ILE SIP Outturn Full Report

Renfrewshire Council · 29 May 2024
Back to Infrastructure, Land and Environment Policy Board — 29 May 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
___________________________________________________________________
To: Infrastructure, Land and Environment Policy Board 
On: 29 May 2024
___________________________________________________________________ 
Report by: Director of Environment, Housing and Infrastructure 
___________________________________________________________________ 
Heading: Environment, Housing and Infrastructure - Service Improvement
Plan 2023-26 Outturn Report
___________________________________________________________________
1. Summary 
1.1 The Environment, Housing and Infrastructure Service Improvement Plan
2023-26 was approved by the Infrastructure, Land and Environment Policy
Board on 24 May 2023. The plan sets out the priorities for the development of
the service over a three-year period.   
1.2 The Service Improvement Plan is part of a suite of documents which describe
the strategic direction of the service and the Council and includes the Council
Plan, Community Plan, Risk Management Plan and the Workforce Plan. 
1.3 The Service Improvement Plan sets out the actions which will ensure
continuous improvement across the service and the performance indicators
which ensure the impact can be measured. These reflect the priority themes
of the new Council Plan which was approved by Council on 29 September
2022. 
1.4 Full details of Environment, Housing and Infrastructure performance and
achievements over the period 1 April 2023 to 31 March 2024 are appended to
this report. The main purpose of the report is to provide: 
• details of the key achievements of the service over the period;
• an update on changes made to the action plan and scorecard to reflect
the new Council Plan themes;

Page 2

2 
• a progress update on implementing the action plan linked to the 2022-25
Service Improvement Plan; and
• an assessment of performance in relation to the service scorecard of core
performance indicators; 
1.5 During 2023/24, the service has made good progress in delivering positive
outcomes for Renfrewshire and its residents. This includes through the
actions within the Service Improvement Plan and other areas of activity which
did not form part of the Service Improvement Plan actions which have
subsequently arisen during 2023/24. 
1.6 A new Service Improvement Plan covering the period 2024-26 is also being
presented to this meeting of the Infrastructure, Land and Environment Policy
Board. 
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy
Board:
2.1 Note the content of this report. 
2.2 Note the progress to date on delivering the actions contained within the
Environment, Housing and Infrastructure - Service Improvement Plan. 
2.3 Note the current performance of the service as measured by the scorecard
indicators.   
3.  Background 
3.1 The Service Improvement Plan is a comprehensive statement of the
outcomes the service aims to achieve, and the actions it will take to achieve
these. It fits within the wider planning framework of the Council by taking
account of Community Planning themes and Council priorities as set out in the
new Council Plan. It enables elected members to have oversight of
developments within the service and to consider and develop policy options
which reflect customer need and resource availability. 
3.2 The service improvement plan also provides a mechanism by which elected
members can evaluate the performance of the service. It contains an action
plan and performance indicators against which progress can be measured.
This outturn report provides an update on progress against the 2023-26 plan.

Page 3

3 
4. Service Update and Key Achievements April 2023 to March 2024 
4.1 Environment, Housing & Infrastructure continues to deliver essential frontline
services across Renfrewshire. Key achievements for Environment, Housing &
Infrastructure under the remit of the Infrastructure, Land and Environment
Policy Board are detailed throughout the action plan and performance
indicators in the appendix. 
5. Areas where actions have been delayed or cancelled 
5.1 Transport Scotland’s Bus Partnership Fund has been removed in 2024/2025
with no guarantees that this will be re-instated in future years. This means
planned improvements at two Paisley town centre junctions (Glasgow Road,
Mill Street, Gauze Street and Incle Street; and Gauze Street, Cotton Street
and Lawn Street) will not be progressed. 
6. Progress against performance measures 
6.1 Environment, Housing and Infrastructure report on 22 performance indicators,
12 which are reported annually and 10 reported quarterly. 
Implications of the Report
1. Financial – The Service Improvement Plan highlights resourcing pressures
arising from increasing demand for services and the current financial
environment.  
2. HR & Organisational Development – The Service Improvement Plan also
highlights workforce development and wellbeing considerations.
3. Community/Council Planning – The report details a range of activities which
reflect Council and Community Planning themes and a direct link to the delivery
of the Council Plan.
4. Legal – none.
5. Property/Assets – none.
6. Information Technology – Service developments relating to information
technology are key enablers of service improvement and modernisation and
support service-level and corporate objectives.
7. Equality & Human Rights – The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights.  No
negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in
the report.  If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored, and
the results of the assessment will be published on the Council’s website.

Page 4

4 
8. Health & Safety – none.
9. Procurement – none.
10. Risk – Risks related to the delivery and management of services are regularly
monitored and included in Renfrewshire Council’s Corporate and Strategic Risk
Registers. 
11. Privacy Impact – none. 
12. COSLA Policy Position – none.
13. Climate Change – Actions and indicators within the SIP covers the ‘green’ theme
of Renfrewshire’s Council Plan which highlights activities across the Council to
tackle climate change. 
___________________________________________________________________ 
List of Background Papers: 
Infrastructure, Land and Environment Policy Board; 24 May 2023 - Environment,
Housing and Infrastructure – Service Improvement Plan 2023/26 – Agenda item 5 
Infrastructure, Land and Environment Policy Board; 8 November 2023 -
Environment, Housing and Infrastructure - Service Improvement Plan 2023/26 Mid-
Year Monitoring Report – Agenda item 4 
___________________________________________________________________ 
Author  Gordon McNeil, Director of Environment, Housing & Infrastructure  
Email: gordon.mcneil@renfrewshire.gov.uk

Page 5

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Environment, Housing & Infrastructure
Service Improvement Plan 2023 - 26
Outturn Report
May 2024

Page 6

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Welcome to our Service Improvement Plan outturn report
• This update reflects  progress over the last year of our Service Improvement Plan (SIP) and the
following pages shine a spotlight on some great projects or practice and highlight areas where we’d
like to improve or develop further. 
• Our Service Improvement Plan is closely aligned to the Council Plan and each of the actions and
performance indicators within the SIP are grouped under the appropriate Council Plan theme to
show the linkage between what we are aiming to achieve and the corporate priorities of the
Council. Towards the end of this document, you’ll find a full update against all the actions and
performance indicators we use to measure progress.
• We report on 22 performance indicators, 12 which are reported annually and 10 reported quarterly.
Our annual indicators are based on data that is one-year behind, owing to having no more recent
comparable information.  This will be updated as comprehensive data becomes available through
subsequent data collections.

Page 7

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
About us
This update covers the Environment, Housing and Infrastructure service areas within the remit of the
Infrastructure, Land and Environment Policy Board. These are:
Operations
Responsibilities include:
• Waste Services
• Fleet & Social Transport
• Neighbourhood Services
• Grass, Grounds & Cemeteries
Maintenance,
• Burials
• Country Park Management
Roads and Transportation
Responsibilities include:
• Council’s roads and
infrastructure
• Winter maintenance
• Public Transport
• Parking & Active Travel services
Service Development
Responsibilities include:
Service Modernisation
• Digitalisation
• Operational Data & Performance
• Operational Policies & Procedures
• Operational Health & Safety and Risks
Management
• Employee Development
• Training
Customer & Member Enquiry Services
• FOI’s
• Elected Member enquiries
• Public enquiries including Complaints

Page 8

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan
Economy: Environment, Housing
& Infrastructure have delivered an
improved and enhanced road
network to improve connectivity
and support growth in the
economy.  This includes the new
road infrastructure to support the
enhanced links between Paisley
Town Centre, Glasgow Airport and
the Advanced Manufacturing
Innovation District Scotland
(AMIDS).
Green: Renfrewshire’s focus on
the journey to Net Zero is
supported by the reduction of
CO2e emissions across the Council
fleet. An Offsetting Strategy is
being developed to align with the
phased road map and costed
delivery plans to identify and
maximise opportunities
associated with offsetting.
Fair: Implementation of the
successful participatory budget
project is well underway.
29 #YouDecide projects are now
complete. Refurbishments at
Glebe Street, Renfrew and
Jennyswell Paisley were
completed along with the outdoor
gym at Old Road Park, Elderslie.

Page 9

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan - Place
Achievements:
• Construction of replacement Plymuir Bridge in Glennifer Braes Paisley was completed in March
2024. This brings the last council owned bridge up to national requirement of being able to carry 40
tonnes.
• £2m funding received from Transport Scotland’s Active Travel Transformation Fund. This
represents 10% of the total £20m fund that was available. £540k of this has been secured for a
segregated shared active travel route on Barnsford Road to Inchinnan Drive and will connect to
existing routes around Glasgow Airport.
• 100% of the carriageway resurfacing works have been complete under the roads capital
programme.
• 100% of Category A,B and C roads inspections were completed on target.
Proactive Actions:
• % of pothole repairs completed within timescales was 94%, which remains high. The average
repair completed within timescales over the last 2 years was 94.5%. This is a significant
improvement over the average for the previous 6 years which was 61.5%. We continue to aim for
high targets for this performance rating and have, subsequently, changed our inspector model and
trained staff accordingly in the risk based model of working.

Page 10

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan - Fair
Achievements:
• 29 #YouDecide participatory budget projects are now complete.
• A selection of completed projects include:
• Play area refurb at Glebe St, Renfrew and Jennyswell, Paisley
• Outdoor gym at Old Road Park, Elderslie
• a new pelican crossing at Magnus Rd, Houston
• a dog exercise area in East End Park, Paisley
• improvements to the playing surface at Howwood Park
• Community engagement will continue throughout the delivery of the remaining
projects.

Page 11

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan - Green
Achievements:
• We have been successful in our application to the Active Travel Infrastructure Fund for a new active travel
route around Inchinnan Business Park. The project will link the segregated shared active travel route on
Barnsford Road to Inchinnan Drive and the existing active travel route at Inchinnan Road.
• Work to improve accessibility to the National Cycle Route Network 7 has seen the path upgraded through
Jenny’s Well Nature Reserve and opening of the footbridge connecting Hawkhead Road Housing
Development
• Community Climate Conversation and Key Stakeholder Organisation engagement events have been
concluded to identify community priorities; partnership working opportunities; and share
knowledge/lessons learned.
• Garden Waste Permit scheme successfully rolled out across Renfrewshire and year two of the scheme has
now commenced
• The LHEES Strategy was approved by Board in January 2024.
• EV Charging Infrastructure installed in Community Meals Service, Renfrew Care Home and Brediland
Childrens Home.
• Fleet Services are piloting vehicles with a new fuel source for the heavy Council fleet, HVO (hydrotreated
vegetable oil) fuel and significantly reducing greenhouse gas emissions on combustion.

Page 12

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Living our Values: making a difference together
We are focusing on understanding the impact of
trauma and reflecting our learning in how we
deliver our services, alongside the language we
use to help tackle stigma.
100% of Freedom of
Information requests were
responded to on time
85% of frontline resolutions
responded to within agreed
timescales
89% of complaints investigations
resolved within agreed timescales
Performance and management processes
continue to provide focus on analysis and
improvement. Work continues to develop
the depth and breadth of content to
continue to provide robust data led
intelligence to shape future service delivery.
Operations, Infrastructure & Service Development have
been successfully re-accredited through strategic review for
the next three years of accreditation to the ISO9001 Quality
Management Systems standard.

Page 13

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Improving Outcomes for Children and Families
Achievements:
• Environment, Housing & Infrastructure have been liaising with the Council's
Promise lead officer to ensure the service is supporting The Promise.
• A play parks strategy titled, ‘Outdoor Access & Play Area Improvements 2023 –
2026’ was approved at the Infrastructure, Land and Environment Policy Board.
Across all of our work and all of our efforts, we hope for loving and happy lives for Renfrewshire’s children – working together to
get it right for children, families and communities – protecting, learning, achieving and nurturing. Every priority of our Council
Plan contributes to improving the lives of Renfrewshire’s children and their families.

Page 14

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Actions and indicators
Infrastructure, Land and Environment Policy Board
May 2024

Page 15

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Place
What we will do Due Date Status Progress update
Deliver the 2023/24 roads and
footways capital investment
programme - £6.7 million
31 March 2024
As of 15 April 2024, we have completed 31 of the original list of 44 carriageways to be resurfaced. The remaining 13
schemes have been reprogrammed to next financial year. We have also completed 50 of 64 footways due to be
resurfaced. 14 footways have been reprogrammed into next financial year. The Network Improvements contract is
almost finished with carriageways and footways complete in Hillington.  Ongoing resurfacing of the A761 Ferguslie
footway will complete this week.
Implement the requirements of
the Transport (Scotland) Act 2019 31 March 2026
Consultants have completed a Review of Renfrewshire’s Bus Network, identifying gaps in current provision and
recommending opportunities for improvement. On behalf of Transport Scotland consultants are assessing Renfrewshire’s
roads for locations to exempt from the national pavement parking ban.

Page 16

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Place
Indicator Current Status
2021/22 2022/23 Q1 Q2 Q3 Q4 2023/24 2023/24
Explanation of performance
Value Target Value Target Value Value Value Value Target Value
(i) A Class Roads 17.29% 22.5% 15.5% 19% Not measured for Quarters N/A Not
available
Local Government Benchmarking
Framework (LGBF) Indicators. This
data is published by the Improvement
Service on an annual basis as part of
the LGBF.
These are annual LGBF Indicators and
relate to financial year 2022/23. The
2023/24 data will not be published
until February 2025.
(ii) B Class Roads 21.25% 24.5% 19.21% 22% Not measured for Quarters N/A Not
available
(iii) C Class Roads 30.55% 36.5% 27.02% 32% Not measured for Quarters N/A Not
available
(iv) Unclassified Roads 30.99% 36.5% 30.12% 32% Not measured for Quarters N/A Not
available
(Maintenance)
Carriageway Condition:
% of roads network
considered for
treatment Overall
28.9% 32.5% 27.4% 32% Not measured for Quarters 30% Not
available
These are annual LGBF Indicators and
relate to financial year 2022/23. The
2023/24 data will not be published
until February 2025.

Page 17

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Place
Indicator Current Status
2021/22 2022/23 Q1 Q2 Q3 Q4 2023/24 2023/24
Explanation of performance
Value Target Value Target Value Value Value Value Target Value
% of Statutory roads inspections categories completed on target:
(i) Category A 100% 95% 83% 95% Not measured for Quarters 95% 100% In 2023/24, 100% of the statutory road
inspections were completed for all
categories. The three categories of statutory
inspections relate to the timing of inspections
and are categorised as follows: A –
Undertaken during the progress of the works
B – Undertaken within the six months
following interim or permanent
reinstatement C – undertaken within the
three month preceding the end of the
guarantee period. The inspection procedure
is designed to enable road work authorities
to monitor statutory undertakers (Gas,
electric, and telecom etc).
(ii) Category B 100% 100% 86% 100% Not measured for Quarters 100% 100%
(iii) Category C 100% 100% 100
% 100% Not measured for Quarters 100% 100%
% Pothole repairs
completed within
timescales
83% 80% 95% 90% 97% 96% 98% 91% 95% 94%
The 2023/24 % of potholes repaired was
94% falling just short of the 95% target.  The
service recently changed the Roads
Inspector model, moving away from having
carriageway inspectors, footway inspectors,
statutory inspectors and capital
inspectors. We now have a bank of 9
inspectors that cover all disciplines within
their set area.  It has taken  time to get
everyone trained up, and for a while, some
of the inspectors that hadn’t covered
carriageways before, were raising
emergency lines for potholes that weren’t
an emergency.

Page 18

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Economy
What we will do Due Date Status Progress update
Provide employment, training
and apprenticeship opportunities
for identified groups of young
people in Renfrewshire 31 March 2024
Annual recruitment of 2 apprentices in Neighbourhood Services has been completed and they have commenced working
across the service. Within Infrastructure & Assets two invest trainees have recently been recruited. One as a trainee
Inspector and the other as a trainee vegetation officer.
Develop a Local Transport
Strategy supported by revised
Active Travel and Public
Transport Strategies (Council
Plan)
31 March 2025
The development of the Local Transport Strategy is underway. The initial phase of this process has included discussions
between the appointed consultants and Renfrewshire Council Officers. This will involve the preparation of a consultation
plan and ‘public conversation’ which will be taken forward in the second half of this financial year.
Continue to invest in
infrastructure to support growth
– from road and rail links to
bridges, cycle and pedestrian
routes (Council Plan)
31 March 2024
Renfrewshire Council continues to invest in infrastructure to support growth. Work is ongoing to expand the active
travel network. The Paisley to Renfrew Cycle Route will complete by July and the Barnsford Road section of the Airport
to Erskine Route is progressing with an expected completion in early June. Improvements to Plymuir Bridge have now
completed and Renfrewshire has no more Council owned weight limited bridges.
The Council is keen to promote a
parking strategy which manages
the supply and demand for
parking, supports economic
regeneration
31 March 2024
The Council’s Parking Strategy was approved at ILE Board. New parking charges in Paisley started from 5th February
2024. The research work for future phases of the Strategy will now be taken forward.

Page 19

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Economy
What we will do Due Date Status Progress update
Conduct a review of
Renfrewshire’s public transport
provision 30 September
2025
The timing of the Council’s review of public transport provision has been altered to tie in with similar work being
undertaken by SPT. A final report is expected by December 2024.
Progress next stage of Paisley
Town Centre junction
improvements as part of the Bus
Partnership works
31 March 2024
Transport Scotland’s Bus Partnership Fund has been removed in 2024/2025 with no guarantees that this will be re-
instated in future years. This means planned improvements at two Paisley town centre junctions (Glasgow Road, Mill
Street, Gauze Street and Incle Street; and Gauze Street, Cotton Street and Lawn Street) will not be progressed. The traffic
signal bus priority improvements are being installed on the Glasgow Road corridor, and were completed in  March 2024.

Page 20

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Fair
What we will do Due Date Status Progress update
Implement the preferred options
from the #YouDecide participatory
budget programme for
infrastructure improvements
31 March2024
• Twenty nine #YD Projects are now complete. Most recently play area refurbishments at Glebe Street Renfrew and
Jennyswell, Paisley was completed along with the outdoor gym at Old Road Park, Elderslie. Remaining play area and outdoor
gym works will follow.
• Lighting works are currently ongoing at Howwood Park, Inchinnan Park, Ellerslie Street Park, Johnstone, Spateston Park,
Johnstone, Kintyre Park, Linwood, Barshaw Park and the entrance to Ferguslie Gardens, Paisley. All other #YD lighting projects
will follow.
• Contracts have been awarded for the construction of a Wheeled Sports Areas at Kintyre Park Linwood and Moss Road Park,
Bridge of Weir and early designs have been submitted. Consultation with potential users taking place May 2024. Construction
is anticipated to start Autumn 2024.
• Visualisation concepts drawings are complete for Barrangary and Chestnut roundabouts, Bishopton. Local consultations will
be complete by the end of May to decide which idea is favoured. Visualisations for Easwald Bank roundabout, Kilbarchan and
both Renfrew Road/Arkleston Road and Glasgow Road/Kings Inch Road roundabouts, Renfrew should be ready by the end of
May and consultation will proceed thereafter.
• Speed sign installations at Main Road Elderslie and Bridge of Weir Road Brookfield have been instructed and will be complete
by the end of May.
• Following discussions with Renfrew Community Council seating improvements have been agreed.  Works to instruct seating
on 24 of the granite blocks around Renfrew Town Centre has been instructed.  We anticipate work to start here June 2024.
• Work to improve paths and signage in Gleniffer country park is ongoing as is information and interpretation boards for the
villages of Inchinnan and Kilbarchan.

Page 21

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
What we will do Due Date Status Progress update
Commence costed, targeted
interventions and actions to
support our net zero journey
within the Council and working
in partnership with key
stakeholders (Council Plan)
31 March 2026
A number of engagement sessions for communities, stakeholder organisations and internal stakeholder were carried out
throughout 2023. These events were well attended and helped to identify community priorities, partnership working
opportunities and knowledge sharing. Work is underway to develop a phased road map and costed delivery plans.
Agreement at PACC Board for an Offsetting Strategy to be developed to align with the phased road map and costed
delivery plans to identify and maximise opportunities associated with offsetting.
Deliver a programme of
enhanced operational
environmental and community
support activities for
environment and place (Council
Plan)
31 March 2024
Team Up 2 Clean Up continue to make positive impacts across towns and villages in Renfrewshire. Community
engagement through social media was up 100% in the 60 days to the start of October with a membership of just over
4,900 local users engaging. With the autumnal weather additional sweeping is being undertaken to ensure gullies are
kept clear of debris and leaves to reduce local flooding risks. Environmental Task Force continue to work alongside
Renfrewshire communities to reduce flytipping. The digitalisation of fly tipping data collection is building a database of
evidence for data led intelligence.
Build additional capacity for
proactive tree asset
management across
Renfrewshire
31 March 2026
The Tree Risk Management Strategy and Operational Tree Management Policy were agreed at Infrastructure, Land &
Environment Board of August 2023.
To support the strategy and policy, new posts and arbor team structure has been developed with the additional
capacity to undertake the increased task under proactive tree management.

Page 22

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
What we will do Due Date Status Progress update
Implementation of a Garden
Waste Permit Scheme for
householders to uplift and
dispose of their garden waste 31 July 2023 Permit scheme rolled out across Renfrewshire with second year now commenced.
Prepare site at Linwood for
improved bin store facility and
consideration of the
infrastructure required to fulfil
the Deposit Return Scheme and
future requirements for
segregation of waste.
31 March 2024
DRS has been delayed. The initial delay was until 2025, and there has been a further delay until 2027– We will develop
a business case and liaise with SEPA on how we can maximise Linwood Facility.
Continue site management
following statutory monitoring
period of the leachate treatment
at Linwood Moss 31 March 2024 We have been carrying out tests to use natural reed bed on site to treat water,  this will be monitored over coming
weeks and months – result of trial will determine what we do moving forward, with monitoring and reporting to SEPA

Page 23

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
What we will do Due Date Status Progress update
Review and consider the
implications of the Circular
Economy Bill and associated
route map when published
(likely summer 2023)
31 March 2024
The Bill ended Stage 1 (General Principles) on 20th March 2024 and moved to  Stage 2 (Changes to detail, whereby
MSPs can propose amendments to the Bill.
The deadline for MSP amendments was Wednesday 24th April and was considered on 30th April 2024.
The Bill as amended at Stage 2 will be published following these proceedings.
The service will be proactive in implementing any legislative requirements resulting from the Circular Economy
(Scotland) Bill when it becomes law.

Page 24

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
What we will do Due Date Status Progress update
Development of Low Emissions /
Electrification Strategy (Council
Plan)
31 March 2024
Refurbishment of six signalised junctions from “old” high energy consumption technology to more efficient LED systems
has been completed in Paisley (3off), Johnstone, Renfrew (2 off). EV Charging Infrastructure for Fleet Vehicles installed in
Community Meals Service, Renfrew Care Home and Brediland Childrens Home. Renfrewshire Council working in
partnership with Glasgow City Region Partners to develop a strategy and investment model for future provision of EV
Charging Infrastructure. Continued Engagement with SPEN legal representatives for the installation of new electric
power supply at Underwood Road Depot that will facilitate additional EV Charging Infrastructure and Fleet
decarbonisation. . Fleet Services are piloting five commercial front line vehicles with a new fuel source for the heavy
Council fleet, HVO (hydrotreated vegetable oil) fuel and significantly reducing greenhouse gas emissions on combustion.
This means that running vehicles with HVO fuel could reduce CO2 emissions by up to 90%, NOx (Oxides of Nitrogen)
emissions by up to 27% and PM (particulate matter) emissions by up to 84%, all of which are key factors to achieving
improved air quality
Pilot and test the creation of
active travel routes between
neighbourhoods, town centres
and business locations using
these to test SMART travel
solutions and evaluate benefits
to biodiversity, air quality and
access
31 March 2024
Active travel route feasibility and engagement are progressing in several areas where Sustrans are leading on a
proposal to improve the NCN7. Active Travel routes have been completed between Paisley and Renfrew, delivered
widening and resurfacing of the route at McClue Lane, Renfrew to accommodate shared use by pedestrians and
cyclists. Active travel connections have also been completed for Nethergreen Road and Kirklandneuk Primary School.

Page 25

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
What we will do Due Date Status Progress update
Deliver the Local Heat and
Energy Efficiency Strategy
(LHEES) for Renfrewshire.
31 December
2023
The LHEES strategy was approved at the Infrastructure, Land and Environment Policy Board in January 2024.  Work is
now underway to develop costed area-based delivery plans.  These plans will align with the Ren Zero road map and
costed delivery plans.

Page 26

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
Indicator Current
Status
2021/22 2022/23 Q1 Q2 Q3 Q4 2023/24 2023/24 Explanation of
performanceValue Target Value Target Value Value Value Value Target Value
Street
cleanliness
Score - % of
areas
assessed as
clean
89.6% 92% 93.3% 92% Not measured for quarters 92% Data not
available
This is an annual target,
and the cleanliness score
is based on 3 sample
surveys carried out
throughout the year by
both the Council and Keep
Scotland Beautiful (KSB).
This score represents the
percentage of areas
assessed as acceptably
clean (categories A and B)
using KSB’s Local
Environment Audit and
Management System
(LEAMS) methodology.
% of
Household
Waste
Recycled
51.7% 50% 53.7% 50% Data not available 50%
Data not
yet
available
The latest data available
relates to the calendar
year 2022.
% of
Household
waste
collected
which is
landfilled
8.2% 5% 2.3% 5% Data not available 2%
Data not
yet
available
The latest data available
relates to the calendar
year 2022.

Page 27

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Green
Indicator Current
Status
2021/22 2022/23 Q1 Q2 Q3 Q4 2023/24 2023/24
Explanation of performance
Value Target Value Target Value Value Value Value Target Value
Amount of CO2
emitted by the
public vehicle
fleet
3,223 3,000 3,267 3,000 812.80 775.2 762.1 768.6 3,000 3,118
The total for the year is 3,118 tonnes of
CO2  emitted which is slightly over
target of 3,000 tonnes of CO2e.
% of the vehicle
fleet which
uses alternative
fuels, such as
electricity
25% 25% 27% 25% 29% 29% 30% 30% 25% 30%
At the end of 2023/24, the current fleet
using alternative fuels includes 114
electric vehicles from a total fleet of
393 vehicles. In addition, there are 5
vehicles using alternative fuel.
% of bins
uplifted first
time
99.8% 99.9% 99.8
% 99.8% 99.8% 99.8% 99.7% 99.85% 99.8% 99.8%
The percentage of bins lifted first time
in 2023/24 was 99.8%. This is
consistent with performance in 
2022/23.
Reduce the
amount of CO2
emitted from
public space
lighting
1,246 1,500 1,138 1,500 Not measured for quarters 1,100 1,216
This performance indicator is an
annual indicator and not measured for
quarters.
Although not measured in quarters, the
emissions levels are anticipated to
level out year on year as the LED
programme is substantially complete.

Page 28

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Living our Values
What we will do Due Date Status Progress update
Provide our employees with the
appropriate support to manage
their attendance, health and
wellbeing 31 March 2024
The provision of appropriate support for employees to manage attendance, health and wellbeing has been ongoing
throughout the year months of the financial year. Notable developments in this period have included the launch of a new
well-being series of RenTalks highlighting Menopause, Preparing for Retirement , Woman’s Health and Wellbeing, Men’s
Health and Wellbeing and Supporting our Unpaid Carers. All services have continued to provide a focus on managing
attendance and it remains a key priority for the service.
Implement the next phase of
transformation as part of Right
for Renfrewshire (Council Plan) 31 March 2024
The Service has undertaken the restructures as part of the wider Right for Renfrewshire programme.
Better use of data and
technology to improve services
performance and delivery
31 March 2024
Following successful trials and testing, the digitisation and delivery of the cleaning audits audit management system
(CLAMS) was rolled out in November and December alongside the revised cleaning specification.
The app has been downloaded onto staff phones to facilitate digital audits of cleaning across all premises. The development
of the app aligns with the British Institute of Cleaning Science system that is also online.
The CLAMS app can also produce reports on Power Bi that help the service to manage and improve performance.
E,H&I staff have been trained in the use of Power Bi which will assist in the continued development of content to provide
robust data led intelligence to help inform future service delivery.
Engage and participate in
trauma informed and
responsive Renfrewshire
programme.
31 March 2024
As part of the Trauma response the service has invested in Mental Health First Aid training. This has been provided to staff to
assist in helping to deal with aspects of trauma.

Page 29

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Living our Values
What we will do Due Date Status Progress update
Embed new approaches to staff
communication and
engagement across all areas of
the service
31 March 2024
A series of manager away days have been held, with the last one taking place in May 2024. The Strategic
Communications Business Partner is now embedded within the service and is supporting the service develop a
wide range of approaches to communication and engagement with staff.
Ensure robust and up to date
business continuity
arrangements are in place
31 March 2024 Civil Contingencies Service continues to support services across the council ensuring that they have in place robust
arrangements for continued delivery of essential services in the event of significant incidents such as disruptive
weather, cyber-attacks, or widespread power outage. Updated draft versions of Business Continuity Plans for all
four service areas within E,H&I have been completed and are now waiting feedback from an external cyber
consultation before final approval.
Embed the enquiry systems for
public and elected members
across Environment, Housing &
Infrastructure services
31 March 2024
In terms of the teams within E,H&I which fall under the remit of the ILE Policy board this is now complete.
Review Health & Safety and Risk
Assessments
31 March 2024
The new Service Development Team are in the process of reviewing H&S and Risk assessments, with the operational
services across the whole of E,H&I

Page 30

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Living our Values
What we will do Due Date Status Progress update
Ensure robust financial
monitoring
31 March 2024 The Senior Leadership Team and service managers continue to meet on a period by period basis with finance
colleagues to monitor budgets and to ensure the service is provided with the most up to date information to ensure
robust financial systems are in place to support the service.
Conduct a strategic fleet review
of all Council vehicles to assess
vehicle specifications
considering fit for purpose and
net zero targets-
31 March 2024 As part of our ongoing commitment to meet the Scottish government get to zero targets for fleet, a Fleet asset
management plan is in draft format. This plan identified the fleet requirements from 2025-2030. Within the Current
Capital Budget programme Fleet are identifying the operational fleet needs of our user departments. This has
focused on older fleet being replaced with newer and more environmentally friendly vehicles. Throughout the
purchasing process fleet are in constant dialogue with the operational departments to ensure all vehicles meet the
needs of the department.
Building Services fleet review – soft market testing has been completed with full tender to be published in 2024.
Review and maintain
continuous improvement
frameworks
31 March 2024 Infrastructure & Service Development services have been successfully re-accredited through strategic review for the
next three years of accreditation to the ISO9001 Quality Management Systems standard.
Following this, a six monthly audit was carried out in March 2024 which resulted in no major non-conformances.

Page 31

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Living our Values
What we will do Due Date Status Progress update
Support the Council in
developing New Ways of
Working
(Council Plan)
31 March 2024 A lot of work and preparation on the New Ways of Working has been undertaken with an initial focus on Renfrewshire
House as the Council headquarters.
This has included setting up cross service Operational and Strategic Groups.
Officers procured a space planner to assist with the design of offices and a large amount of work has been undertaken
to relocate staff from Abbey House to Renfrewshire House between November 2023 and January 2024 thus ending the
lease. Other leases e.g. 5a High Street have ended and work continues to review different strands/themes e.g.
Community Halls/Self Managed Halls, surplus properties etc.
Pilots of sound proof pods, new ICT meeting equipment, head phones and break out areas have been undertaken and
reviewed.
The work has been undertaken to give the flexibility for staff to continue to work in a hybrid model (wherever
possible) and therefore rationalise the number of desks for each team. Work has also been undertaken to understand
leases and assess if other organisations e.g. RVJB could be located in Renfrewshire House.

Page 32

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Living our Values
Indicator Current
Status
2021/22 2022/23 Q1 Q2 Q3 Q4 2023/24 2023/24
Explanation of performance
Value Target Value Targe
t Value Value Value Value Target Value
% of members enquiries completed
within timescale by E,H&I 87% 85% 93% 85% 91% 92% 94% 93% 85% 92%
Environment, Housing &
Infrastructure received 5,084
members enquiries in 2023/24, of
which 92.3% were responded to
within timescale.
% of FOI requests completed within
timescale by E,H&I 96% 100% 100% 100% 100% 99% 100% 100% 100% 100%
Environment, Housing &
Infrastructure dealt with 257
Freedom of Information requests in
2023/24, of which 256 (99.4%) were
responded to within timescale. 103
of these requests were cross
departmental and 154 were
departmental.
% of front-line resolutions dealt with
within timescale by E,H&I 81% 85% 87% 85% 88% 89% 88% 77% 85% 85%
Environment, Housing &
Infrastructure received 9,395 front
line resolutions in 2023/24, of which
85.1% were responded to within
timescale.
% of complaint investigations
completed within timescale by E,H&I 65% 95% 93% 85% 95% 95% 81% 84% 85% 89%
88.8% of 508 investigation
complaints received have been
responded to on time

Page 33

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Living our Values
Indicator Current
Status
2021/22 2022/23 Q1 Q2 Q3 Q4 2023/24 2023/24
Explanation of performance
Value Target Value Target Value Value Value Value Target Value
Complete inspection process for all
headstones and burial grounds 38% 20% 85% 65% Not measured for quarters 100% 93%
The service has carried out 29,600
headstone inspections which
equates to around 93%, however
this figure is continuing to rise daily
and so too is the number of new
lairs added. Neighbourhood
Services continue to inspect all
new and existing lairs
Average number of work days lost
through sickness absence per
employee (FTE) (cumulative)
As reported to the Audit, Risk and Scrutiny Board in
August 2023 (Agenda item 5), E,H&I is a new service
with no previous data.
3.5
days
3.36
days
3.93
days
4.12
days TBC 14.91
days
As reported to the Audit, Risk and
Scrutiny Board in May 2024

Page 34

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Delivering the Council Plan – Cross Cutting Theme -
What we will do Due Date Status Progress update
EH&I will work towards keeping
The Promise 31 March 2024
Service Areas have been liaising with the Council's Promise lead officer to ensure the service is supporting The
Promise.
Develop a Play Parks Strategy
31 March 2024 A play parks strategy titled, ‘Outdoor Access & Play Area Improvements 2023 – 2026’ was approved at the
Infrastructure, Land and Environment Policy Board meeting held on 30 August 2023.

Page 35

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Environment, Housing & Infrastructure
Service Improvement Plan 2023 - 26
Outturn Report
May 2024