ARGYLL AND BUTE COUNCIL       OBAN LORN AND ISLES
AREA COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH      14 JUNE 2023 
GIBRALTAR STREET PUBLIC REALM PROJECT - UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to update the Oban, Lorn and the Isles Area
Committee on the Gibraltar Street public realm project. 
1.2 Argyll and Bute Council agreed to allocate £250,000 of Place Based Investment
(PBI) Programme Funding to Gibraltar Street, Oban to enhance the public realm
and improve access to Oban Town Centre given the function of this space as a
key pedestrian thoroughfare linking a key centre of retail to the town centre. 
1.3 It was agreed at Oban, Lorn and Isles Area Committee in March 2023 that officers
progress with the resurfacing option and report back to Committee in June 2023
with a progress report. 
RECOMMENDATIONS 
It is recommended that the Oban, Lorn and the Isles Area Committee: 
 Agree to endorse the proposed approach for this project including that
construction will take place within the autumn/winter period.

Page 2

ARGYLL AND BUTE COUNCIL       OBAN LORN AND ISLES
AREA COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH    14 JUNE 2023 
GIBRALTAR STREET PUBLIC REALM PROJECT - UPDATE 
2.0 INTRODUCTION 
2.1 The purpose of this report is to update Oban, Lorn and the Isles Area Committee
on the Gibraltar Street public realm project.
2.2 On the 12th August 2021, Argyll and Bute Council agreed to allocate £250,000 of
Place Based Investment (PBI) Programme Funding to Gibraltar Street, Oban to
enhance the public realm and improve access to Oban town centre.  
2.3  It was agreed at Oban, Lorn and Isles Area Committee in March 2023 that officers
progress with the resurfacing option and will report back to Committee in June
2023. 
3.0 RECOMMENDATIONS 
It is recommended that the Oban, Lorn and the Isles Area Committee: 
3.1 Agree to endorse the proposed approach for this project including that
construction will take place within the autumn/winter period. 
4.0 DETAIL 
4.1 On 12th August 2021, Argyll and Bute Council agreed to allocate £250,000 of
Place Based Investment (PBI) Programme funding to Gibraltar Street, Oban to
enhance the public realm and improve the access to Oban town centre. The total
budget for the project is £250,000.

Page 3

4.2 Roads and Infrastructure colleagues are currently drawing up a full cost
breakdown to replace the existing paviours with the proposal being to use similar
paviours to those used on Combie Street; repairs to steps; and installation of new
lighting. 
4.3  Officers will procure bespoke high quality street furniture, consisting of benches,
planter and signage.  
4.4 The works will take place within the autumn/winter period to minimise disruption
for businesses by avoiding the busy summer season. 
4.5 It is anticipated that works will be delivered within the existing budget.
5.0 CONCLUSION
5.1 The purpose of this report is to update Oban, Lorn and the Isles Area Committee
on the Gibraltar Street public realm project.
6.0 IMPLICATIONS
6.1 Policy – the works would support Oban Town Centre which in turn will support
the overarching objective and long term outcomes of the Council’s Corporate
Plan, Argyll and Bute Outcome Improvement Plan, the Local Development Plan
and the Economic Strategy. Capital works must be in line with the Place Based
Investment Programme criteria.
6.2 Financial - £250,000 of Place Based Investment funding has been allocated to
the project. Budget remaining for construction works is £216,000. 
6.3  Legal – None.
6.4  HR – None.
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – None. 
6.5.2   Socio-economic Duty – The project supports local economy and
community through place-based regeneration activity. 
6.5.3  Islands - None.
6.6 Climate Change – Construction works undertaken will result in carbon emission
although it is anticipated that these will be restricted to the construction period.
The works are to a key pedestrian thouroughfare that links the town centre to
the adjacent retail park and carpark. 
6.7 Risk – Project implementation needs to be keep within the available budget.
6.8  Customer Service – None. 
Kirsty Flanagan
Executive Director with responsibility for Development and Economic Growth

Page 4

Policy Lead for Strategic Development, Councillor Robin Currie
4 May 2023                                                  
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 