To: Leadership Board
On: 26 April 2023
Report by:  Chief Executive, Director of Finance and Resources, and Chief
Finance Officer Renfrewshire HSCP
Heading:  Revenue and Capital Budget Monitoring as at 6 January 2023 
1. Summary of Financial Position
1.1. The projected revenue outturn at 31 March 2023 for those services reporting
to the Leadership Board is an underspend position of £0.004m. 
1.2. The projected capital outturn at 31 March 2023 for projects reporting to the
Leadership Board is a breakeven position against the revised budget for the
year.
1.3. This is summarised in the table below and further analysis is provided in the
Appendices. 
Table 1: Revenue
Division
Revised
Annual
Budget
£000 
Projected
Annual
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance 
%
Adult Services 93,607 92,765 842 0.9%
Chief Executives 20,570 21,408 (838) (4.1%)
Total 114,177 114,173 4 0.0% 
Table 2: Capital
Division
Revised
Annual
Budget
£000
Projected
Annual
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance 
%
Chief Executives 38,926 38,926 0 0%
Leisure Services 1,688 1,688 0 0%
Total 40,614 40,614 0 0%

Page 2

2. Recommendations
2.1. Members are requested to:
(a) Note the projected Revenue outturn position detailed in Table 1 above; 
(b) Note the projected Capital outturn position detailed in Table 2 above; and 
(c) Note the budget adjustments detailed at sections 4 and 6. 
3. Revenue
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual underspend of £0.004m for all services reporting to this Board.
Detailed division reports can be found in Appendix 2, along with an
explanation of each significant projected variance.
3.2. The projected outturn is based on information currently available, and
assumptions made by service budget holders.
3.3. The main reasons for the projected outturn position are indicated in the
appendices showing both the subjective analysis (what the budget is spent
on) and the objective analysis (which division is spending the budget).
3.4. The most significant areas to bring to member’s attention are outlined below: 
• OneRen continues to experience increased cost and reduced revenue
generation in the short to medium term as a result of both temporary and
more permanent behavioural changes in recovery from COVID-19. In
addition the level of pay award agreed for 2022/23 is in excess of the level
of budgetary provision made, resulting in an increased forecast overspend.
OneRen is also facing steeply increasing utilities costs which are currently
being managed within existing resources through close financial
management. The Board and management team of OneRen continue to
put measures in place to mitigate the level of financial support required. 
• Within Adult Services, managed by Renfrewshire HSCP, the service
continues activity in response to the pandemic, which includes providing
support to external care providers in order to ensure their ongoing financial
sustainability. 
At Period 10, the service estimates that costs of £2.419m will be incurred
specifically in relation to COVID-19 Adult Social Care services by the end
of the financial year; this includes costs related to financial sustainability
payments to private adult and elderly care providers. The projected costs
are however based on the current position and may change depending on
any further impact of COVID on internal and externally provided services.

Page 3

The Scottish Government provided the HSCP with additional COVID-19
funding in the final quarter of 2021/22, and this was held as an earmarked
reserve and utilised to fund COVID-19 costs incurred this financial year. In
this context, additional costs specifically relating to the COVID-19
response are not therefore included within this report. The uncommitted
proportion of this funding was returned to the Scottish Government in
February 2023. 
4. Revenue Budget Adjustments
4.1. Members are requested to note from Appendix 1 that budget adjustments
totalling £0.207 million have been processed since the previous report to
board; this relates to the allocation of budget to fund the 2022/23 pay
settlement. 
5. Capital
5.1. The Capital Investment Programme 2022/23 to 2026/27 was approved by the
Council on 3 March 2022.
5.2. For the Chief Executive’s Service, the approved capital spend for 2022/23 is
£38.926m (£44.981m approved Capital Plan). For Leisure Services, the
approved capital spend for 2022/23 is £1.688m (£0.754m approved Capital
Plan). 
5.3. Further details can be found in Appendix 3. 
6. Capital Budget Adjustments
6.1. Since the 2022/23 budget was approved in March, budget adjustments
totalling £5.121m have arisen. £6.580m of these adjustments have occurred
since the previous board report as a result of: 
• Leisure Services
Budget carried forward into 2023/24 from 2022/23 (£0.698m):
o Community Halls Refurbishment: (£0.698m) to reflect expected
timing of work at Steeple Hall and Bargarran. 
• Chief Executives
Budget carried forward into 2023/24 from 2022/23 (£5.882m) based on
updated cashflows for the following projects:
o Glasgow Airport Investment Area: (£2.700m);
o Clyde Waterfront and Renfrew Riverside: (£2.646m);
o AIMIDS South: (£0.536m).

Page 4

___________________________________________________________________ 
Implications of this report 
1.  Financial
The projected budget outturn position for the revenue budget reported to
the Leadership Board is an underspend of £0.004m. Income and
expenditure will continue to be monitored closely for the rest of the financial
year and, where necessary, steps will be taken to mitigate any overspend.   
The projected outturn position for capital budgets reported to the
Leadership Board is breakeven. The Capital programme will continue to be
monitored closely for the rest of the financial year. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning 
None directly arising from this report. 
4.  Legal 
None directly arising from this report. 
5.  Property/Assets 
Capital projects will result in new assets (City Deal) and refurbishment, and
improvement to Cultural Infrastructure and Public Realm assets. 
6.  Information Technology 
None directly arising from this report. 
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health and Safety
None directly arising from this report.

Page 5

9. Procurement 
None directly arising from this report.
10. Risk 
The risk that the Council will overspend its approved budgets for the year
will be managed at a Council-wide level by the Chief Executive and
Directors. 
11. Privacy Impact
None directly arising from this report. 
12.  Cosla Policy Position 
N/a. 
13.  Climate Risk
None directly arising from this report.
__________________________________________________________________ 
List of Background Papers 
The Capital Investment Programme 2022/23 to 2026/27, approved by Council on 3
March 2022
__________________________________________________________________ 
Authors: Revenue - Valerie Howie, Finance Business Partner 
Capital - Geoff Borland, Finance Manager

Page 6

No embedded text on this page.

Page 7

Appendix 1   
Objective Summary
Approved
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Adult Services 93,607 0 93,607 92,765 842 0.9% 1,021 (179)
Chief Executive's Service 20,363 207 20,570 21,408 (838) (4.1%) (835) (3)
NET EXPENDITURE 113,970 207 114,177 114,173 4 0.0% 186 (182)
Subjective Summary
Approved
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 44,111 211 44,322 43,833 489 1.1% 682 (193)
Premises Related 815 0 815 917 (102) (12.5%) (53) (49)
Transport Related 837 0 837 475 362 43.2% 349 13
Supplies and Services 15,522 0 15,522 16,268 (746) (4.8%) (747) 1
Third Party Payments 76,446 487 76,933 77,461 (528) (0.7%) (727) 199
Transfer Payments 6,430 900 7,330 7,167 163 2.2% 332 (169)
Support Services 91 0 91 74 17 18.7% 16 1
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 144,252 1,598 145,850 146,195 (345) (0.2%) (148) (197)
Income (30,282) (1,391) (31,673) (32,022) 349 1.1% 334 15
NET EXPENDITURE 113,970 207 114,177 114,173 4 0.0% 186 (182)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance
(Adverse) or Favourable
Budget Variance
(Adverse) or Favourable
POLICY BOARD :  LEADERSHIP BOARD

Page 8

No embedded text on this page.

Page 9

Appendix 2   
Objective Summary
Approved
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Older People 60,147 0 60,147 60,920 (773) (1.3%) (846) 73
Physical or Sensory Difficulties 7,536 0 7,536 7,354 182 2.4% 198 (16)
Learning Difficulties 21,251 0 21,251 20,200 1,051 4.9% 1,240 (189)
Mental Health Needs 3,870 0 3,870 3,497 373 9.6% 437 (64)
Addiction Services 803 0 803 794 9 1.1% (8) 17
NET EXPENDITURE 93,607                       0   93,607 92,765 842                    0.9% 1,021                   (179)
Objective Heading
Older People
Physical or Sensory Difficulties
Learning Difficulties
Mental Health Needs
Key Reasons for Projected Variance
POLICY BOARD :  LEADERSHIP BOARD - ADULT SERVICES
Underspends in employee costs reflecting national recruitment issues facing all Health & Social Care. Further underspend within
adult care placements reflective of the current client profile but subject to change depending on demand and the implementation
of planned adult care placements over the financial year.
Underspends in employee costs reflecting national recruitment issues facing all Health & Social Care. Further underspend within
adult care placements reflective of the current client profile but subject to change depending on demand and the implementation
of planned adult care placements over the financial year.
Spend within care at home continues to increase as the service continues to support delayed discharges and demand.
Underspends in employee costs reflecting national recruitment issues facing all Health & Social Care.
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance
(Adverse) or Favourable

Page 10

Appendix 2   
Subjective Summary
Approved
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 38,952 0 38,952 38,483 469 1.2% 661 (192)
Premises Related 442 0 442 486 (44) (10.0%) (51) 7
Transport Related 836 0 836 474 362 43.3% 349 13
Supplies and Services 2,220 0 2,220 2,099 121 5.5% 120 1
Third Party Payments 76,320 487 76,807 77,335 (528) (0.7%) (727) 199
Transfer Payments 4,265 904 5,169 5,004 165 3.2% 332 (167)
Support Services 87 0 87 70 17 19.5% 16 1
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 123,122 1,391 124,513 123,951 562 0.5%                    700 (138)
Income (29,515) (1,391) (30,906) (31,186) 280 0.9% 321 (41)
NET EXPENDITURE 93,607 0 93,607 92,765 842 0.9% 1,021                   (179)
1 April 2022 to 6 January 2023
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
POLICY BOARD :  LEADERSHIP BOARD - ADULT SERVICES
Budget Variance
(Adverse) or Favourable

Page 11

Appendix 2   
Objective Summary
Approved
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Chief Executive and Management 299 (31) 268 265 3 1.1% 3 0
Policy and Commissioning 4,627 152 4,779 4,767 12 0.3% 11 1
Marketing and Communications 3,703 86 3,789 3,784 5 0.1% 9 (4)
City Deal & Infrastructure 0 0 0 0 0 0.0% 0 0
Leisure Services (incl Renfrewshire Leisure) 11,734 0 11,734 12,592 (858) (7.3%) (858) 0
NET EXPENDITURE 20,363 207 20,570 21,408 (838) (4.1%) (835) (3)
Objective Heading
Chief Executive and Management
Policy and Commissioning
Marketing and Communications
City Deal & Infrastructure
Leisure Services (incl Renfrewshire Leisure)
Key Reasons for Projected Variance
No significant projected year end variances to report.
REVENUE BUDGET MONITORING STATEMENT 2022/23
Budget Variance
(Adverse) or Favourable
1 April 2022 to 6 January 2023
RENFREWSHIRE COUNCIL
POLICY BOARD :  LEADERSHIP BOARD - CHIEF EXECUTIVE'S SERVICE
No significant projected year end variances to report.
The projected overspend position reflects the significant challenges OneRen continues to face following the pandemic and its
impact on commercial income, in addition to the higher level of pay award now agreed for 2022/23.
No significant projected year end variances to report.
No significant projected year end variances to report.

Page 12

Appendix 2   
Subjective Summary
Approved
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 5,159 211 5,370 5,350 20 0.4% 21 (1)
Premises Related 373 0 373 431 (58) (15.5%) (2) (56)
Transport Related 1 0 1 1 0 0.0% 0 0
Supplies and Services 13,302 0 13,302 14,169 (867) (6.5%) (867) 0
Third Party Payments 126 0 126 126 0 0.0% 0 0
Transfer Payments 2,165 (4) 2,161 2,163 (2) (0.1%) 0 (2)
Support Services 4 0 4 4 0 0.0% 0 0
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 21,130 207 21,337 22,244 (907) (4.3%) (848) -59
Income (767) 0 (767) (836) 69 9.0% 13 56
NET EXPENDITURE 20,363 207 20,570 21,408 (838) (4.1%) (835) (3)
Budget Variance
(Adverse) or Favourable
1 April 2022 to 6 January 2023
POLICY BOARD :  LEADERSHIP BOARD - CHIEF EXECUTIVE'S SERVICE
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23

Page 13

Appendix 3   
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2022* 2022-23 in 2022-23 2022-23 2022-23 Budget Outurn
Project Title to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
LEISURE SERVICES
Leisure Investment Programme 52,279 0 321 321 321 0 0% 52,600 52,600 0 0%
Grass Pitches & Changing Facilities 3,872 0 369 369 369 0 0% 4,241 4,241 0 0%
Community Halls Refurbishment 1,710 754 244 998 998 0 0% 3,433 3,433 0 0%
Lagoon Internal Play Centre 0 0 0 0 0 0 0% 1,000 1,000 0 0%
Total Leisure Services 57,861 754 934 1,688 1,688 0 0% 61,274 61,274 0 0%
CHIEF EXECUTIVES
City Deal Projects
Glasgow Airport Investment Area 38,662 2,314 -766 1,548 1,548 0 0% 43,053 43,053 0 0%
Clyde Waterfront & Renfrew Riverside 21,821 37,714 -11,554 26,160 26,160 0 0% 117,748 117,748 0 0%
Airport Access 2,934 0 0 0 0 0 0% 141,991 141,991 0 0%
Economic Development
GAIA Regeneration 2,109 0 1,891 1,891 1,891 0 0% 5,500 5,500 0 0%
AMIDS: Public Realm Phase 1 Netheron Square 246 2,726 962 3,688 3,688 0 0% 3,933 3,933 0 0%
AMIDS: District Heating Network 3,882 2,007 1,204 3,211 3,211 0 0% 7,093 7,093 0 0%
AMIDS: South 415 220 2,208 2,428 2,428 0 0% 42,328 42,328 0 0%
Total Chief Executives 70,069 44,981 (6,055) 38,926 38,926 0 0% 361,646 361,646 0 0%
TOTAL LEADERSHIP BOARD 127,930 45,735 (5,121) 40,614 40,614 0 0% 422,920 422,920 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 6th January 2023
POLICY BOARD: LEADERSHIP
Current Year 2022-23 Full Programme - All years