Electric Vehicle Charging Infrastructure (EVCI) - Regional Collaboration

Renfrewshire Council · 20 March 2024
Back to Infrastructure, Land and Environment Policy Board — 20 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

_________________________________________________________________________
To: Infrastructure, Land and Environment Policy Board
On: 20 March 2024
_________________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure
_________________________________________________________________________
Heading: Electric Vehicle Charging Infrastructure (EVCI) - Regional Collaboration
_________________________________________________________________________
1. Summary 
1.1. This report provides the Infrastructure, Land Environment Policy Board with an
update on work undertaken to develop a collaborative approach to expanding the
public electric vehicle charging infrastructure network across the 8 local authorities of
Glasgow City Region and seeks approval for the next steps required to progress
towards a commercial delivery arrangement. 
1.2. A version of this report is being submitted to each of the 8 local authorities in the
region to secure local approval for the proposed approach of this project.  
_________________________________________________________________________
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board: 
2.1 Notes the content of the report and the collaborative work undertaken to date;
2.2 Approves the participation of the Council in a collaborative procurement to engage a
commercial partner through a partnership with all 8 local authorities in Glasgow City
Region, to deliver the benefits set out in the report (Section 3)
2.3 Notes the detail at section 7.2 regarding the proposed cessation of Chargeplace
Scotland by the end of 2025 and the Council will have to have alternative
arrangements in place for back-office systems regardless of the delivery model
agreed
2.4 Agrees in principle to entering into an Inter Authority Agreement (IAA) among the 8
local authorities, and delegate the subsequent procurement and commercial
decisions relating to the commencement and conclusion of the procurement process
to the Director of Environment, Housing and Infrastructure, in line with the approach
set out in the report (Section 7); and,
2.5 Instructs officers to provide update reports on the progress of the work to the
Infrastructure, Land and Environment Policy Board as required throughout the
development of the project.
_________________________________________________________________________

Page 2

3. Background 
3.1 This section summarises the work that has been undertaken to date to support the
expansion of the EVCI network across Renfrewshire and the other 7 local authorities
in Glasgow City Region. 
3.2 In January 2022, the Scottish Government launched the Electric Vehicle
Infrastructure Fund (EVIF) with the objective of unlocking private sector investment to
expand the publicly accessible charging network on local authority land and assets.   
3.3 Transport Scotland has engaged the Scottish Futures Trust to support local
authorities in the development of their EVCI strategies and is also actively
encouraging local authorities to collaborate in their strategy and delivery activity to
expand the charging network. 
3.4 At the outset it was agreed that a regional approach to this issue would be
advantageous to all local authorities in order to secure maximum return but also to
provide the widest possible coverage of EV infrastructure across the region. 
3.5 In December 2021, Renfrewshire and the 7 other local authorities agreed to progress
an initial report into current electric vehicle charging provision, tariffs, and forecast
future needs of the authorities, jointly funded using the EVIF allocations for each local
authority.  The report was concluded in June 2022. 
3.6 Further to the initial report, Renfrewshire and the 7 other local authorities engaged
consultants on behalf of the local authorities to develop more detailed Strategy and
Expansion Plans (SEP).   
3.7 Building upon the SEP, the GCR Electric Vehicle Senior Officers’ Group (‘the Senior
Officers’ Group’) was established, chaired by South Lanarkshire Council, and with
senior officer representation from each of the 8 GCR member authorities (MA’s). 
3.8 The Senior Officers’ Group oversaw a Prior Information Notice (PIN), published in
June 2023, to engage with the Charge Point Operators (CPOs), explore market
appetite and inform GCR’s approach to the expansion of EVCI. There was significant
private sector interest with 33 responses received and a clear preference expressed
by most CPOs to engage collaboratively with all 8 GCR local authorities as part of a
planned and strategic approach. 
3.9 In August 2023, GCR Cabinet agreed that a collaboration between the local
authorities to expand the EVCI network should be based upon a clear set of agreed
principles: 
i. To deliver a just transition, we must ensure equitable access to electric
vehicle charging infrastructure, with a clear recognition of geographical
characteristics and the different solutions that may be applicable.
ii. Ensure that all residents are able to access electric vehicle charge points
close to their home.
iii. Align with the priorities of the Sustainable Travel hierarchy to ensure that
public transport, walking, wheeling and cycling options are prioritised
wherever possible.
iv. Collaborate across the GCR member authorities to identify cost savings and
ways to deliver a high standard of customer experience.
v. Work together to identify and overcome grid capacity issues.
vi. Identify opportunities to develop joint public and fleet EVCI projects, and
where there are opportunities to align with HGV, hydrogen refuelling and the
introduction of rapid and ultra-rapid charging stations.

Page 3

3.10 Further commercial and financial analysis was undertaken during the summer of
2023, to more fully understand the risks and opportunities of the different commercial
arrangements that local authorities could use to expand EVCI. On 7 November 2023,
the Cabinet was advised of the conclusion of this stage of the work with a preferred
approach to progress through a continued collaboration among the 8 local authorities
on the basis of a concessionary-type commercial model.
4. Objectives and Benefits of GCR Collaboration 
4.1 The work to date indicates clear advantages of progressing with the expansion of the
public EVCI network as a collaboration of GCR’s 8 local authorities. 
4.2 Collaborating to expand the EVCI infrastructure overs a range of benefits for the local
authorities’ wider policy objectives and these are described in the following
paragraphs.   
4.3 Leveraging Private Sector Investment 
Proceeding with a collaborative concession type contract provides the opportunity to
maximise the amount of private sector investment to pay for the majority or totality of
the new EVCI.  The PIN exercise (see 3.8 above) indicated an appetite from a
number of chargepoint operators to fully fund the expansion of the network, with
none of the capital costs being provided by the local authorities (this was dependent
on other contract conditions, such as the contract term).   
4.4 The additional chargepoints forecast in the Strategy and Expansion Plan indicated a
total capital cost of £71 million across the City Region. It will be an objective to
develop a proposal that can be fully funded by the commercial partner with no
requirement upon the local authorities to fund the infrastructure costs.  There
will be an amount of capital grant available from the EVIF to assist in the delivery. 
The amount has not yet been agreed by Transport Scotland. 
4.5 From a Renfrewshire perspective, should we wish to go out alone on a Renfrewshire
only basis, the indicative capital costs are estimated to be in the region of £10million
at 2023 prices, this figure will only increase and any future model should deliver the
best return for the area. 
4.6 Financial & Commercial Risks 
A concession-type commercial arrangement would allow the local authorities to
transfer the potentially significant commercial, financial, technical, and
regulatory risks to a commercial partner.  It is proposed that a private sector partner
would be invited to take on the operation, maintenance, and ownership of the existing
network of 600 (approx.) local authority owned chargepoints in GCR, as well as
providing the investment required to significantly expand the number and location of
chargepoints equitably across the City Region. 
4.7 Generating an Income Stream 
Allowing a commercial partner to operate EVCI on local authority land and assets
has the potential to generate an income stream for the GCR local authorities.  This
could be through a variety of different arrangements – e.g. income share, revenue
share, a rental fee, or a combination. The amount and type of income stream will be
influenced by the broader commercial arrangements of a contract, such as the
contract term and where the risks and responsibilities are assigned between the local
authorities and private partners. 
4.8 Economies of Scale and Reduced Duplication of Effort

Page 4

While the objective of this project is to expand the EVCI network at no/minimal cost
to the local authorities, collaboration offers significant economies of scale and
financial savings during the developmental and delivery phases. The cost of technical
consultancy support, procurement, and programme management will be shared
among the 8 local authorities.  Discussions between the PMO and consultants during
initial soft market testing prior to going to the market indicate that this saving could be
in the region of £500,000 across the authorities.   
4.9 There will be other, currently unquantified, savings in an arrangement where one
lead local authority, acting on behalf of all 8, enters into a contract with a commercial
partner, avoiding the need for 8 individual procurement and contracting exercises
and the costs associated with this. It is also proposed the long-term contract
management arrangements could be undertaken by a central team, with the ongoing
costs of this met through the pooling of an element of the local authority income
stream generated by the contract. 
4.10 Again, from a Renfrewshire perspective, should we wish to pursue this agenda on
our own, the level of resource required for procurement and contract management
would all need to be put in place and all associated risk coming to Renfrewshire
alone. 
4.11 Ensuing All Communities Can Access the Chargepoint Network 
Through collaboration we can take a strategic approach to locating EVCI.  CPOs will
be able to make commercial decisions looking across a much larger number of
chargers and will be able to balance high usage sites against lower usage areas. The
scale of a GCR collaboration will enable private investment in the network where
individual local authority initiatives on their own may be too small to be commercially
attractive. 
4.12 Taking a package of sites across all local authority areas to the market will also avoid
a situation where local authorities are going individually and competing for CPOs – a
situation where GCR local authorities were competing to secure engagement with
CPOs would disadvantage those areas seen as less attractive and wouldn’t meet the
objective of making EV chargers available to all, especially more disadvantaged
communities within the City Region. Taking a GCR collaborative approach will allow
GCR to go to the market at scale, giving a stronger voice in the sequencing of
installation and the locations in which chargers are sited, ensuring that no
communities are neglected. 
4.13 Community and Supply Chain Benefits 
Responses to the PIN, issued in June 2023, indicated that given the scale and
commercial attractiveness of a GCR collaboration, some CPOs were explicit in their
intention to work with local supply chains during the installation and the ongoing
maintenance of such a large EVCI network. These opportunities will be explored
during the procurement process. As with all major contracts, there will be a
requirement for the inclusion of community benefit clauses in the tender and
procurement process.   
5 Potential Shape of a GCR EVCI Collaboration 
5.1 In early January 2024, the Scottish Futures Trust (SFT) and officers from GCR
Programme Management Office undertook a series of workshops with officers from
each of the eight local authorities.  The workshops were structured around discussion
of key issues relating to potential: 
• commercial arrangements with a private sector partner; 
• joint working arrangements between the local authorities; and

Page 5

• procurement options and routes to market. 
5.2 A number of the key technical aspects of a future commercial arrangement with the
private sector were discussed at the workshops, providing a firm basis to develop
joint tender documents that would be used in the procurement process to identify a
private partner. 
5.3 The total number of residential, destination, and journey chargepoints that were
forecast in the GCR SEP are set out in the table below and broken down by local
authority. 
Residential AC
(7kW)
Destination AC
(7 – 22kW)
Journey - Rapid DC
(50kW +)
East Dunbartonshire 105 66 17
East Renfrewshire 143 122 29
Glasgow City 1,317 207 53
Inverclyde 172 93 36
North Lanarkshire 481 276 34
Renfrewshire 405 258 51
South Lanarkshire 467 242 33
West
Dunbartonshire 141 81 9
GCR Totals 3,231 1,345 262 
5.4 Following discussions among the MAs, SFT and Transport Scotland, and informed by
the consultation with the market through the PIN issued in June 2023, the proposed
approach discussed with the EV Senior Officers’ Group and the GCR Chief
Executives’ Group, is to split the total number of forecast chargepoints into a
series of lots.  This pragmatic approach will help to align EVCI installation with the
capacity of the market and of local authorities to deliver across the proposed sites. 
5.5 The proposed approach, based on discussions with officers from the local authorities,
is that the first lot of chargepoints should include: 
- all existing EVCI (approximately 600);
- all destination AC (7-22kW) chargepoints (approximately 1,345);
- all rapid DC (50kW) chargepoints (approximately 262); and,
- 20-25% of the forecast residential chargepoints (approximately 650-800). 
5.6 In addition, it is also proposed that the first lot will also include sites where there is
the opportunity to install Ultra Rapid Charging (100kW to 350kW). The SEP identified
potential sites that met a set of basic criteria where they may be attractive as ultra-
rapid charging stations. Further work will be required to identify which of these sites
can be progressed. 
5.7 The exact number of EVCI locations and chargepoints will be determined during the
site selection process.  Each local authority will require to undertake their own
analysis about the suitability of the proposed locations for EVIF included in the SEP
and to provide a list of sites within their area to be included in the package that is
offered to a commercial partner.  Each local authority will also be asked to prioritise
these sites.   
5.8 It is anticipated that subsequent lots will be weighted towards the remaining
residential charging infrastructure, and any additional journey and destination sites
that are identified. During the development of the procurement documents a strategy
for bringing future lots to the market will also be considered. 
6 Joint Working and Procurement Options

Page 6

6.1 The feedback from the officer workshops demonstrated support for a collaboration
across GCR through the planning, procurement and delivery stages.  There was also
a recognition of the need to put in place an Inter-Authority Agreement to facilitate this
collaboration. 
6.2 There was a consensus view expressed in the workshops that one local authority
should contract with a commercial partner on behalf of all 8 MAs, with a preference
for a single procurement, rather than establishing a framework for MAs to draw down
from. 
7 Draft Timeline 
7.1 If the approach to progress the collaboration is approved by Infrastructure, Land and
Environment Policy Board then the GCR PMO will work with the EV Senior Officers’
Group to monitor the operational timeline for delivery of the project.  Current key
dates are set out below: 
Action/Milestone Estimated
Date/Timescale
Finalise EVIF arrangements for consultancy support February 2024
Engage Consultancy Support for the Procurement Stage February to April 2024
Secure Local Authority Agreements to Collaborate on EV March to May 2024
Appoint Consultants to Support Development of Tender
and GCR Proposal
May/June 2024
Preparation of Tender Documents  June to November 2024
Commence Procurement December 2024/January
to April 2025
Evaluation of Tenders  May to June 2025
Contract Awarded to CPO July to August 2025
Charge Place Scotland Transition  
Network Planning & Mobilisation
September to December
2025 
New Chargepoint Installations January 2026 onwards 
7.2 The most pressing issue is Transport Scotland’s decision not to renew the Charge
Place Scotland (CPS) contract. This will require all local authorities (and other
chargepoint owners currently using the CPS system) to put in place an alternative
arrangement for the back-office and maintenance of their chargepoints before
December 2025.  GCR’s ambition is to have these 600 (approx.) existing
chargepoints included within the scope of the first lot, however there is a significant
risk that the timing of this new arrangement being in place will fail to align with TS’s
ending of the Charge Place Scotland service. The GCR PMO is liaising closely with
TS to identify potential mitigations for this risk.   
8. Governance and Support arrangements 
8.1 A collaboration of the 8 GCR local authorities will require a clear governance and
decision-making process. In addition to endorsement by the Glasgow City Region
Cabinet, the key decisions will require the approval through the relevant local
governance structures of each of the 8 authorities.   
8.2 The collaboration will also require an Inter Authority Agreement to be put in place and
signed off by all 8 GCR local authorities.  In order to allow the project to meet the
proposed timeline set out above, this report proposes that: 
- the approval of the Inter Authority Agreement;
- issuing of the tender documents; and,

Page 7

- approval of the preferred bidder and agreement to enter into a contract;
is delegated by the Infrastructure, Land and Environment Policy Board to the Director
of Environment, Housing and Infrastructure on behalf of Renfrewshire Council.
8.3 All 8 local authorities will require to approve the proposed approach through their
own local governance structures prior to any contract being entered into. A longer-
term agreement between the 8 GCR local authorities will be finalised at the point of
entering into a contract with a commercial partner – this will include the ongoing
contract management arrangements. 
8.4 In order to support the development of the tender documents, site selection process,
and development of the GCR EVCI proposal, Glasgow City Region PMO will
continue to provide support to the EV Senior Officers’ Group. Expert technical
consultancy support will be engaged by the GCR PMO and funded by contributions
from each local authority through their allocations from Transport Scotland’s EVIF. 
8.5 To ensure each local authority is engaged in the development process and able to
influence the development of the tender, officer support groups will be established to
provide expert advice and to update their own organisations as required. In addition
to the existing EV Senior Officers’ Group, it would also require groups with a focus on
legal, procurement, and technical aspects. 
9. Next Steps 
9.1 The next steps that will be progressed if the recommendations to this report are
approved: 
i. Finalise an Inter Authority Agreement among the 8 local authorities with sign
off delegated to the Director of Environment, Housing and Infrastructure;
ii. GCR PMO will secure expert external consultancy support to draft the tender
and technical documents, and oversee the site selection process;
iii. Put in place a procurement strategy to go to the market to identify a
commercial partner;
iv. Undertake a site selection process with each local authority to identify their
preferred sites for the location of EVCI;
v. Commence a procurement process with Glasgow City Council, on behalf of
the 8 local authorities, acting as the Lead Authority for the procurement stage;
and,
vi. Evaluate the responses to the tender and recommend appointment of a
commercial partner. 
10. Financial and Revenue Implications 
10.1 The intention is to utilise Transport Scotland’s EVIF to meet the costs of the
development of the GCR proposal, development of the procurement documents,
specialist external legal advice, and other costs associated with the development of
the collaboration. Each local authority will contribute a portion of their grant award
which will be pooled by the GCR PMO who will engage the required consultancy and
advice services on behalf of the 8 local authorities as required. 
10.2 The overarching aim of the approach set out in this report is to leverage private
sector investment so that no/or minimal capital investment is required from the local
authorities to deliver the expansion in EVCI.  On this basis there is not anticipated to
be any requirement for capital investment.

Page 8

10.3 It is anticipated that the long-term contract management of the commercial
arrangement will be met by the collective income stream that is generated.  It is
suggested that the income stream from a commercial partner is pooled to meet the
central contract management costs, with the surplus income then being distributed
among the local authorities based upon an agreed formula. 
10.4 Overall, there should be no cost to Renfrewshire Council and the other local
authorities from this proposed approach.  However, this will depend on the market
appetite to engage with GCR and can only be confirmed on conclusion of the
procurement process. The funding to provide the resource required to deliver the
procurement exercise is all being met from Transport Scotland’s EVIF fund. 
11. Legal Implications 
11.1 The main legal requirement will be the establishment of an Inter Authority Agreement
that allows one local authority to act as lead in the process to procure and contract
with a commercial partner on behalf of the other 8 authorities. 
11.2 There will be a requirement for expert external legal advice to support the
development of the GCR proposal and this will be engaged by the GCR PMO. 
11.3 A legal support group, consisting of solicitors from each of the 8 local authorities, will
be established to support the development of the project.
___________________________________________________________________
Implications of the Report
1. Financial – At the current time, the financial implications are unknown, although the
preferred model is for the Council to incur no capital or revenue expenditure costs
and to generate revenue as a result of the preferred model.   
2. HR & Organisational Development – None 
3. Community/Council Planning – 
• Our Renfrewshire is thriving – providing access to charging facilities for electric
vehicles across all communities will ensure no communities are left behind. 
4. Legal – early engagement has been carried out with officers in Legal Services to
identify any potential risks with the various models under consideration and this will
continue throughout the procurement process. 
5. Property/Assets – None 
6. Information Technology – None 
7. Equality & Human Rights -  The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights. No
negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in the
report because for example it is for noting only.   If required following implementation,
the actual impact of the recommendations and the mitigating actions will be reviewed
and monitored, and the results of the assessment will be published on the Council’s
website.
8. Health & Safety – None.
9. Procurement – early engagement has been carried out with officers in Procurement
to identify any potential risks with the various models under consideration and this
will continue throughout the procurement process.

Page 9

10. Risk – Detail of associated risks will be worked through with the Council’s Risk
Manager when details of potential preferred models become available.
11. Privacy Impact - None 
12. COSLA Policy Position – None.
13. Climate Risk – The proposed expansion of EV infrastructure across Renfrewshire
and the wider City Region complements the overall aims of the Council’s Ren Zero
plan.
____________________________________________________________________
List of Background Papers
____________________________________________________________________ 
Author:  Gerard Hannah, Head of Climate, Public Protection and Roads