To: Infrastructure, Land and Environment Policy Board
On: 30 August 2023 
Report by:  Director of Finance & Resources, Director of Environment and
Infrastructure & Director of Communities and Housing
Heading:  Revenue and Capital Budget Monitoring as at 23 June 2023 
1. Summary of Financial Position
1.1. The projected Revenue outturn as at 31 March 2024 for Infrastructure, Land
and Environment is an overspend position of £2.348m (7.6%) against the
revised budget for the year.
1.2. The projected Capital outturn as at 31 March 2024 for Infrastructure, Land and
Environment is a break-even position.  
1.3. This is summarised over the relevant services in the table below and further
analysis is provided in the attached appendices. 
Table 1: Revenue
Division
Revised
Annual Budget
Total
Projected
Outturn
Budget
Variance
(Adv)/Fav
Budget
Variance  
£000 £000 £000 %
Environment and Infrastructure 30,806  33,154  (2,348) (7.6%) 
Table 2: Capital
Division 
Revised
Annual Budget 
£000
Total
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance 
%
Environment and Infrastructure 16,676 16,676 0 0%
___________________________________________________________________

Page 2

2. Recommendations
It is recommended that the Infrastructure, Land and Environment Policy
Board:
2.1  Note the projected Revenue outturn position as detailed in Table 1 above;  
2.2 Note the projected Capital outturn position as detailed in Table 2 above; and 
2.3 Note the Revenue and Capital budget adjustments detailed in sections 4   
and 6. 
___________________________________________________________________
 
3 Revenue
3.1 The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £2.348m (7.6% of total budget) for Infrastructure, Land
and Environment. Narrative is provided in the Appendices below to provide
context and explanation to the budget position for service areas.  
3.2 The projected costs for this financial year are based on the financial information
available at the time of writing this report, and future projections and outturns
may vary depending on the operational and current market conditions.   
3.3 The forecast financial overview for the Council being reported to Finance,
Resources and Customer Services Board incorporates the overspend position
reflected in this report. 
3.4 The main reasons for the projected outturn position are indicated below, with
the tables showing both the subjective analysis (what the budget is spent on)
and the objective analysis (which division is spending the budget). The main
drivers are the loss of parking income, as has been the case since the beginning
of the pandemic, refuse collection costs that are largely driven by inflationary
pressures, absence cover as a result of annual leave and sick leave, and the
impact of other inflationary pressures across the services. 
3.5 It should also be noted that additional expenditure has been incurred as a result
of ongoing tree management work that the Streetscene team is legally obligated
to carry out. However, further analysis is required to be undertaken and the
detailed report also being presented to this board provides further background
information, including the estimated financial costs. 
4 Revenue Budget Adjustments
4.1 Since the last report there have been net budget adjustments of £317k,
reflecting a number of savings targets for 2023/24 incorporated into the
reported position, as well as a drawdown from reserves.

Page 3

5 Capital      
5.1 The Capital Investment Programme 2023/24 to 2027/28 was approved by the
Council on 2 March 2023.  The approved spend for 2023/24 at that time was
£11.868m.
5.2 The Capital Monitoring report at Appendix 2 indicates adjustments in the
approved capital programme of £4.808m.  This mainly arises from new grant
funding for projects including Cycling, Walking & Safer Routes and
Strathclyde Passenger Transport and budget carried into 2023/24.
5.3 The projected outturn at 31 March 2024 is to break-even.
5.4 Further detail, including reasons for significant variances, can be found at
Appendix 2.
 
 
6 Capital Budget Adjustments
6.1 Since the last report, budget adjustments of £4.808m have arisen, which
reflect the following changes:   
o Net budget reprofiled from 2022/23 to 2023/24 £0.721m to reflect updated
cash flows for the following projects;
 Roads Footways £0.374m; 
 Vehicle Replacement Programme £0.124m;
 Bridge Assessment/Strengthening (£0.133m);
 Light Columns Replacement £0.053m;
 Traffic Management £0.061m;
 Core Pathways & Cycle Network £0.051m;
 Improvement to Outdoor Access £0.160m;
 Nature Restoration Fund £0.031m.
o Budget increases in 2023/24 £4.087m:
 Cycle, Walking & Safer Routes - £0.363m for grant awarded from
Active Travel
 Roads and Footways - £0.500m funding from Investment Capital Fund
to meet committed costs for 2023/24;
 Traffic Management £0.300m for capital element of funding approved
by Council on 2 March 2023 to support delivery of roads
improvements and traffic reduction measures;
 Public Litter Bin Replacement - £0.090m to reflect funding approved
by Council on 2 March 2023 to support first year of public litter bin
replacement programme;
 Renewal of Play Parks - £0.350m for capital element of play park
renewals approved by Council on 2 March 2023;

Page 4

 Nature Restoration Fund - £0.199m for Scottish Government Grant
award for 2023/24;
 Strathclyde Passenger Transport - £1.485m for grant funding awarded
by Strathclyde Passenger Transport.
 Roads and Footways - £0.800m brought forward from 2024/2025 to
support commitment costs. 
___________________________________________________________________ 
Implications of this report
 
1.  Financial – The projected outturn position for the Infrastructure, Land and
Environment Revenue budget is an overspend of £2.348m.   
The projected outturn position for the Infrastructure, Land and Environment
Capital budget is a break-even position. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning
None directly arising from this report. 
4.  Legal 
None directly arising from this report. 
5.  Property/Assets 
Capital projects result in lifecycle improvements and replacements to
Roads & footways network and vehicles. 
6.  Information Technology 
None directly arising from this report. 
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only.   If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website.   
8. Health and Safety
None directly arising from this report. 
9. Procurement 
None directly arising from this report.

Page 5

10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact
None directly arising from this report. 
12. 
13.
Cosla Policy Position 
N/a. 
Climate Risk
None directly arising from this report.
__________________________________________________________________ 
List of Background Papers 
Revenue Budget and Council 2023/24. Council, 2 March 2023 
Non Housing Capital Investment Programme, Prudential Framework and
Treasury Management Strategy, and Capital Strategy 2023/24 – 2027/28.
Council, 2 March 2023. 
___________________________________________________________________ 
Authors:       Alastair MacArthur, Director of Finance & Resources and Gordon
McNeil, Director of Environment, Housing & Infrastructure

Page 6

Appendix 1
 
 
 
 
Objective Summary
Approved 
Annual 
Budget 
Budget 
Adjustments
Revised 
Annual 
Budget at 
Period 3
Projected 
Outturn
 
£000 £000 £000 £000 £000 %
Directorate and Service Co‐ordination 1,293 (22) 1,271 1,101 170 13.4%
Refuse Collection 5,727 (961) 4,766 5,811 (1,045) (21.9%)
Household Waste Recycling Centres 806 130 936 1,019 (83) (8.9%)
Refuse Disposal 7,052 (6) 7,046 7,120 (74) (1.1%)
Streetscene 6,104 711 6,815 7,137 (322) (4.7%)
Sustainability and Place 653 (210) 443 465 (22) (5.0%)
Fleet Services (84) 0 (84) 12 (96) (114.3%)
Social Transport  1,597 0 1,597 1,565 32 2.0%
Roads Operations 3,075 (10) 3,065 3,019 46 1.5%
Infrastructure and Assets 1,832 12 1,844 1,876 (32) (1.7%)
Transportation & Development 1,028 22 1,050 1,050 0 0.0%
Parking of Vehicles (1,128) (53) (1,181) (259) (922) (78.1%)
Strathclyde Partnership for Transport 
Requisition
3,168 70 3,238 3,238 0 0.0%
NET EXPENDITURE 31,123 (317) 30,806 33,154 (2,348) (7.6%)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 23 June 2023
Budget Variance 
(Adverse) or Favourable
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 7

Appendix 1
 
 
 
 
Objective Heading  Key Reasons for Projected Variance 
Waste Services 
This reflects the financial position for Refuse Collection, Refuse Disposal and Household Waste Recycling 
Centres. In the main the overspend relates to increased costs relating to bins, caddies and bin liner supplies. 
Both Streetscene and Waste Services are currently experiencing high levels of overtime that is likely to continue 
throughout this financial year. This is due to two additional annual leave days within the pay award, additional 
public holidays and 2024 being a leap year, (6 extra days). In addition, the LGV driver training referred to in the 
Operational Performance Report will result in a further 4 days to be covered for drivers. In addition, there has 
been a reduction in demand for special uplifts, as well as increased tonnage costs despite reduced levels of 
waste being disposed of, resulting in an overspend on the Clyde Valley Waste contract. However, the market is 
highly volatile and as a result this will be closely monitored through the remainder of the year. The finance team 
is working closely with the service to review the current methods of projecting the tonnages for each of the 
waste streams. 
Streetscene 
The current projected overspend within Streetscene largely relates to additional tree management and 
associated health and safety issues, such as tree inspections and tree health monitoring, including Ash Dieback 
and Larch infection activities. It should be noted that the level of work with regards to the tree management 
activities being undertaken has increased significantly and this has been reflected into the revised outturn 
position. Like other areas within the service, the projected outturn is showing inflationary pressures in other 
supplies and services. This will be closely monitored through the remainder of the financial year. A report will 
be present to ILE on 30 August 2023 with regards to Tree Management.  
Social Transport  
The service is reflecting a projected underspend mainly as a result of vacancies. However, it should be noted 
that this will be monitored throughout the remainder of the financial year and any changes will be reported to 
future boards.  
Infrastructure and Assets 
The current forecast reflects a projected overspend as a result reduced construction consent income being 
offset by a projected over‐recovery in sales, fees and charges. Due to the income generated in sales, fees and 
charges being of a reactive nature, this is an area that is difficult to predict, however this position will be closely 
monitored for the remainder of the financial year.

Page 8

Appendix 1
 
 
 
 
Parking of Vehicles 
Off‐street parking charges have been reintroduced for a significant period of time, however on and off street 
parking income and fine recovery remain significantly lower than pre‐pandemic levels and this is expected to 
continue for the rest of the financial year. In 2022/23 an under recovery of £1m was incurred, with a similar 
amount being forecast for 2023/24. Assuming there is no change, the under‐recovery is expected to continue 
for 2023/24. It should be noted that the position will be closely monitored throughout the year, with an 
expected drawdown from ringfenced reserves being actioned if required at the end of the financial year to 
cover any shortfall that may result during 2023/24.

Page 9

Appendix 1
 
 
 
 
 
 
 
Subjective Summary
Approved 
Annual 
Budget 
Budget 
Adjustments
Revised 
Annual 
Budget at 
Period 3
Projected 
Outturn
£000 £000 £000 £000 £000 %
Employees 22,642 319 22,961 23,526 (565) (2.5%)
Premises Related 1,023 200 1,223 1,324 (101) (8.3%)
Transport Related 5,902 15 5,917 6,147 (230) (3.9%)
Supplies and Services 11,965 42 12,007 13,000 (993) (8.3%)
Third Party Payments 3,201 70 3,271 3,259 12 0.4%
Transfer Payments 108 0 108 148 (40) (37.0%)
Support Services 34 0 34 46 (12) (35.3%)
Depreciation and Impairment Losses 0 0 0 0 0 0.0%
GROSS EXPENDITURE 44,875 646 45,521 47,450 (1,929) (4.2%)
Income (13,752) (963) (14,715) (14,296) (419) (2.8%)
NET EXPENDITURE 31,123 (317) 30,806 33,154 (2,348) (7.6%)
Budget Variance 
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 23 June 2023
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 10

Appendix 2
 
 
 
 
Prior Years Approved   Budget  Revised  Projected 
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2023 2023‐24 in 2023‐24 2023‐24 2023‐24 Budget Outurn 
Project Title to 31‐Mar‐27 to 31‐Mar‐27
£000 £000 £000 £000 £000 £000 £000
ENVIRONMENT & INFRASTRUCTURE
Cycling, Walking & Safer Routes 0 786 363 1,149 1,149 0 0% 1,149 1,149 0 0%
Roads/Footways Upgrade Programme 73,464 5,848 1,674 7,522 7,522 0 0% 81,785 81,785 0 0%
Vehicle Replacement Programme 0 2,235 124 2,359 2,359 0 0% 2,359 2,359 0 0%
Bridge Assessment/Strengthening 0 680 (133) 547 547 0 0% 547 547 0 0%
Lighting Columns Replacement 0 1,012 53 1,065 1,065 0 0% 1,065 1,065 0 0%
Traffic Management 0 0 361 361 361 0 0% 361 361 0 0%
Core pathways & cycle network 85 64 51 115 115 0 0% 200 200 0 0%
Parks Improvement Programme 2,237 63 2 65 65 0 0% 2,302 2,302 0 0%
Improvements to Outdoor Access and Play Area Programm 1,553 161 160 321 321 0 0% 1,873 1,873 0 0%
Multi Pupose Bins 60 20 0 20 20 0 0% 80 80 0 0%
Public Litter Bin Replacement Programme 0 0 90 90 90 0 0% 90 90 0 0%
Improvements to Cemetery Estate 1,238 305 (2) 303 303 0 0% 1,541 1,541 0 0%
Renewal of Play Parks 158 307 350 657 657 0 0% 2,044 2,044 0 0%
Nature Restoration Fund 191 387 230 617 617 0 0% 808 808 0 0%
Strathclyde Partnership Transport 0 0 1,485 1,485 1,485 0 0% 1,485 1,485 0 0%
TOTAL INFRASTRUCTURE, LAND & ENVIRONMENT 
BOARD 78,986 11,868 4,808 16,676 16,676 0 0% 97,689 97,689 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Budget Variance (Adverse) or 
Favourable
Budget Variance (Adverse) or 
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY ‐ NON‐HOUSING SERVICES
1st April to 23rd June 2023
POLICY BOARD: INFRASTRUCURE, LAND & ENVIRONMENT
Current Year 2023‐24 Full Programme ‐ All years