To:  Leadership Board
On:  16 September 2026
___________________________________________________________________
Report by:  Chief Executive 
___________________________________________________________________
Heading: OneRen Update
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to provide an update in relation to several
matters which relate to the provision of services through OneRen. 
Specifically: 
• An update relating to the forthcoming opening of the Lagoon Adventure
Zone.
• A progress update on the final stages of the Paisley Museum Re-Imagined
Project ahead of its completion. 
• The development of an operational agreement through which OneRen will
manage the operation of community facilities within Paisley Grammar
School Community Campus.
• An update on the reprovisioning of library provision in Erskine. 
___________________________________________________________________ 
2. Recommendations 
2.1  It is recommended that Elected Members: 
• Note the content of the report.
• Note the progress in terms of the Lagoon Adventure Zone, which is
scheduled to open during October.
• Note that the Paisley Museum fitout and install is due to complete in
December ahead of a formal opening to the public early in the new year

Page 2

PUBLIC
and that Elected Members will be kept updated regarding the opening
programme. 
• Agree a short-term suspension of the provision of library services in
Erskine as detailed in paragraph 6.5 of this report to facilitate the decant
of Erskine Library from Bridgewater Shopping Centre to the temporary
building at Erskine Sports Centre.
___________________________________________________________________
3. Background 
3.1 Regular updates are provided to Leadership Board on the activities and
performance reported in relation to the services and activities which OneRen
deliver in line with its service agreement with the Council. Additional reports
are submitted to board to cover any matters arising or requiring decisions
outwith planned reporting cycles. 
3.2 As outlined in section 1 of the report, several specific operational matters are
currently being progressed by officers and require the provision of an update
to elected members. These relate to: 
• The forthcoming opening of the new Lagoon Adventure Zone facility.
• A progress update on the final stages of Paisley Museum Re-Imagined
Project ahead of its completion.
• The development of an operational agreement through which OneRen will
manage the operation of community facilities within Paisley Grammar
School Community Campus.
• The reprovisioning of library provision in Erskine. 
4. Lagoon Adventure Zone – Lagoon Leisure Centre 
4.1 The Lagoon Adventure Zone will offer a vibrant multi-age play experience
featuring an interactive TAG active arena, the first of its kind in Scotland, a
dedicated sensory area supporting people with additional support needs, a
baby and toddler area, party room, spacious seating and an enhanced café
offering. The facility has been developed through £1million of investment by
the Council in inclusive play facilities, and will be operated by OneRen. 
4.2 The Certificate of Practical Completion is pending subject to final
requirements, and the project remains on schedule for launch in October, with
final fit-out works and operational commissioning to be completed. 
4.3 A number of centre improvements are being delivered to support the
investment, including enhanced toilet and baby-changing facilities, and
upgraded CCTV to strengthen safeguarding arrangements. 
4.4 Operational readiness is progressing well, with specialist product, safety, and
RoSPA training scheduled ahead of opening. 
4.5 A flexible operating model has been developed to manage variations in
demand throughout the week, and a dedicated brand and marketing

Page 3

PUBLIC
campaign has been developed to initiate the launch of this new offer over the
coming weeks. Catering, delivered by local supplier, Brew & Bite, will be
launched to support a full menu of hot food and beverages in the play
experience during opening hours. 
4.6 A phased programme of testing and soft-launch activity with key stakeholders
will take place prior to the official public opening in October 2026. 
4.7 Investment in the new Adventure Zone play offer supports access to inclusive
play facilities, and is part of our approach to making Renfrewshire fairer and
more inclusive for children and families across Renfrewshire.  The
development of the facility, will also promote the Lagoon as a visitor
destination and supports the wider economic regeneration of Paisley. 
5. Paisley Museum Reimagined 
5.1 Paisley Museum has been completely reimagined through rebuild, redisplay,
and new practices evolved by collaborative decision-making and co-production
with over 70 local groups and over 4000 conversations. This collaborative
approach has shaped a new offer designed as a world-class destination telling
the inspirational stories of Renfrewshire’s people and places as well as
showcasing its internationally significant collections including the Paisley
pattern. 
5.2 The redesigned offer includes the Grade A-listed Museum building and Grade
A-listed Coats Observatory & Observatory House, as well as Transit House and
the Oakshaw buildings. The original Museum building is the work of the practice
of Honeyman, Keppie & Mackintosh. Through the lifetime of the project, the
influence of Charles Rennie Mackintosh on the design of later parts of the
building has become more apparent. 
5.3 Following practical completion earlier this year, the second and third phases of
the project of exhibition fitout and installation of the Museum have been
underway. Contractors have been working to make up time from the delayed
construction phase and are due to complete by the end of this year ahead of a
formal opening to the public early in the new year. A further update will be
brought to the next Leadership Board to provide further detail on the opening
programme. 
5.4 The major redevelopment has brought the historic buildings up to modern
standards to safeguard their long-term future and increased the amount of
space available to showcase Renfrewshire’s internationally significant
collections as a visitor destination to place Paisley Museum firmly among
Europe’s leading museums. 
5.5. The new design provides for 21st Century facilities with lift access to all areas,
toilets on every level, a café facility with picnic area, a changing places toilet,
lockers, water fountains, buggy park and the introduction of a public courtyard
ensuring street level access for everyone.

Page 4

PUBLIC
5.6. A new outdoor garden has been created opening up previously hidden views
of the Coats Observatory, the first publicly accessible Observatory in Scotland
and spectacular views towards the High Street and the hills beyond. 
5.7. The newly extended galleries will allow more of Renfrewshire’s remarkable
collections to be displayed with a 100% increase in objects on display. 
Main Works 
5.8 Practical Completion was achieved on 9 February 2026 and handover of the
museum site from Construction Contractor Kier to the Exhibition Fit-out
Contractor, Hub Build was confirmed. 
5.9 The completion of the construction phase marked a significant milestone and
the realisation of the architectural vision. The design has taken opportunities
to improve the operational efficiency of the campus as well as resolve
significant access issues including: 
• Improving the energy efficiency and lowering the carbon footprint of the
building, including upgrading the insulation where possible, the use of
energy LED efficient lighting, specifying for reduced energy consumption
and sustainability of materials and using natural ventilation where
environmental conditions allow. 
• All 24 historic roofs have been replaced or restored with brand new, high-
performance materials that are sympathetic to the historic fabric and to
maximise operational sustainability. Replacement roof tiles have been
carefully salvaged from Scottish heritage sites or sourced from working
Welsh slate mines. 
• Modern accretions removed to reveal historic details in the restored
galleries, allowing and through the development of a lighting strategy
daylight has been reintroduced to the galleries while simultaneously
reducing solar gain. 
• The museum features step-free, full level access directly from the street
through the main entrance into a new entrance lobby.  The interior of the
building is fully accessible with lifts serving all public floors, ensuring
unrestricted movement between the gallery spaces, exhibition zones, and
amenities. 
5.10 Kier continue to maintain an onsite presence to complete snagging works.
These are programmed to avoid disruption to the fit-out progress. 
5.11 Renfrewshire Council’s Facilities Management team and OneRen Estates
team are working together on ensuring statutory and planned maintenance
inspections which are scheduled in conjunction with the fitout contractor Hub
Build.

Page 5

PUBLIC 
Left: New red drum entrance and replaced rooflights in Grade A-listed main
building 
Right: West extension Garden Gallery with view to Observatory and Garden
Exhibition Fitout and Install 
5.12 Following a period of site set-up, the fitout contractor Hub Build commenced daily
deliveries of setworks and showcases from the storage facility in Linwood. 
5.13 The Exhibition Fit-out contract has progressed into all areas of the museum and
nearing completion in 60% of the galleries. Sectional completion has been
successfully achieved in the upper galleries of the Main Building and Coats
Observatory. 
Both images: Click Netherfield, case manufacturer, install cases in the upper
galleries ahead of object install. 
Object Preparation and Install Schedule 
5.14 Approximately 80% of objects selected for display required conservation
treatment. 23 separate conservation studios or individuals across the UK were
contracted to conserve 1050 objects. All work has now been completed ahead
of object install.   
5.15 The completion of the conservation programme has benefited from several
key national and international partnerships agreements with organisations
such as the American Museum of Natural History, New York, The Royal

Page 6

PUBLIC
Armouries, Leeds, The Centre for Textile Conservation (CTC), Glasgow and
The People’s History Museum, Manchester. 
5.16 Nearly 20% of conservation costs have been sourced from external grant
bodies including Museums Galleries Scotland, the Henry Moore Foundation
and the National Manuscript Conservation Trust. 
Left: Centre for Textile Conservation student with child’s dress prepared for
display
Right: Buddie the Lion crated ahead of move back to Museum 
5.17 By the end of August, the majority of display objects have been packed in
preparation for install. Ahead of the main install programme large or complex
install objects have been moved to the museum. All object displays require
multi-trades and specialist input in an increasingly complex building layout as
display cases and display furniture fitout continues. 
Left: Museum team install Steven Campbell’s 3m long painting The Golden City 
Right: Dr Dan Coughlan completes the installation of the Jacquard Binary Loom

Page 7

PUBLIC
Feedback and Recognition 
5.18 In 2024 the project design won the Architecture Review’s Cultural
Regeneration category at the Future Awards.  The prestigious award
recognises the significant role the project is playing in the town and wider
region’s cultural regeneration. The shortlist included the Prado Museum in
Madrid, the Shanghai Opera House, and the Bilbao Fine Arts Museum. 
5.19 In 2026 the project secured its second major industry accolade winning
Scotland’s top heritage project at the Royal Institution of Chartered Surveyors
(RICS) award. The project was shortlisted alongside The Canna House, The
National Trust, Preston Tower Doocot, and John O’Groats Mill. The project
will now go forward to compete at the RICS UK Grand Final in October. 
5.20 The National Lottery Heritage Fund has been a major funder since 2017.
Caroline Clark, Director for Scotland recently noted that: 
“The Paisley Museum project is a serious re-imagining of the role of the
museum. It would be enough to deliver an international quality museum as a
heritage destination, but this project has had the ambition to deliver much
more and aim to fulfil a wider role, inherent to the vibrancy and wellbeing of
Paisley. The design supports this approach, welcoming in the whole
community whether to explore the collections or simply to enjoy the museum
environment. There has been a deeply thoughtful and innovative approach to
what a museum can offer the people of Paisley, and its visitors”.
5.21 International Museum Consultant Elaine Heumann Gurian has worked in
museums for over 50 years including The United States Holocaust Memorial
Museum, The Children’s Museum, Boston, The Powerhouse Museum,
Sydney, and Te Papa The National Museum of New Zealand.  In 2004 the
American Association of Museums honoured her with the Distinguished
Service to Museums Awards, the most prestigious recognition in the American
museum profession. Visiting Paisley last year she noted: 
“The impact is clear. It is going to make ‘place’ an important part of our
conversation. This museum is using every inclusive technique they can think
of to go about doing their work. Outsiders are going to come to watch how a
real place for a real community works and have that joy spread to them as
well’
5.22 During February stakeholder site visits with local businesses were organised.
Feedback was extremely positive with one business owner writing: 
“I have got to say I’m completely blown away by what has been done to the
museum. The museum is state of the art but somehow and I don’t know how,
you have all managed to keep that true feeling of Paisley, it’s a people’s
place, it’s calm, it’s inviting, it’s exciting, it’s exactly what Paisley needs.”

Page 8

PUBLIC
Community Engagement 
5.23 The Schools Learning Programme has been co-created through work with
every Primary school in Renfrewshire so that it meets the needs of local
teachers and pupils. Over 500 primary and secondary pupils have been
involved in the testing and development of activities. 
5.24 As part of the development of the Museum’s public programme, over 70 local
services, organisations and groups were consulted through an ‘Active Listening’
programme to ensure that the museum could serve their needs. 27 community
and partner organisations involved in creating and testing new approaches to
and creation of resources for audience engagement. Over 500 participants
attended test events, workshops and coproduction activities. 
5.25 The development of the main displays involved 2500 participations with direct
engagement with over 600 people including consultation for research and
content development purposes to the delivery and build of interpretation and
interactives. 50 of the 88 displays have either been co-produced, or involved
consultation with experts and audiences. 
Operational Readiness
5.26 OneRen has adopted an inclusive, informal, and community-focused
approach to recruitment. Local community partners were asked for their
advice on how to recruit in a way that removes barriers and gives everyone an
equal opportunity to succeed. The result is a values-based approach that
encourages open communication before the advert is live and an opportunity
to demonstrate the value that individuals could bring the organisation in
practical ways. 
5.27 230 people attended the initial recruitment day information session held at
Paisley Town Hall. Formal evaluation of the process has shown that the
events successfully encouraged applications from those who attended, with
particularly positive perceptions of the approach among disabled applicants,
applicants with long-term health conditions and care-experienced applicants. 
5.28 499 applications were received for the initial recruitment phase. Recruitment
has now concluded for the majority of Visitor Operations staff including Visitor
Assistants, Visitor Operations Supervisors, Visitor Operations Manager,
Archivist and Retail Manager. Further recruitment for the Heritage Archive
Centre staff will take place in August and September and a programme of
training and familiarisation has been organised.

Page 9

PUBLIC
6. Update on reprovisioning of library services in Erskine 
6.1 At its meeting on 18 June 2025, the Leadership Board considered an update
paper relating to the Reshaping Renfrewshire programme, which included
information relating to the current review of leisure and culture services
commissioned by the Council and delivered by One Ren. The paper highlighted
that the current lease for Erskine Library at Bridgewater Shopping Centre was
due to expire in May 2026, and that the landlord had indicated that they would
not be willing to extend the current lease beyond that date. 
6.2 Whilst the provision of library services is a key element of the ongoing One Ren
review process, it was recognised that a short to medium term solution would
require to be identified to ensure that library provision in Erskine could continue
whilst the wider review progresses. The report at that time, outlined that officers
from One Ren and the Council would progress arrangements to commission
new temporary modular buildings at the Erskine Sports Centre site, in order that
these could support the reprovisioning of Erskine library when the current lease
comes to an end. 
6.3 Following a tendering exercise, a contract authorisation report was approved
by the Finance, Resources and Customer Service Policy Board in November
2025 to award a contract to Portakabin in relation to these works.  Due to
procurement and legal issues, there was an extended period required to
formally appoint Portkabin to install the temporary library facility at Erskine
Sports Centre.  This has had an impact on the previously planned project
timescales, which had been set to allow for the new facility to be on site before
the end of the current lease at Bridgwater Shopping Centre in May 2026. 
6.4 In order to ensure there was no disruption or gap in library provision in Erskine,
a short term extension of the current lease at Bridgwater Shopping Centre was
put into place to allow additional time for the new buildings to be put into place
and for One Ren to ensure all necessary statutory and operational
arrangements were made to support the opening of the new facility. 
6.5 Following completion of all regulatory processes, groundworks commenced at
the site in August 2026, with the targeted date for installation of the new
temporary building being mid-September 2026.  A programme is now in place
to formally decant the library facility to the temporary building, which will involve
a short closure period. The decant will necessitate a short-term suspension of
the provision of library services in Erskine. Officers will work with OneRen to
endeavour to minimise the duration of the suspension. Engagement with the
local community on the planned opening date for the new facility will be
undertaken.  Subject to final completion, this is being targeted for October
2026. 
6.6 Ongoing updates will continue to be provided to ward members ahead of the
opening date, with wider updates on the OneRen review being reported on a
regular basis to Leadership Board.

Page 10

PUBLIC
7. Operational agreement – Community facilities within Paisley Grammar
School Community Campus (PGSCC) 
7.1  As elected members will be aware, Paisley Grammar School Community
Campus opened on 20 August 2026 and provides facilities for community use,
the co-ordination of which will be managed operationally by One Ren. This
includes community rooms, the football pitch, gym hall and games hall,
including at weekends and will be operational from 29 September 2026 (after
September weekend) to allow the school and staff to settle in. OneRen have
updated let holders and are currently recruiting staff to work at the facility. 
7.2 In April 2026, elected members were asked to note that the current Services
Agreement between One Ren and the Council will require to be updated to
reflect this operational change, however, OneRen have agreed in principle to
undertake this.  Work has been undertaken to develop an initial operational
agreement between the Council and One Ren which supports the day to day
running of the community facilities, with agreements to be developed for
formal approval by the Council and the OneRen Board.  It is anticipated that
this approach will be replicated to support operational arrangements at other
facilities operated by One Ren within a shared campus arrangement. 
___________________________________________________________________
Implications of the Report
1. Financial – none within this report 
2. HR & Organisational Development – None 
3. Community/Council Planning – the projects and facilities highlighted
within the report will provide a significant positive impact for specific
local communities and on a Renfrewshire wide basis. 
4. Legal – A service agreement is in place between OneRen and the
Council which clearly identifies the requirements that OneRen must
fulfil in relation to the service payment.  As noted within the paper, this
will require to be updated in light of the developments being
progressed. 
5. Property/Assets – As outlined in the paper, there a range of property
related developments ongoing at present which require to be closely
managed by OneRen and the Council. 
6. Information Technology – not applicable 
7. Equality & Human Rights – N/A 
8. Health & Safety – not applicable 
9. Procurement – not applicable

Page 11

PUBLIC 
10. Risk – not applicable 
11. Privacy Impact - not applicable 
12.                Climate Risk – not applicable
13.                Children’s Rights – not applicable.
14. Cosla Policy Position – not applicable
_________________________________________________________ 
List of Background Papers
___________________________________________________________________ 
Author: Laura McIntyre, Head of Policy and Partnerships