Page 1

PUBLIC
___________________________________________________________________
To:  Infrastructure, Land and Environment Policy Board 
On:  27 May 2026 
___________________________________________________________________ 
Report by: Director of Environment, Housing and Infrastructure 
___________________________________________________________________ 
Heading:  Community Facilities - £1m Budget Allocation
___________________________________________________________________
1. Summary 
1.1 At the Council meeting on 27 February 2025, £0.800m was allocated to
improving community facilities across Renfrewshire. 
1.2 The wording of the funding allocation stated: 
“Council has committed to the aims of the strategic property review and has
long recognised that the size and condition of our current property estate
demands significant maintenance obligations. Council also recognises the
aims of the Community Empowerment (Scotland) Act in empowering
communities through the ownership or control of land and buildings. In
support of both these objectives, Council commits £0.800 million to invest in
council properties where this investment could be an enabler for
increased community ownership of assets currently owned or controlled
by the Council, such as through a community asset transfer request. Further
detail on the operation of this scheme will be the subject of a report to the
Infrastructure, Land and Environment Policy Board.” 
1.3 Further to the above, at the Council meeting on 26 February 2026, a further
£0.2m was allocated to sports pavilions and was outlined as follows: 
“Council has previously committed £800,000 to invest in council properties
where this investment could be an enabler for increased community
ownership of assets currently owned or controlled by the Council. Sports
pavilions have been identified as an area where some are underutilised by
communities and sports teams due to issues of condition and general
appearance. Council therefore allocates an additional £200,000 to invest in
sports pavilions which are in active use and require attention.”

Page 2

PUBLIC
1.4 In particular, and as detailed in the budget allocations above, the preference
is for the funding allocation to be used as an enabler to upgrade Renfrewshire
Council owned buildings to a standard that would assist/support a community
in taking them on e.g. CAT and reduce the financial burden on the Council. 
1.5 The objective above is aligned to a key objective in the Strategic Property
Programme and draft Property Asset Management Strategy in that the asset
would remain for the community, however, the Council would not be investing
in the building going forward, either through staffing costs
(cleaning/caretaking) or in the maintenance of the building (compliance,
repairs or lifecycle maintenance). 
1.6 In relation to CAT, Officers will look for a clear plan and commitment towards
the process e.g. validation of an application, however, Officers may also
allocate funds where required for essential repairs to other community
buildings assessed as being needed within the community as part of the
Strategic Property Programme. 
1.7 Whilst funding may be committed after the validation of an application, the
works will not be carried out until the CAT has been approved at the
Community Asset Transfer Sub-Committee. 
1.8 Officers would take proposals for discussion to the closely aligned Grants
Officer Panel (Officer led Group) which would allow cross services scrutiny
and governance before an update was provided to the Infrastructure, Land
and Environment Policy Board. This would also align the process with the
Connected Communities programme. 
1.9 Over the last 4 years, the Council has approved 14 asset transfer requests, 9
of which have been for full transfer of ownership and 5 have been long-term
leases. 7 of the 14 approved transfer requests assets have concluded i.e.
ownership has transferred or leases finalised. A further 12 assets are subject
to submitted expressions of interest and formal CAT requests at various
stages of completion. 
1.10 It should be noted that the fund will not act as a grant fund where
organisations/groups bid for funding. As the properties in scope are Council
buildings, Officers will recommend investment based on need e.g. condition
survey as detailed in Section 4. Works will be arranged and undertaken by
Renfrewshire Council and their approved contractors where required or
overseen by Renfrewshire Council. 
1.11 In relation to pavilions, Officers have been reviewing the condition and need
for works in certain pavilions across Renfrewshire that are currently in use.
This could include works to make a pavilion more attractive for CAT transfer
or to bring back to a standard more than wind and watertight. Initial costs for
pavilions show that substantial costs may be required and therefore,
consideration will be given to additional funding via lifecycle maintenance if
deemed appropriate.

Page 3

PUBLIC
1.12 To date, £0.140m of the fund has been committed to projects as detailed
further in Section 3.6. 
1.13 This paper outlines the principles, criteria and rationale for the allocation of
both the £0.800m for community facilities and the £0.200m for pavilions. Due
to some of the works that may require to be done (including resources,
procurement, building warrants, design elements), and the time for a CAT to
progress, funding has been carried over into the 2026/27 financial year to
allow completion of both processes and may carry on into further financial
years to ensure best value is obtained.
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy
Board: 
2.1 Approves the principles, criteria and rationale for the allocation of the funding
as detailed below in Sections 3; 
2.2 Notes the work undertaken to date by colleagues in Regeneration, the
Officers CAT panel and the Community Asset Transfer Sub Committee to
move Renfrewshire Council buildings into community ownership under the
Community Empowerment (Scotland) Act 2015. 
2.3 Approves the governance model in relation to Officers discussing and
agreeing at the Grants Officer Group and a future report being brought to the
Infrastructure, Land and Environment Policy Board.
_________________________________________________________ 
3. Funding Principles and criteria 
3.1 The following principles have been outlined for the targeting of the funding
available to improve properties through this budget allocation: 
 There is a commitment to the CAT process with those having a full
validated application being given priority for the funding.
 Whilst Grants Officer Panel will discuss early in the process and potentially
commit to works, Council will not carry out works until the CAT is approved
at the Community Asset Transfer Sub-Committee.
 Conditions surveys should drive investment (wherever possible) and work
should align with properties that have been reviewed and targeted as part
of the Strategic Property Programme.
 As the fund will look to undertake capital works, a maximum of £0.150m
will be allocated to a single building to allow improvements.

Page 4

PUBLIC
 To ensure that the fund is manageable and minimise small works, there
will be a lower limit between £20,000 up to the £150,000 maximum for
capital works.
 This funding could be used as match funding (wherever possible) or
investment to help lever external funding. 
3.2 Projects could be identified at any time; however, the most likely avenue is via
active discussions with the Programme Manager – Community Asset Transfer
and Regeneration and Sustainable Communities Fund. 
3.3 In determining a process for targeting the fund, as detailed in 1.4, the
preference is for the funding allocation to be used as an enabler to upgrade
Renfrewshire Council owned buildings to a standard that would assist/support
a community in taking them on e.g. CAT and reduce the financial burden on
the Council. To support this, consideration will be given the stage/gateway
that the project/CAT application is at in the process as detailed below in 3.5.  
3.4 Each facility identified will be assessed on their own merit. To assist with the
potential for CAT, this fund could assist with work being undertaking that may
lead to validation and approval of the CAT. Other works such as condition
surveys, building improvement works and obtaining industry expertise to
progress towards CAT would be considered for allocation from this fund. 
3.5 The following gateways have been identified in the CAT process and where
funding could be allocated to a group/project: 
1.
No registered enquiry or interest – other routes should be considered e.g. disposal or demolition.
2.
One or more enquiries or expression of interest received for an asset, this is unlikely to be successful at
this stage due to being too early in the process and not developed enough.
3.
Asset transfer application is currently being developed – investment from the fund could help increase
chances of success. This would be discussed at Grants Officer Panel and may lead to investment.
4.
A full application has been received and validated. This is the preferred routes for upgrades to
properties as it minimises the risks of failure and increases chances of completion of CAT.
5.
Asset transfer has already been approved at CAT Sub-Committee – this would not be considered for
this fund, unless previously agreed by Grants Officer Panel or relatively new CAT.

Page 5

PUBLIC
Compliance, Repairs and Maintenance 
3.6 It is noted that not all public buildings will be suitable for CAT and community
groups may not wish to take them on. However, some of this fund may be
used in relation to compliance, repairs, maintenance and upgrades to
maximise the use for the communities. This may also include funding for
demolition to maximise the use of the land. 
3.7 In relation to this fund, £0.140m has already been allocated/committed to the
following buildings for minor upgrades and works: 
 Lochwinnoch Annexe
 Howwood Village Hall
 Glenburn Resource Centre
 Beechwood Community Centre 
3.8 Officers will continue to assess if there are other buildings in the portfolio that
would benefit from improvements whilst not necessarily progressing towards
CAT.
___________________________________________________________________ 
4. Community Asset Transfer (CAT) 
4.1 Over the last 4 years, the Council has approved 14 asset transfer requests, 9
of which have been for full transfer of ownership and 5 have been long-term
leases. 7 of the 14 approved transfer requests assets have concluded i.e.
ownership has transferred or leases finalised. A further 12 assets are subject
to submitted expressions of interest and formal CAT requests at various
stages of completion. Beyond these, there are numerous enquiries and
informal interest, particularly in football pitches and pavilions but also in a few
key buildings where investment may act as leverage to formalise a CAT
interest. 
4.2 A full list of assets where there is current and/or potential CAT interest is
attached as Appendix 1 to this report.
___________________________________________________________________ 
5. Next Steps 
5.1 Officers from the relevant services and associated governance groups
(Grants Officer Panel) will review current applications/interest and assess
which buildings may benefit the most from the fund. 
5.2 For these buildings, a review of the Condition Surveys or the procurement of
up-to-date surveys will be undertaken to assess the upgrades that are
essential to allow improvements and facilitate a CAT. 
5.3 Discussions will also take place with relevant Community Groups to upgrade
certain facilities for community use that are not moving towards CAT as
detailed in Section 3.6.

Page 6

PUBLIC
5.4 A future report on the use of the funding and the outcomes of the funding
allocation, will be brought back to this Board in due course.
___________________________________________________________________ 
Implications of the Report 
1. Financial – There is £1m allocated for improvements to community
facilities/pavilions and this resides with Finance and Resources until allocated
to projects. 
2. HR & Organisational Development – None 
3. Community/Council Planning – 
 Place – Working with groups to increase the community ownership of
buildings will hopefully lead to facilities meeting the on-going needs of
the community. 
4. Legal – As detailed within the report. 
5. Property/Assets – This paper outlines the allocation of grant funding, and
this will lead to improved facilities across Renfrewshire. Should facilities go
through a CAT, this will reduce the Renfrewshire Council public building
portfolio. 
6. Information Technology – None 
7. Equality & Human Rights 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website. 
8. Health & Safety - None 
9. Procurement – None 
10. Risk – None 
11. Privacy Impact - N/A 
12. Climate Risk – By reducing the Renfrewshire Council Public Building portfolio
will reduce the Council carbon emissions and buildings requiring to work
towards Net Zero.

Page 7

PUBLIC
13. Children’s Rights - N/A 
14. COSLA Policy Position - N/A
__________________________________________________________________ 
List of Background Papers - N/A
__________________________________________________________________ 
Author:    Chris Dalrymple, Head of Facilities and Property Services 
chris.dalrymple@renfrewshire.gov.uk

Page 8

PUBLIC
Appendix 1 
Assets with Current/Potential CAT Status 
 Former Longcroft Children’s Home
 Ralston Community Sports Centre
 Hunterhill Community Centre
 St Ninian’s Church Hall
 Beechwood Community Centre
 Barshaw Park Toilet Block
 Falcon Day Centre
 Durrockstock Pavilion & Playing Fields
 Lochfield Pavilion and Playing Fields
 Glenpatrick Pavilion
 Viewfield Park and Pavilion
 Inchinnan Pavilion & Playing Fields
 Bridge of Weir Pavilion
 West End Community Centre, Underwood Road
 Barwood Park & Pavilion, Erskine
 McMaster Sports Centre, Johnstone
 Brediland Community Centre
 Craigielea House
 The Annexe, Lochwinnoch
 Johnstone Bowling Club
Potential for CAT Interest to be developed 
 Former Police Station, Renfrew
 Ralston Community Centre & Library 
 Non-CAT disposal Kirklandneuk Community Centre
 Robertson Park Admin Block
 Shanks Park Bothy
 Bishopton Pavilion & Playing Fields
 Bridgewater Sports Centre
 Robertson Park Bowling Club
 Elderslie Village Hall
 Foxbar Community Centre
 Glenburn Community Centre
 Gallowhill Community Centre
 Steeple Hall
 Foxbar Rivers Community Centre
 Former Gallowhill Housing Office
 Clyde Muirshiel Visitor Centre
 Moredun Playing Fields