Service Update Report

Renfrewshire Council · 18 March 2026
Back to Infrastructure, Land and Environment Policy Board — 18 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
To:         Infrastructure, Land and Environment Policy Board 
On:  18 March 2026 
Report by:       Director of Environment, Housing and Infrastructure 
Heading:       Service Update Report 
1. Summary 
1.1      This report provides an overview of key service activities since the last Policy
Board report on 21 January 2026 and an update on the services and key
projects delivered during this period. 
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy
Board: 
2.1      Notes the wide range of activities provided in the service update. 
2.2      Notes the Memorandum of Understanding (MOU) process for the Paisley
Central District Heating Network Outline Business Cases outlined in section
4.1.

Page 2

PUBLIC
3. Background 
3.1 Environment, Housing & Infrastructure provides essential services to every
household in Renfrewshire and works in partnership with the local community,
other service areas and Community Planning Partners, to deliver key Council
priorities and initiatives. A progress update on the main activities delivered by
the services in respect of the areas of activity delegated to this Policy Board,
is detailed below. 
Updates for Infrastructure, Land and Environment Policy Board 
4. Climate Change  
4.1 Energy Management 
District Heating Network Outline Business Cases 
4.1.1  Extensive work continues to develop the Outline Business Cases for two potential District
Heating Networks in Renfrewshire: the extension of the existing network at AMIDS through
to Glasgow Airport and the creation of a new network in the Paisley Central area. 
4.1.2  A collaborative exercise has been undertaken to explore various delivery options through
detailed review in order to identify preferred models for both networks and to inform a soft
market testing exercise. 
4.1.3 A Memorandum of Understanding (MOU) has been developed and shared with
stakeholders who have been identified as key to the development and potential prospects
of the Paisley Central Network. Partners include OneRen, the NHS and the University of
the West of Scotland (UWS). The MOU is intended as a non-legally binding agreement
between stakeholders and Renfrewshire Council, outlining the broad terms and conditions
of cooperation and providing a means to express support and commitment to the project.
These partners are key to the success of the project given the energy consumption of the
properties they are responsible for. Such agreements add weight to the potential viability of
a future network. More legally binding proceedings would take place at a later phase
through an Energy Supply Agreement (ESA) as the network connects. 
4.1.4 It is expected that the business cases will be concluded in June 2026 with further detail
presented to board members in due course. It is recommended that the board note the
MOU process outlined and the more detailed report to follow.

Page 3

PUBLIC
5.  Community Development 
5.1 Team Up to Clean Up 
5.1.1 Team Up to Clean Up worked in partnership with colleagues in Transport & Infrastructure
and Neighbourhood Services to support Renfrewshire’s Winter Maintenance
Campaign.  Over 60 volunteer Grit Kits were issued in response to winter resilience
requests from community volunteers. Each kit included a salt spreader, snow shovel,
gloves and a 25kg bag of salt, alongside a Team Up to Clean Up branded hi-vis vest. 
5.1.2 Volunteers were required to confirm compliance with the issued risk assessment and to
follow the care and maintenance guidance provided for the spreaders, supporting safe use
and ensuring the longevity of the equipment. 
5.1.3 In January, Team Up to Clean Up responded directly to volunteer feedback by procuring A-
frame stand-alone safety signage for use during litter-picking activity. The signage is
designed to alert passers-by, including pedestrians and motorists, that litter-picking is
taking place, improving volunteer visibility and supporting safer working practices on site. 
6. Fleet, Roads, and Transportation   
6.1   Fleet Services 
6.1.1  Fleet Services has recently added 24 new vehicles and fleet assets as part of the Council’s
ongoing Vehicle Replacement Programme. The new additions include: 
• 3 x Long Range electric cars – allocated to the Sustainable Travel Pool Car
Scheme based at Renfrewshire House.
• 17 x new L1 electric car-derived vans - Allocated across a range of Council
services to replace older or hired vehicles—helping reduce running, repair, and
fuel costs while  supporting carbon-reduction targets.
• 2 x five-seater electric cars - Delivered to Children’s Services to meet operational
needs and contribute to lower emissions.
• 1 x Luton van with extended tail lift - Provided to Waste Services to improve the
efficiency of household bin deliveries and turnaround.
• 1 x 17-seater bus - Supplied to Social Transport to replace a hired vehicle,
improving reliability and reducing costs.
• 4 x new 35-yard skips - For Underwood Road HWRC to replace damaged or
end-of-life skips. 
6.1.2 All new vehicles meet Euro 6 emissions standards or are fully electric, directly supporting
Renfrewshire Council’s sustainability and Net Zero ambitions. This investment will improve
service reliability, reduce long-term operational and maintenance costs, lower emissions
and enhance environmental performance.

Page 4

PUBLIC
Roads & Transportation 
6.2  Roads Capital Investment Programme 
6.2.1  As part of the Roads Capital investment programme, in 2025/2026 we have resurfaced 47
carriageways, 16 footways and surface treated 38 carriageways.   
6.2.2 The Roads Capital team are finalising the resurfacing improvement programme for
2026/2027. 
6.2.3  Major resurfacing schemes at Collier Street car park, Barnsford Road (Phase 2) to Red
Smiddy roundabout, junctions at George Street, Canal Street, Maxwellton Street Paisley,
High Street Paisley (outside museum), Fairway Avenue, Paisley and Hillington Road are
scheduled for March, April and May 2026 respectively. 
6.2.4 We recently completed the trial of an Asphalt preservation method (spray application of a
sealant treatment) at Lonend. This process is intended to prolong the life of a carriageway,
delaying the requirement for full resurfacing, which has a far greater carbon footprint. This
will be monitored in the coming year to see how it performs under traffic loadings and
officers will report back to a future Board. 
6.2.5 Roundabout improvements as part of the Roads Capital programme for 2025/26 have
continued to upgrade A761 Main Road at Station Road Paisley, Abbotsinch Road at Arran
Avenue Glasgow Airport, Inchinnan Drive, Greenock Road at Barrangary Road Bishopton. 
6.2.6 The programme of roundabout improvements for 2026/27 includes A761 Linwood Toll,
A761 Linwood Road at Barskiven Road, Bridge of Weir Road Linwood at St Benedict’s
High School, Kings Inch Road at Laymoor Avenue and Kings Inch Drive Renfrew. 
6.3  Ready for Winter 
6.3.1  The service commenced winter resilience arrangements on the 1 October 2025, and this
will run through until May 2026. To the 9 March 2026, the Winter Maintenance programme
has used a cumulative total of over 1,980 tonnes of salt gritting Renfrewshire roads. The
service has gritted primary network routes 103 times and our secondary network on 15
occasions with gritting teams working around the clock to keep Renfrewshire moving
throughout this recent winter period. In comparison with the same period for 2025 (October
to early March), the service used 3,146 tonnes of salt gritting which is a significant
decrease in gritting and milder winter. Although, the first few months of 2026 provided a
variety of challenging weather, with Environment, Housing & Infrastructure services dealing
with gritting, heavy rain and high winds. 
6.3.2 In addition, we have completed full refurbishment of Rankine Street flood pumping station
in Johnstone. This will ensure its effective use for the coming years helping to protect
adjacent properties. We intend to roll this out to Collier Street pumping station this coming
financial year.

Page 5

PUBLIC 
6.4  Street Lighting Capital Investment Programme 
6.4.1  A new street lighting installation, comprising of heritage columns and lanterns (with dark
skies optics) has completed on Main Street and Church Street Lochwinnoch, awaiting a
new power supply. The heritage nature of the scheme, intended to be sympathetic to the
conservation area, has been well received by residents. An application for a new power
supply has been submitted to Scottish Power and we should have an install date within the
next couple of weeks, following which, the old lighting system will be removed, disposed of
in accordance with the WEEE Regulations (Waste Electrical and Electronic Equipment) and
the footway reinstated around the old column holes. 
6.4.2 A further column and loop replacement contract is currently underway, addressing isolated
knocked down and life expired columns throughout Renfrewshire. This has led to the
replacement of 86 columns and 41 damaged loops, bringing areas in previous darkness
into light. During this contract we have continued to work closely with colleagues at Scottish
Power to expediate new supplies. 
6.5  Active Travel & Infrastructure Improvement Update 
Red Smiddy, Inchinnan to Erskine Active Travel Route 
6.5.1  The Council has received £1.6million in funding from Transport Scotland for the Red
Smiddy, Inchinnan to Erskine Active Travel Route. A tender process concluded in
December 2025 with construction work started on site in early February. This will create a
shared use footway for walking and cycling expanding the network in the area. 
6.5.2 To allow the works to take place, temporary traffic lights will continue to be in operation on
a phased basis along the route to ensure the safety of workers and road users. 
6.5.3  The first phase of works will be construction of 1.4km of shared footway & cycleway from
the end of the existing shared footway/ cycleway on Greenock Road, round Red Smiddy
Roundabout, north onto Southbar Road to Southholm Roundabout. There is an existing
footway at Red Smiddy Roundabout which is widened, and new construction footway on
Southbar Road. 
6.5.4  The second phase will see the construction of 0.6km of shared footway & cycleway from
Southholm Roundabout to the overbridge on the A726 on the northbound verge.
Associated relocation of street lighting columns, road signs and installation of new
drainage. The works will involve the construction of a ramp to create a connection to the
existing footway overbridge over the A726 providing direct access to Park Mains High
School and Erskine shopping area. 
6.6 Renfrew to Paisley Active Travel Route (Gallowhill Link) 
6.6.1 The Council received funding from Transport Scotland for the Gallowhill Active Travel
Route. This will create a shared use footway for walking, wheeling and cycling expanding
the network in the area and also provide a safe, off-road, lit, access route from Gallowhill to
the new Paisley Grammar School, under the disused railway bridge on Renfrew Road (an
essential condition of Planning for the school) and onwards to the wider cycle network.

Page 6

PUBLIC 
6.6.2 Works commenced in late October and included site clearance, installation of drainage,
construction of a new 600m long shared footpath with streetlighting, and landscaping
works. The works completed ahead of schedule at the beginning of March, with an official
opening on the 10th of March.   
6.7  Elderslie for Everyone Project 
6.7.1  The developed design is continuing on from the concept design stage which has been
completed. Within this stage we will continue to gather feedback on the design from the
community and prepare more technical information to inform the developed design stage.
Ongoing public communication, meetings with local businesses and elected members have
taken place and will continue throughout the project process. 
6.8 Inspection of Carriageways and Footways held in the Housing Account 
6.8.1 We have recently recruited an inspector who will work part time in the roads service and
part time in the housing service. The intention is to ensure that road infrastructure held
within the Housing Estate is managed in the same manner as the public road, with cyclical
safety inspections and a matrix for prioritising repairs against competing priorities. This will
be the first time that the Housing road asset will be managed in such a proactive manner. 
6.9 Villages Safe Walking Initiative 
6.9.1 Phase 1 of the Villages Safe Walking Initiative has concluded its second round of
consultation on the refined detailed design and location of proposed traffic calming
measures in Houston, Howwood and Kilbarchan. Detailed drawings of measures were
consulted on with the Community Councils and subsequently they were letter dropped to
directly affected residents. 
6.9.2 Comments asking for changes or objecting to elements were accepted by officers and
responses have been prepared. They explain where we have been able to accommodate
requests for change and where, due to considerations of road safety and practicality of
construction, we have not. We will be looking to meet with ward members to discuss the
conclusions of the consultations and the finalised construction drawings. Implementation of
the measures will follow in the new financial year. Officers continue to progress more
complex designs at Houston Cross, Kilbarchan Cross and Howwood Black Cart Water
Bridge. 
6.9.3 Phase 2 of the Villages Safe Walking Initiative has completed its concept design stage and,
on the basis of the support shown by responses received to the consultation, our
consultant is now developing the detail of those designs through engaging with the
communities of Bishopton, Bridge of Weir, Elderslie, and Lochwinnoch to refine the
proposals once again.

Page 7

PUBLIC 
6.9.4 We will also refine cost estimates and develop a proposed implementation programme
which will be contingent on the availability of future years’ funding. Based on current high
level estimates, to complete all measures outlined within the work to date would cost
around £3million. Officers will prioritise the interventions in order of impact and would then
look to explore potential funding sources to be able to deliver a prioritised list. Ward
members will be updated as this progresses. 
6.9.5 In response to requests for Langbank’s inclusion in Phase 2 of the Villages Safe Walking
Initiative, we have separately begun investigating potential measures for Langbank village.
We are preparing to consult with the community on their concerns and for feedback on
proposed potential measures. 
7.   Neighbourhood Services 
7.1   Cemetery Update 
7.1.1  A programme of seasonal winter maintenance has been completed across all sites. Teams
have undertaken intensive scraping in targeted cemetery areas, alongside hedge-pruning
activities. The service continues to monitor public feedback to identify any additional priority
areas requiring maintenance.     
7.1.2  A conservation inspection of the Glen Cinema Memorial in Hawkhead Cemetery identified
several areas requiring enhancement. A conservation specialist was appointed to carry out
these works, which commenced in December 2025. Progress is ongoing and remains
dependent on weather conditions. 
7.2  Country Parks 
7.2.1  Paisley and District Scout Groups continue to support their “Better World” project  through
organised volunteer activity days at Glennifer Braes Country Park. Under the guidance of
their leaders and the Countryside Rangers, this Spring’s programme focuses on woodland
management activities within Glen Park. 
7.2.2  Avian Flu has been confirmed within Castle Semple Country Park. All required public health
and biosecurity measures have been implemented, including the installation of appropriate
signage and updates to visitor communications. 
7.2.3 Summer opening hours will operate from April to October and will include the full  delivery
of outdoor activity sessions and environmental education programmes.        
7.3  Play Parks Update 
7.3.1 The play park renewal programme for 25/26 continues to progress with the following work
completed: 
• Tinto Square Playpark, Renfrew - An inclusive seesaw has been installed
and designed to accommodate up to two wheelchairs. This represents the
first installation of its kind to be trialled within Renfrewshire.

Page 8

PUBLIC
• Moss Road Playpark, Bridge of Weir - A new section of link path has been
constructed outside the fenced play area, ensuring that park users can
avoid walking through the playpark itself when ground conditions are wet.
• Park Road, Johnstone - A new fenced dog exercise area has been
completed on the site of the former derelict BMX course, providing a safe
and dedicated space for dog owners. 
7.3.2 Further improvements are planned for delivery including: 
• Robertson Park (Main Play Area), Renfrew – anticipated start: April 2026
• Stuart Road, Bishopton – anticipated start: March 2026
• Campbell Street, Johnstone – programme to be confirmed
• East Fulton, Linwood – anticipated start: late April to early May
• Ferguslie Gardens (Bottom Play Area), Paisley – anticipated start: March 2026
• Red Blaes BMX Track, Barshaw Park, Paisley (conversion to pump track) –
currently at tender return stage
• New Outdoor Gym, Lochwinnoch Public Park – anticipated completion: end of
March 2026 
7.4  Seasonal Grass Cutting Programme     
7.4.1  The service has completed the recruitment process for this year’s intake of seasonal staff
to support the extensive summer grass cutting program. The grass cutting season will start
on 1 April 2026. 
7.5  Open Space 
7.5.1  Fountain Gardens, Paisley – A contract has been awarded for the conservation of the
Robert Burns statue. Due to its historical and cultural significance, the works are expected
to take several weeks once commenced. The Grand Fountain is scheduled for cleaning
and servicing in March, following the winter shut-down period. The water features will be
switched back on at the same time. 
8. Bus Service 514 
8.1 As reported to the ILE Board of August 2025, Council officers have been working with SPT
to extend the bus service connecting Dargavel to Braehead. This resulted in the proposed
end date of the contract being extended from January 2026 to May 2026. 
8.2 Due the continued low patronage levels on the route there is not going to be any possibility
to extend the service beyond the first week in May 2026. The route has been funded as
part of the Section 75 agreement with BAE, however that funding will expire in May 2026
and as such the service will come to an end. 
8.3 SPT engaged with the market to understand if there was any market interest in taking this
service forward, however given the patronage figures this service is unsustainable and SPT
have advised that they are not in a position to operate the service as a subsidised route.

Page 9

PUBLIC   
8.4 Council officers will continue to liaise with SPT to assess what opportunities may exist to
improve access to public transport for Dargavel residents.   
9. Waste Services 
9.1    Waste Services Website Update  
9.1.1  As part of the route optimisation software integration, the service is advancing the system’s
automated online forms. This work includes linking the Council’s existing website
processes directly into the new system making the process more efficient. The online forms
for requesting assisted collections, bin swaps, bin deliveries, and bulky uplifts have been
updated to support direct integration with the route management system. All updated forms
are live and available through the Council’s website. 
9.2 Library WEEE Banks Project (Waste Electrical and Electronic Equipment) 
9.2.1 The first year of the WEEE Bank project across Renfrewshire libraries has delivered 
excellent results. The initiative exceeded expectations, with 2.44 tonnes of small 
electrical items collected surpassing the original estimate of 2.16 tonnes. 
9.2.2 Alongside this, Waste Services recorded a significant rise in WEEE recycling 
across both the library banks and the Household Waste Recycling Centres. An
additional 75.10 tonnes of electrical items were collected for recycling, supported by a 
communications campaign highlighting the importance of recycling unwanted 
electricals. This positive first year demonstrates growing public engagement and the 
impact of making recycling more accessible to residents. 
9.3   Service Improvement 
9.3.1  The performance of bin collections is a key priority for Waste Services. To support this, a
temporary Business Improvement Officer post was created to focus on data analysis and
performance management within the service from February 2026. A core element of this
work is improving outcomes for residents who receive an Assisted Collection.  Although the
work is in its infancy, throughout February there has been improved performance with
99.84% of bins and 99.45% of assisted bins collected emptied on collection.  The team will
continue to focus on this area of work to support sustained performance both across the
service and with specific addresses that require bespoke arrangements for collections.     
9.4   Packaging & Recycling Handling Facility – Linwood 
9.4.1 The service is progressing a detailed Business Case for the construction of a packaging
and recycling handling facility at Middleton Road, Linwood. This facility would be able to
handle materials from the blue, brown and green bins, street sweepings and gulley
cleanings, bulky items from special uplifts, waste upholstered domestic seating and white
goods etc. In addition, the construction would include a new secure bin store with a wash
and repair facility. The Business Case is under review by the Councils finance section; a
further update will be brought to a future board.

Page 10

PUBLIC    
10.  #YouDecide 
10.1.1 Improvements works at the Barrangary and Chestnut roundabouts in Bishopton have been
completed in preparation for new public sculpture installations. A horse sculpture is planned
for Chestnut roundabout and a tree sculpture for Barrangary roundabout. Both are
scheduled for completion by the end of March 2026. 
10.1.2 An outdoor gym has been installed in Lochwinnoch Park, marking the completion of
Lochwinnoch #YouDecide projects. 
10.1.3 The access path to Glencoats Park play area has been resurfaced and this completes
#YouDecide projects for Paisley North West and Central. 
10.1.4 The following projects remain in progress. Individual completion reports will be submitted
as each project is finalised:
• Roundabout improvement schemes in Kilbarchan and Renfrew 
• Activity/Heritage trails in Inchinnan and Kilbarchan 
• Car park and path improvements at Gleniffer Braes 
• Outdoor Gym installation at Poplar Avenue, Johnstone 
11.  Public EV Charging Infrastructure Update 
11.1.1 Renfrewshire continue to work alongside all Glasgow City Region partners to expand public
use EV charge points across each local authority partner area including Renfrewshire. The
programme will involve the migration of around 600 existing charge points in and the
installation of around 3,000 new charge points. 
11.1.2 The updated programme timeline highlights that the procurement process to appoint a
commercial Charge Point Operator (CPO) has now commenced with an appointment of an
operator due to be concluded by September 2026. 
11.1.3 To allow for the prompt transfer and migration of existing EV assets to the new CPO, once
appointed, each member authority require to have authority to grant licences in place prior
to contract award. A more detailed update will be provided to the board in May.

Page 11

PUBLIC 
Implications of the Report 
1.  Financial – Any financial elements referenced in this report will be progressed through the
Council’s financial & budget planning process. 
2.   HR & Organisational Development – None       
3. Community/Council Planning – The report details a range of activities which reflect local
community and council planning themes. 
4. Legal – None 
5. Property/Assets – None 
6.   Information Technology – None 
7. Equality & Human Rights - The recommendations contained within this report have been
assessed in relation to their impact on equalities and human rights. No negative impacts on
equality groups or potential for infringement of individuals’ human rights have been
identified arising from the recommendations contained in the report. If required following
implementation, the actual impact of the recommendations and the mitigating actions will
be reviewed and monitored. 
8. Health & Safety – None 
9. Procurement – None 
10. Risk – None 
11.   Privacy Impact – None 
12.  Climate Change – there are a range of actions and activities throughout the Service
Update Report which support the Council’s Plan for Net Zero. 
13.  Children’s Rights – None 
14.  Cosla Policy Position – None 
List of Background Papers: None 
Author:  Gordon McNeil, Director of Environment, Housing & Infrastructure 