To:  INFRASTRUCTURE, LAND AND ENVIRONMENT POLICY BOARD 
On:  31 AUGUST 2022 
Report by: DIRECTOR OF ENVIRONMENT & INFRASTRUCTURE 
Heading: WINTER MAINTENANCE AND SEVERE WEATHER PLAN 2022 – 2027 
1. Summary 
1.1 This report details the Council’s Winter Maintenance and Severe Weather Plan for 2022
– 2027 and reflect the preparations and operational arrangements for the 2022/23
winter period for ensuring Renfrewshire’s road network, footpaths and schools are
accessible during the winter, to support the economy and connecting people with jobs,
learning and social needs.   
1.2 The Winter Maintenance and Severe Weather Plan sets out the preventative and
reactive activities that happen over the winter period.  The Plan also details the
Council’s approach to incidents of excessive rainfall which can give rise to flooding
events in Renfrewshire. 
1.3 As part of the Plan, a review of the Council’s Winter Maintenance Activities has been
carried out, including the reciprocal arrangements that exist between Renfrewshire
Council and our neighbouring authorities. 
1.4 Recognising the potential impacts Covid-19 may continue to have on our workforce and
the potential for impacts on our resilience, a mutual aid protocol has been agreed
between the 9 Glasgow City Region authorities. The mutual aid arrangement
recognises the importance of collaborative working and ensures that arrangements are
in place for authorities to support each other during any periods whereby operational
activities may be impacted. 
1.5 The Plan has been developed taking into account the experience gained from the
conditions of previous winters and recent developments in winter service best practice

Page 2

to ensure coordination and consistency of the response provided by Environment &
Infrastructure services. 
1.6 Although a 5 year Plan, the Service will provide regular progress updates to the Policy
Board through the Operational Performance reports and should there be any significant
changes required to the Plan a revised version will be submitted to the Policy Board for
approval. 
2. Recommendations
2.1  It is recommended that the Infrastructure, Land and Environment Policy Board
approves the Winter Maintenance and Severe Weather Plan 2022 – 2027, as set out at
Appendix 1 to this report. 
3. Background 
3.1 Renfrewshire Council has a statutory obligation under section 34 of the Roads
(Scotland) Act 1984 to take such steps as it considers reasonable to prevent snow and
ice endangering the safe passage of pedestrians and vehicles over public roads.  This
applies to adopted carriageways, footways, footpaths and pedestrian precincts for
which the Council is responsible. The official winter period is considered to be the
beginning of October to the end of April. 
3.2 The Winter Maintenance and Severe Weather Plan sets out the Council’s duties and
responsibilities with regards to our response to periods of adverse weather in
Renfrewshire.  The objective of the plan is to: 
• Allow the safe passage of vehicles and pedestrians,  
• Minimise delays caused by winter weather, 
• Ensure that all road operations are carried out safely, and
• Ensure that appropriate proactive and reactive maintenance arrangements are in
place to minimise disruption to our communities. 
3.3 The plan is not exhaustive and does not cater for every unique set of weather
conditions, however it provides a framework for operational responsibilities whilst still
providing flexibility in the response to severe weather incidents. 
Implications of the Report 
1. Financial – Met from within existing resources 
2. HR & Organisational Development – None 
3. Community / Council Planning 
Creating a sustainable Renfrewshire for all to enjoy – The Winter Maintenance Plan
aims to ensure that pedestrians and motorists in Renfrewshire are protected during

Page 3

periods of adverse weather minimising disruption and ensuring all road operations are
carried out safely. 
4. Legal – None. 
5. Property/Assets – None 
6. Information Technology – None.   
7. Equality & Human Rights - The recommendations contained within this report have
been assessed in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the report. If
required following implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the assessment
will be published on the Council’s website 
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – None. 
11. Privacy Impact – None. 
12. CoSLA Policy Position – none 
13. Climate Risk – none 
List of Background Papers: None   
Author:  Gavin Hutton, Head of Operations & Infrastructure 
e-mail:   gavin.hutton@renfrewshire.gov.uk

Page 4

Renfrewshire Council
Winter Maintenance and
Severe Weather Plan
2022 - 2027

Page 5

Contents
1. Policies and Responsibilities
2. Route Planning & Treatment
3. Weather Forecasting & Deployment
4. Organisational Response Arrangements
5. Communications
6. Flooding Incidents Response
Appendix 1 – Arrangements with adjacent
Local Authorities
Appendix 2 – Grit Bin Policy and
Arrangements

Page 6

No embedded text on this page.

Page 7

1. Policies and
Responsibilities
1.1 Statutory Requirements
• Under Section 34 of the Roads (Scotland) Act 1984, the Council has a statutory obligation to take steps as it considers reasonable, to prevent snow and ice endangering the safe passage of pedestrians and vehicles over public roads.
• This applies to all adopted carriageways, footpaths, footways and pedestrian areas for which the Council is responsible for
• This Winter Maintenance and Severe Weather Plan is prepared in the context that not every carriageway and footway will be treated during every period of adverse weather, however a risk based approach is adopted which demonstrates that we are taking reasonable steps to keep the public safe during winter periods.
• The aims of the Winter Maintenance and Severe Weather Plan are to ;
• Ensure the necessary preparations and responses are deployed, and
• Protect the public and minimise disruption to the road network.
1.2 Roles and Responsibilities
• The strategic responsibility for the effective delivery of the Winter Maintenance and Severe Weather Plan sits with the Head of Operations & Infrastructure.
• The operational preparations and implementation of the Plan are overseen by the management team within Infrastructure and Transportation.
• The operational responsibilities include;
• Reviewing and implementing the Winter Maintenance and Severe Weather Plan,
• Implementing reciprocal arrangements with neighbouring authorities,
• Designating the priority routes for treatment during periods of adverse weather,
• Ensuring that the Winter Maintenance Supervisors are supported with the correct resources to deliver the Winter Maintenance service effectively

Page 8

1. Policies and
Responsibilities Cont’d
1.3 Operational Responsibilities
• The Infrastructure and Transportation team are responsible for the
delivery of the Winter Maintenance and Severe Weather Plan, the
duties include but are not limited to:
• Ensuring appropriate arrangements are in place for salt storage
and delivery
• Providing specialist vehicles and equipment throughout the
winter period
• Ensuring all salt spreading equipment is calibrated
• Ensuring all operatives have received appropriate training in
Winter Maintenance activities
• Monitoring all aspects of the Winter Maintenance Service and
maintaining management information on these activities
• Maintaining comprehensive records of all activities undertaken
• Assessing real time information to identify if appropriate
further actions are required during gritting periods
• Carrying out an annual review of the Winter Maintenance and
Severe Weather Plan
• Liaison with relevant stakeholders such as Transport Scotland,
adjacent Local Authorities and Emergency Services
• Publicising contact details to ensure appropriate resilience
arrangements are in place
• Arranging for weather forecasting and monitoring information
to be available throughout the Winter period
• Maintaining a list of suitable contractors with appropriate plant
for snow clearing purposes and deploying these resources as
necessary
• Ensuring vehicles and plant are maintained effectively
throughout the Winter period through liaison with our
Transport Service
• In the case of a severe weather event the service will make
contact with
• The Environment & Infrastructure Resilience Group
• The Council’s Civil Contingencies Service
• The Communications Team, and
• The relevant elected members for the area affected.

Page 9

1. Policies and
Responsibilities Cont’d
1.4  Decision Making
• The Winter period is classed as being from the beginning
of October to the end of April.
• Operational decisions throughout this period will be
taken by the designated Winter Controller and
implemented by the designated Winter Supervisor.
• Should there be a need to amend instructions, the
Winter Supervisor will liaise with the Winter Controller of
the need to change at the earliest possible opportunity
• Day to day decisions will be made using forecasts from
the weather provider and the road and weather data
from monitoring stations to support decision making.
• On receipt of a weather forecast or update through the
Winter period, the Winter Controller will reach a decision
on action for the next 24hours.
• If treatment is planned a decision record will be produced
which will include the required salt spread rate, including
post salting and/or snow clearance.
• The decision will be distributed to those members of the
Environment & Infrastructure Resilience Group.
• The Council will endeavour to ensure that salt is spread, as
necessary, prior to the formation of ice or the setting of
snow on the priority network.
• When the road surface temperature falls below 1oC with
forecast of freezing conditions and ice forming,
precautionary treating shall take place unless;
• There is enough residual salt on the road to deal with
the expected conditions, or
• The weather forecast information indicates that the
road surface temperature will rise before the roads
could be salted or there will be no period of frost that
could cause icing

Page 10

1. Policies and
Responsibilities Cont’d
1.4 Decision Making Cont’d
• Snow clearance operations will be carried out across the network
as conditions require. The high ground areas of Renfrewshire are
more prone to snowfall and at times may require more localised
treatment.
• The majority of low level snow incidents are dealt with through the
application of rock salt as per standard gritting instructions.
• Where a snowfall is predicted to exceed 100mm will be treated
with repeated applications of rock salt. On occasions where
snowfall is expected to exceed this for a period of time, the use of
ploughs may be required.
• Care is taken when ploughing is deployed to ensure that junctions
or side roads are not blocked as a result of this activity.

Page 11

2. Route
Planning and
Treatment
2.1 Road Network
The Council keeps the road
network operating through
precautionary treatment by
pre-salting roads to reduce
the effect of frost and frozen
conditions.
The road network is currently
split into Primary and
Secondary routes. Planned
pre-gritting is only
undertaken on the Primary
network. The Secondary
network may be treated after
the Primary routes, where
there is time and resources
to cover them, and it is likely
that freezing conditions will
continue.

Page 12

2. Route Planning and Treatment Cont’d
2.2 Treatment Priorities
• The routes for the priority road network have been devised to ensure
efficient coverage of the road network within reasonable timescales.
• When forecast that road surface temperatures will fall below 1oC,
roads will be treated at the discretion of the Winter Controller
• Precautionary treatment is the best method of dealing with both
snow and ice. Salt spread rates are set to the appropriate width of the
carriageway, which may be both lanes of a single carriageway or both
lanes of one side of a dual carriageway. Vehicles will generally travel
in the left hand lane and the spreading pattern will be set to cover
both lanes unless multiple passes are required.
• Sustained low temperatures occur only rarely, however, when this
occurs account is taken of the need to increase the rate of spread of
salt. Below -9oC the action of salt is largely ineffective.

Page 13

2. Route Planning and Treatment Cont’d
2.3 Carriageway Priorities
• The road network has been assessed in terms of priority for treatment in periods of adverse weather.
• The prioritisation of the road network in Renfrewshire has resulted in the development of three different route types for treatment during adverse weather.
• The three route types are:
• Primary Routes – these routes include the strategic road network in Renfrewshire and include main distributor roads and access routes to hospitals, schools and emergency services locations. There are 7 primary routes which cover 54% of Renfrewshire’s road network.
• Secondary Routes – Treatment of secondary routes will only take place during periods of exceptionally poor weather or prolonged periods of freezing. The secondary routes include local distributor roads serving industrial estates and isolated communities of local access roads within communities. There are 7 secondary routes.
• High Ground Routes – On occasions there may be borderline conditions which require an “on the ground” assessment of conditions. In these instances our two high ground patrol routes will be deployed so that the live information can be relayed to the Winter Supervisor.   The high ground routes are part of the primary network but are identified as the areas most at risk from periods of severe snowfall
The Council has published our gritting routes at:
Winter gritting - Renfrewshire Website

Page 14

2. Route Planning and Treatment Cont’d
2.4 Footway Priorities
• The priority footpath network has been identified as;
• Paisley, Johnstone and Renfrew town centre pedestrian areas,
• Routes serving the hospital and health centres,
• Access to schools and community centres, and
• Other high pedestrian usage areas such as sports centres
• The gritting of footways is not done on the same basis as the priority
carriageways. The treatment of the carriageways is the number one priority
and all other activities flow after that.
• The treatment of footways will generally only be considered after freezing
conditions for several days without thaw, however should there be a
significant snow event forecast then precautionary treatment of footways may
be carried out in advance.
• During any snow event focus will solely be on the treatment of the priority
networks, complaints in relation to local or residential areas will only be
considered once the priority road network has been attended to.
2.5 Schools Gritting
• Facilities Management staff at the school will clear snow and grit from the
entrance door of the school to the gate at the entrance to the school grounds.
• During snow or prolonged ice events 100m of footpath either side of the main
entrance gate will be treated. Walking routes to school are not gritted.
• In periods of severe prolonged weather it will not be possible to keep all
entrance paths into schools clear.

Page 15

2. Route Planning and
Treatment Cont’d
2.6 Snow Clearance
• Whilst snow is lying, only the designated priority routes will be ploughed and treated in order to effectively manage the road network in Renfrewshire.
• Once the snowfall has stopped but is still lying the priority routes will continue to be ploughed and treated and as resources become available the secondary routes will be treated.
• Only once the primary and secondary routes have been treated effectively will resources be directed to treat the remaining road network.
2.7 Route and Response Times
• From October to April the Roads Service operates a 24hr service with a dedicated night shift ensuring a quick response to any weather incidents.
• The treatment of the priority routes will commence prior to the onset of the forecast ice, hoar frost or snow where possible.
• The primary routes are designed to be completed within 3 hours of the treatment being instructed.
2.8 Grit Bins
• There are over 540 grit bins sited locally throughout Renfrewshire for Communities and members of the public to access, the location of all grit bins is available on the Council website.
• The criteria for assessment of a grit bin is attached as Appendix B to this document.
• The grit bins are stocked before the winter season commences and restocking requests should be made to the Council’s Customer Contact Centre on 0300 300 300.
• In addition to the 540 grit bins, there are 20 larger community grit bins located throughout Renfrewshire. During periods of severe weather these bins will be prioritised for restocking.
• Maintaining stock in grit bins is a labour intensive manual process and is dependant on available resources. In prolonged periods of adverse weather we may not be able to carry out restocking as our resources will be directed towards treating the priority road network.

Page 16

3. Weather Forecasting &
Deployment
3.1 Forecasting
• To provide a reliable and robust winter
service, the Council have a number of
forecasting tools at our disposal to plan
the best treatment regime throughout
the winter period. These include;
• Weather forecasting – both short
and medium term,
• Road and weather monitoring data,
and
• Actual conditions of the network.
• The Council is a member of the West of
Scotland Local Authority partnership
that receives detailed weather for each
day for the period 1st October to 15th
May each year.
• All road weather forecasts are provided
via an online weather management
system.
• Contact is made directly with the
Winter Controller out of hours to
ensure all decisions are based on the
most up to date information.

Page 17

3. Weather Forecasting
and Deployment Cont’d
3.2 Weather Stations
• There are 4 local weather monitoring stations, which
are also used to provide supporting information for
decision making, these are located at;
• A737 at Howwood,
• B786 Stepends Road,
• B775 Gleniffer Road, and
• East Fulwood at Georgetown Road.
• A range of supporting data is provided through the
weather stations which is available for the Winter
Controllers to review and assess, including;
• Road Surface temperature,
• Air temperature,
• The dew point, which indicates moisture on the
road,
• Precipitation levels and timings,
• Surface information, including level of salt on the
road, and
• Wind speed and humidity.

Page 18

3. Weather Forecasting
and Deployment Cont’d
3.4 Information Sharing and Decision Making
• Weather reports are provided 3 times a day during the
winter period, 5am, 11am and 5pm by the DTN group,
the Councils forecasting provider.
• The weather reports provide an accurate picture of
conditions over the next 36hr period and provides the
confidence levels in the predictions of a range of
hazards including ice, snow, strong winds and rain.
• The Winter Controller will relay this message and the
relevant actions to take to the Winter Supervisor and
those officers who are on the Environment and
Infrastructure Resilience Group. The information will
be shared at 7am, 12pm and 7pm each day.
• All actions taken by the Controller and Supervisor are
logged for peer review to aid continual learning.
• The group coordinator will also decide if the weather
prediction is sufficiently severe that it should be
shared wider with relevant stakeholders.
• During periods of more adverse weather more regular
updates will be provided to the Resilience Group and
thereafter shared more widely within the Council and
with relevant partners.
• Should the predicted conditions vary significantly the
DTN group will contact the Winter Controller
immediately to allow them to take corrective action if
need be.
• The DTN group provide a 24 hour 365 day a year
response service to the Council should any clarification
around weather forecasting be required.

Page 19

4. Organisational
Response Arrangements
4.1 Organisational Responsibilities
• The strategic responsibility for the effective delivery
of the Winter Maintenance and Severe Weather Plan
sits with the Head of Operations & Infrastructure.
• The operational preparations and implementation of
the Plan are overseen by the management team
within Infrastructure and Transportation.
4.2 Winter Controller
• From October to May there is a Winter Controller on
a standby rota each week and available 24/7.
• The Winter Controller is responsible for assessing the
weather conditions and taking decisions on any
required action to mitigate adverse weather.
4.3 Winter Supervisor
• There is a Winter Supervisor on call each week from
October to May, mirroring the shift of the Winter
Controller.
• The Winter Supervisor is responsible for organising
and overseeing the instructions relayed to them by
the Winter Controller.
• The role of the Winter Supervisor is to utilise and
manage all resources under their control, including
plant, labour and materials to effectively treat the
road network.
• It is the responsibility of the Winter Supervisor to
ensure all records are maintained during and
immediately after each gritting shift.

Page 20

No embedded text on this page.

Page 21

4. Organisational
Response Arrangements
Cont’d
4.4 Winter Maintenance Operatives
• During the period September to April, the Council has
a permanent nightshift in place to respond to adverse
weather incidents.
• The primary role of the nightshift is to act on gritting
instructions from the Winter Controller or Supervisor.
• The operatives are responsible for ensuring gritting
activities are carried out in a safe and efficient
manner.
• All personnel involved will be familiar with the
gritting routes, equipment and transport to carry out
their duties.
• Working procedures and training is refreshed on an
annual basis to ensure all personnel are able to carry
out the role safely.
• When the nightshift is not gritting, they will be
responsible for the delivery of other frontline duties
such as streetsweeping, gulley cleaning and road
repairs in suitable locations.
• During the Winter period and especially in severe
weather conditions the resources available will be
supported by additional resources from other Service
areas and/or the use of private contractors.
4.5 Training
• Annual refresher training is carried out by DTN for all
our Winter Controllers and Winter Supervisors and
over the last number of years we have brought in
employees to shadow these roles to build capacity in
the service.
• Prior to the gritting season a “dry run” of the routes
and machinery is carried out to identify any issues
prior to any periods of Winter weather.

Page 22

4. Organisational
Response Arrangements
Cont’d
4.7 Plant, Vehicles & Equipment
4.7.1 Gritting Fleet
• The Council has a fleet which consists of dedicated
gritting vehicles deployed between October and April
and supplements this with a number of vehicles
which can be quickly converted to gritters as
required.
• In addition to the gritting vehicles there are also a
number of tractors and smaller vehicles which can be
fitted with mounted gritters and ploughs to increase
resilience during severe weather.
• All of the gritting operations are delivered from our
Underwood Road Depot and supported by dedicated
provision from our garage over the winter period to
minimise down time of the fleet during Winter.
• All gritting vehicles are calibrated prior to the start of
the Winter period and are recalibrated during the
Winter to ensure salt spreading operations are
effective.
• Our StreetScene colleagues use additional plant
which can be fitted with gritting units in order to
efficiently treat footways
4.7.2 Salt
• The Council uses rock salt for its gritting operations
and stores approximately 4,000 tonnes of salt at
Underwood Road for the start of the Winter season.
• Arrangements are in place with suppliers to ensure
deliveries continue through the Winter period should
the need arise.
• On an average Winter the Council will use
approximately 6,500 tonnes of salt on the road and
footway network.

Page 23

No embedded text on this page.

Page 24

5. Communications
5.1 Communication Arrangements
• The Winter Controller and Winter Supervisor are contactable on 24hrs a
day 7 days a week during the Winter period.. The Winter Controller
copies the Environment & Infrastructure Resilience Group into every
gritting action taken during the Winter period.
• Should there be significantly severe weather circumstances the
Resilience Group coordinator will notify the Council’s Corporate
Communications Team to assess whether wider communications are
required.
• During these periods of significant adverse weather more regular
updates will be communicated with the wider Council and stakeholders.
• Should there be a Red weather incident or a period of weather be severe
enough the Council’s Civil Contingencies Service will assist with the
wider Council response to a particular incident or prolonged period of
severe adverse weather.
• In the case of a Red weather alert, the relevant Senior Officers will
decide whether it is necessary to set up the Councils Incident
Management Team.
• The Council maintains an Emergency Contacts directory which the Civil
Contingencies Team update on a regular basis. The directory has the
relevant contact details of key officers within the Council who could
assist in dealing with a Council wide response.
5.2 Operational Action Logs
• The Winter Controller and Winter Supervisor will ensure the following
records are retained:
• Weather report action,
• Daily gritting logs,
• Weight tickets from each gritting vehicle, and
• A record of any actions taken over and above the identified actions
from the weather report.
5.3 Public Communications
• The Council’s website has a dedicated Winter Service section on the
website that provides relevant information to the public including the
detail of our gritting routes, location of our grit bins and the gritting
tracker to give real time information on gritter locations.
• During particularly prolonged periods of snow and ice or adverse
weather, information will be made available to the public across our
communities using all appropriate communications channels.

Page 25

6. Flooding Incidents
Response
6.1 Flooding Incidents
• As a result of climate change, both the chance and consequence of
flooding are increasing.  As sea levels rise there will be more
frequent and higher storm surges, increased winter rainfall and
more intense summer rainfalls are predicted, adding to the existing
risk.
• Renfrewshire has experienced major flooding events throughout
the years and more recently in 2021. In Renfrewshire flood events
are typically caused by:
• Intense rainfall events,
• Water courses exceeding peak flow capacities,
• Surface water run off from developed areas,
• Lack of capacity in the sewerage system, and
• Tidal influence of the Clyde.
• The aim of this Plan is to ensure an informed and co-ordinated
response to a flooding incident, focussing on the welfare of those
effected, mitigation of property and environmental damage.
6.2 Statutory Responsibilities
• Under Section 18 and 59 of the Flood Risk Management (Scotland)
Act 2009 the Council has a duty to assess bodies of water for the
purpose of ascertaining whether any such body gives rise to a risk
of flooding, and to carry out a schedule of clearance and repair
works to substantially reduce any such risk.
• Local authorities have a duty under the Roads (Scotland) Act 1984
to maintain road drainage systems and to clear roads of flooding.
• The Code of Practice for Well Maintained Highways recommends
that local authorities should ensure drainage assets are maintained
in good working order to reduce the threat and scale of flooding.

Page 26

6. Flooding Incidents
Response Cont’d
6.3 Roles and Responsibilities
• The Council has the overall responsibility to provide an
effective Flood Management Service in accordance
with its duties.  The responsibility for the efficient and
effective delivery of Operational flood management
sits within Environment & Infrastructure. The more
strategic areas of Flooding such as Development
Management and Flood Risk Planning sits within the
Chief Executives Service.
• The Road Operations Team in conjunction with our
Roads Inspectors play a key role in any emergency
response to any flooding alert in terms of preparing,
responding, and recovering from a flooding incident.
• The Council uses a variety of measures to ensure it
fulfils its statutory duties in relation to flood
management. These include:
• Cyclical inspection, cleaning and maintenance of
our 30,000 road gullies,
• Regular cleaning of grids at watercourses,
• Installation and maintenance of flood prevention
schemes, and
• Capital drainage improvements.
6.4 Flooding Incidents
• The Scottish Environment Protection Agency issue two
types of notification of flooding in advance of an event
happening. The first is a Flood Alert, this will highlight
there is a chance of flooding occurring in a larger
geographical area, such as a local authority area. The
other notification is a Flood Warning and this is an
indication of an imminent risk to flooding in more
specific locations.

Page 27

6. Flooding Incidents
Response Cont’d
• Key officers in Environment & Infrastructure are on the SEPA
contact list for when flood alerts are issued. The flood alert
provides a reasonably accurate prediction of timing and severity
of the adverse weather expected.
• When an alert is issued that indicates there will be a severe
rainfall event, officers from Environment & Infrastructure will
immediately instruct the following actions to take place prior to
the event occurring:
• The flood prevention schemes and pumping stations will be
inspected,
• The priority watercourse grids will be cleaned,
• The priority gulley locations where known flooding has
previously occurred will be cleaned,
• Communications will be issued to Elected Members and the
public, and
• River levels monitored where appropriate
• There will be occasions where excessive rainfall events
overwhelm the surface water drainage system and no amount
of clean gullies would help in these instances. Regular liaison
meetings take place with Scottish Water to inform future plans
for upgrades to the combined sewer system to minimise the
impact of such events.
• If a flooding incident occurs out of hours the Roads Stand By
Supervisor will be responsible for co-ordinating resources. 
Resources will initially be directed to priority 1 locations.  These
are locations which historically causes flooding and where there
is a risk of road closures and damage to properties.
• In recent years excessive rainfall events have been occurring on
a more localised basis and as such the response to incidents has
to be flexible to allow resources to be deployed where the need
is required.
• The operational protocols will continue to be reviewed and
amended as required to respond to the changing environment
we continue to operate in.

Page 28

6. Flooding Incidents
Response Cont’d
6.5 Flood Prevention Schemes and Pumping Stations
Renfrew Flood Prevention Scheme
• A dedicated protocol has been developed which includes responsibilities
from a number of service areas. Should there be a tidal warning issued
from SEPA for Renfrew, this operational protocol is activated.
Moredun Flood Prevention Scheme
• A visual check of the grids and the perimeter fencing is carried out
weekly.  In addition to the visual checks, a reservoir engineer inspects this
site annually.  They also advise on embankment safety issues.
Pumping Stations
• There are five pumping stations located at the following locations:
• Collier Street, Johnstone
• Rankine Street, Johnstone
• Linwood Toll, Paisley
• Howie Street, Paisley
• Fingal Road, Renfrew
• These routinely maintained by a specialised contractor and they issue
reports on the maintenance to the Council. The contractor also provides a
dedicated emergency out of hours service to respond to any issues
associated with the pumping stations.

Page 29

6. Flooding Incidents
Response Cont’d
6.6 Role of other agencies
• Whilst local authorities have responsibilities in relation to flooding,
other agencies also have responsibilities for flooding issues.
• The division of responsibilities for flood prevention and watercourse
maintenance, piped water systems, flood warning and flood
emergency response requires co-operation between the respective
agencies involved, principally the local authority, SEPA, Scottish Water
and the emergency services, in order to secure appropriate action
during emergency flood events.
• It is recognised that the responsibility for the protection of property
lies with the property owner, there are a number of useful advice
sources to utilise to protect properties from flooding.
• FloodlineScotland – www.floodlinescotland.org.uk
• Floodline is a free advance warning service for the public and is
operated by the Scottish Environment Protection Agency. Anyone
can access SEPA's live flooding information online, but by
registering a contact number with Floodline, you will get notified
when flooding is likely in your area.
• Scottish Flood Forum – www.scottishfloodforum.org
• The Scottish Flood forum aim to reduce the impact of flooding on
individuals and communities, through providing immediate
support and by establishing a network of community resilience
groups in flood risk areas to equip communities to cope with the
impactsand threat of flooding.
• The forum provide advice and information to individuals to help
protect their home from flooding or, if the worst has happened, to
recover from flooding.

Page 30

Appendix A – Arrangements
with Adjacent Local
Authorities and Others
1.    Arrangements with Adjacent Local Authorities
At Boundary with Glasgow City Council, Renfrewshire Council treats:
• Hurlet Rd (A726) from the boundary to Glasgow Rd (Hurlet
Junction),
• Paisley Road West (A761) from the boundary to Glasgow Road,
• Hillington Road (A736) at Queen Elizabeth Roundabout,
• Penilee Road at the junction of Corse Road, and
• Glasgow Road (A8) and Kingsinch Road at Hillington Rd / Govan Rd
Roundabout.
At Boundary with East Renfrewshire Council, Renfrewshire Council
treats:
• Gleniffer Rd to CaplawRd (joint responsibility),
• CaplawRd from Seargentlaw Rd to Gleniffer Rd (joint responsibility),
• Grahamston Rd to Barrhead Rd, Paisley, and
• Caplethill Rd to Grahamston Road, Barrhead (Cross Stobs);  Roebank
Rd (B776) to Hall of Caldwell (B775).
At Boundary with North Ayrshire Council, Renfrewshire Council treats:
• Kilbirnie Rd (A760) to Kerse Rd.  
At Boundary with Inverclyde Council, Renfrewshire Council treats:
• Kilmacolm Rd (A761) to CraigendsRoad and Stepends Road (B786)
to Torr Rd, and
• Inverclyde Council treats:  Old Greenock Rd, Finlaystone Rd to the
Burnside Smithy.
2. Arrangements with Others
• During periods of adverse weather the Council implements
arrangements it has with local farmers for the clearance and
treatment of the rural road network.
• The contact details for each of the farmers is updated on an annual
basis prior to the commencement of the Winter period.

Page 31

No embedded text on this page.

Page 32

Appendix B – Grit Bin Locations
and assessment criteria
1.    Grit Bin Locations
• Renfrewshire Council provides grit bins for residents and communities to
assist themselves and their communities.
• There are 540 grit bins located throughout Renfrewshire.  These can be
located through the attached link:
http://www.renfrewshire.gov.uk/article/2236/priority-roads-for-grtting
• In addition to the standard 540 grit bins a number of larger Community
Grit Bins are located across Renfrewshire at central locations for the
community to access and help them to self-serve during periods of
adverse weather. These locations are detailed in the table below:
Bishopton Community Centre Car Park.
Bridge of Weir Livery Walk Car Park
Brookfield Albert Drive
Crosslee Car park at Crosslee shops.
Elderslie Car Park at Village Hall
Erskine 1. Household Waste Recycling Centre, Barrhill Road, Erskine
2. Car Park to the rear of the Library.
Houston Carrick Centre Car Park
Howwood Village Hall Car Park
Inchinnan Playing Fields Car Park opposite the Primary School
Johnstone 1. Household Waste Recycling Centre, Miller Street, Johnstone 
2. Car Park of Floor Street Industrial Estate
Kilbarchan Adjacent to clock tower at Steeple Hall on Steeple Street
Langbank Footpath adjacent to tennis courts
Linwood Household Waste Recycling Centre, Middleton Road, Linwood.
Lochwinnoch McKillop Centre Car Park
Paisley 1. Household Waste Recycling Centre, Underwood Road, Paisley
2. Glenburn Community Centre Car Park
Renfrew 1. Household Waste Recycling Centre, Haining Road, Renfrew
2. Car Park of Kirklandneuk Community Centre

Page 33

Appendix B – Grit Bin Locations
and assessment criteria
2.    Grit Bin Assessment
• Requests for new grit bins will be received through the Customer Service
Centre and will be assessed against the criteria outlined below.
• All current grit bins are being retrospectively assessed against this
criteria to identify locations where grit bins have been provided where
not required or any areas where there is an over provision.
Description of
gradients
Steep
Moderate
Slight / level
Description of bends Sharp / many
Moderate / few
Slight / straight
Traffic type Domestic / housing estate
Industrial
Rural
Traffic flow Heavy
Light
Pedestrian activity Elderly / less mobile
Heavy (town / large village)
Light (small village)
On a treated route Yes – Primary
Yes – Secondary
No
Salt bin nearby Yes
No
Proximity of health
centre/surgery
Near / distant
Other important local
services – pharmacy,
schools, community
centre, shops etc
Near
Distant
Bus route Untreated
Treated
Accident history Yes
No