Play Park Engagement - Update Report

Argyll and Bute Council · 13 September 2023
Back to Oban Lorn & The Isles Area Committee — 13 September 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL                   OBAN, LORN AND THE
ISLES AREA COMMITTEE 
ROAD AND INFRASTRUCTURE                    SEPTEMBER 2023
SERVICES                     
PLAY PARK ENGAGEMENT – UPDATE REPORT 
1.0 EXECUTIVE SUMMARY 
1.1 In August 2022, the Scottish Government confirmed a full 5 year funding package
to all Scottish Local Authorities from 2020/21 through to 2025/26.  Argyll and Bute
Council will receive a total of £938k for Play Park funding. 
1.2 In December 2022, the Environment, Development and Infrastructure Committee
noted the priority list of play parks in each area, based on inspections and
feedback from Youth Forums.  A copy of this can be found in the following link:- 
Environment, Development and Infrastructure Committee 1 December 2022 
1.3 The March 2023 Environment, Development and Infrastructure Committee
agreed a process for further engagement with other groups, including youth
forums and relevant Community Councils.     
1.4 This report outlines the response from the engagement exercise and seeks
agreement for spend on Tobermory Play Park.   
RECOMMENDATIONS 
It is recommended that the Oban, Lorn and the Isles Area Committee: 
 Note the breakdown of engagement and consultation responses in each
area with the majority of responses focussing on new/replacement
equipment; 
 Agree the relevant spend on the Tobermory Play Park.

Page 2

ARGYLL AND BUTE COUNCIL                   OBAN, LORN AND THE
ISLES AREA COMMITTEE 
ROAD AND INFRASTRUCTURE                    SEPTEMBER 2023
SERVICES                     
PLAY PARK ENGAGEMENT – UPDATE REPORT   
2.0 INTRODUCTION 
2.1 This report provides an update to the Play Park engagement responses for the
Oban, Lorn and the Isles Area Committee. 
3.0 RECOMMENDATIONS 
3.1  It is recommended that the Oban, Lorn and the Isles Area Committee: 
 Note the breakdown of engagement and consultation responses in each
area with the majority of responses focussing on new/replacement
equipment; 
 Agree the relevant spend on the Tobermory Play Park.   
4.0  DETAIL 
4.1  In August 2022, the Scottish Government confirmed a full 5 year funding package
to all Scottish Local Authorities from 2020/21 through to 2025/26.  Argyll and Bute
Council will receive a total of £938k for Play Park funding. 
4.2 The below table highlights the funding split for each area as well as the number   
of play parks, as per previous Environment, Development and Infrastructure
Committee agreement, the funding was an indicative £33,500 per play park which,
when the engagement process has been fully reviewed, this can be amended by
the local Area Committee.  
Area Number of Play
Parks
Funding Total
Helensburgh and
Lomond 
11 £368,500
Mid Argyll, Kintyre and
the Islands
11 £368,500
Bute and Cowal  5 £167,500
Oban Lorn and the Isles 1 £33,500

Page 3

TOTAL  28 £938,000 
4.3 The March 2023 EDI Committee agreed a process for further engagement with
other groups, including youth forums and relevant Community Councils. 
4.4 Area Committee Business days with Elected members took place in 2022. A full
engagement process has since taken place and the online engagement for adults
and youths closed on Friday 14 July 2023 with the following update:- 
 1054 Adult Responses
 408 Youth Responses 
This was a remarkable return for the play park engagement process and
highlights the depth of feeling play parks have on our communities who are clearly
keen to express their views. 
4.5 The responses were broken down as follows: 
A Total of 1054 adult responses: 
Area New/Replacement
Equipment
Health and Safety Access for ALL
Bute and
Cowal
146 35 64
Helensburgh
and Lomond
226 74 54
Mid Argyll,
Kintyre and
Islands
215 40 37
Oban Lorn
and the Isles
9 3 4 
Out of the 1054 adult responses there were a total of 147 which were void either
due to referring to a non-council play park or being unable to assess the correct
location from the comments.    
A Total of 408 Youth Responses: 
Area New/Replacement
Equipment
Health and Safety Access for ALL
Bute and
Cowal
68 7 5
Helensburgh
and Lomond
101 7 4 (Plus 2 don’t
know)
Mid Argyll,
Kintyre and
Islands
129 5 8 (plus 1 Don’t
Know)

Page 4

Oban Lorn
and the Isles
1 0 0 
Out of the 408 young person responses there were a total of 70 which were void
either due to referring to a non-council play park or being unable to assess the
correct location from the comments. 
A note of the responses to the engagement priorities from the Oban, Lorn and
the Isles community is attached at Appendix 1 of this report. 
4.6  The Council now requires to consider what equipment is needed for each play
park.     
4.7 The costings of equipment only:- 
 Swings - £6500 + VAT
 Spring Seesaw - £2750 + VAT
 Climbing Net - £11,250.00 + VAT
 Wheel Chair Accessible Roundabout - £5000-£12000 +VAT 
The funding for the Oban, Lorn and the Isles area to cover its 1 play park is
£33,500. 
4.8  The timeline for play parks is noted as follows:-   
ACTION  TIMESCALE 
Engagement with Community Councils and
Education Department 
Commenced March-May 2023 
Engagement with Disability Forums  Expected to commence
Autumn/Winter 2023
Area Business Days to agree how funding
will be spent 
Autumn (prior to Area Committee
Meetings in December 2023) 
Area Committee to formally agree the
funding for each play park 
December 2023 
Procurement process (which will last 8 – 12
weeks) 
Expected to commence early 2024
Installations Expected to commence Spring 2024
(dependent on procurement process
as above) 
5.0 CONCLUSION 
5.1 The Scottish Government has allocated a total of £938k for Play Park funding to
Argyll and Bute Council for investment in play park equipment through to 2025/26
from the Capital Allocation for Renewal of Play Parks Fund.

Page 5

5.2 Officers will make the necessary arrangements for Tobermory Play Park and
report an update to the December Area Committee.     
6.0 IMPLICATIONS 
6.1 Policy – This project will be delivered within the Procurement tendering process
however, as we have had two unsuccessful processes already as well as a
direct award failure members should note that this may well delay matters and
officers. 
6.2 Financial – funded from grant funding from Scottish Government. 
6.3  Legal – None known. 
6.4  HR – None known. 
6.5  Fairer Scotland Duty: None known 
6.5.1   Equalities - protected characteristics – engagement will take place with
appropriate groups, including the disability forum, to provide a positive impact
on our young people. 
6.5.2   Socio-economic Duty – None known. 
6.5.3 Islands – elements of renewal on all play parks, which therefore will not
adversely affect islands. 
6.6. Climate Change – we will endeavour to minimise carbon footprint of this project. 
6.7  Risk – Failure to deliver within the allotted Scottish Government timescales may
result in losing the budget allocated. 
6.8  Customer Service – the intention of this funding is to provide better facilities for
our customers. 
Executive Director with responsibility for Road and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Climate Change and Environment, Councillor Ross Moreland 
August 2023                             
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk

Page 6

Hugh O’Neill, Network and Standards Manager 
Hugh.ONeill@argyll-bute.gov.uk 
APPENDICES: 
Appendix 1 – Breakdown of community responses to consultation 
Appendix 2 – Breakdown of indicative costs for equipment and fitting

Page 7

APPENDIX 1: BREAKDOWN OF COMMUNITY RESPONSES TO
CONSULTATION 
Play Park
Name/Location
Responses for
priority being
Renew/Replace 
Responses for
priority being
Health and Safety 
Responses for
priority being
Access for ALL 
Young Adult Young Adult Young Adult
Tobermory  1 9 0 3 0 4
Total  1 9 0 3 0 4

Page 8

APPENDIX 2: INDICATIVE COSTS FOR PLAY EQUIPMENT 
1. CUSTOM Ship £18,800.00 plus installation £3,125.00 
2. Featured Springer between £500 to £630.00 plus Installation £294.00
3. Spring Seesaw £2,250.00 plus Installation £514.00 
4. Climbing Net £11,250.00 plus Installation £3,372.00
5. Frame £4,360.00 plus Installation £698.00
6. Spinner Bowl £680.00 plus Installation £231.00 
7. Swing Frame, £5,040.00 plus Installation £1,452.00 
8. Flexus stand up swing, £3,120.00 plus Installation £514.00 
9. Ground Preparation £54,966.62
 Site Set up
 Excavate area and remove spoil off site, 
 Supply & install kerb edging, 
 Supply & lay cultivated turf 
 Supply & sow seed 
 Safer Surfacing WETPOUR 
 Heras site security fencing 
 Removal of packaging and Waste 
10. Equipment Delivery Charge £4,181.20 
11. Total Excl. VAT £115,477.82 
12. Total Inclusive of VAT = £138,573.38