Page 1

2 
PUBLIC 
___________________________________________________________________
To: Infrastructure, Land and Environment Policy Board 
On: 27 May 2026
___________________________________________________________________
Report by:   Chief Executive
___________________________________________________________________
Heading: Lease extension at 9 High Barholm, Kilbarchan, PA10 2EF
_______________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek approval to a lease extension at 9 High
Barholm, Kilbarchan, PA10 2EF (the old library) in favour of Kilbarchan
Improvement Projects (KIPCO) (SC216097). 
___________________________________________________________________ 
2. Recommendations
2.1 It is recommended that the Infrastructure Land & Environment Policy Board
approve a lease extension at 9 High Barholm, Kilbarchan on the provisionally
agreed terms.
___________________________________________________
3. Background
3.1 Kilbarchan Improvement Projects (KIPCO) (SC216097) was granted a 25 year
lease of the former library building at 9 High Barholm, Kilbarchan in October
2001. As shown in the attached plan E3724.
3.2 The lease allows for the property to be used for community purposes.  The
property has been successfully run in this manner for 25 years.   
3.3 The current lease agreement is on full repairing and insuring terms with no
ongoing liabilities or costs for Renfrewshire Council.  The property has
continued to be well maintained throughout the period of lease.

Page 2

3 
PUBLIC 
3.3 The group have considered the position as the end of the lease has neared and
have requested an extension for a period of 5 years on the same terms, with an
annual break option, in order to continue to provide the facility for community
use. 
3.4 The provisionally agreed terms are as follows:- 
• Tenant - Kilbarchan Improvement Projects (SC216097)
• Use – as per existing lease, for sporting, recreational fund raising activities
or cultural facilities for the benefit of the community.
• Term – 5 year lease extension with annual tenant only break option from 6
October 2026.
• Rent – As per existing lease, £1 per annum if asked
• Repair – Full repairing and insuring lease.  Tenant responsible for all repair
and maintenance and payment of insurance.
• Utilities – Tenant responsible for all costs relating to utilities.
• Rates – Tenant responsible for all local authority charges.
• Fees – each party to be responsible for their own legal fees.
• Any other reasonable terms and conditions considered necessary by the
Head of Corporate Governance and the Head of Economy & Development
to protect the Council’s interest.
___________________________________________________________________
Implications of the Report
1. Financial – None 
2. HR & Organisational Development – None 
3. Community Planning – None 
4. Legal – Lease extension to be documented. 
5. Property/Assets – As per this report 
6. Information Technology – None 
7. Equality & Human Rights  The Recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report because no groups or individuals
have any involvement currently at the property. If required following
implementation, the actual impact of the recommendations and the mitigating
actions will be reviewed and monitored, and the results of the assessment will
be published on the Council’s website.

Page 3

4 
PUBLIC
8. Health & Safety – None.
9. Procurement – Not applicable.
10. Risk – None.
11. Privacy Impact – Not applicable.
12. Cosla Policy Position – Not applicable.
13. Climate Risk - Not applicable.
14. Children’s Rights - Not applicable.
_________________________________________________________
List of Background Papers - None 
___________________________________________________________________ 
Author:           Aileen Johnson; Principal Estates Surveyor; aileen.johnson@renfrewshire.gov.uk;
07483 420781

Page 4

I9 High Barholm, Kilbarchan
Report / Lease Plan Ref. E3724
Notes:
Date: 23/04/2026User: howardhaughj2
Scale: 1:980
Legend
Area to be leased
© Crown copyright and database rights 2026.  Licence number AC0000815792.