Democracy Spraffa

1 - Disposal of Land for Substation – CWRR Bridge Supplies - Report

Renfrewshire Council · 24 January 2024
Back to Infrastructure, Land and Environment Policy Board — 24 January 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Infrastructure, Land & Environment Policy Board
On:  24 January 2024
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Disposal of Land for Substation– CWWR Bridge Supplies
___________________________________________________________________
1. Summary 
1.1 This report seeks to obtain the Boards agreement to the disposal of property,
required for the creation of an electricity substation within the land acquired for
the Clyde Waterfront and Renfrew Riverside (CWRR) project.
__________________________________________________________________
2. Recommendations 
2.1 It is recommended that the Board: - 
(i) agree to declare the property outlined in red on the attached plan (number
R08-JAC-ZZ-XX-DR-KK-0019-P01) surplus (The “Property”); 
(ii) agree to sell the Property to SP Distribution plc (“SPD”), along with
servitude rights for appropriate connections, subject to the City Deal and
Infrastructure Programme Director agreeing their exact location and subject
to the terms and conditions detailed within the body of this report; 
(iii) grant authority to the Head of Corporate Governance in conjunction with
the City Deal & Infrastructure Programme Director to make minor
alterations to the documents, (being the Disposition and Plan to reflect the
final agreed substation orientation) and to conclude the disposal of the
Property as detailed in this Report.

Page 2

3. Background 
3.1 The Clyde Waterfront and Renfrew Riverside (CWRR) project comprises a new
‘opening’ bridge across the River Clyde; the Renfrew Northern Development
Road and new cycle routes, all of which are aimed at providing improved access
to development opportunities, employment, education, health and leisure
locations. 
The Project will link the communities of Renfrew, Yoker and Clydebank and will
provide improved access to the considerable job opportunities being delivered
by the Glasgow Airport Investment Area Project (GAIA), including the national
development known as the Advanced Manufacturing Innovation District
Scotland (AMIDS). AMIDS is already home to the new National Manufacturing
Institute for Scotland (NMIS) and the Medicine Manufacturing Innovation Centre
(MMIC). 
3.2 Planning consent for the Project was granted by Scottish Ministers on 16th
November 2018. 
3.3 The Renfrewshire Council (Clyde Waterfront and Renfrew Riverside, City Deal)
Compulsory Purchase Order 2018 was approved by Scottish Ministers and
became operative on 4th September 2020. 
3.4 The CWRR project provides the infrastructure for: improved traffic flows to and
from the GAIA area; removal of potential increased congestion in Renfrew Town
Centre; enhanced connectivity of AMIDS to Glasgow and West Dunbartonshire
- thus increasing its potential for success and increased rate of employment
delivery.
 
3.5 CWRR also opens currently stalled opportunities for residential development
sites on the river front, which could house the families attracted by the new
employment opportunities at AMIDS. 
4. Current Construction 
4.1 Work on the CWRR infrastructure started in December 2022 and to date new
roads have been constructed and land prepared for the new river crossing. 
4.2 The new opening bridge will require power supplies for smaller parts of
infrastructure on both sides of the river to operate each swinging section of the
bridge. 
4.3  SPD has identified a suitable location on Meadowside Street, Renfrew  to house
the required substation.  The location is within land acquired by the Council to
facilitate the delivery of the CWRR project. 
5. Provisional Terms and Conditions 
5.1 The new electricity substation is required to provide power to smaller parts of
infrastructure on both sides of the bridge.

Page 3

5.2 The Council will sell the land shown outlined in red extending to 25 square
metres or thereby at the location, together with servitude rights over the areas
shaded blue, on the attached plan, for a price of £1 each. The Servitude rights
granted will be subject to the normal commercial terms of making good etc. 
5.3 The land sale will be subject to the following ground burdens: 
 The Property will be used as an outdoor electricity substation with
underground cables connecting thereto as described in the missives; 
5.4 The Council will include the following restrictions on the land adjacent to the
Property, in order to protect the SPD equipment: 
 No buildings or permanent fixtures shall be erected within a lateral
distance of 2m on either side of the proposed underground cables, with
the exception of street furniture required for the safe operation of the
cycleway/footway and/or the road, including, but not limited to, lighting
columns, fences and guard rails:
 No trees or deep-rooted shrubs shall be permitted to be grown within a
lateral distance of 2m on either side of the proposed underground
cables. 
5.5 In the event that the new outdoor electricity substation is required to be
constructed in advance of the completion of the new access roads leading to
the site, the Council shall grant sufficient temporary rights of access for vehicles
etc for the construction of the substation together with the installation of the
associated underground cables from the public road to the Property.
_________________________________________________________________________
Implications of the Report
1. Financial and Legal – The Council has a valuation report from an internal
registered valuer and the land could reasonably be sold for between £127,000
-   £150,000 per acre, as part of a larger disposal. This would value each 25
square metres (0.006 acre) to be transferred to SPD currently at circa £762 -
£900. 
Section 74(2A) of the Local Government (Scotland) Act 1973 (“the 1973 Act”)
permits the Council to dispose of land for less than the best consideration where
either the best consideration that can reasonably be obtained is less than the
threshold amount (£10,000), or the difference between that consideration and
the proposed consideration is less than the marginal amount (25% of the best
consideration). In this instance the Authority is satisfied the disposal is
reasonable as the best consideration is well below the £10,000 threshold. The
benefits to Renfrewshire and its residents of attracting occupiers to the AMIDS
site includes the high-quality jobs and training in manufacturing skills that will
be created and thereafter, high quality businesses and investment will be
attracted to the surrounding location thereby creating further high-quality jobs.
The Council’s position is also protected by the use restrictions and provisions
detailed at clause 5.3 and 5.4 above.

Page 4

2. HR & Organisational Development – Not Applicable. 
3. Community/Council Planning – 
 Our Renfrewshire is thriving – The opening bridge will help regenerate the
Clyde Waterfront as an attractive riverside and urban area that supports
existing and promotes new residential, industrial, commercial, business,
retail and leisure opportunities. 
The project will better link communities and businesses on both sides of the
river to a number of key locations including the Clyde Riverside, the
Advanced Manufacturing and Innovation District Scotland (AMIDS),
Clydebank, Renfrew, Paisley Town Centre and Braehead Centre. The
project will help improve the attractiveness of the vacant, derelict and
underused sites that offer immense potential for development of new and
enhanced commercial, business and housing uses. Improved connections
between key educational and health centres would also improve
educational and health opportunities for people within the local communities
as well as aiding employees to access these major employment centres.
Projects outcomes are envisioned to reduce traffic congestion in Renfrew
town centre and aid in improving air quality. 
 Reshaping our place, our economy and our future - The completed CWRR
infrastructure will provide connectivity and access to new and existing jobs
for people in our communities and across the Glasgow City Region. 
 Tackling inequality, ensuring opportunities for all - the employment related
community benefit commitments create job opportunities for all but targeted
at hard to reach citizens through liaison with Invest in Renfrewshire and
similar Glasgow City Region employability services. 
 Creating a sustainable Renfrewshire for all to enjoy - The completed CWRR
infrastructure will help enable active travel and improve access to public
transport links for people in our communities.  
 Working together to improve outcomes - The CWRR project includes works
within the boundaries of 3 local authorities: Renfrewshire Council; West
Dunbartonshire Council and Glasgow City Council. The Council has worked
closely with these other Glasgow City Region Member Authorities and Peel
Ports, the Harbour Authority to take the project forward. By linking the
communities of Renfrew, Yoker and Clydebank the CWRR project will
provide improved connections between key educational and health centres,
such as: Queen Elizabeth University Hospital; Golden Jubilee Hospital;
West College Scotland (Clydebank and Paisley Campuses) and West of
Scotland University. 
4. Legal - Disposal of the Property as outlined in the body of the report. Best Value
duty has been considered and this transaction is compliant. State Aid has been
considered and the transfer of this Property is not State Aid.

Page 5

5. Property/Assets – As per this report 
6. Information Technology – None. 
7. Equality & Human Rights -   
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. 
If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.   
8. Health & Safety – None. 
9. Procurement – None. 
10. Risk – The Property is conveyed subject to development conditions to ensure
the land is used for outdoor electricity substations. Failure to provide the
required land to SPD will lead to lack of supply and the new bridge will not
function. 
11. Privacy Impact – None. 
12. Cosla Policy Position – Not Applicable. 
13. Climate Risk – project has been designed based on the climate change
parameters applicable at the time. The project has been designed in
accordance with PAS 2080 which aims to reduce embedded carbon within the
project development. 
_________________________________________________________
Author:  Barbara Walker, City Deal and Infrastructure Programme Director. 
Email Barbara.walker@renfrewshire.gov.uk

Page 6

Depot
SM
4.3m
4.0m
4.3m
Dock
Sinks
Depot
Fishers Road
Track
MLW
Yard
Car Breakers
SM
Refuse Heap
4.3m
Pier
5/1
1
4.0m
Depot
Fishers Road
Depot
4.5m
28
PROJ:
DATE:
SHEET:
DWG:
GENERAL NOTES
SUIT DESCRIPTION APPBYREV
REVISION: SUITABILITY:
DATE
DESIGN: DRAWN: CHK: APP:
Jacobs UK Ltd.
C/O 95 Bothwell Street, Glasgow, G2 7HX
Tel +44 (0)141 243 8000
Reproduced by permission of Ordnance Survey on behalf of His Majesty's Stationary Office, © Crown copyright and database right 2023. All rights reserved. Ordnance Survey Licence Number: 100046668.
CLYDE WATERFRONT AND RENFREW RIVERSIDE
SUBSTATION ACQUISITION
MEADOWSIDE STREET, RENFREW PA4 8SR
CP JMcC CP CP
04/01/2024
B2423300
R08-JAC-ZZ-XX-DR-KK-0019
1 of 1 P01 S3
P01 S3 04/01/24 FIRST DRAFT JMcC CP
5M VEHICLE AND PERSONNEL ACCESS
KEY
NOTES
1. THIS DRAWING IS NOT TO BE USED IN THE WHOLE OR PART
OTHER THAN FOR THE INTENDED PURPOSE AND PROJECT AS
DEFINED ON THIS DRAWING. REFER TO THE CONTRACT FOR
FULL TERMS AND CONDITIONS.
2. DO NOT SCALE FROM THIS DRAWING
3. SERVITUDE RIGHTS AND ACCESS ROUTES SHOWN ARE
INDICATIVE ONLY. EXACT DETAILS OF ACCESS RIGHTS
AND SERVITUDES WILL BE CONFIRMED BY SCOTTISH
POWER ENERGY NETWORKS IN DUE COURSE.
SCALE: NTS
KEY PLAN
2M CABLE RIGHTS
COMBINED VEHICLE ACCESS AND CABLE RIGHTS
SUBSTATION AREA 25SQ/M OR THEREBY
SUBSTATION DETAIL
SCALE 1:250
SEE
SUBSTATION
DETAIL