Page 1

___________________________________________________________________
To: Infrastructure Land & Environment Policy Board 
On: 24 May 2023
___________________________________________________________________
Report by:   Chief Executive
___________________________________________________________________
Heading:  Robertson Centre, 16 Glasgow Road, Paisley, PA1 3QG 
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek approval to declare Robertson Centre,
Paisley surplus to operational requirements and to instruct the marketing for sale
of the buildings and site. 
1.2 The building and associated car parking are located at 16 Glasgow Road,
Paisley, in an area of mixed use, as per the attached plan in Appendix 1.
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Infrastructure Land & Environment Policy Board
declares that the buildings and site, as indicated within Appendix 1 attached, are
surplus to operational requirements to enable the marketing for sale of the
buildings and site.
_________________________________________________________
3. Background
3.1 The Robertson Centre is a two storey building of traditional construction, built in
1923 as the headquarters for the Renfrewshire Education Authority.  The building
was refurbished in 2010 and has been leased out since 2011.  The building is
not listed. 
3.2 The Robertson Centre has been leased to the RVJB (Renfrewshire Valuation
Joint Board) since 2011.

Page 2

The Board will be aware that the RVJB consists of Renfrewshire, East
Renfrewshire and Inverclyde Council’s and is the body responsible for valuing
properties for Council Tax purposes and Non Domestic Rates along with
maintaining the Electoral Roll. Each Council makes a proportionate contribution
to the running costs, with Renfrewshire Council being the lead authority. 
3.3 In November 2018 authority was granted to extend the lease to the RVJB until
March 2024 and alter the area leased from the whole building to the ground floor
only.   
3.4 The area vacated by RVJB on the first floor in 2018 was used to accommodate
One Ren (Renfrewshire Leisure as was) during the period of the Museum’s
project.  Due to the COVID 19 hiatus, the period of use has extended longer than
expected however they will remove from the space by March 2024, sooner if
possible, as the Paisley Museum refurbishment nears completion. 
3.5 It is intended that the lease to RVJB will terminate in March 2024.  There are on
going discussions to accommodate RVJB thereafter within Renfrewshire House
although they are at liberty to consider other locations in any of the relevant
Council areas. 
3.6 Due to changing working practices following the pandemic there is a surplus of
office accommodation at Renfrewshire House resulting in no Council demand for
the vacant space at the Robertson Centre. 
3.7 In order to assist in rationalising Renfrewshire Council’s property holding against
a background of reduced budgets  and in order to generate a capital receipt as
well as attract new investment to the centre of Paisley, it is proposed to declare
the Robertson Centre surplus and market for sale. 
4. Next Steps. 
4.1 A development brief is being prepared for approval in parallel with this report and
this will be considered by the Council’s Planning and Climate Change Policy
Board. This brief will set out expectations in terms of any subsequent proposal
for reuse of the site. 
4.2 Discussion will continue with the RVJB regarding their accommodation within
Renfrewshire House.  It is intended RVJB will be accommodated at the
Robertson Centre until they are accommodated in Renfrewshire House or
elsewhere. 
4.3 Marketing of the Robertson Centre to begin as soon as practically possible in
order that the period it is vacant is kept to a minimum.
___________________________________________________________________
Implications of the Report
1. Financial – Savings on utilities, rates and repairs and maintenance.  Future capital
receipt.

Page 3

2. HR & Organisational Development – None. 
3. Community Planning – None. 
4. Legal – Title search to be completed prior to sale.  Formal termination of lease
to RVJB at end date. 
 
5. Property/Assets – As per this report. 
6. Information Technology – None. 
7. Equality & Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts on
equality groups or potential for infringement of individuals’ human rights have
been identified arising from the recommendations contained in the report
because no groups or individuals have any involvement currently at the property.
If required following implementation, the actual impact of the recommendations
and the mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website.   
8. Health & Safety – None. 
9. Procurement – Not applicable. 
10. Risk – None. 
11. Privacy Impact – Not applicable. 
12. Cosla Policy Position – Not applicable. 
________________________________________________________
List of Background Papers – None. 
___________________________________________________________________ 
Author:           Aileen Johnson; Principal Estates Surveyor; aileen.johnson@renfrewshire.gov.uk;
07483 420781

Page 4