Democracy Spraffa

8 - Houston Village Hall

Renfrewshire Council · 25 January 2023
Back to Infrastructure, Land and Environment Policy Board — 25 January 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Infrastructure, Land & Environment Policy Board
On: 25 January 2023
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Houston Village Hall
___________________________________________________________________
1. Summary 
1.1 This report seeks Board approval to declare Houston Village Hall a surplus asset
to allow it to be advertised for sale on the open market. 
2. Recommendations 
2.1 It is recommended that the Board: 
2.2 Declare Houston Village Hall surplus to requirements and authorise the Head of
Economy & Development to advertise the property for sale on the open market. 
2.3 Note that the Planning & Climate Change Board approved a development brief
for this property on 1st November 2022. The sale of this property will be
progressed subject to the approval of a development brief.
_________________________________________________________
3. Background 
3.1 Houston Village Hall is a 2 storey traditional sandstone building from the late 19th
century, with a small rear brick extension from the 1950’s/1960’s. As well as a
main hall on the upper floor, it comprises various smaller meeting rooms, and
appropriate toilet and kitchen facilities. It was tenanted by the Church of
Nazerene from 1st June 2011 until they decided to end the lease on 30th April
2022.   
3.2 During their tenancy, the Church sub-leased both the main hall and the smaller
rooms to a variety of local community groups and organisations.

Page 2

Following the expiry of the head lease, most of these sub-tenants were able to
find alternative premises with the assistance of OneRen. Grants Music School
were unable to find alternative premises initially therefore a 2 month short term
licence to occupy was granted to enable them more of an opportunity to secure
other premises, which they now have. The Hall is now unoccupied. 
3.3 A condition survey of this building was undertaken in 2010 by Drivers Jonas
Deloitte. The recommendation at that time was that the Village Hall required
approximately £180,000 of investment over a 20 year period (from 2010) to
remain in a good condition and fit for occupation. The Church of Nazerene as
tenants were only able to carry out basic maintenance. 
3.4 The investment required in the property makes Community Asset Transfer a
difficult route for eligible groups. The music school initially considered this but
rejected on cost grounds.  There have been no other requests forthcoming.
Community facilities are also available in the adjacent Carrick Centre. This has
been leased to Houston Old School Trust since 1994 and the Centre operates
as a facility for community organisations to hold arts events, organise classes
and activities etc. 
3.5 The Council itself does not have dedicated funds available to invest in ensuring
the long term sustainability of the building, and are not aware of any other local
group or organisation that does. The view of officers is that this would be best
achieved by a disposal on the open market, with the benefit of an approved
development brief. 
3.6 In Nov 2022, the Council’s Planning and Climate Change Board approved a
Development Brief for the site.
___________________________________________________________________
Implications of the Report 
1. Financial – None at present. Potential capital receipt if sold. 
2. HR & Organisational Development – None. 
3. Community Planning - 
Jobs and the Economy – To ensure the long term sustainability of the building.  
4. Legal – None at Present.  
5. Property/Assets – As per report. 
6. Information Technology – None. 
7. Equality & Human Rights 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights.

Page 3

No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. Required following implementation,
the actual impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be published
on the Council’s website. 
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – None. 
11. Privacy Impact – None. 
12. Cosla Policy Position – Not Applicable.
_________________________________________________________
List of Background Papers 
(a)  Not Applicable.
___________________________________________________________________
Author:          andrew.smith@renfrewshire.gov.uk

Page 4

VILLAGE HALL
School
Wester
Dunira
The
Rackets
Hall
The Manse
2
Ardenlee
Rowantree
Kingslea Cottage
West Manse
Lamorna
Houston
Cottage
Yonderton
Rosemount
Shaw
Place
Houston
Ty-Mawr
1
7
7
Kersmakin
Shakeston
FOUR WINDINGS
Langcroft
10
Barrfield
Village Hall
Cottage
Killellan
Carrick Centre
Meltham
8
House
Kilmory
MAIN  
STREET
VILLAGE HALL, MAIN STREET, HOUSTON
REPORT PLAN
N
E
S
W
E3290
JW
1:1250
OCT 2022
CHIEF EXECUTIVE'S SERVICE
DATE
TITLE
SCALE
ASSET & ESTATES SECTION
All rights reserved.  Ordnance Survey Licence number 100023417.
Reproduced by permission of Ordnance Survey on behalf of HMSO.  © Crown copyright and database right 2022.
SHEET SIZE - A4
DRAWN BY
DRAWING No. Renfrewshire
Council