To:  Infrastructure, Land and Environment Policy Board
On:  28 August 2024
___________________________________________________________________
Report by: Director of Environment, Housing, and Infrastructure
___________________________________________________________________
Heading: Renfrewshire’s Local Heat and Energy Efficiency Delivery Plan
___________________________________________________________________    
1. Summary 
1.1 Reducing Carbon Emissions is one of the principal measures to address climate
change and is a key priority for all Local Authorities. Renfrewshire Council recognises
that climate change will have far reaching effects on Renfrewshire’s economy, its
people and its environment and is determined to lead by example in tackling the
causes of climate change. 
1.2 Renfrewshire Council declared a climate emergency in June 2019 and approved the
Plan for Net Zero in August 2022, which committed to working towards net zero by
2030 for both the Renfrewshire area as a whole and Renfrewshire Council as an
organisation.  This challenging target covers all aspects of energy use within the
Renfrewshire wide area. Homeowners can help achieve these targets by ensuring
their home is energy efficient. In doing so, there are many long-term benefits, such as
carbon savings, reducing energy bills and by supporting the local economy. 
1.3 In 2022, the Scottish Parliament passed The Local Heat and Energy Efficiencies
(Scotland) Order 2022. This places a statutory duty on Local authorities to publish a
Local Heat and Energy Efficiency Strategy (LHEES) and Delivery Plan (LHEEDP),
and for these to be updated at intervals of no more than 5 years. 
1.4 LHEEDP are designed to be local authority-led, however stakeholder engagement
and partnership working are key as the plan addresses all building stock at a local
authority wide level (Council, public, private, 3rd sector and all tenures of residents). 
1.5 It is hoped that LHEEDP will also act as a prospectus for government funding and
external investment using a robust evidence base and place-based approach. 
1.6 Renfrewshire’s Local Heat and Energy Efficiency Strategy (LHEES) was approved by
the members of the Infrastructure, Land and Environment Policy Board on 24
January 2024. 
___________________________________________________________________

Page 2

2.  Recommendations 
It is recommended that members of the Infrastructure, Land and Environment Policy
Board:
2.1 Approves the proposed Local Heat and Energy Efficiency Delivery Plan 
2.2 Notes the high-level information available at this time on Renfrewshire’s Local Heat
and Energy Efficiency Delivery Plan 
2.3 Notes that updates will be provided to the relevant Policy Boards outlining potential
opportunities and proposed projects, activities, and interventions. 
___________________________________________________________________    
3.  Background 
3.1 In addition to Scotland’s net zero targets, there are strategic national targets relating
to lowering emissions from our buildings through the decarbonisation of heat.   
These targets are: 
• improving energy efficiency in domestic and non-domestic building stock;
• removing poor energy efficiency as a driver for fuel poverty; and 
• in 2040, as far as reasonably practicable, no household is in fuel poverty. 
Clean Energy is one of the 5 focus areas as approved within Renfrewshire’s Plan for
Net Zero which aligns with these targets at a local level.     
3.2 Development of Renfrewshire’s LHEEDP includes identifying: 
• a range of projects and actions to be developed, with outline costs and
carbon savings associated with the proposed interventions.
• an assessment of potential large-scale heat supply – not just looking at new
infrastructure but also using existing infrastructure and assets (such as water
sources) and innovative methods of waste heat recovery, such as those used
in the Advanced Manufacturing Innovation District Scotland (AMIDS) district
heating network in Renfrewshire.
• opportunities for partnership working and engaging with all key stakeholders
throughout the process. 
__________________________________________________________________     
4.  Next Steps 
4.1 Following approval of the LHEEDP, progression of the plan’s actions can be made. 
This will also allow feasibility studies and outline business cases to be carried out
and to seek appropriate funding on conclusion of the studies if/where potential
delivery area opportunities are identified.   
4.2 Continued engagement and collaboration are critical in the successful delivery of
LHEES to understand the views, opportunities, and constraints. Stakeholders were
identified through a range of engagement activities during the preparation of the
Strategy which was approved January 2024 as noted in section 1.6 of this report.  All
stakeholders have been mapped out in an action plan to support the delivery.  This
will provide a good understanding of the level of engagement required for each
stakeholder.

Page 3

4.3 The Delivery Plan is a living document and is expected to be updated in line with
policy and target development using version control. 
__________________________________________________________________     
Implications of the Report 
1. Financial – No current implications.  The Scottish Government committed to a
funding package of £75,000 per annum for each Local Authority from 2023 to 2027. 
Delivery of the LHEES will have resource implications for the Council and includes a
commitment to working collaboratively to ensure best value for our approach. As the
full extent of the resource implications for Renfrewshire Council emerge, reports will
be brought to the relevant future Policy Boards.    
2. HR & Organisational Development – No current implications. 
3. Community/Council Planning – No current implications.  However, delivery of
Renfrewshire’s LHEES will require engagement and collaboration with local
residents, businesses, partners and communities on the climate emergency agenda. 
The Delivery Plan will highlight the continued activities which support the key
priorities set out in the Council and Community Plans to tackle inequality and widen
opportunity.   
4. Legal - No current implications. However, future actions may have some level of
implication. 
5. Property/Assets - No current implications. However, delivery of Renfrewshire’s
LHEES may have significant implications for property and assets given the nature of
the work involved. 
6. Information Technology – No implications. 
7. Equality and Human Rights - The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights. No
negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in the
report because it is for noting only. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the Council’s
website.     
8. Health and Safety – No implications. 
9.  Procurement – No current implications. However, delivery of Renfrewshire’s LHEES
will have significant procurement implications given the nature of the work involved. 
10. Risk – No current implications. 
11.  Privacy Impact – No current implications. 
12. COSLA Policy Position – Renfrewshire’s LHEES aligns with COSLA’s current work
alongside the Scottish Government in response to the climate emergency. 
13. Climate Risk – as noted in para 3.1, Renfrewshire’s LHEES aligns with
Renfrewshire’s Plan for Net Zero, specifically the Clean Energy theme. 
14. Childrens Rights – No implications. 
___________________________________________________________________

Page 4

List of Background Papers:  None 
Author:  Ryan Cameron, Local Heat and Energy Efficiency Strategy Officer
Environment, Housing, and Infrastructure

Page 5

Table of Contents 
RENFREWSHIRE’S 
LOCAL HEAT & ENERGY EFFICIENCY DELIVERY PLAN (LHEEDP) 
Environment, Housing & Infrastructure

Page 6

2 
Table of Contents 
Page No
1.  Introduction to Local Heat and Energy Efficiency Delivery Plan 03
2.  Approach to Delivery Plan 04 
2.1  Local Heat and Energy Efficiency Strategy Priorities 04 
2.2  Renfrewshire Priorities 04
3.  Action Plan 05
4.  Summary of Actions 07
5.  Actions in Detail 10
6.  Renfrewshire Examples 17 
6.1  Pilot Project 17 
6.2  Housing-led Regeneration Programme 18 
6.3  New Build Homes Programme 19 
6.4  Eco Flex 4  19 
6.5  Energy Advocacy Advice 20
7.  Feasibility Studies 21 
7.1  Paisley East/West/Central 21 
7.2  Paisley North 22 
7.3  Johnstone 22 
7.4  Foxbar 23  
Appendix 1 – Glossary of Terms 24  
Appendix 2 – Stakeholders 28  
Appendix 3 – National Policies 32  
Appendix 4 – Local Policies 34

Page 7

3 
1.   Introduction To Local Heat & Energy Efficiency Delivery Plan (LHEEDP) 
This document is the Delivery Plan for the Renfrewshire Local Heat and Energy Efficiency Strategy (LHEES).  It should be read in
conjunction with the Renfrewshire LHEES itself. 
The Delivery Plan sets out how Renfrewshire LHEES is to be implemented, with a focus on actions over the period 2024 to 2029.   
The plan proposes to support Renfrewshire Council and our partners to work towards delivery of the changes and opportunities
identified in the Strategy. This is intended as a 5 year term delivery of actions, based on local priorities, LHEES considerations and
stakeholder engagement.   This helps understand what actions can currently be delivered, given the changing policy landscape as well
as understanding that new future policies and programmes will be developed alongside new technologies being adopted as they
become viable. 
Continuing engagement with both internal and external stakeholders will be critical to support the delivery of LHEES and embed LHEES
within the local governance structures and processes, not just of the Council but our Community Planning Partners and all stakeholders,
in order to identify and optimise new opportunities, including collaboration and partnership working opportunities as they arise.   
The high-level LHEES Delivery Plan is a living document and is subject to change when the Council and partner organisations start
delivering LHEES and/or large-scale renewables projects as well as new developments and the emergence of new technologies.  It is
expected to be updated in line with local and national policy and target developments, with a statutory obligation to update at intervals
of no more than 5 years.

Page 8

4 
2.  Approach to Delivery Plan
2.1 LHEES Priorities
The purpose of this Delivery Plan is to detail the specific opportunities and delivery mechanisms for Renfrewshire to reduce our energy
emissions and decarbonise our heating systems through large-scale projects, such as developing local heat network portfolios (both
new network developments and expansion of existing networks).  Also by installing measures at individual building level through
improving energy efficiency to reduce energy costs and alleviate fuel poverty.
This covers short and medium goals within a 5-year timeframe and longer-term aspirational actions; thus the plan focuses on
opportunities and approaches for this first phase of the LHEES, with the next Delivery Plan scheduled to be published no later than
December 2028.
2.2 Renfrewshire Priorities
Renfrewshires two key themes to guide the development of this Delivery Plan are intended to maximise the effectiveness of LHEES
delivery are:
1. Maximising and exploring in detail the potential for heat networks beginning with the 6 first phase heat network zones identified
in the Renfrewshire LHEES. 
2. Investigating the outline costs of installation and potential savings (carbon and cost savings) of identified solutions on an area by
area basis, with the alleviation of fuel poverty as a priority.

Page 9

5 
3. Action Plan
Officers have identified a mixture of high level actions which are set out in the summary of actions in section 4 and these will be
incorporated and developed in more detail on a project by project basis to ensure benefits are optimised and will include specific
details relating to timescales, inputs and desired outcomes.  Through a monitoring and evaluation process we will work towards targets
set throught the delivery plan and from this we can identify more specific projects within the Renfrewshire area. 
These actions in a Local Heat and Energy Efficiency Strategy (LHEES) delivery plan are crucial for its success. This involves a
comprehensive approach to communication, education, awareness raising and collaboration with all stakeholders. 
Heat Networks:  This involves creating infrastructure for distributing heat efficiently across multiple buildings. Heat networks (or district
heating systems) provide centralised heat from a single source or a combination of sources to multiple end-users via buried pipework
leading to more sustainable, efficient, and cost-effective heating solutions when compared with individual carbon-intense heating
systems within each building and through the optimisation of low carbon heat sources and waste heat recovery. 
Funding:  This is a critical component for the successful delivery of a Local Heat and Energy Efficiency Strategy (LHEES). Securing
adequate funding ensures that all phases of the project, from planning to implementation and maintenance, are carried out effectively
ensuring sustainable and impactful energy solutions for the community.  LHEES is also an opportunity for private investment
opportunities attracting private sector-led projects, public sector exemplar opportunities, and external funding; coordinating and
collaborating on joint ventures; and identifying innovative delivery models to turn sectoral ambitions into investable projects.

Page 10

6 
Skills and Jobs:  LHEES is an opportunity to upskill and reskill the local workforce and create significant sustainable jobs opportunities
across various sectors, from design and contruction through to operation and maintenance, as well as local supply chain and
manufacturing opportunities.  By developing these skills and creating related job opportunities, the delivery of a Local Heat and Energy
Efficiency Strategy can effectively contribute to both environmental sustainability and local economic growth. 
Awareness and engagement:  This involves a comprehensive approach to communication, education, awareness raising and
collaboration with various stakeholders.  Within the Plan for Net Zero, Renfrewshires LHEES is a key thread where the proposed
solutions reflect local needs and priorities of our communities and extensive engagement will ensure that the needs of all groups are
considered with a focus on addressing inequalities and fuel poverty.   
Building Level:  This involves a series of steps to improve the energy performance of individual buildings, whether residential,
commercial, or public. This plan ensures that each building within the target area benefits from improved heating systems, enhanced
energy efficiencies/savings, and reduced carbon emissions leading to enhanced living conditions.  It is important to consider the whole
building as a system when understanding retrofit works and associated costs.  The ‘fabric-first’ approach considers what is required,
prioritising repairs, insulation, draught-proofing and ventilation as key first measures to ensure energy conservation, reducing the
amount of energy needed and reducing energy waste in our buildings.

Page 11

7 
4. Summary of Actions
It should be noted that the actions along with stakeholders within the delivery plan will be updated and amended as projects are
identified and feasibility studies are concluded. 
Heat Networks
• Conduct feasibility studies to explore heat network
opportunities, including expansion of existing networks to
meet heat decarbonisation targets. 
• Ensure that the Delivery Plan aligns with new and existings
plans for example the new Local Development Plan.
• Engage with key internal and external stakeholders in
relation to heat network potential.
• Further develop heat network portfolio of projects
identified in the Strategy.
• Engage with non-domestic properties within heat network
zones that have high suitability for heat network
connection and/or anchor load potential.
• Explore collaboration opportunities with neighbouring
Local Authorities, including potential cross-boarder heat
networks.
• Building Assessment Reports (BARs) including, identifying
the best approach to implementation in partnership with
Scottish Government and all 32 Scottish Local Authorities. 
Funding
• Identify and review existing funding programmes and schemes for
energy efficiency and heat decarbonisation.
• Consider national and local levels on available opportunities for
different housing stocks. 
• Engage with the Scottish Government to report the funding gap,
as identified by this LHEES and further analysis, for energy
efficiency measures of regional building stock (domestic and non-
domestic).
• Explore innovative delivery models, including regional approaches,
joint ventures and public-private partnerships.
• Outline Business Case Development has been successful for
accessing both Council and external funding.
• Outline Business Case (OBC) Council and Scottish Government
matched funding has been successful for Paisley North (AMIDS)
and Paisley Central – progress to next steps developing the OBC.

Page 12

8 
Skills and Jobs
• National and regional co-ordination of skills and jobs
baseline to identify and address the skills gap and develop
the skills transition. 
• Support the development of new and existing supply
chains to encourage growth of local skills and reduce the
risk of local skill shortages.
• We will produce a proposed pipeline of our major
infrastructure projects in order to link with skills transition
and local employment opportunities and identify skills
gaps, shortages and requirements ahead of time. This
proposed pipeline will build on work that is already
underway to encourage investment in local areas; enable
local supply chain and manufacturing opportunities to be
identified; de-risk private sector investment; and bring
about regeneration of local areas.
• We will work with colleges, schools, universities, local
training providers, apprenticeships and staff training, to
ensure that the courses and training opportunities exist for
the stable and sustainable, quality jobs that will be created
to ensure every person is able to reskill and upskill. 
Awareness and Engagement
• Work collaborativly to improve data with a focus on non-domestic
buildings in order to gather information on energy consumption,
carbon emissions, building types, and existing infrastructure that
may be incorporated into a network. 
• Community surveys and stakeholder consultations to understand
local energy needs and behaviors.
• Use media channels to promote and educate about energy
efficiency, as well as providing energy advice and support.  
• Host workshops and training sessions to spread awareness of the
Local Heat and Energy Efficiency Strategy.  
• Provide details of funding opportunities and financial support
schemes available to residents and businesses.
• Continue with internal working group for discussing LHEES delivery
with relevant people/organisations.
• Engagement with Scottish Power to identify existing grid capacity
to meet heat decarbonisations requirements and identify
innovative solutions to local grid constraints.

Page 13

9 
Building Level
• Further work to understand the scale and costings of the
specific energy efficiency retrofit works and heat
decarbonisation measures required across Renfrewshire for
domestic and non-domestic building stock.
• Set out planned projects to decarbonise heating within
buildings and housing stock.
• Set out planned projects to improve energy efficiency
within buildings and housing stock.
• Align with Historic Environment Scotlands ‘Historic and
Traditional Buildings’ report to ensure traditional
contruction buildings specific needs and characteristics are
taken into account.
General
• Ongoing data collation and verification to inform projects and
identify high certainty actions and low regret measures and ensure
the most current information is being used.
• Continue to review methodology to inform future iterations of the
Strategy and the Delivery Plan. 
Table 01 - Summary of actions

Page 14

10 
5. Actions in detail
Please see Appendix 2 which sets out the various stakeholder groups that are referenced in the tables below. The Delivery Plan is a live
document and details of funding, timeframes and progress will be included as they become available.
Heat Networks 
Actions Lead Stakeholders Timeframe
01 Conduct feasibility studies to explore heat network
opportunities, including expansion of existing
networks to meet heat decarbonisation targets.
Energy Management
Unit
• Internal 
• External 01
2023-2024
02 Ensure that the Delivery Plan aligns with new and
existings plans for example the new Local
Development Plan.
LHEES Working Group • Internal
• External 01
2024
03 Engage with key internal and external stakeholders in
relation to heat network potential.
Climate Team N/A 2024-2029
04 Further develop heat network portfolio of projects
identified in the Strategy.
Energy Management
Unit
• Internal
• All External
2024-2029
05 Engage with non-domestic properties within heat
network zones that have high suitability for heat
network connection and/or anchor load potential.
Climate Team • Internal 2024-2029

Page 15

11 
06 Explore collaboration opportunities with neighbouring
Local Authorities, including potential cross-boarder
heat networks.
Climate Team • Internal Ongoing
07 Building Assessment Reports (BARs) including,
identifying the best approach to implementation in
partnership with Scottish Government and all 32
Scottish Local Authorities.
Building Standards • Internal 2024-2029 
Funding 
Actions Lead Stakeholders Timeframe
01 Identify and review existing funding programmes and
schemes for energy efficiency and heat
decarbonisation.
Energy Management
Unit/Housing Investing
Team/ Climate Team
• Internal Ongoing
02 Consider national and local levels on available
opportunities for different housing stocks
Energy Management
Unit/Housing Investing
Team
• Internal
• All External
Ongoing
03 Engage with the Scottish Government to report the
funding gap, as identified by this LHEES and further
analysis, for energy efficiency measures of regional
building stock (domestic and non-domestic).
Energy Management
Unit/Housing Investing
Team
• Internal  Ongoing

Page 16

12 
04 Explore innovative delivery models, including regional
approaches, joint ventures and public-private
partnerships.
Energy Management
Unit/Housing Investing
Team/ Climate Team
• Internal
• All External
2024-2029
05 Outline Business Case (OBC) Council and Scottish
Government matched funding has been successful for
Paisley North (AMIDS) and Paisley Central – progress to
next steps developing the OBC.
Energy Management
Unit
• Internal 2024-2025 
Skills and Jobs 
Actions Lead Stakeholders Timeframe
01 National and regional co-ordination of skills and jobs
baseline to identify and address the skills gap and
develop the skills transition.
Climate Team • Internal
• All External
Ongoing
02 Support the development of new and existing supply
chains to encourage growth of local skills and reduce
the risk of local skill shortages.
Climate Team • Internal
• All External
Ongoing
03 We will produce a proposed pipeline of our major
infrastructure projects in order to link with skills
transition and local employment opportunities and
identify skills gaps, shortages and requirements
ahead of time. This proposed pipeline will build on
Climate Team • Internal
• All External
2024-2029

Page 17

13 
work that is already underway to encourage
investment in local areas; enable local supply chain
and manufacturing opportunities to be identified; de-
risk private sector investment; and bring about
regeneration of local areas.
04 We will work with colleges, schools, universities, local
training providers, apprenticeships and staff training,
to ensure that the courses and training opportunities
exist for the stable and sustainable, quality jobs that
will be created to ensure every person is able to
reskill and upskill.
Climate Team • Internal
• All External
Ongoing 
Awareness and Engagement 
Actions Lead Stakeholders Timeframe
01 Work collaborativly to improve data with a focus on
non-domestic buildings in order to gather
information on energy consumption, carbon
emissions, building types, and existing infrastructure
that may be incorporated into a network. 
Energy Management
Unit
• Internal
• All External
2024-2029

Page 18

14 
02 Community surveys and stakeholder consultations to
understand local energy needs and behaviors.
Climate Team • Internal
• All External
Ongoing
03 Use media channels to promote and educate about
energy efficiency, as well as providing energy advice
and support.   
Energy Management
Unit/Communications
Team
• Internal Ongoing
04 Host workshops and training sessions to spread
awareness of the Local Heat and Energy Efficiency
Strategy.   
Climate Team • Internal Ongoing
05 Provide details of funding opportunities and financial
support schemes available to residents and
businesses.
Climate Team • Internal
• External 01
Ongoing
06 Continue with internal working group for discussing
LHEES delivery with relevant people/organisations.
Energy Management
Unit
• Internal 2023-2029
07 Engagement with Scottish Power Energy Networks
(SPEN) to identify existing grid capacity to meet heat
decarbonisations requirements and identify
innovative solutions to local grid constraints.
Energy Management
Unit
• Internal
• External 02
Ongoing

Page 19

15 
Building Level 
Actions Lead Stakeholders Timeframe
01 Further work to understand the scale and costings of
the specific energy efficiency retrofit works and heat
decarbonisation measures required across
Renfrewshire for domestic and non-domestic
building stock.
Energy Management
Unit/Housing Investing
Team/ Climate Team
• Internal  2024-2029
02 Set out planned projects to decarbonise heating
within buildings and housing stock. 
Energy Management
Unit/Housing Investing
Team/Planning/Buildin
g Stanadards
• Internal  Ongoing
03 Set out planned projects to improve energy efficiency
within buildings and housing stock. 
Energy Management
Unit/Housing Investing
Team
• Internal  Ongoing
04 Align with Historic Environment Scotlands ‘Historic
and Traditional Buildings’ report to ensure traditional
contruction buildings specific needs and
characteristics are taken into account.
Climate Team/Planning • Internal
• External 01
2023-2029

Page 20

16 
General 
Actions Lead Stakeholders Timeframe
01 Ongoing data collation and verification to
inform projects and identify high certainty
actions and low regret measures and ensure the
most current information is being used. 
Energy Management Unit • Internal  2023-2029
02 Continue to review methodology to inform
future iterations of the Strategy and the Delivery
Plan. 
Climate Team • Internal
• External 01
Ongoing

Page 21

17 
6. Renfrewshire Examples
6.1 Projects 
Housing Investment Team - pilot project where insulation works and fabric improvements have been carried out in conjunction with an
Air Source Heat Pump.  The project will assess whether the heat demand has been reduced sufficiently to allow a heat pump to run at
lower or at least equal costs for the tenant as a gas combi boiler (Wenlock Road, Paisley).
Renfrewshire are also working on various work programmes outwith the regeneration programme which is detailed below in section 6.2.  
The Council were granted funding from the Social Housing Net Zero Heat Fund (SHNZHF).  The project will aim to deliver energy
efficiency measures and low emission heating and will allow the Council to assess whether this is something which can feasibly be rolled
out to the wider housing stock.
To achieve a sufficient reduction in heat loss and heat demand, designs using passive house principles will be produced and then the
homes will be retrofitted with a package of energy efficiency improvements which will include external wall insulation, loft insulation,
roof replacement with integrated Solar PV arrays, new energy efficient windows and doors and other related works such as Mechanical
Ventilation with Heat Recovery (MVHR) systems. Individual Air Source Heat Pumps will then be installed to replace existing Gas
Combination Boilers.
Of the 12,000 properties within the housing stock, around 10,000 of these have gas combi boilers installed, and currently these are the
cheapest, most controllable systems for tenants.  It is important to note the risk that changing to lower carbon heating systems before
reducing the demand, could put tenants into fuel poverty.  Over a period of time the boilers will have a replacement programme but it is
important to find the balance between meeting carbon targets and fuel poverty.

Page 22

18 
Various capital programmes will include returning to properties where external wall insultation and new roofs over the last 10 years were
installed, to now install PV panels, top up loft insulation and install new windows.  A large scale window replacement programme of all
our housing stock will also be progressing.
6.2 Housing-led Regeneration Programme 
Our Housing Regeneration and Renewal Programme will improve the quality of housing in eight areas across Renfrewshire.  We are
taking forward a £100m ten-year investment programme to help improve council housing within Renfrewshire by creating modern,
affordable, high-quality, energy-efficient council homes. Phase 1 will focus on eight areas across Paisley, Renfrew and Johnstone. 
The programme will make major improvements to existing buildings, but it is about much more than that - we will also consider how to
improve the wider environment, including outside and communal areas, and how to keep fuel bills down by making homes more
energy-efficient. As well as improvements to existing homes, we are building around 350 new council homes across four of the areas.
Residents were consulted in summer 2021 on the initial plans for their area, and changes were made to the plans based on the
responses to that. 
This will in most cases include measures such as: 
• new roofs, including new roof trims, gutters and rainwater pipes, and the addition of solar panels;
• external wall insulation; 
• new close doors, repainted closes and repairs to stair treads;
• (in some cases) new windows; 
Further details of the programme can be found on our website at:  Housing-led Regeneration Programme

Page 23

19 
6.3  New Build Homes Programme 
70 new build affordable homes will be delivered as part of the Howwood Road Area regeneration in Johnstone with a further 60
affordable homes to be constructed at Gallowhill, Paisley. These homes will be delivered to Gold Aspects 1 – 8 of the Scottish Technical
Standards (domestic) in terms of sustainability with Air Source Heat Pumps being the primary source of heating complimented
mechanical ventilation heat recovery and solar panels. These homes will also be digitally enabled. 
The Council’s new build housing specification requires that our new build homes meet Gold Aspects 1 – 8 of the Scottish Technical
Standards (Domestic) as a minimum with the primary source of heating provided by Air Sourced Heat Pumps. Where suitable Ground
Sourced Heat Pumps and district heating systems will be used.
6.4  ECO Flex 4 
Renfrewshire’s Energy Management Unit manage the ECO Flex 4 funding scheme.  The Energy Company Obligation (ECO Flex 4) is a
scheme where funding is available to make eligible homes more energy efficient.  It applies to: 
• private housing in Renfrewshire
• fuel-poor households that do not meet criteria for other schemes
• low-income or vulnerable households that are vulnerable to the effects of the cold
• energy inefficient homes who may benefit from heating and energy saving measures. 
The scheme does not apply to Council Housing or Registered Social Landlords. 
Further details of the scheme can be viewed on our website at:  Funding to make homes more energy efficient (ECO4 Flex)

Page 24

20 
6.5  Energy Advocacy Advice 
Renfrewshire Council have been providing Energy Advocacy since 2012.  The energy advocates support residents of all tenure within
Renfrewshire.  This includes fuel debt, supplier disputes, priority service provision, supplier switching and energy usage. 
The advocates partner with a wide range of external partners in order to offer an integrated, more comprehensive and efficient service to
the advantage of our clients. Renfrewshire Council has provided Energy support to its residents for over 25 years and continues to be
very successful at providing invaluable assistance to the local community. Considering recent and expected rises on fuel costs, the
service is destined to become even more essential than ever before. 
Further details on Renfrewshire’s energy advice service can be viewed on our website at:   Renfrewshire Energy Advice

Page 25

21 
7. Feasibility Studies 
Renfrewshire Council obtained funding to carry out feasibility studies at a number of locations across Renfrewshire which are detailed
below.  These initial areas were identified through data analysis during the preparation of the Local Heat and Energy Efficiecy Strategy
identifying as having the high heat demand, being close to an energy source and in the presence of public buildings as potential achor
loads.  The areas not currently within the first phase heat network zone will be looked at in closer detail to identify opportunities for
smaller scale networks or communal heat sources. 
7.1 Paisley East/Paisley West/Paisley Central
East 
There is an opportunity for a new heat network around the Abbey in Paisley, making use of air source heat pumps at an energy centre,
with electric boiler top up. Thermal storage at the energy centre can maximise the annual heat demand to be provided by heat pumps
while backup/top-up electric boilers provide resilience and can facilitate meeting peak demands.
West 
There is an opportunity for a new heat network in West Paisley, making use of wastewater (sewer) source heat pumps and air source
heat pumps at an energy centre adjacent to George Court, with electric boiler top up. Thermal storage at the energy centre can
maximise the annual heat demand to be provided by heat pumps while back-up/top-up electric boilers provide resilience and can
facilitate meeting peak demands.
Central 
There is an opportunity for a new network in Paisley Central, making use of waste heat recovery and wastewater source heat pumps
alongside air source heat pumps at an energy centre adjacent to Renfrewshire House, with electric boiler top up. Thermal storage at the

Page 26

22 
energy centre can maximise the annual heat demand to be provided by heat pumps while back-up/top-up electric boilers provide
resilience and can facilitate meeting peak demands.
7.2 Paisley North – Advanced Manufacturing Innovation District Scotland (AMIDS) 
There is an opportunity for to extend the existing AMIDS wastewater heat recovery heat network to Glasgow Airport making use of water
source heat pumps at each building supplied by AMIDS as the main source of heat. Buffer vessels at each building can maximise the
annual heat demand to be provided by AMIDS while back-up/top-up electric boilers provide resilience and can facilitate meeting peak
demands. 
Following the results and findings of the Paisley Central and Paisley North (AMIDS) feasibility studies, Renfrewshire are progressing with
outline business case applications to the Heat Network Support Unit which would enable Renfrewshire Council to further develop the
opportunities which have been identified at a scale and will also enable knowledge sharing and lessons learned that can be applied
across Scotland. 
7.3 Johnstone 
The proposed location for the district heat network (DHN) was Howwood Road area, within the area several buildings were identified as
having the potential for district heat connection. The main buildings identified for the pre-feasibility report include Johnstone High
School, Johnstone Community Sports Hub, Fordbank Primary School and West Johnstone Shared Campus. In addition, it was proposed
a number of residential sites should also be considered within the DHN; two sites owned by Linstone Housing Association, one site
owned by the council near Howwood Road. 
The conclusion from the study determined that the area is not heat dense and a heat network solution may not be the most cost-
effective approach in this specific scenario. It was recommended to consider other routes to net-zero. For example, consider an options
appraisal for discrete scale, as buildings connected in a localised area, and building-level low-carbon heat such as ASHP.

Page 27

23 
An options appraisal for routes to net zero could include considerations on the following: 
• Discrete scale heat networks and building-level low-carbon heat with low-carbon heat technologies
• Energy efficiency opportunities, including heat demand reduction measures, heating system control
• Consider complementary renewable low-carbon electricity technology (e.g. PV for on-site electricity generation)
• Building condition survey – assess heat equipment age and condition (replacement plans), opportunities to reduce heat operating
temperatures building-side, connect with survey for energy efficiency measure opportunities.
• Consider funding opportunities for discrete scale heat networks and building-level improvements – low-carbon and energy efficiency. 
Ultimately, although heat networks are an efficient means to distribute low-carbon heat, they are not the only solution to achieve low-
carbon heating. It is equally valid to consider building-level and discrete scale low-carbon heat opportunities as part of the Council’s
route to net zero.
7.4 Foxbar 
The conclusion from the study determined that the area is not heat dense and a heat network solution may not be the most cost-
effective approach in this specific scenario. It was recommended to consider other routes to net-zero. For example, consider an options
appraisal for building-level low-carbon heat technologies such as individual ASHP. 
An options appraisal for routes to net zero could include consideration of: 
• Building-level low-carbon heat with low-carbon heat technologies
• Energy efficiency opportunities, including heat demand reduction measures, and heating system control
• Consider complementary renewable low-carbon electricity technology (e.g. PV for on-site electricity generation)
• Building condition survey – assess heat equipment age and condition (replacement plans), opportunities to reduce heat operating
temperatures building-side, connect with survey for energy efficiency measure opportunities
• Funding opportunities for building-level improvements – low-carbon and energy efficiency 
Ultimately, although heat networks are an efficient means to distribute low-carbon heat, they are not the only solution to achieve low-
carbon heating. It is equally valid to consider building-level low-carbon heat opportunities as part of Renfrewshire’s route to net zero.

Page 28

24 
Appendix 1 – Glossary of terms 
Terms Description 
Anchor Loads
Buildings with significant heat demands that are critical to making a heat network viable and have high
potential to be one of the first connected demands on a network. 
Baselining
A fixed point of reference for reference for comparison. For LHEES this is to understand at local authority or
strategic level, the current status of all building stock against the LHEES Considerations. 
Building-level Pathway
The outcome of assessment to provide the likely energy efficiency retrofit technologies, as well as the low
carbon heating system (where applicable) to support building level decarbonisation. 
Carbon Dioxide
The most abundant greenhouse gas (making up around ⅔ of greenhouse gases). It is naturally occurring but
is also a by-product of human activities such as burning fossil fuels, land-use changes and other industrial
processes and contributes to climate change and global warming. It is the reference gas against which other
greenhouse gases are measured.
Carbon Dioxide Equivalent
(CO2e)
A metric measure used to compare the emissions from various greenhouse gases based upon their global
warming potential (GWP). 
Carbon Emissions The release of carbon dioxide (CO2) into the atmosphere. 
Carbon Offsetting
The process of compensating for carbon dioxide emissions arising from activities by participating in schemes
which remove equivalent levels of carbon dioxide in the atmosphere, e.g. tree planting, carbon capture,
peat bogs. 
Climate Change
Refers to any significant change in the measures of climate lasting for an extended period of time, including
major changes in temperature, rainfall and severe weather patterns that occur over several decades or
longer.
Data Zone Output areas which have populations of around 500 to 1,000 residents.

Page 29

25 
Decarbonisation
The reduction or removal of carbon dioxide (CO2) into the atmosphere resulting from human activity, with
the eventual goal of minimising emissions as far as possible. 
Delivery Area
Areas at a higher granularity (higher level of detail) than Strategic Zones. These spatial zones should set out
clusters of buildings within a Strategic Zone that identify potential solution(s) at a delivery level. They will be
an important starting point for identifying a range of projects, regulation and actions to be developed in the
LHEES Delivery Plan. 
Energy Performance
Certificate (EPC)
Gives information on how energy efficient a building (including homes) is; how it could be improved; and an
environmental impact rating to show CO2 emissions. Buildings are rated on a scale of A to G, with A being
the most energy efficient. An EPC is required for new buildings/homes; when you are selling a building/home;
or when renting to a new tenant.
Fossil Fuels Non-renewable energy sources formed from fossilised plants and animals over millions of years such as
coals, oil and gas.
Fuel Poverty Defined as any household spending more than 10% of their income on energy after housing costs have been
deducted.
Greenhouse Gases Any gas that absorbs infrared radiation in the atmosphere and contribute to global warming and climate
change.
Intermediate Zone Statistical geographical areas (2,500 - 6,000 household residents) within local authorities, built up from
aggregates of data zones.

Page 30

26 
LHEES Considerations
The LHEES Considerations are a list of technologies, building typologies and policy priorities used to
identify and target interventions. They include:
- Heat networks
- Off-gas grid buildings
- On-gas grid buildings
- Poor building energy efficiency
- Poor building energy efficiency as a driver for fuel poverty 
- Mixed-tenure, mixed-use and historic buildings 
LHEES Delivery Plan A document setting out how a local authority proposes to support implementation of its local heat and
energy efficiency strategy. 
Linear Heat Density
A measure of heat load per meter of district heating pipework. In short, this approximates how much
revenue a branch of a network can generate for a given capital cost.
Low Temperature District
Heating Network
Reduces the amount of energy lost converting and transporting heat to buildings.
Net Zero Emissions When greenhouse gas emissions are balanced by removals over a specified period. 
Resilience
The capacity to anticipate, prepare for, respond to, absorb and recover from the stresses imposed by
climate change from significant multi- hazard threats with minimum damage to social well-being, the
economy and the environment. 
Strategic Zone
A visualisation of the potential pathways to decarbonise the building stock at a local authority level, split
out by intermediate zone or data zone. These are useful to understand the baseline performance, the
scale of potential and initial areas of focus, which could be used to inform Delivery Areas and follow on
engagement.

Page 31

27 
Wet central heating system
A system with central heat source (usually a boiler) that produces hot water which is distributed around the
building, heating radiators and can be used for hot waters from hot taps and showers.

Page 32

28 
Appendix 2 – Stakeholders 
Renfrewshire Council - Internal Stakeholders
Councillors
Infrastructure, Land and Environment Policy Board 
Planning and Climate Policy Board
Housing Services
Property Services
Planning and Building Standards
Corporate Governance - Legal Services
Finance and Procurement
City Deal and Infrastructure
Regeneration and Economic Development
LHEES Officers Working Group
Climate Team
Energy Management Unit

Page 33

29 
Renfrewshire Council - External Stakeholders
01. National • Scottish Government
• Energy Saving Trust
• Coal Authority
• Historic Environment Scotland
• Scottish Environmental Protection Agency
• NatureScot
• National Trust for Scotland
• Zero Waste Scotland
• Viridor (Energy from Waste – Clyde Valley Waste Partnership)
• Energy Savings Trust Scotland
• Home Energy Scotland
• Scottish Futures Trust
• Community Energy Scotland
• Local Energy Scotland
• Scottish Local Authority LHEES Forum 
02. Energy/Utilities  • Scottish Power Energy Networks
• Scottish Gas Network
• Scottish Water 
03. Housing Associations • Bield
• Blackwood
• Bridgewater
• Cairn
• Ferguslie Park
• Hanover
• Horizon
• Key

Page 34

30 
• Link
• Linstone
• Loretto
• Paisley
• Sanctuary
• Williamsburgh 
04. Community Planning Partners • OneRen
• University of the West of Scotland
• West College Scotland
• NHS
• Police Scotland
• Scottish Fire and Rescue
• Renfrewshire Health and Social Care Partnership
• Renfrewshire Chamberof Commerce
• Engage Renfrewshire
• Scottish Enterprise
• Skills Development Scotland 
• Clyde Muirshiel Regional Park Authority 
05. Skills and Supply Chains • Schools
• Colleges
• Universities 
• Training providers
• Apprenticeship providers
• Local employers

Page 35

31 
06. Other Key Interest Groups • Community Councils
• Community Groups
• Local Partnership Areas
• Care Homes and Nursing Homes
• Tenants Groups
• Developers
• Third Sector Organisations 
• Local Businesses
• Large Businesses (Potential Anchor Loads)
• Industry (potential Anchor Loads and Potential Waste Heat)
• Neighbouring Local Authorities

Page 36

32 
Appendix 3 – National Policies 
Climate Change (Emissions Reduction Targets)
(Scotland) Act 2019 Sets a 2045 net zero emissions target and interim targets: 75% by 2030; and 90% by 2040.
Climate Change Plan: third report on
proposals and policies 2018-2032 (RPP3)
Sets out the path to a low carbon economy while helping to deliver sustainable economic growth
and secure the wider benefits to a greener, fairer, and healthier Scotland in 2032.
Draft Energy Strategy and Just Transition Plan Sets out clear policy positions and a route map of actions with a focus out to 2030 that the
Scottish Government will take and the changes that the UK Government must deliver.
Energy efficiency in social housing
Aims to improve the energy efficiency of social housing in Scotland. It will help to reduce energy
consumption, fuel poverty and the emission of greenhouse gases. It is based on the minimum
Energy Performance Certificate (EPC) rating.  All social
housing must meet, or be treated as meeting, EPC band B, or is as energy efficient as practically
possible, by December 2032.
Fuel Poverty (Targets, Definition and Strategy)
(Scotland) Act 2019
Sets targets relating to the eradication of fuel poverty; to define fuel poverty; to require the
production of a fuel poverty strategy; and to make provision about reporting on fuel poverty. 
no more than 5% of households in Scotland are in fuel poverty, 
no more than 1% of households in Scotland are in extreme fuel poverty, 
the median fuel poverty gap of households in Scotland in fuel poverty is no more than £250.
Heat Networks (Scotland) Act 2021  Regulates heat networks, supporting objectives in the Heat in Buildings Strategy to grow heat
network opportunities. This strategy helps Renfrewshire meet part of its duty within the Act by
identifying potential heat network zones.
Heat in Buildings Strategy
Sets out our vision for the future of heat in buildings, and the actions we are taking in the
buildings sector to deliver our climate change commitments, maximise economic opportunities,
and ensure a just transition, including helping address fuel poverty.
Housing to 2040
Sets out a vision for housing in Scotland to 2040 and a route map to get there. It aims to deliver
our ambition for everyone to have a safe, good quality and affordable home that meets their
needs in the place they want to be.

Page 37

33 
National Planning Framework 4
Sets out spatial principles, regional priorities, national developments, and national planning
policy.  How Scotland will work together in the coming years to improve people’s lives by making
sustainable, liveable, and productive places. 
Central Scotland Priorities: 
To deliver sustainable places, Regional Spatial Strategies and Local Development Plans in this
area should support net zero energy solutions including extended heat networks and improved
energy efficiency, together with urban greening and improved low carbon transport. 
To deliver liveable places, Regional Spatial Strategies and Local Development Plans in this area
should pioneer low carbon, resilient urban living by rolling out networks of 20-minute
neighbourhoods, future proofing city and town centres, accelerating urban greening, investing in
net zero homes, and managing development on the edge of settlements. 
To deliver productive places, Regional Spatial Strategies and Local Development Plans in this
area should target economic investment and build community wealth to overcome disadvantage
and support a greener wellbeing economy. 
Across these priorities, there is a need for greater investment in, and development of, net zero
homes and places supporting green jobs. Local Development Plans and strategies like Local Heat
and Energy Efficiency Strategies will focus on decarbonising heat and energy networks, and the
just transition to greener, low carbon heat generation.

Page 38

34 
Appendix 4 – Local Policies
Council Plan – 2022-2027
"Creating a fairer Renfrewshire built on innovation, wellbeing and opportunity". The Council Plan
sets out how the Council will collaborate with partners, communities, and business to progress
our five strategic outcomes. 
There are five strategic outcomes: place, economy, fair, green, and living our values. 
Housing-led Regeneration and Renewal
Programme
A £100m ten-year Housing-led Regeneration and Renewal Programme aimed at delivering
modern, high quality, energy-efficient and affordable council housing throughout Renfrewshire,
and creating nicer places to live. 
Renfrewshire Community Plan 2017-2027
Developed together and signed up to by key public, private and third sector organisations. It
marks a shared responsibility to work together to get things right for people in Renfrewshire, and
a real commitment to addressing the inequalities that exist. 
The content of Our Renfrewshire is the result of conversations with partners and local people
about opportunities, challenges, and aspirations, informed by a comprehensive data and
evidence set. 
Renfrewshire Economic Strategy 2020-2030
Sets out the ambitions and actions to achieve sustained, inclusive growth of the Renfrewshire
economy over the next 10 years. 
Renfrewshire Local Development Plan Sets out the spatial strategy and proposals for Renfrewshire over the next 10 years. 
Renfrewshire Local Housing Strategy 2023-
2028
Sets out the strategic approach of the Council and its partners to delivering high quality housing
and housing related services across all tenures to meet identified housing need in Renfrewshire.

Page 39

35 
Renfrewshire’s Plan for Net Zero
Developed in collaboration with all our stakeholders, we are committed to working towards net
zero by 2030 for the whole of Renfrewshire to ensure a safer, healthier, greener, and fairer place
for everyone to live, work and spend time in. 
Renfrewshire Strategic Housing Investment
Plan
Identifies affordable housing projects which are to be supported by Scottish Government
funding and sets out how this investment will be targeted to meet the strategic priorities of
Renfrewshire’s Local Housing Strategy. 
Vacant and Derelict Land Strategy The strategy identifies actions to promote the redevelopment and/or re-use of brownfield and
previously used land to enhance places and support sustainable economic growth.