To: Leadership Board
On: 23 April 2025
___________________________________________________________________
Report by: Chief Executive, Director of Finance and Resources, and Chief Finance
Officer Renfrewshire HSCP
___________________________________________________________________
Heading: Revenue and Capital Budget Monitoring as at 7 January 2025
___________________________________________________________________
1. Summary
1.1. At the close of reporting Period 10 on 7 January 2025, the projected revenue
outturn at 31 March 2025 for those services reporting to the Leadership Board
was an overspend position of £3.618m (2.8%) against the revised budget for
the year.
1.2. The projected capital outturn at 7 January 2025 for projects reporting to the
Leadership Board is a break even position against the revised budget for the
year.
1.3. This is summarised in the tables below and further analysis is provided in the
Appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
Adult Services 106,810 110,476 (3,666) (3.4%)
Chief Executive’s Service 20,487 20,439 48 0.2%
Total 127,297 130,915 (3,618) (2.8%)
Capital 24,643 24,643 0 0%

Page 2

2. Recommendations
2.1. Members are requested to:
a) Note the projected Revenue outturn overspend position of £3.618m;
b) Note the projected Capital outturn break-even position; 
c) Note the budget adjustments detailed at section 6.2.
_________________________________________________________
3. Revenue Budget Projection – overspend of £3.618m by 31 March 2025
3.1. The tables in Appendix 1 present the projected year-end position for all
services reporting to this board, by both subjective analysis (what the budget
is spent on) and objective analysis (which division is spending the budget).
Significant variances affecting the projected position are analysed further
below.
3.2. It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. This is the last Budget monitoring report until the outturn
position is presented to the Council in June. Budget holders are obliged to
seek mitigating action to minimise significant budget variances.
_________________________________________________________
4. Objective Analysis – Significant Variances
4.1. Adult Services - £3.666m overspend
The overspend is mainly due to external care at home packages for both
Older People and those with Physical or Sensory Difficulties. This results from
increased acuity of patients with more complex needs discharged from
hospital, meaning more intensive Care at Home packages are required to
support people to remain in their own homes. The overspend is further
impacted by inflationary increases as a result of the adult supported living
framework renewal in November 2024.  Since the last report the overspend
has reduced by £0.977m mainly due to vacancy management controls now in
place, and further recovery of payments relating to changes in package costs.
This forecast position now includes costs associated with the care at home
staff regrade. 
4.2. Chief Executive’s Services - £0.048m underspend
There are no significant variances to report for those divisions of the Chief
Executives Service reporting to this Policy Board.
_________________________________________________________

Page 3

5. Subjective Analysis – Significant Variances
5.1. Employee Costs - £1.559m underspend 
This forecast underspend predominantly arises within Adult Services
(£1.512m) due to the ongoing recruitment challenges and retention issues
across all service areas due to the limited availability of the required skills mix. 
5.2. Premises Related - £0.136m overspend 
This forecast overspend within Adult Services relates to increased cleaning
costs and repairs, including the purchase of track hoists. 
5.3. Transport Related - £0.050m underspend 
This forecast underspend relates fully to Adult Services and reflects current
vehicle demand for the service and a reduction in employee travel costs. 
5.4. Third Party Payments - £4.829m overspend 
This forecast overspend relates fully to Adult Services and is mainly due to
external care at home packages. This results from increased acuity of patients
discharged from hospital, with more complex needs, meaning more intensive
Care at Home packages are required to support people to remain in their own
homes. Further overspends are forecast within adult supported living
packages and carer's respite, reflective of client needs and demand for these
services. The position is further impacted by anticipated inflationary increases
as a result of the adult supported living framework renewal in November 2024
and the agenda for change increase on the Nursing National Care Home
Contract rate.  Since the last report the overspend has reduced by £1.292m
mainly due to the ongoing review and scrutiny of third party payments. 
5.5. Transfer Payments - £0.325m overspend 
This forecast overspend arises within Adult Services due to a projected
increase to the provision for bad debts, based on current outstanding debt
levels. 
5.6. Income - £0.085m over-recovery 
Adult Services is currently reporting an expected over-recovery on income
from community alarms due to an increase in the number of service users;
this offsets community alarm contractual increases. The projected over-
recovery also relates to funds received for new charging orders registered so
far during 2024/25, and also new out-of-area placements within our care
homes allowing us to recover additional income.
_________________________________________________________

Page 4

6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as budget virement. 
Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and Resources
for submission to the relevant policy board for approval. 
6.2. The following budget adjustments are the allocation of centrally-held and
reserve budgets, and are therefore for noting only: 
Objective Heading Subjective Heading  Amount
(£m)
Reason
Adult Services Employees 0.350 Pay award inflation 24/25
transferred from centrally-
held budgets
Chief Executive’s
Service Employees  0.155 
Chief Executive’s
Service
Supplies and
Services 0.139
Pay award inflation 24/25 
for OneRen transferred from
centrally-held budgets
Chief Executive’s
Service Transfer Payments 0.066
Fairer Renfrewshire project
transferred from ringfenced
reserves
_________________________________________________________
7. Capital Budget Projection - break even position by 31 March 2025 
7.1. The Capital Investment Programme 2024/25 to 2028/29 was approved by the
Council on 29 February 2024. The Leadership Board approved capital spend
for 2024/25 was £28.034m. 
7.2. The in-year Capital budget is forecast to break even by 31 March 2025
however, this will be monitored as the projects progress. Further details of the
programme can be found in the Capital Monitoring report at Appendix 2. 
7.3. Budget adjustments totalling £3.391m since Period 8 have taken place
between years to reflect revised programming of capital projects. The revised
capital spend for 2024/25 is £24.643m, and details of these adjustments are
as follows:

Page 5

Capital Budget Adjustments
Project Amount
(£m)
Reason
GAIA Regeneration (3.391) Reprofiled from 2024/25 to 2025/26
to reflect expected cash flow timings.
Total (3.391) 
Implications of the Report
1. Financial 
The projected budget outturn position for the Leadership Revenue budget is an
overspend of £3.618m (2.8%) at 31 March 2025.  Income and expenditure will
continue to be monitored closely for the rest of the financial year and as far as
possible, steps will be taken by services to mitigate any overspend.  
The projected outturn position for the Leadership Capital budget is break even,
after the adjustments outlined at section 7.     
2. HR & Organisational Development 
None directly arising from this report. 
3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe 
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes

Page 6

4. Legal 
There are no direct implications arising from the recommendations in this
report. 
5. Property/Assets 
The capital expenditure noted in this report will result in new assets (City Deal),
regeneration (GAIA and AMIDS) and refurbishment and improvement of leisure
and culture assets. 
6. Information Technology 
While ICT assets and revenue costs are included within these reported
budgets, there are no direct implications arising from the recommendations in
this report. 
7. Equality & Human Rights 
While certain areas of spend may impact on particular groups, any such impact
would be assessed prior to the spend being incurred, therefore there are no
direct implications arising from the recommendations in this report. 
8. Health & Safety 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets, which may
in some cases rectify health and safety issues. 
9. Procurement 
While Procurement is a key consideration prior to the Council incurring any
revenue or capital spend, there are no direct implications arising from the
recommendations in this report. 
10. Risk 
The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this report 
12. Cosla Policy Position 
There are no direct implications arising from the recommendations in this
report.

Page 7

13. Children’s Rights 
There are no direct implications arising from the recommendations in this
report. 
14. Climate Change 
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report. 
_________________________________________________________ 
List of Background Papers
Revenue Budget and Council Tax 2024/25, Council, 29 February 2024.
2024-25 Delegated Health and Social Care Budget, Renfrewshire Integration Joint
Board, 22 March 2024
Non-Housing Capital Investment Programme, Prudential Framework and Treasury
Management Strategy, and Capital Strategy 2024/25 – 2028/29, Council, 29
February 2024.
___________________________________________________________________ 
Authors:  Revenue - Valerie Howie, Finance Business Partner / Alison Burns,
Corporate Finance Manager
Capital – Geoff Borland, Finance Manager

Page 8

No embedded text on this page.

Page 9

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 7 January 2025                  
POLICY BOARD :  LEADERSHIP BOARD                  
Objective Summary
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Adult Services 106,460 350 106,810 110,476 (3,666) (3.4%) (4,643) 977
Chief Executive's Service 20,127 360 20,487 20,439 48 0.2% 35 13
NET EXPENDITURE 126,587 710 127,297 130,915 (3,618) (2.8%) (4,608) 990                  
Subjective Summary
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Employees 41,672 2,294 43,966 42,407 1,559 3.5% 1,712 (153)
Premises Related 839 1 840 976 (136) (16.2%) (71) (65)
Transport Related 814 0 814 764 50 6.1% 51 (1)
Supplies and Services 18,395 140 18,535 18,556 (21) (0.1%) (122) 101
Third Party Payments 68,585 350 68,935 73,764 (4,829) (7.0%) (6,121) 1,292
Transfer Payments 26,354 364 26,718 27,043 (325) (1.2%) (103) (222)
Support Services 106 1 107 108 (1) (0.9%) 0 (1)
GROSS EXPENDITURE 156,765 3,150 159,915 163,618 (3,703) (2.3%) (4,654) 951
Income (30,178) (2,440) (32,618) (32,703) 85 0.3% 46 39
NET EXPENDITURE 126,587 710 127,297 130,915 (3,618) (2.8%) (4,608) 990

Page 10

Appendix 1 
Objective Summary
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous Projected
Outturn Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Older People 59,444 223 59,667 61,965 (2,298) (3.9%) (2,636) 338
Physical or Sensory Difficulties 14,347 13 14,360 15,086 (726) (5.1%) (824) 98
Learning Difficulties 27,255 98 27,353 27,181 172 0.6% (294) 466
Mental Health Needs 4,697 12 4,709 5,548 (839) (17.8%) (1,020) 181
Addiction Services 717 3 720 694 26 3.6% 131 (105)
NET EXPENDITURE 106,460                    350 106,810 110,476 (3,666) (3.4%)                      (4,643)                    977
Subjective Summary
Annual Budget
at Period 8
Budget
Adjustments
Revised Annual
Budget at
Period 10
Projected
Outturn
Previous Projected
Outturn Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 38,007 2,140 40,147 38,635 1,512 3.8% 1,673 (161)
Premises Related 456 1 457 593 (136) (29.8%) (70) (66)
Transport Related 813 0 813 763 50 6.2% 51 (1)
Supplies and Services 3,671 1 3,672 3,688 (16) (0.4%) (97) 81
Third Party Payments 68,585 350 68,935 73,764 (4,829) (7.0%) (6,121) 1,292
Transfer Payments 24,389 298 24,687 25,033 (346) (1.4%) (126) (220)
Support Services 74 0 74 75 (1) (1.4%) 1 (2)
GROSS EXPENDITURE 135,995 2,790 138,785 142,551 (3,766) (2.7%)                      (4,689) 923
Income (29,535) (2,440) (31,975) (32,075) 100 0.3% 46 54
NET EXPENDITURE 106,460 350 106,810 110,476 (3,666) (3.4%)                      (4,643)                    977
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 7 January 2025
Budget Variance
(Adverse) or Favourable
POLICY BOARD:  LEADERSHIP BOARD - ADULT SERVICES

Page 11

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 7 January 2025                  
POLICY BOARD:  LEADERSHIP BOARD - CHIEF EXECUTIVE'S SERVICE                  
Objective Summary
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Budget
Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Chief Executive and Management 268 12 280 278 2 0.7% (1) 3
Policy and Commissioning 3,705 147 3,852 3,822 30 0.8% 9 21
Marketing and Communications 2,719 61 2,780 2,764 16 0.6% 27 (11)
City Deal & Infrastructure 29 0 29 29 0 0.0% 0 0
Leisure Services (incl Renfrewshire Leisure) 13,406 140 13,546 13,546 0 0.0% 0 0
NET EXPENDITURE 20,127 360 20,487 20,439 48 0.2% 35 13                  
Subjective Summary
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Budget
Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Employees 3,665 154 3,819 3,772 47 1.2% 39 8
Premises Related 383 0 383 383 0 0.0% (1) 1
Transport Related 1 0 1 1 0 0.0% 0 0
Supplies and Services 14,724 139 14,863 14,868 (5) 0.0% (25) 20
Third Party Payments 0 0 0 0 0 0.0% 0 0
Transfer Payments 1,965 66 2,031 2,010 21 1.0% 23 (2)
Support Services 32 1 33 33 0 0.0% (1) 1
GROSS EXPENDITURE 20,770 360 21,130 21,067 63 0.3% 35 28
Income (643) 0 (643) (628) (15) (2.3%) 0 (15)
NET EXPENDITURE 20,127 360 20,487 20,439 48 0.2% 35 13

Page 12

No embedded text on this page.

Page 13

Appendix 2 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2024 2024-25 since previous 2024-25 2024-25 Budget Outurn
Project Title Board report to 31-Mar-29 to 31-Mar-29
£000 £000 £000 £000 £000 £000 £000
LEISURE SERVICES
Artificial Pitches Fund 0 800 0 800 800 0 0% 800 800 0 0%
Community Halls Refurbishment 24,920 162 0 162 162 0 0% 25,751 25,751 0 0%
Linwood Running Track at On-X 4 450 0 450 450 0 0% 454 454 0 0%
Lagoon Internal Play Centre 0 0 0 0 0 0 0% 1,000 1,000 0 0%
Total Leisure Services 24,924 1,412 0 1,412 1,412 0 0% 28,005 28,005 0 0%
CHIEF EXECUTIVES
City Deal Projects
Glasgow Airport Investment Area 40,849 2,215 0 2,215 2,215 0 0% 43,064 43,064 0 0%
Clyde Waterfront & Renfrew Riverside 98,513 19,261 0 19,261 19,261 0 0% 117,824 117,824 0 0%
Airport Access 2,934 0 0 0 0 0 0% 141,992 141,992 0 0%
Economic Development
GAIA Regeneration 0 3,391 (3,391) 0 0 0 0% 3,391 3,391 0 0%
AMIDS: Public Realm Phase 1 Netheron Square 3,808 126 0 126 126 0 0% 3,933 3,933 0 0%
AMIDS: District Heating Network 6,783 311 0 311 311 0 0% 7,093 7,093 0 0%
AMIDS: South 5,432 1,318 0 1,318 1,318 0 0% 43,098 43,098 0 0%
Total Chief Executives 158,319 26,622 (3,391) 23,231 23,231 0 0% 360,395 360,395 0 0%
TOTAL LEADERSHIP BOARD 183,243 28,034 (3,391) 24,643 24,643 0 0% 388,400 388,400 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 7th January 2025
POLICY BOARD: LEADERSHIP
Current Year 2024-25 Full Programme - All years
Budget Variance
(Adverse) or
Favourable
Budget Variance
(Adverse) or
Favourable