City Deal and Infrastructure Programme

Renfrewshire Council · 18 February 2026
Back to Leadership Board — 18 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
___________________________________________________________________ 
To: Leadership Board 
On: 18 February 2026
___________________________________________________________________ 
Report by: Chief Executive 
___________________________________________________________________ 
Heading: City Deal and Infrastructure Programme
___________________________________________________________________ 
1. Summary 
1.1 This report is to update the Board on the finalisation of the City Deal and
Infrastructure Programme delivery phase and the arrangements to transition
business as usual functions to appropriate core service areas. 
2. Recommendations 
2.1 The Leadership Board is asked to: 
i) Note the report on progress to conclude delivery of the city deal
infrastructure projects and the operational changes to bring the
infrastructure delivery arrangements to a conclusion.
___________________________________________________________________ 
3. City Deal and Infrastructure Programme Delivery 
3.1 Since the Glasgow City Region City Deal was approved in 2014, Renfrewshire
Council has successfully delivered an ambitious regeneration agenda, focused
on creating the infrastructure and business environment to generate economic
growth and jobs, while promoting active travel and green opportunities to
ensure the area is a fairer, more inclusive place where all our people,
communities, visitors and businesses thrive. 
3.2 This ambitious programme has been delivered during an unprecedented period
of economic disruption caused by several significant global events including the
COVID-19 pandemic, the war in Ukraine and the significant consequential
economic disruption as well as ongoing geopolitical and economic volatility.

Page 2

PUBLIC
During this period, the City Deal and Infrastructure team ensured the Council
built on the enabling investment provided by the City Deal and delivered the full
planned investment programme. The completion of the city Deal infrastructure
projects has been a key element of the recovery and inclusive growth in the
Renfrewshire economy. 
3.3 The Renfrew Bridge formally opened in May 2025, and the new bridge and
active travel infrastructure has proved hugely popular with communities on both
sides of the River Clyde. Over the past 7 months of the bridge being open, more
than 2.46 million users have crossed the bridge. This performance far exceeds
the projected volumes calculated throughout the business case development
stages and highlights the strategic importance of this travel link for Renfrewshire
and the wider City Region The route has quickly established itself as a vital
travel link which has enhanced connectivity and is supporting sustainable travel
across the Glasgow City Region. 
3.4 The ambitious enabling infrastructure elements of the Advanced Manufacturing
Innovation District Scotland (AMIDS) have also been completed, including
roads, bridges and drainage provided by the Glasgow Airport Investment Area
(GAIA) project; the design and construction of a state-of-the-art, fifth generation
District Heating Network; the procurement of private sector delivery partner
Buccleuch Property; the design and construction of the high quality Netherton
Square public realm; and an active travel link from AMIDS to Inchinnan
connecting subsequently to new housing at Dargavel. 
3.5 The Council was also successful in attracting two anchor tenants - the National
Manufacturing Institute Scotland and the Medicines Manufacturing Innovation
Centre, both of which are open for business operating at Netherton Campus.

Page 3

PUBLIC   
3.6 AMIDS South is a £59million infrastructure project which will connect Paisley
town centre with the Advanced Manufacturing Innovation District Scotland
(AMIDS) and Glasgow Airport through a series of transport and infrastructure
improvements. It is a key component of Renfrewshire’s long-term strategy to
enhance connectivity, support economic growth, and promote sustainable
transport. 
3.7 The construction phase of the AMIDS South project is underway to create a
new road bridge across the White Cart river, a gateway route along Abercorn
Street and Harbour Road, a new road linking Renfrew Road to the bridge which
also serves the new Paisley Grammar Community Campus, and a new crossing
under Renfrew Road to connect one end of Gallowhill with the Renfrew to
Paisley walking and cycling route (which connects into the new school). 
3.8 Significant work was required to develop the Levelling-Up and Council funded
project and reach this stage, including the design of roads and the new bridge,
alignment with the new Paisley Grammar Community Campus project,
designing and securing funding for the Gallowhill Link, undertaking a complex
compulsory purchase process, planning considerations, coupled with an
unusual court of session declarator case. This has all now been completed and
the final phase of this project is underway with full completion expected in 2028,
albeit the Gallowhill Link and new road connecting to the school is scheduled
to finish in 2026. Management of the delivery of this project is being managed
by the Environment Housing and Infrastructure Service as part of the significant
strategic investment portfolio in the Council’s transport and active travel
network.

Page 4

PUBLIC
3.9 Work on the build out and economic development of AMIDS continues with
Netherton Campus now in the final stages of becoming a designated tax site
alongside Glasgow Airport as part of the Glasgow City Region Investment Zone.
This specialised tax status will provide a further incentive to attract major inward
investment to AMIDS and help establish the development and Renfrewshire as
a major global destination of choice for advanced manufacturing and innovation
investment 
Planning for the flexible Tech Terrace speculative space project is expected to
be submitted in the coming weeks and will provide opportunities for smaller and
start-up businesses to locate to AMIDS in highly flexible growth space,
supporting the opportunity for expanding to their own purpose-built facility on
site. Scalable start-up space of this nature for developing advanced
manufacturing businesses is in scarce supply across the city region and this is
therefore expected to provide in-demand facilities. 
AMIDS has also been designated by the UK Government as a ‘Priority Project’
for investment. This was announced by the UK Chancellor at a Regional
Investment Summit in October 2025 and the National Wealth Fund (NWF) has
been appointed to assist the Council and its partners in accelerating
development. Considerable work is ongoing with NWF and other bodies in
ensuring the maximum benefit to AMIDS is forthcoming. 
3.10 In parallel, the City Deal and Infrastructure team has also managed the delivery
of generational investment in Paisley town centre venues, namely Paisley Town
Hall, Paisley Arts Centre and the creation of a new Learning and Cultural Hub
on Paisley High Street which includes Paisley Central Library. These were
delivered as part of the Cultural Infrastructure Programme and numerous
projects have won awards for their successful completion and impact on the
town – having been noted by judges as a key part of Paisley’s recent accolade
as Scotland’s Town of the Year.

Page 5

PUBLIC
3.11 The major construction phase of the final element of this programme, the
flagship Paisley Museum Reimagined project, has very recently completed and
is transitioning to the extensive fit-out period and object install, expected to be
completed over the remainder of 2026 ahead of a planned public reopening. It
is the first major transformation of Paisley Museum in its 150-year history and
will bring the historic building up to modern standards, safeguarding its long-
term future, and will also through modern areas of expansion double the amount
of space available to showcase its internationally significant collections,
creating a visitor attraction that places Paisley for the first time firmly among the
UK’s leading museum destinations. 
3.12 The improved cultural infrastructure across Paisley is now better placed than
ever to capitalise on the internationally significant cultural and heritage story
to transform the future for visitors and events within Scotland. The completion
of this programme of work will bring new footfall, added life and vibrancy to
the town centre, boosting the local economy and opportunities for businesses,
provide new homes for top class cultural events, and preserves the heritage
of the town. In this context, work is progressing with the City Region Hub
Team, who will provide specialist expertise to develop arrangements to assess
the economic impacts arising from the investment over the long term. 
3.13 The CD&I team also worked with heritage building owners to deliver the
Paisley Townscape Heritage Initiative and Conservation Area Regeneration
Scheme (TH/CARS2) which invested to save some of Paisley’s local privately-
owned heritage buildings from deterioration – with the Liberal Club on Paisley
High Street being a notable success. In the absence of the investment grant
provided, the building was at significant risk of deteriorating beyond repair.

Page 6

PUBLIC 
3.14 Further successful investment has been delivered in a range of external sports
facilities, including an international-standard hockey pitch and running track at
the On-X Leisure Centre in Linwood, an upgrade of facilities at Ferguslie Sports
Centre, and provision of new pavilions to bring back into use grass pitches at
St James Playing Fields in Paisley. This ensures recreation and sporting
facilities are available at all levels for our local young people and residents.

Page 7

PUBLIC
3.15 Community Benefits 
It is worth also noting that since 2015, the City Deal and Infrastructure
programme has secured and delivered significant community benefit outcomes
and activities within the local area. 
Targeted Recruitment and Employment  Delivered
Targeted Recruitment and Employment  over 60
Targeted Skills & Training over 200
Supply Chain Development  over 20
Community Engagement more than 240 hours
volunteer time 
Community Investment   Over £80,000
Local Glasgow City Region Supply
chain spend Over £35,000,000
* 
*the local spend only relates to CWRR main works and Paisley Town Hall as
Morrisons/ Grahams are the only contractors that formally recorded and
reported it. 
The construction phase of the Paisley Museum Re-imagined project and the
AMIDS South project continue, and Contractors involved are committed to
delivering the following additional outcomes/ activities. 
Commitments secured for
AMIDS S +remaining PMR
Targeted Recruitment and
Employment  13
Targeted Skills & Training 24
Supply Chain Development  10
Community Engagement 8
Community Investment   10 
3.16 Project Evaluation 
The City Deal and AMIDS South Projects have formal ongoing post
completion/operations evaluation requirements set out in the approved
business cases to ensure the benefits are realised. In respect of benefits
realisation for both the GAIA and CWRR projects, officers have been
continually reviewing completed commercial and other developments in and
around the respective project areas. This includes integrating the annual
Renfrewshire Housing Land Audit, reviewing planning applications, and
engaging in discussions with developers and landowners.  Several positive
outcomes from both projects have been recorded. Outcomes are submitted
quarterly to the City Region Programme Management office. A similar
requirement will follow completion of the AMIDS South project in terms of
reporting the benefits realised to UKG through the Levelling Up Fund officers.

Page 8

PUBLIC
Going forward, officers will continue to monitor completed developments,
utilising GIS searches to ensure all benefits are captured accurately. 
OneRen will also monitor the benefits of the completed cultural infrastructure
venues, Paisley Central Library and external sports projects and report this
through their Board. For example, for the Museum, when completed, OneRen
will record footfall/visitors and a year after opening OneRen will undertake a
summative evaluation which will be both quantitative (number of people etc) as
well as qualitative. In addition, and as referenced above, an economic impact
assessment will be progressed in partnership with the City Deal Hub team to
track the long term economic benefits secured from the investment. 
4. Operational Changes 
4.1 The City Deal Infrastructure Team was established in 2015 to support the
Council to develop and progress the Council’s projects through the City Deal
business case process and once approved provide a dedicated resource to
procure and deliver the complex range of major infrastructure projects. The
remit of the team was subsequently expanded to provide the lead for the
delivery of the Cultural Infrastructure investment programme across Paisley,
working in partnership with OneRen colleagues. 
4.2 Taken together, this programme of investment represents the most significant
and complex ever delivered by the Council and as referred to above has been
delivered during the most difficult and volatile economic and construction
environments experienced for generations. The foresight of the Council to
establish a dedicated team for this purpose has therefore served the Council
well in terms of being able to respond to rapidly changing circumstances. 
4.3 It was always planned that the City Deal delivery team was a temporary
arrangement to support the projects development and delivery phases. As the
investment programme has progressed projects to a conclusion, the scale of
the city deal team has been gradually reduced in line with long term plans
through natural turnover and with key professional support officers (finance,
legal, procurement etc) transitioning to other major projects. 
4.4 Over the coming months, a range of residual activities will be progressed that
will bring the delivery of the infrastructure programme to a full conclusion and
following completion of this phase the City Deal Infrastructure team will be fully
disbanded. 
4.5 There remains several residual investment elements and business-as-usual
aspects arising from the projects which have been transitioning to the
appropriate core service areas across the Council as summarised below: 
• Support in relation to the Council’s ongoing City Region activities along
with the Council’s role to develop out AMIDS with our procured
commercial Joint Venture partner, has transitioned to the Head of
Economy and Development.

Page 9

PUBLIC
• Operational Management of the Renfrew Bridge and the bridge team has
transferred to EH&I. 
• As referred to above delivery of the AMIDS South project is being
delivered by the EH&I investment team alongside the wider strategic
investment in the transport network. 
• The Paisley Museum Reimagined fit out, object install and planned
opening programme following completion of the construction phase will be
led by the OneRen team. 
___________________________________________________________________ 
Implications of the Report 
1. Financial – there are no direct financial implications arising from this report. 
2. HR & Organisational Development – the wind down of the City Deal team will
be managed through natural deletion of posts, redeployment to core activities
and other major projects and use of the Council’s voluntary severance
arrangements where appropriate. Any use of the severance arrangements will
be progressed through the Council’s existing governance and reporting
arrangements. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – These projects will link our communities
and facilitate new development opportunities and business growth with
both projects improving skills development, educational and health
opportunities for people within the local communities as well as aiding
employees to access these major existing and new employment centres.
The projects align with and aid the outcomes of the Renfrewshire
Economic Strategy 2020 -2030 and the Renfrewshire Economic
Recovery Plan 
• Our Renfrewshire is well - The new safer walking and cycling
infrastructure incorporated within these projects, will help encourage
active travel by children and young people, as well as adults. 
• Reshaping our place, our economy and our future – These infrastructure
projects provide connectivity and access to new and existing jobs for
people in our communities. During the project construction period
hundreds of new jobs have been created and as a result of new business
creation it is estimated that thousands of additional new permanent jobs
will be created. NMIS and MMIC are already up and running as a direct
consequence of this enabling infrastructure. The combined projects
investment in linking active travel infrastructure and education and will
provide connectivity and access to new and existing jobs for people in our
communities.

Page 10

PUBLIC
• Tackling inequality, ensuring opportunities for all – CWRR provides
access to development opportunities along Meadowside Street,
increases the potential to reinvigorate Blythswood Retail Park and
improves access for the communities on both sides of the River Clyde to
facilities and employers on the other side such as the Queen Elizabeth
University Hospital; NHS Golden Jubilee; West College Scotland’s
Clydebank campus and Yoker train station. The project also increases
the employee catchment area for businesses planning to locate at
AMIDS, while improving links to suppliers and customers. 
• Creating a sustainable Renfrewshire for all to enjoy - The completed
infrastructure includes segregated provision for walking and cycling and
will also enable improved public transport links CWRR opens up
development opportunities, which through the LDP will be managed as
sustainable linked communities.   
• Working together to improve outcomes - Officers are working closely with
local communities, neighbouring councils, private sector organisations,
Scottish Government, Scottish Enterprise, and other partners to ensure
the maximisation of positive outcomes from the projects noted within this
report. 
4. Legal – none 
5.  Property/Assets – completed assets will require to be maintained and 
operated by  the Council. 
6. Information Technology - none 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report because it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health & Safety - none 
9. Procurement – all contracts are tendered in accordance with Council
procurement procedures and where relevant taken to FRCS Board for approval. 
10. Risk – Project specific and Programme level risk registers have been
established for all projects. These are kept under regular review and reported
to the Council’s internal City Deal and Infrastructure Programme Board. Should
the Regional project funding bid be successful the project will be further scoped
through the Glasgow City Region Business Case development process.

Page 11

PUBLIC
11. Privacy Impact - none 
12. COSLA Policy Position – not applicable 
13. Climate Risk – the project will provide sustainable active travel routes and
encourage sustainable neighbourhoods and transport links including provision
of blue green infrastructure 
14. Children’s Rights – None 
List of Background Papers 
None
___________________________________________________________________