City Deal and THCARS2 Projects Update Report

Renfrewshire Council · 21 February 2024
Back to Leadership Board — 21 February 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Leadership Board
On: 21 February 2024
___________________________________________________________________
Report by: Chief Executive and Director of Finance and Resources
___________________________________________________________________
Heading: City Deal and TH.CARS2 Projects Update
___________________________________________________________________
1. Summary 
1.1 This report is to update the Board on the progress of Renfrewshire Council’s
Glasgow City Region City Deal and TH/CARS2 projects being undertaken by
the Council’s City Deal and Infrastructure Team. 
1.2 Renfrewshire Council is delivering an ambitious regeneration agenda, focused
on creating the infrastructure and business environment that will generate
economic growth and jobs whilst promoting active travel and green opportunities
ensuring that the area is a fairer, more inclusive place where all our people,
communities, visitors and businesses thrive. As a partner in the Glasgow City
Region City Deal, signed in 2014, Renfrewshire Council along with the Scottish
Government, the UK Government and the other Member Authorities is tasked
with growing the economy through the delivery of £1.13bn of infrastructure
projects and supporting economic development activity. 
Since the City Deal projects were approved in 2014, the scale of the economic
shock we have since experienced from global events such as the pandemic and
war in Ukraine has been unforeseeable. Renfrewshire continues to invest and
build on the enabling infrastructure provided by the City Deal to deliver its
ambitious Advanced Manufacturing Innovation District Scotland (AMIDS) and
the Levelling Up funded AMIDS South project as completion of these projects
are central to the recovery and inclusive growth of the Renfrewshire economy. 
1.3 Alongside this investment in economic regeneration the Townscape Heritage
Conservation Area Regeneration Scheme Project (TH/CARS2) in Paisley Town
Centre has been ongoing. 
This project aims to improve Paisley’s historic core by improving the condition
of Paisley’s historic fabric (including building repairs, shopfront and streetscape
improvements); providing opportunities for people to learn and develop skills

Page 2

based on Paisley’s heritage and delivering community engagement via heritage
education, training and events.
___________________________________________________________________ 
2. Recommendations 
2.1 The Leadership Board is asked to: 
i) Note the scale of ambition and progress of the City Deal projects as
outlined in this paper.
ii) Approve EH&I officers participation in the collaborative work being taken
forward described in section 3.9 and that a  report seeking relevant
approval to next steps including any proposal to move forward and
advance arrangements to go to market with the concession model will be
taken to the Infrastructure, Land and Environment Board.
iii) Note the completion of the TH.CARS2 project.
iv) Approve the allocation of the remaining contingency funds of up to £40,000
to the Building Repair project at 32 High Street (note this has been
approved in principle by funders).
___________________________________________________________________ 
3.  Project Updates 
At the commencement of the City Deal programme in 2014, the Glasgow
Airport Investment Area (GAIA) project and the Clyde Waterfront and Renfrew
Riverside (CWRR) project were viewed as complementary. Whilst each project
individually contributed to economic growth, it was accepted, that the
combined social and economic outcomes from both would be greater than the
sum of the two individual parts, and that the absolute maximum potential of
AMIDS would be achieved with the construction of both GAIA and CWRR City
Deal Projects. It was also recognised that the development opportunities
provided by CWRR will gain increased investor attention as a result of AMIDS.
Coupled with the significant investment in cultural venues in Paisley and the
TH/CARS2 investment, these ambitious projects will transform our area and
together lead to a new sense of Place, where people will want to live, work and
play in Renfrewshire. 
3.1 Glasgow Airport Investment Area Project 
The Glasgow Airport Investment Area project provides the enabling
infrastructure for AMIDS. Construction was completed in October 2022 and
the project is now in an extended (5 year) defects and maintenance period.
The CD&I project team are working with external advisers and the Contractor,
Wills to close out a number of construction defects and bring the contract to a
financial close. 
GAIA realigned a section of Abbotsinch Road between a point north of Arran
Avenue and the existing A8 Inchinnan Road to the west of the existing Bascule
Bridge. 
This has created a new road called Netherton Avenue which has wide shared
active travel footways and high-quality lighting and landscaping to ensure the
vision for the manufacturing district is achieved. A new vehicular bridge (the

Page 3

Barnwell Street Bridge) across the White Cart links the industrial and
commercial sites at the bottom of Wright St including Westway Park with the
realigned Abbotsinch Road and a new pedestrian and active travel bridge
across the Black Cart which links to the cycling and walking improvements on
Greenock Road (Inchinnan) land onwards to Inchinnan Business Park and
beyond. 
This City Deal investment has been the catalyst for the location and delivery
of the two anchor tenants, the National Manufacturing Institute Scotland and
the UK Medicines Manufacturing Innovation Centre. Two new developments
being planned and brought forward in the next couple of years – the Tech
Terrace provided by our Joint Venture Development Partner which will provide
much needed flexible space for small to medium university spin out
organisations to expand and the new Oligionucleotide Manufacturing
Innovation Centre (OMICE) which will be provided by CPi.  In addition to these
successes within Netherton Park there are noticeable private sector
developments already emerging at Westway Park and the new Bidfoods
development at the foot of Wright Street. This development of infrastructure
was anticipated within the GAIA business case as a consequence of the
significant increase in the connectively and attractiveness of these sites,
creating greater confidence for investment. 
3.2 Clyde Waterfront Renfrew Riverside Project 
The Clyde Waterfront and Renfrew Riverside (CWRR) project consists of a
new opening road bridge at Meadowside Street, Renfrew linked to a new road
network which links to Dock Street on the north side of the River Clyde and a
new road connecting the bridge to AMIDS. The road will run between
Meadowside Street, and Argyll Avenue, Renfrew to link with Inchinnan Road.
The roads and bridge include provision for walking and cycling and will enable
improved public transport links. CWRR provides an alternative route around
Renfrew Town centre (for traffic travelling from and to locations outwith the
area) by delivering the North Renfrew Development Road. This has a
consequential improvement in air quality and public transport reliability, within
Renfrew town centre. 
The main contractor, Graham Construction is progressing well with delivery of
the project. Earthworks and road foundation courses are now in place for much
of the North Renfrew Development Road, with the structures of the north and
south bridge piers well advanced. Fabrication of the bridge structure is also
well advanced and delivery of the two bridge spans is expected, by barge, in
April and May of 2024 with construction due to be completed during 2024. 
The economic outcomes from the project remain the most significant within the
whole of the City Deal infrastructure programme, providing the opportunity and
environment to attract an estimated £230million of private sector investment
over 25 years into the project area. 
Value for money checks on the project project a strong  benefit to cost ratio of
10.2 for public sector spend and 3.1 for the combined public and private sector
spend, following investment in development and business creation.

Page 4

As an outcome of the CWRR Project, 1,440 permanent jobs and 950
temporary construction roles are projected to follow from the estimated
£230million in private sector investment attracted to both sides of the Clyde. 
Around 700 jobs already support the project construction. Included in these
additional jobs resulting from construction of the CWRR project, there will be
a minimum of 17 new entrant job opportunities and 25 work experience
opportunities.  Contractor Grahams have already employed 16 new entrants
and 11 work experience personnel. Career awareness events and site visits
have also been managed with clients from Invest in Renfrewshire employability
team and schools. This project is also sustaining a significant number of
existing jobs in the construction industry including 11 job opportunities for local
experienced workers. 
The Construction Contract for the CWRR project requires that subcontract and
supplier opportunities over a value of £10,000 are advertised through the PCS
Tender portal. This requirement ensures that as the large-scale project is
broken into smaller work parcels, local companies and SME’s have the
opportunity to bid for packages of work. To date 21 works packages have been
advertised, five awarded, three of which to companies within the City Region.
This effort to attract local contractors and suppliers has seen the fabrication of
a significant portion of the vessel layby berth (located at Rothesay Dock) at
Westway in Renfrew. 
Additionally, a commitment of a minimum of 12 days will be spent by the
Contractor undertaking supply chain development, to encourage and coach,
local organisations and SME’s how to prepare to enable access to this and
therefore other public sector work opportunities. Thus far five sessions of
training have been held. 
3.3 Airport Access Project/Clyde Metro 
The Airport Access project (AAP), a joint Glasgow City and Renfrewshire
Council City Deal project, led by Renfrewshire was paused in April 2020 to
allow a feasibility study to be undertaken on an alternative Clyde Metro
solution, which would incorporate access to Glasgow Airport via a link from
Paisley Gilmour Street Station. The City Region Cabinet agreed that the
element of city deal funding already approved for the AAP (up to £14M was
approved in December 2016) would be allocated as a contribution to the Clyde
Metro feasibility costs. 
In December 2022, the Scottish Government published the Strategic Transport
Projects Review (STPR2) which included the Clyde Metro. This inclusion
places the Clyde Metro Project as a key priority project by the Scottish
Government for future investment i.e. a project of national significance. 
The Chief Executive Group on 6 December 2023 agreed the reallocation of
the remaining £12.155M of the business case stage funding previously
approved by GCR Cabinet to Glasgow City Council to promote and accelerate
business case development of Clyde Metro proposals towards key gateway
decisions. Reporting and monitoring of this spend/activity will continue through
GCR structures.

Page 5

SPT were confirmed in Nov 2023 as the lead and procuring organisation for
the Clyde Metro, working in partnership with Glasgow City Council and
Transport Scotland to deliver the Case for Investment which will include a
network of route options to improve connectivity to key sites across the region,
including Glasgow Airport. The scope of the previous City Deal Airport Access
Project has now been incorporated within the wider development of a Clyde
Metro network and delivery phasing options. 
Transport Scotland will provide an oversight role for the Clyde Metro Project.
SPT aim to deliver the Case for Investment for the Clyde Metro vision within 2
years. Alongside this Glasgow City Council will lead on the supporting regional
transformation aspects of the overall project network, including consideration
of access to healthcare, housing, education and employment. Governance is
currently being mapped out with Renfrewshire Council being invited, by SPT,
to join the Clyde Metro Project Board. 
Whilst our understanding remains that the first line for the Clyde Metro is likely
to be the South Clyde Growth Corridor, ie linking Glasgow, QEUH, AMIDS and
the Airport this decision will be taken by SPT/Transport Scotland following the
Case for Investment. 
3.4 City Deal Reprogramming 
Following discussions with the UK and Scottish Governments, at this stage it
is likely that 50% of the remaining AAP funds (circa £64M) will be distributed
across the member authorities to assist in meeting exceptional project costs
and inflationary pressures that have emerged due to the prevailing economic
conditions and volatility. Renfrewshire will receive a share of this, expected to
be circa £8M for the CWRR project. 
The remaining 50% (circa £64M) will be allocated to a new “Regional Project”.
The governments have indicated a preference for a single regional project of
scale, however given the timescales it is perhaps more likely funds will be
allocated to two or maybe three regional projects. Member authorities will be
invited to submit an expression of interest if there they have a suitable
project(s) for consideration. It is expected Expressions of Interest will be
required to be submitted in May for evaluation and scoring by the PMO.
Council officers are currently considering potential options in this regard and
an update and required approvals will be provided at an appropriate future
board. 
3.5 UK Share Prosperity Fund 
The Shared Prosperity Fund (SPF) is part of the UK Government Levelling Up
agenda. It provides £2.6 billion of funding for local investment by March 2025,
with all areas of the UK receiving an allocation from the Fund via a funding
formula rather than via a bidding process.   
Renfrewshire Council have been awarded £6.3M for the first 3 year
programme from 2022-25. There are 3 Core Fund priorities with both capital
and revenue funding; Communities and Place; Supporting Local Business and
People and Skills. £1.1M of the total award is specifically allocated to the

Page 6

Multiply Programme to support greater numeracy skills for adults over 19 years
of age. 
The SPF will support the following levelling up objectives: 
• Boost productivity, pay, jobs and living standards by growing the private 
sector, especially in those places where they are lagging, 
• Spread opportunities and improve public services, especially in those 
places where they are weakest, 
• Restore a sense of community, local pride and belonging, especially in 
those places where they have been lost, 
• Empower local leaders and communities, especially in those places 
lacking local agency. 
Good progress has been made across all the core programmes and the
Multiply programme. Within Renfrewshire, an early start was achieved on most
interventions once investment plans were approved. £1.15M has been claimed
to date with most budgets now fully committed until the end of the year. 
Priority Spend to date by
Priority at end Dec
2023
Forecast Spend at end
FY (March 2024)
Communities & Place £84,145.62 £574,248.00
Local Business £376,044.87 £579,959.00
People & Skills £504,676.20 £930,131.00
Multiply £143,986.31 £268,264.00
Management &
Administration
£44,353.90 £100,000.00 
The 2024-25 budget is the largest of the three years. Much of the additional
budget will be allocated through grants for other organisations to deliver
services. The grant commissioning process is already underway for delivery in
2024-25 and investment plans have been submitted to Glasgow City Region. 
3.6 GCR Investment Zone 
In June 2023, Glasgow City Region was announced as one of two new
Investment Zones in Scotland following a joint selection process by the UK and
Scottish Governments. The two Investment Zones, in Glasgow City Region and
the Northeast, were each initially supported by an overall funding envelope of
up to £80 million in targeted investment, tax reliefs and other incentives over
five years.  This was subsequently increased to £160m each over 10 years in
the Chancellors Autumn Statement. Funds are based around the principle of
flexibility, meaning that areas can tailor their bids for funding to suit local needs,
whether this be utilising the investment to develop facilities through the creation
of new infrastructure or tax incentives to encourage additional inward
investment. These new Investment Zones aim to meet the specific standards
and policy agenda set out in the National Strategy for Economic Transformation
(NSET).

Page 7

In January 2024  an open call was launched for project funding bids from eligible
businesses/organisations.  To be eligible to bid for funding, projects must fall
within three key sectors: Life Sciences; Advanced Manufacturing and Precision
Engineering; and Digital and Enabling Technologies.  The Council is currently
working alongside its AMIDS delivery partner and Strathclyde University to
submit a comprehensive, evidence-based submission for the Netherton
Campus site which will support the ambition to create Scotland’s main centre
for advanced manufacturing. In addition, officers are meeting with Renfrewshire
businesses wishing to submit applications to discuss what support we can offer.
The deadline for applications is 31 March 2024 and a further update on the
results of this process will be provided later this year. 
3.7 Clyde Mission 
The Clyde Mission is a regeneration programme supported by the Scottish
Government which seeks to unlock the potential of the River Clyde to support
sustainable and inclusive economic growth in the West of Scotland.  Initially
launched by the Scottish Government in 2020, it has supported 13 different
projects within the Clyde Mission footprint at a cost of £13.6 million.  This
includes funding to support the Paisley to Renfrew walking and cycling route in
Renfrewshire.  Responsibility for the programme has now been transferred to
the Glasgow City Region, with additional funding from the Scottish
Government.  In total over £40m has now been allocated to support the
programme.  New funding will provide Glasgow City Region and Argyll & Bute
Council with an investment over three years (2023-26) for the development of a
masterplan which will set out plans for stimulating growth of a sustainable,
wellbeing economy in the Clyde Mission area and wider city region.  Updates
on the masterplan development and the Programme as a whole will be provided
on a rolling basis. 
3.8 Regional Economic Strategy 
The Glasgow City Region launched the Regional Economic Strategy (RES) in
December 2021.  It was developed in partnership with the Region’s eight local
authorities, government partners and agencies. Its overall aim is for the
Glasgow City Region to have the most innovative, inclusive and resilient
economy in the UK by 2030.  Key issues covered include the climate emergency
and the drive to net zero along with several other challenges such as COVID-
19, Brexit, AI and demographic shifts.  An Action Plan for the Strategy was
agreed in August 2022 and it sets out the high-level actions which will support
the Region’s key economic challenges and ambitions.  Eight portfolios have
been set up to support the delivery of the Economic Strategy, including
Enterprise, which is led by Renfrewshire Council.  Going forward the Council
will continue to try and support the delivery of the plan to achieve the goal of
becoming an innovative economy through the development of key priority areas
such as the Advanced Manufacturing Innovation District Scotland.     
3.9 Electric Vehicle Charging Infrastructure 
Officers from Renfrewshire have been working with the Glasgow City Region
local authorities to explore opportunities that can be offered through a
collaborative approach to establish an EV strategy and expansion plan to meet
the exponential growth that is anticipated for publicly accessible electric vehicle

Page 8

charging demand across the region in the years ahead. The city region
authorities produced an indicative expansion plan in February 2023 which
allowed an estimated scale of future demand to be established for each local
authority area to inform this collaborative work. The City Region has agreed that
officers will continue to progress this collaborative work to explore further the
business case for delivering future expansion collaboratively as a region.
Officers from Environment and Infrastructure continue to work with the other
City Region authorities with a view to taking a regional approach to the next
phase roll out of electric charging infrastructure. This will involve engagement
with the private sector to decide on the most appropriate model for taking this
issue forward across the region. 
This work will  explore the different models potentially available, including the
option for a mixed public/private concession model which would limit the risks
to the city region councils, deliver a scheme which would require minimal
investment from the member councils, provide influence over charging locations
to ensure equity of access across the region (including to areas that may not
necessarily provide strong commercial opportunities) and potentially secure a
revenue return which could be reinvested in the charging network. The Glasgow
City Region PMO is leading this on behalf of the Councils and has arranged
workshops with each of the authorities to identify local needs that would need
to be addressed through any future procurement process. 
An update will be brought to a future Board detailing the proposals on a potential
way forward. Proposals will also be presented to the City Region Cabinet with
individual Councils considering proposals and appropriate approvals through
their own internal governance processes. 
3.10 Housing Retrofit 
The Housing Retrofit section of the Glasgow City Deal, is exploring the
opportunities a collaborative approach may offer to help member authorities to
meet the wide scale retrofit of domestic properties that are and will emerge from
housing investment programmes and the investment needs to help deliver net
zero carbon and meet fuel poverty targets. The collaborative work to date has
focused on identifying the challenges and possible solutions within the key area,
reviewing key standards and assessing government policies. This has identified
common challenges are around mixed tenure, financing & funding and skills
development of contractors to deliver such a large-scale project. In addition, the
varied approaches Local Authorities and Housing Association are currently
adopting to tackle housing investment, current area-based schemes, differing
retrofit standards and tackling fuel poverty has been identified as a key
challenge. 
A baseline survey is being agreed by the group for each Authority to complete,
which will outline how each Authority is currently setup to deliver housing
investment, area-based schemes and if they have a defined retrofit standard. At
present, Renfrewshire Council is not set up to deliver a wide scale multi tenure
retrofit programme. 
Renfrewshire Council currently has a contract in place to produce housing
retrofit designs to a particular high standard. This is for our housing stock and
for owners within mixed tenure that the Council still has an interest in. Owners

Page 9

are offered area-based scheme (ABS) funding and some private sector housing
grant, to assist them to fund their participation in a scheme. The current eight
Housing Regeneration areas will operate with enhanced grants to encourage
uptake. Recently owners where the Council has no interest have been offered
ABS, concentrating in areas where the Council has carried retrofit works in the
past. EESSH2 has recently been replaced with the Social Housing Net Zero
Standard (SHNZS), which is currently in consultation and the current retrofit
standard meets the proposed SHNZS. It is noted that owner occupiers and
private landlords will have a lower standard to achieve and different backstop
dates. This mix of standards undoubtedly creates challenges trying to retrofit
mixed tenure blocks, of which there is a high proportion within Renfrewshire.
The outcome from the Green Heat Finance Task Force is awaited, which is
advising methods to attract private finance for owners to support participation in
retrofit schemes and legislation from the Scottish Government on improvement
to communal repairs and whole buildings assessment is also awaited and which
may present additional considerations. 
4. Paisley Townscape Heritage and Conservation Area Regeneration
Scheme 2 
The TH.CARS2 project is funded by National Lottery Heritage Fund,
(£1,882,000), Historic Environment Scotland (£998,554), and through approved
service budgets for the delivery of the Paisley Town Centre Heritage Asset
Strategy (£1,218,706). The scheme is now drawing to a close with final scheme
completion expected 31 March 2024. The delivery of TH.CARS2 has
successfully improved the historic fabric of Paisley Town Centre as well as
providing opportunities for  local people to take part in heritage education,
training and events. 
Building Repair grants of £1.56m have been awarded to ten external Building
Repair projects with owners’ contributions totalling over £1m, and owners further
investing in interiors of properties in some projects. Building Repair projects
supported through TH.CARS2 include 2-3 County Place, (now converted to flats
funded by the owner), 20 New St (Vienna’s),  41 High St (Right Way Credit
Union), Sma Shot Cottages, 10 Shuttle St, 9 Gilmour St (Walker Laird offices),
5 George Place (The Paisley Trophy Centre), 18 Georges Gate and 28 High St.
Grant supported works to properties have significantly improved the condition
and appearance of these properties and helped to secure their long-term
futures. 
The final Building Repair Project to complete on site will be the former Liberal
Club at 32 High St. Completion of the project has been delayed by additional
works discovered on site, with the building in a much poorer condition than
original surveys had indicated, in particular significant rot works, with resultant
increased costs in the region of £200,000. The project has received a
TH.CARS2 grant of £600,000 split between the upper floor and  shop owners,
and additional support through the Place Based Investment Fund.  It is proposed
to increase the TH.CARS2 grant by up to £40,000, subject to funders approval,
using remaining contingency within the existing TH.CARS2 budget. The
external works to 32 High St are now expected to complete in May 2024 but
TH.CARS2 funded works will complete by end of February 2024 allowing
TH.CARS2 to conclude. Following completion of the external works at 32 High
St, the owners will carry out works to the interior. The owners have decided not

Page 10

to proceed with converting the building into residential units. Interest has been
shown in the property for let which would allow the building to retain its existing
rooms and features. The external works project at 32 High St, has enabled very
urgent and essential repairs significantly improving the condition and
appearance of the property and securing the long- term future of this important
building for the town centre. 
In addition to Building Repair projects, TH.CARS2 shopfront improvement
grants of a total value of £400,000 have been awarded to ten shopfronts in
Paisley Town Centre. Shopfronts which have been improved include recently
completed projects at 18A and B High Street, (owners negotiation with tenants
in progress)  63 High St (Nomads), 67 High St (Houston Kilts), 30 A and 30 B
High St (Sinclair’s of Paisley and Paisley Gift Cart), 36 High Street (Shelter), 44
High St (Uptown Barbers), 61 High St (Print and Copy It) 41 High St (Right Way
Credit Union). 
Small Grants of a total of over £58,000 have been awarded to twelve property
owners in the TH.CARS2 area, mainly for repairs to traditional sash and case
windows but also to support restoration of architectural details including
replacement of decorative railings. 
TH.CARS2 has also delivered Public Realm Improvements at George Place,
Weighhouse Close and the High Street pavements opposite the museum (with
additional support from the Place Based Investment Fund and Environment and
Infrastructure budgets). Resurfacing and lighting improvements at George
Place have enhanced the townscape and the setting for TH.CARS2 grant
projects in the vicinity. Resurfacing works have also improved the public realm
at the junction of Weighhouse Close and the High Street. Works to resurface
the High St pavements have also now successfully completed. This was a
complex project involving structural works to basements below the pavements
but now completed with the townscape opposite the museum significantly
improved. 
The HETE Activity Plan has concluded and has delivered a successful
programme of community engagement. Activity valued at over £550,000 has
been delivered including £347,000 of TH.CARS2 grant and £205,000 of
contributions from other sources such as in-kind support and volunteer support. 
A wide range of activities have been delivered in association with local
community groups and stakeholders, with a focus on engaging young people
and harder to reach groups. Effective partnership working has been key to the
plan’s success, with over 100 local and national organisations involved. The
HETE Activity Plan delivered 42 activities across 3 themes: Fabrication, Social
Fabric and Built Fabric. 
TH.CARS2 will conclude with final reports submitted to the funders NLHF and
HES including a detailed Evaluation report. Completion of the project will also
involve archiving records of building repair and HETE projects and also to allow
continued access to resources created through the HETE activity plan.
___________________________________________________________________

Page 11

Implications of the Report 
1. Financial – The financial implications arising from the Council’s participation in
City Deal are set out in detail in item 3 Financial Sustainability and General Fund
Financial Outlook section 7.7 and 7.8 of the report approved by Council on 30th
June 2022. A The increased funding requirement can be accommodated within the
existing revenue provision that has already been built into the Council’s financial
plans. In total £45M City Deal prudential borrowing and £4M from ringfenced
provision. 
2. HR & Organisational Development – None. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – These projects will link our communities and
facilitate new development opportunities and business growth with both
projects improving skills development, educational and health opportunities for
people within the local communities as well as aiding employees to access
these major existing and new employment centres. The projects align with and
aid the outcomes of the Renfrewshire Economic Strategy 2020 -2030 and the
Renfrewshire Economic Recovery Plan 
• Our Renfrewshire is well - The new safer walking and cycling infrastructure
incorporated within these projects, will help encourage active travel by children
and young people, as well as adults. 
• Reshaping our place, our economy and our future – These infrastructure
projects provide connectivity and access to new and existing jobs for people
in our communities. During the project construction period hundreds of new
jobs have been created and as a result of new business creation it is estimated
that thousands of additional new permanent jobs will be created. NMIS and
MMIC are already up and running as a direct consequence of this enabling
infrastructure. The combined projects investment in linking active travel
infrastructure and education and will provide connectivity and access to new
and existing jobs for people in our communities. 
• Tackling inequality, ensuring opportunities for all – CWRR provides access to
development opportunities along Meadowside Street, increases the potential
to reinvigorate Blythswood Retail Park and improves access for the
communities on both sides of the River Clyde to facilities and employers on
the other side such as the Queen Elizabeth University Hospital; NHS Golden
Jubilee; West College Scotland’s Clydebank campus and Yoker train station.
The project also increases the employee catchment area for businesses
planning to locate at AMIDS, while improving links to suppliers and customers. 
• Creating a sustainable Renfrewshire for all to enjoy - The completed
infrastructure includes segregated provision for walking and cycling and will
also enable improved public transport links CWRR opens up development
opportunities, which through the LDP will be managed as sustainable linked
communities.

Page 12

• Working together to improve outcomes - Officers are working closely with local
communities, neighbouring councils, private sector organisations, Scottish
Government, Scottish Enterprise, and other partners to ensure the
maximisation of positive outcomes from the projects noted within this report. 
4. Legal – None. 
5. Property/Assets – Completed assets will require to be maintained and
operated by the Council. 
6. Information Technology – None. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report because it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health & Safety – None. 
9. Procurement – All contracts are tendered in accordance with Council
procurement procedures and where relevant taken to FRCS Board for approval. 
10. Risk – Project specific and Programme level risk registers have been
established for all projects. These are kept under regular review and reported
to the Council’s internal City Deal and Infrastructure Programme Board. 
11. Privacy Impact - None 
12. COSLA Policy Position – Not applicable. 
13. Climate Risk – the project will provide sustainable active travel routes and
encourage sustainable neighbourhoods and transport links including provision
of blue green infrastructure. 
__________________________________________________________________
List of Background Papers 
None.
__________________________________________________________________ 
BW 
February 2024 
Author: Barbara Walker, City Deal and Infrastructure Programme Director; Email
Barbara.walkers@renfrewshire.gov.uk