ILE Budget Monitoring Report - Period 10

Renfrewshire Council · 15 March 2023
Back to Infrastructure, Land and Environment Policy Board — 15 March 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

To: Infrastructure, Land and Environment Policy Board
On: 15 March 2023 
Report by:  Director of Finance & Resources and Director of Environment &
Infrastructure
Heading:  Revenue and Capital Budget Monitoring as at 6 January 2023 
1. Summary of Financial Position
1.1. The projected Revenue outturn as at 31 March 2023 for Infrastructure, Land
and Environment is an overspend position of £2.402m (7.3%) against the
revised budget for the year. 
1.2. The projected Capital outturn as at 31 March 2023 for Infrastructure, Land and
Environment is a breakeven position for the year.  
This is summarised over the relevant services in the table below and further analysis is provided in
the Appendices. 
Table 1: Revenue
Division
Revised
Annual
Budget
Projected
Outturn
Budget
Variance
(Adv)/Fav
Budget
Variance  
£000 £000 £000 %
Environment & Infrastructure 32,755  35,157  (2.402) (7.3%) 
Table 2: Capital
Division
Revised
Annual
Budget
Projected
Outturn
Budget
Variance
(Adv)/Fav
Budget
Variance  
£000 £000 £000 %
Environment & Infrastructure 18,416  18,416  0 0.0%

Page 2

2. Recommendations
Members are requested to:
2.1. Note the projected Revenue outturn position as detailed in Table 1 above,
considering that the forecast position is based on best estimates at this time;  
2.2. Note the projected Capital outturn position as detailed in Table 2 above; and
2.3. Note the Revenue and Capital budget adjustments detailed in sections 4 and
6. 
3. Revenue
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £2.402m (7.3% of total budget) for Infrastructure, Land
and Environment. Narrative is provided in the Appendices below to provide
context and explanation to the budget position for service areas 
3.2. The projected costs for this financial year are based on the financial information
available at the time of writing this report, and future projections and outturns
may vary depending on the operational and current market conditions.   
3.3. The forecast financial overview for the Council being reported to Finance,
Resources and Customer Services Board incorporates the overspend position
reflected in this report. The main reasons for the projected outturn position are
indicated below.
3.4. It should also be noted that additional expenditure has been incurred as a result
of the additional tree management work that is currently being carried out by
the Streetscene team and it is the intention that a further detailed report will be
presented to board at a later date providing background information including
the estimated financial costs that may be incurred. 
4. Revenue Budget Adjustments
4.1. The budget adjustments actioned between reporting periods were in the main
in relation to an increase in employee costs budget as a result of the recent pay
award. In addition, a drawdown from reserves was actioned (Environment and
Place (£500k) and Memorial Safety (£360k). 
5. Capital      
5.1. The Capital Investment Programme 2022/23 to 2026/27 was approved by the
Council on 3 March 2022.  
5.2. The Capital Monitoring report at Appendix 2 indicates adjustments in the
approved capital programme of £0.733m, of which £3.215m have occurred

Page 3

since the last board report at Period 8.  This largely reflects updated cash flows
for various projects in 2022/23.
5.3. The projected outturn at 31 March 2023 is a breakeven position. Further detail,
including reasons for significant variances, can be found at Appendix 2. 
6. Capital Budget Adjustments
6.1. Since the last report, budget changes of £3.215m have arisen which reflect the
following:   
Budget Increases in 2022/23 (£0.248m) for grant awarded in the following
projects:
 Flooding (£0.248m) reflecting grant awarded by the Scottish
Government in 2022/23; 
Budget brought forward from 2023/24 into 2022/23 (£0.070m) for the following
projects:
  Bridge Assessment/Strengthening (£0.070m) due to timing of planned
work being accelerated;
Budget reprofiled from 2022/23 into 2023/24 (£3.533m) for the following
projects:
  Roads/Footways Programme (£2.448m) largely as a result of expected
timings of footways programme;
 Vehicle Replacement Programme (£0.085m) to reflect updated delivery
times for vehicles;
 Core Pathways & Cycle Network (£0.064m) for timing of planned work
expected in early 2023/24;
 Park Improvement Programme (£0.063m) for updated cash flows
received for the project;
 Improvements to Outdoor Access (£0.161m) for various sites expected
to complete in early 2023/24;
 Multi Purpose Bins (£0.020m) due to expected delivery dates for
completion of the project;
 Improvement to Cemetery Estate (£0.305m) to reflect expected timing
of tender for planned work at Hawkhead Cemetery;
 Nature Restoration Fund (£0.387m) as planned work is required to be
carried out over the summer months when the weather/climate are in
more favourable conditions.
Budget transfers in 2022/23:

Page 4

 Transfer (£0.200m) from Bridge Strengthening to Renfrew Riverside to
Paisley Town Centre Active Travel Route as described in the Revenue
and Capital Monitoring Report on 31 August 2022. 
Implications of this report 
1.  Financial – The projected budget outturn position for Infrastructure, Land
and Environment Revenue budget is an overspend of £2.402m.   
The projected outturn position for Infrastructure, Land and Environment
Services’ Capital budget is breakeven position. The Capital programme will
continue to be monitored closely for the rest of the financial year. 
2.  HR and Organisational Development - None directly arising from this
report. 
3.  Community/Council Planning - None directly arising from this report.
4.  Legal - None directly arising from this report.
5.  Property/Assets - Capital projects result in lifecycle improvements and
replacements to Roads & footways network and vehicles. 
6.  Information Technology - None directly arising from this report. 
7.  Equality and Human Rights - The recommendations contained within this
report have been assessed in relation to their impact on equalities and
human rights. No negative impacts on equality groups or potential for
infringement of individuals’ human rights have been identified arising from the
recommendations contained in the report because for example it is for noting
only. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website.   
8. Health and Safety - None directly arising from this report. 
9. Procurement - None directly arising from this report. 
10. Risk - The potential risk that the Council will overspend its approved budgets
for the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact- None directly arising from this report.

Page 5

12. 
13.
Cosla Policy Position - N/a. 
Climate Risk - None directly arising from this report.
__________________________________________________________________ 
List of Background Papers 
Revenue Budget and Council Tax Policy Board report, Council 3 March 2022 
Capital Investment Programme 2022/23 to 2026/27, Council 3 March 2022. 
___________________________________________________________________ 
Authors:      Director of Finance & Resources and Director of Environment &
Infrastructure

Page 6

Appendix 1   
Objective Summary
Approved
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Directorate and Service Co-ordination 1,249 7 1,256 1,104 152 12.1% 124 28
Refuse Collection 5,392 381 5,773 7,076 (1,303) (22.6%) (1,689) 386
Household Waste Recycling Centres 768 40 808 932 (124) (15.3%) (68) (56)
Refuse Disposal 7,602 0 7,602 7,467 135 1.8% 715 (580)
Streetscene 6,208 1,089 7,297 7,506 (209) (2.9%) (88) (121)
Sustainability and Place 606 52 658 682 (24) (3.6%) 21 (45)
Fleet Services (105) 55 (50) (121) 71 142.0% (22) 93
Social Transport 1,521 83 1,604 1,467 137 8.5% 121 16
Roads Operations 2,895 81 2,976 3,025 (49) (1.6%) (137) 88
Infrastructure and Assets 1,664 81 1,745 1,975 (230) (13.2%) (115) (115)
Transportation & Development 992 51 1,043 909 134 12.8% 107 27
Parking of Vehicles (1,130) 5 (1,125) (33) (1,092) (97.1%) (1,067) (25)
Strathclyde Partnership for Transport
Requisition
3,168 0 3,168 3,168 0 0.0% 0 0
NET EXPENDITURE 30,830 1,925 32,755 35,157 (2,402) (7.3%) (2,098) (305)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance
(Adverse) or Favourable
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 7

Appendix 1   
Subjective Summary
Approved
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 21,632 1,740 23,372 23,478 (106) (0.5%) (893) 785
Premises Related 1,053 0 1,053 1,446 (393) (37.3%) (413) 20
Transport Related 6,039 16 6,055 7,241 (1,186) (19.6%) (1,165) (21)
Supplies and Services 12,408 18 12,426 13,699 (1,273) (10.2%) (368) (905)
Third Party Payments 3,196 0 3,196 3,227 (31) (1.0%) (28) (3)
Transfer Payments 104 1 105 161 (56) (53.3%) (49) (7)
Support Services 34 0 34 25 9 26.5% 11 (2)
Depreciation and Impairment Losses (300) 0 (300) 0 (300) (100.0%) (300) 0
GROSS EXPENDITURE 44,166 1,775 45,941 49,277 (3,336) (7.3%) (3,205) (133)
Income (13,336) 150 (13,186) (14,120) 934 7.1% 1,107 (173)
NET EXPENDITURE 30,830 1,925 32,755 35,157 (2,402) (7.3%) (2,098) (305)
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 8

Appendix 1   
Service Area 
Refuse Collection
The overspend in the main relates to increased costs relating to fuel costs, bins, caddies and bin liner supplies. Also, due to high
levels of annual leave as a result of the pandemic, additional overtime is being incurred in order to cover this from an
operational perspective. In addition, there has been a reduction in demand for special uplifts from the Housing Service.
Household Waste Recycling Centres The forecast overspend is mainly related to transport related costs as a result of increased fuel prices and external vehicle hires.
Refuse Disposal
The current projected position relates to reduced levels of waste being disposed of and is expected to continue for the
remainder of the financial year, resulting in an underspend on the Clyde Valley Waste contact. In addition, income is expected
to over-recover this financial year due to income for mixed plastics, cans and glass now expected. However, the market is highly
volatile and as a result this will be closely monitored through the remainder of the year. The finance team have been working
closely with the Operational Manager to review the current methods of projecting the tonnages for each of the waste streams.
Streetscene
The current projected overspend within Streetscene largely relates to additional tree management and associated health and
safety issues, such as tree inspections and tree health monitoring, including Ash Dieback and Larch infection activities. It should
be noted that the level of work with regards to the tree management activities being undertaken has increased significantly
and this has been reflected into the revised outturn position. Like other areas within the service, the projected outturn is
showing inflationary pressures in fuel and other supplies and services. This will be closely monitored through the remainder of
the financial year. 
Social Transport  Due to supporting in year projects, the service is receiving additional income. However, it should be noted that this will
monitored throughout the remainder of the financial year and any changes will be reported to future boards. 
Infrastructure and Assets
The current projection reflects an increase in costs associated with electrical power in relation to street lighting and traffic
signals, based on current market trends. In line with other utility costs, this position will be closely monitored for the remainder
of the financial year. 
Parking of Vehicles Off-street parking charges have been reintroduced for a number of months, however on and off street parking income and fine
recovery remain significantly lower than pre-pandemic levels and this is expected to continue for the rest of the financial year.

Page 9

Appendix 2   
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2022* 2022-23 in 2022-23 2022-23 2022-23 Budget Outurn
Project Title to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
ENVIRONMENT & INFRASTRUCTURE
Cycling, Walking & Safer Routes 0 785 432 1,217 1,217 0 0% 1,467 1,467 0 0%
Roads/Footways Upgrade Programme 15,584 11,068 (2,476) 8,592 8,592 0 0% 39,180 39,180 0 0%
Safe Road Crossing 59 0 191 191 191 0 0% 250 250 0 0%
Vehicle Replacement Programme 0 2,257 1 2,258 2,258 0 0% 2,492 2,492 0 0%
Bridge Assessment/Strengthening 0 481 (342) 139 139 0 0% 320 320 0 0%
Lighting Columns Replacement 0 560 404 964 964 0 0% 964 964 0 0%
Traffic Management 0 100 83 183 183 0 0% 183 183 0 0%
Core pathways & cycle network 62 138 (64) 74 74 0 0% 200 200 0 0%
Parks Improvement Programme 2,142 63 34 97 97 0 0% 2,302 2,302 0 0%
Improvements to Outdoor Access and Play Area Programme 264 1,100 349 1,449 1,449 0 0% 1,873 1,873 0 0%
Multi Pupose Bins 60 20 (20) 0 0 0 0% 80 80 0 0%
Improvements to Cemetery Estate 1,220 141 (126) 15 15 0 0% 1,541 1,541 0 0%
Underwood Depot - Workshop Improvements 320 0 2 2 2 0 0% 322 322 0 0%
Clyde Mission Fund - Renfrew Riverside to Paisley TC
Active Travel Route 33 970 232 1,202 1,202 0 0% 1,235 1,235 0 0%
Renewal of Play Parks 0 0 158 158 158 0 0% 1,694 1,694 0 0%
Flooding 0 0 248 248 248 0 0% 248 248 0 0%
Nature Restoration Fund 1 0 221 221 221 0 0% 609 609 0 0%
Recycle Improvement Fund 0 0 346 346 346 0 0% 346 346 0 0%
Strathclyde Partnership Transport 0 0 1,060 1,060 1,060 0 0% 1,060 1,060 0 0%
TOTAL INFRASTRUCTURE, LAND & ENVIRONMENT
BOARD 19,745 17,683 733 18,416 18,416 0 0% 56,366 56,366 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 6th January 2023
POLICY BOARD: INFRASTRUCURE, LAND & ENVIRONMENT
Current Year 2022-23 Full Programme - All years