infrastructure team are progressing the AMIDS South project with 90%
funding from the UK government Levelling Up Fund. The project will provide a 1.7km ‘gateway
route’ along the White Cart river with a network of road, cycling and walking links from Paisley
Gilmour Street train station and bus interchange to Glasgow Airport, AMIDS and onto
Inchinnan. The project includes a new bridge crossing at Paisley Harbour for pedestrians,
cyclists and vehicular traffic and landscaping along the route. AMIDS South is a high-impact
local transport scheme which will reduce carbon emissions, improve air quality, cut
congestion, support economic growth and improve the experience of transport users. 
Economic analysis demonstrates the project could bolster the local economy by an additional
£136million, cut carbon emissions by 21,700 tonnes and help existing and new companies to
grow creating new job opportunities for years to come. 
A new east-west road linking Renfrew Road to the new Gateway route is also included and
will increase connectivity to and from AMIDS and improve accessibility to the new Paisley
Grammar School community campus, West College Scotland and the Gallowhill area. The
project team are working closely with Council teams delivering these other projects to ensure
designs are aligned and that benefits are maximised. An extension to the new Renfrew to
Paisley active travel route into the Gallowhill catchment area will provide a new safe active
travel route to the education facilities.

Page 5

The funding also enabled the construction of the walking, cycling and road safety
improvements on Greenock Road (Inchinnan) which is now largely complete providing
improved walking and cycling between Inchinnan Business Park and Netherton at AMIDS.
This route links to the pedestrian and active travel bridge over the Black Cart river and is
already being well used providing a safe route and reduced speed of traffic. 
Inclusion of traffic calming works on Love Street will improve the environment for local
residents and pedestrians with this residential area benefiting from a reduction in traffic flow
due to the new routes. 
Design development for the project is underway with consultants Amey. Stakeholder
engagement proposals are being progressed and discussions with any affected landowners
underway. A planning application was submitted in May 2022 and is expected to be presented
to the Planning Board in January. 
Ground Investigation works have been completed across the project area which will feed into
the design development phase of the project. Due to the number of different landowners it is
not feasible or efficient to progress land assembly on an individual basis and so a paper asking
for approval to progress a compulsory purchase order will be presented to Infrastructure Land
and Environment Board in January. 
Construction is due to be completed by the end of 2025. 
Recognising the volatility in the cost of construction projects currently, regular reviews of
estimated project costs are completed. This process will continue with each stage of the
design development. 
Airport Access Project/Clyde Metro 
The Airport Access project (AAP), a joint Glasgow City and Renfrewshire Council City Deal
project, led by Renfrewshire was paused in April 2020 to allow a feasibility study to be
undertaken on an alternative Clyde Metro solution, which would incorporate access to
Glasgow Airport via a link from Paisley Gilmour Street Station. Should the Clyde Metro
progress, the Cabinet agreed that the approved city deal funding for the AAP would be
allocated as a contribution to the Clyde Metro build costs from Paisley Gilmour Street to
Glasgow Airport. 
The Glasgow City Council team are working with Transport Scotland, neighbouring councils
(including representatives from Renfrewshire Council) and other key stakeholders to progress
route options and a programme for delivery of the Clyde Metro to present a “Case for
Investment” by summer 2024. 
Transport Scotland identified Clyde Metro as a strategic priority with the draft Strategic
Transport Projects Review 2 (STPR2) in early 2022. Consultation on the draft is now closed
and publication of the final STPR2 document is expected early in 2023 with a commitment to
Clyde Metro.
___________________________________________________________________ 
Implications of the Report 
1. Financial – The financial implications arising from the Council’s participation in City
Deal are set out in detail in item 3 Financial Sustainability and General Fund Financial
Outlook section 7.7 and 7.8 of the report approved by Council on 30th June 2022. A
The increased funding requirement can be accommodated within the existing revenue
provision that has already been built into the Council’s financial plans. In total £45M
prudential borrowing and £4M from Covid construction ringfenced provision.

Page 6

2. HR & Organisational Development - none 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – These projects will link our communities and
facilitate new development opportunities and business growth with both projects
improving skills development, educational and health opportunities for people
within the local communities as well as aiding employees to access these major
existing and new employment centres. The projects align with and aid the
outcomes of the Renfrewshire Economic Strategy 2020 -2030 and the
Renfrewshire Economic Recovery Plan 
• Our Renfrewshire is well - The new safer walking and cycling infrastructure
incorporated within these projects, will help encourage active travel by children
and young people, as well as adults. 
• Reshaping our place, our economy and our future – These infrastructure
projects provide connectivity and access to new and existing jobs for people in
our communities. During the project construction period hundreds of new jobs
will be created and as a result of new business creation it is estimated that
thousands of additional new permanent jobs will be created. The combined
projects investment in linking active travel infrastructure and education and will
provide connectivity and access to new and existing jobs for people in our
communities. 
• Tackling inequality, ensuring opportunities for all – the successful City Deal
labour market programmes are now completed and targeted hard to reach
citizens. The AMIDS South project links our less advantaged communities with
education and job opportunities and provides healthy transport options 
• Creating a sustainable Renfrewshire for all to enjoy - The completed
infrastructure includes segregated provision for walking and cycling and will also
enable improved public transport links. AMIDS incorporates an overarching
sustainable transport plan, which is currently being further developed as
occupiers begin to locate in the area. CWRR opens up development
opportunities, which through the LDP will be managed as sustainable linked
communities.   
• Working together to improve outcomes - Officers are working closely with local
communities, neighbouring councils, private sector organisations, Scottish
Government, Scottish Enterprise and other partners to ensure the maximisation
of positive outcomes from the projects noted within this report. 
4. Legal - none 
5. Property/Assets – land acquisition required to deliver AMIDS South will be subject to
a Compulsory Purchase Application. All land acquisition matters will be approved by
relevant ILE Boards. some land acquisition will be required to deliver aspects of the
AMIDS South project although much is already owned by Renfrewshire Council or in
the current public road network 
6. Information Technology - none

Page 7

7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts on
equality groups or potential for infringement of individuals’ human rights have
been identified arising from the recommendations contained in the report
because it is for noting only. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the Council’s
website. 
8. Health & Safety - none 
9. Procurement – all contracts are tendered in accordance with Council procurement
procedures and where relevant taken to FRCS Board for approval. 
10. Risk – Project specific and Programme level risk registers have been established for
all projects. These are kept under regular review and reported to the Council’s internal
City Deal and Infrastructure Programme Board. 
11. Privacy Impact - none 
12. COSLA Policy Position – not applicable 
13/ Climate Risk – the project will provide sustainable active travel routes and
encourage sustainable neighbourhoods and transport links including provision of blue
green infrastructure 
_________________________________________________________
List of Background Papers 
none
__________________________________________________________________ 
BW 
November 2022 
Author: Barbara Walker, City Deal and Infrastructure Programme Director; Email