Service Update Report

Renfrewshire Council · 20 March 2024
Back to Infrastructure, Land and Environment Policy Board — 20 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

_________________________________________________________________________
To: Infrastructure, Land and Environment Policy Board 
On: 20 March 2024
_________________________________________________________________________ 
Report by:  Director of Environment, Housing & Infrastructure
_________________________________________________________________________ 
Heading:  Service Update Report
_________________________________________________________________________ 
1. Summary 
1.1 This report provides an overview of key service activities since the last Policy Board
report on 24 January 2024 and an update on the services and key projects delivered
during this period. 
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board: 
2.1 Approves the content of this report. 
3. Background 
3.1 Environment, Housing & Infrastructure provides essential services to every household
in Renfrewshire and works in partnership with the local community, other service
areas and Community Planning Partners, to deliver key Council priorities and
initiatives. A progress update on the main activities delivered by the services in
respect of the areas of activity delegated to this Policy Board, is detailed below. 
Updates for Infrastructure, Land and Environment Policy Board 
4. Climate Change
4.1 Energy Management
ECO4 Flex  
4.1.1 ECO4 Flex will allow the Council to approve funding to Renfrewshire’s private sector,
fuel poor households that do not meet criteria for other schemes, as well as low-
income households that are vulnerable to the effects of the cold. The scheme is part
of the UK Government Energy Company Obligation and is managed by Ofgem.

Page 2

4.1.2 The qualifying criteria for ECO-Flex, as set by Ofgem, is published on our website in a
document called a Statement of Intent. Renfrewshire’s Statement of Intent can be
found here: https://www.renfrewshire.gov.uk/media/15354/ECO4-flex-statement-of-
intent/pdf/Renfrewshire_Council_Statement_of_Intent_for_ECO4_flex.pdf?m=167568
7584337ECO-flex. ECO-flex, does not apply to Council Housing or Registered Social
Landlords.
4.1.3 The energy efficiency measures being installed within Renfrewshire include: boilers,
loft insulation, cavity wall insulation, air source heat pumps, solar panels, heating
controls, first time central heating etc.
The table below highlights the savings ECO4 Flex has achieved to date based on
annually recurring savings:
Financial
Year
Value of Grant
Funding
Requested (£)
Total Annual
CO2 Saving in
Kg
Total Annual
Cost Saving (£)
2023/24 £2,811,545        565,600 £181,870 
4.2 Local Heat and Energy Efficiency Strategies (LHEES)
4.2.1 Renfrewshire Council’s Local Heat and Energy Efficiency Strategy was approved at
this Board in January 2024. The Energy Team are currently working on the delivery
model as part of phase 2 of the project.
4.2.2 Renfrewshire have been successful in obtaining funding for 5 feasibility studies to
look at the potential for proposed heat networks. The areas of focus are Foxbar,
Johnstone, Paisley West, Paisley East and the potential to extend the existing Energy
Centre at the Advanced Manufacturing Innovation District Scotland (AMIDS). This
takes the funding for District Heating feasibilities up to £250,000 through Zero Waste
Scotland.
4.3 Winter Resilience Update
4.3.1 To the middle of March 2024, the Winter Maintenance programme has used a
cumulative total of over 4,606 tonnes of salt gritting Renfrewshire roads, although the
winter season has some time to go, this volume alludes to an average winter period.
The service has continued to grit our primary and secondary network routes during
this period. Grit bin stocks continue to be replenished as and when required.
4.3.2 Since 1 April 2023 to 5 March 2024, the service attended to 37,480 gullies with 85%
of these cleaned on the first visit. This figure significantly improves upon previous
years performance.  Processes are in place where arrangements are made to re-visit
those gullies that could not be accessed due to parked cars or where gullies require
further investigation.
4.3.3 During the winter period, the service responded to a number of severe weather
events which required the Roads and Neighbourhood Services teams to work
together on a 24/7 basis to support communities during periods of severe weather.

Page 3

5.         Team Up to Clean Up 
5.1.1   Team Up to Clean Up partners SEPA, Zero Waste Scotland and Keep Scotland
Beautiful are delivering 5 events across Scotland to gather the views of communities
in accordance with the new Scottish Litter & Flytipping Strategy.  Renfrewshire House
hosted the Renfrewshire Community Litter Workshop on 21 February. The event
proved very popular, providing attendees an opportunity to share ideas, learn about
behaviours and attitudes and what they can do to help.  
5.1.2   Zero Waste Scotland has partnered with University College London Centre for
Behaviour Change to investigate the complex causes of littering and flytipping
behaviours.  Renfrewshire responded to the survey issued which aims to generate a
new approach to preventing items becoming litter/flytipping, and tackle behaviours
through effective intervention.
5.1.3   The Big Spring Clean was launched on 1 March and is operating across March and
April.  Schools are registering their ongoing interest in delivering local litterpicks
and/or receiving a school presentation.  The Team is further working with local retail
parks to encourage take up there, presenting a more attractive area for customers, so
far Linwood fast food retailers have agreed to join the event.
5.1.4   Three further Wildflower Workshops will be delivered over the course of the Big
Spring Clean, one in Elderslie, hosted by Evergreen Elderslie, one in Paisley at the
West End Growing Ground Association (WEGGA) Sanctuary Gardens, and the final
workshop in Renfrew at Broadloan, hosted by Renfrew Association of Growing
Grounds (RAGG).  Groups and individuals will be treated to a workshop then attend
an onsite area for a demonstration. 
5.2  Environmental Taskforce 
5.2.1    The Environmental Taskforce continues to deliver intervention to reduce instances of
flytipping. Key statistics for the most recent period are:
Action  2023 total 1 Jan – 29 Feb
Proactive visits to identified
hotspot areas 
2,258 506 
Number of reports investigated  1,321 378
Tonnes of flytipping removed  436 48 tonnes
Number of sites secured to
prevent further flytipping 
11 1
Letters to private landowners re
flytipping
85 7 
Visits to businesses to ensure
Waste Disposal Arrangements in
place 
126 17 
Fixed Penalty Notices Issued  93 11

Page 4

5.2.2    Using captured footage, the first £500 Fixed Penalty Notice was issued in
January to a company, based out with the Authority, who flytipped in Paisley.
6. Fleet, Roads and Transportation 
6.1 Fleet Services 
6.1.1 As part of the Capital Vehicle replacement programme Roads services have procured
a Multihog MH75 & Planer. This is an additional vehicle to the service that will
perform a range of municipal duties including highways and winter maintenance. This
vehicle is a common tool carrier for pothole, patching and pre surfacing patching
applications. This machine maximises productivity, efficiency, and safety to reduce
costs whilst improving permanent repair outputs.  The service has also procured an
additional roads gully vehicle, a highly developed, multifunction machine ideal for
working on mainline sewers, gullies, and drains. Elsewhere in the Council there have
been three electric vehicles ordered, bespoke vehicles for the Dog Wardens service,
Community Meals services these will be delivered and added to operations in the
next few weeks.   
6.1.2  The Driver and Vehicle Standards Agency have recently carried out an in-depth
desktop audit of the Councils fleet operations. This is the first audit the Council has
had for many years. Local Authorities across Scotland are being audited at this
current time. These audits are complex and include Vehicle Maintenance, Drivers
Hours, Policies & Procedures and Operating Centres. The report concluded a
“satisfactory” result with some minor opportunities for improvement, with no need for
an onsite audit and inspection. This is a positive outcome for the Council and in
particular the Fleet Management Compliance Team and the operational services that
utilise heavy fleet. The risk rating on the Councils Risk register for Fleet Compliance
and operator licence will be reviewed and lowered as a result of this outcome.  
6.2 Roads & Transportation
6.2.1 Roads Capital Investment Programme
6.2.2   The service has concluded the roads and footway resurfacing programme for
2023/24.
6.2.3   The service is currently finalising the capital investment programme for 2024/2025,
this revised programme will take cognisance of the capital budget taking the total
Capital Investment to £5million in 2024/25, in addition to money carried over from
2023/24 where some schemes were delayed into 2024/25.
6.2.4   Recent Local Government Benchmarking Framework (LGBF) data has shown that
there have been improvements in Renfrewshire’s roads across every road category in
recent years and significantly better than the Scottish average, with road condition
sitting in the top quartile for its condition in 3 of the 4 categories, as summarised
below:
• A class roads – The percentage of roads requiring maintenance is 15.5%
(2018 figure was 23.8%), against a Scottish average of 27.2% 
• B class roads - The percentage of roads requiring maintenance is 19.2%
(2018 figure was 26%), against a Scottish average of 31.5% ,
• C class roads - The percentage of roads requiring maintenance is 27% (2018
figure was 37.5%), against a Scottish average of 32.7, and

Page 5

• Unclassified roads - The percentage of roads requiring maintenance is 30.1%
(2018 figure was 35.1%),against a Scottish average of 36.4%,
6.2.5 In addition to the capital investment programme the service continues to perform to a
high standard in relation to reactive roads maintenance, with the pothole performance
of the year being 96% of potholes being responded to within the time period specified
by their classification. During the winter period, the service expects to receive a
higher than average number of potholes and where necessary due to traffic sensitive
locations or emergencies will carry out a temporary repair. This temporary repair is
then scheduled for a permanent repair to allow planning for appropriate traffic
management arrangements. 
6.3 Active Travel & Infrastructure Improvement Update
6.3.1  The next phase of the Paisley to Renfrew active travel route including upgraded
shared footways with new lighting columns at Wright Street from the new housing
development to business units towards White Cart Water will start in May.  Pedestrian
crossings at Gilmour Street and Niddry Street to Toucan crossings will commence in
April 2024.
6.3.2 An application for a new active travel route around Inchinnan Business Park has been
submitted to Active Travel Infrastructure Fund in February 2024.  This £1.1 Million
project, if approved, will link with the segregated shared active travel route on
Barnsford Road to Inchinnan Drive due for completion in May 2024 and the existing
active travel route at Inchinnan Road. This is an important element in the Council’s
active travel network and will connect to existing routes around Glasgow Airport.  In
addition, City Deal Teams re-applied for AIMDS South Gallowhill link to existing
Paisley to Renfrew active travel route. 
6.3.3 Transport Scotland’s Bus Partnership Fund has been removed in 2024/2025 with no
guarantees that this will be re-instated in future years. This means planned
improvements at two Paisley town centre junctions (Glasgow Road, Mill Street,
Gauze Street and Incle Street; and Gauze Street, Cotton Street and Lawn Street) will
not be progressed. We would like to thank everyone who took the time to provide
feedback and share their views during the stakeholder engagement period. Our
transportation team is considering the specific feedback in detail in case there are any
future improvements which can be brought forward for detailed consideration and
engagement as part of our wider strategic transport and travel planning. This does not
impact on work to upgrade the traffic signals introducing bus prioritisation technology
on Glasgow Road at the junctions with Lacy Street, Penilee Road and Hawkhead
Road. This work is fully funded through the Bus Partnership and is currently
underway, being completed by Spring 2024. 
6.3.4 SPT Capital Programme in 2024/2025 has been reduced to zero from the annual £1.2
Million capital funding provided for New Pedestrian Crossings, traffic signal upgrades,
bus boarder kerb installations. Officers are currently reviewing what options exist in
order to deliver some of these areas during 2024/25.
6.3.5 Construction of a replacement Plymuir Bridge in Gleniffer Braes Paisley was
completed on 8th March 2024.  This brings the last council-owned bridge up to
national requirement of being able to carry 40 tonnes.
6.3.6 The construction phase for a bus turning circle at Linburn Road in Erskine started in
February 2024. The initial phase of public utility diversionary works include working
with BT Openreach, Virgin Media and SGN then requires tying into the Contractors
submitted schedule.  The recent announcement that the SPT Capital Programme in
2024/2025 has been reduced to zero has placed the continued construction phase at

Page 6

risk.  Officers are working with SPT to determine what funding options exist to deliver
this project during 2024/25.
6.3.7 Consultants continue to analyse data from survey locations that may be suitable for
exemption from the Pavement Parking Ban. The exemption traffic regulation order will
then be prepared for consultation. Elected Members, emergency services and
community councils will be consulted in the first stage of the consultation process
before the second stage wider public consultation.  Objections permitting, the ban will
become enforceable in November 2024.
7. Neighbourhood Services (formerly Streetscene Services) 
7.1 Play Parks/ Parks
7.1.1  Refurbishment of Howwood Park Toddler / Junior, Houston Public Park and
Inchinnan Playing Field play areas is now complete. 
7.1.2 Installation of the next 6 play areas to be renewed through Capital and Scottish
Government grant will commence from mid-March. These are Miller Street,
Johnstone; Anne Avenue, Renfrew; Netherhill Road, Paisley; Victory Gardens,
Renfrew, Tannahill Crescent, Johnstone and Urquhart Crescent, Renfrew. 
7.1.3 The Lawn Tennis Association (LTA) funded project to upgrade the tennis courts at 3
locations in Renfrewshire, is nearing completion. The sites are Brodie Park, Paisley,
Robertson Park, Renfrew and Park Road, Johnstone. Courts at all 3 locations will be
painted at the earliest opportunity from early April, however, the weather needs to be
mild and dry to allow completion.
7.2 Grass Cutting 
7.2.1 The recruitment of the seasonal workforce for the grass season is complete, cutting
will commence at the beginning of April, with preparatory works starting mid-March,
these will include strimming, edging, tidying any grassed areas before cutting and
training and induction for the workforce. 
7.3 Clyde Muirshiel
7.3.1  Regional Park staff deliver many recreational, conservation and health and welling
services to benefit the environment, visitors, and locals alike.   
7.3.2 Winter maintenance activities are nearing completion, public consultation for Parkhill
Wood on the next Woods In and Around Town (WIAT) application is progressing.   
7.3.3 ‘Dark Sky’ evenings, hosted with Coats Observatory staff at either Castle Semple or
Clyde Muirshiel Country Park have been very popular, selling out within 24 hrs of
being advertised.   
7.3.4 With Easter being early in 2024, summer opening hours for retail and catering
activities begin at both Country Parks on Fri 29 March.  The Outdoor Activities team
are already busy with primarily school bookings. 
7.4 Monuments, Statues & Memorials
7.4.1 Neighbourhood Services have commissioned a conservation specialist to survey and
provide condition reports for 14 key monuments and memorials in Renfrewshire. We
have prioritised the war memorials due to more than one of them being in their
centenary year. The Paisley Cenotaph was surveyed on 23rd February and a

Page 7

comprehensive condition report was produced, the Johnstone War Memorial in
Houston Square was given a specialist wash last month and is also on the list to be
surveyed as it approaches its centenary in May this year. The John Forbes Orr and
Robert Allan Drinking Fountain are also due to be surveyed as part of initial surveys. 
8. Recycling Performance and Waste Collection
8.1 The Scottish Government has set the ambitious targets to recycle 70% of all waste,
with a maximum of 5% going to landfill by 2025.
8.2 Waste policy continues to evolve with a national route map being developed
identifying major policy interventions which drive forward zero waste and deliver a
circular economy. 
8.3 Locally, we are working towards Renfrewshire being net zero by 2030 and part of this
will be achieved through a zero-waste society, maximising reuse, recycling and
recovery of resources.
8.4 Our recycling rate in Renfrewshire continues to improve, and
is just under 54%, placing us in the top eight councils in
Scotland, while in 2022, 2.3% of waste was landfilled. Our
ability to reduce the amount being landfilled results from
investment in an energy-to-waste facility.
8.5 A recent waste composition analysis of grey bin waste in
Renfrewshire carried out by Zero Waste Scotland over 2022
to 2023 found 61% of material should have been recycled or
disposed of elsewhere. Of this, 33% was food waste, 15%
plastic, cans, and glass, 6% paper and card, 6% should have
been disposed of at a Household Waste Recycling Centre
and 1% was garden waste.
8.6 Analysis of food waste in Renfrewshire found just 19% is
being recycled in the correct bin, with 74% being put in the
grey general waste bin and 7% in the wrong recycling bin.
8.7 Our waste team has applied for capital funding from the Scottish Government
Recycling Improvement Fund which is managed by Zero Waste Scotland.
8.8 This is to fund a package of measures which will enable us to greatly improve our
recycling performance in Renfrewshire and address local challenges including the
need for better recycling infrastructure at flats and high-rise properties and extending
the full range of recycling facilities to all Renfrewshire homes. It will also include the
procurement of a route optimisation and collection management system to improve
the consistency, reliability and overall quality of the household waste collection
service, while maximising operational efficiency. This will be beneficial when
scheduling collections by reducing the number of miles covered while collecting these
waste streams, having a positive impact through lower carbon emissions and reduced
operating costs.
8.9 We expect to hear the outcome of this funding bid in May and will bring back a
detailed report to a future board for consideration. 
8.10 Separate to the Recycling Improvement Fund bid, a review of our waste collection
arrangements has identified opportunities to simplify the process, support greater
participation in recycling, tackle contamination of waste and reduce the carbon
emissions from our waste collection vehicles.

Page 8

8.11 Currently we collect different colour waste and recycling bins on the same day across
multiple routes.
8.12 A project is being developed whereby all households would have the same recycling
bin collected on the same day, following the pattern:
Week 1 - Blue bin
Week 2 - Brown bin
Week 3 – Green bin
Week 4 – Brown bin
8.13 The grey general waste bin would be moved to a separate collection day, with the
collection frequencies of each bin remaining the same.
8.14 The service is looking to introduce this approach as part of an initial first phase to
households who currently have a Saturday bin collection.
8.15 During this phase, recycling bins would continue to be collected on a Saturday and
general waste bins would be collected on a Wednesday. 
8.16 Specific details and timings of the initial phase are currently being developed and
further information will come forward as to implementation. Householders who require
assisted collections or additional collections will continue to receive this. 
8.17 Outcomes will be reported to the Infrastructure, Land and Environment Policy Board
informing consideration of its potential wider rollout.
9.  #YouDecide
9.1 Seventeen #YouDecide projects are now complete. Most recently a new path to allow
accessible provision to Helicopter Park, Houston and an upgrade to the path running
through Station Road Park, Langbank. A programme of 14 lighting projects will
commence from March 2024 onwards along with the 4 play area upgrades and 3
outdoor gyms. Work has started on visualisation concepts for improvements to
roundabouts at the entrances to Bishopton, Kilbarchan and Renfrew. These should
be ready for public consultation between March and May 2024. 
9.2 Design work has started on the wheeled sports areas for Kintyre Park, Linwood and
Moss Road Park, Bridge of Weir.  Speed signs will be installed at Main Road Elderslie
and Bridge of Weir Road Brookfield by the end of May 2024. Dialogue regarding
seating improvements for Renfrew Town Centre is ongoing with Community Council
and installation is anticipated for summer 2024.  Work to improve paths and signage
in Gleniffer country park is in progress as is information and interpretation boards for
the villages of Inchinnan and Kilbarchan. 
Implications of the Report 
1. Financial – Any financial elements referenced in this report will be
progressed through the Council’s financial & budget planning process.  
2.       HR & Organisational Development – None.

Page 9

3. Community/Council Planning – The report details a range of activities which reflect
local community and council planning themes. 
4. Legal – None 
5. Property/Assets – None 
6.     Information Technology –None 
7. Equality & Human Rights - The recommendations contained within this report have
been assessed in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the report. If
required following implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the assessment
will be published on the Council’s website. 
8. Health & Safety – None 
9. Procurement – None 
10. Risk – None 
11. Privacy Impact – None 
12.  COSLA Policy Position – None 
13.  Climate Change – there are a range of actions and activities throughout the
Service Update Report which support the Council’s Plan for Net Zero.
__________________________________________________________________________ 
List of Background Papers:     None 
Author: Gordon McNeil, Director of Environment, Housing & Infrastructure