Democracy Spraffa

Clyde Valley Update Report

Renfrewshire Council · 21 January 2026
Back to Infrastructure, Land and Environment Policy Board — 21 January 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
___________________________________________________________________ 
To: Infrastructure, Land and Environment Policy Board 
On: 21 January 2026
___________________________________________________________________ 
Report by: Director of Environment, Housing & Infrastructure
___________________________________________________________________ 
Heading: Clyde Valley Update Report
___________________________________________________________________ 
1. Summary 
1.1 This report provides an update on the first six years of the Clyde Valley Residual
Waste Contract, a 25-year partnership between East Dunbartonshire, East
Renfrewshire, North Ayrshire, North Lanarkshire, and Renfrewshire Councils for
the treatment and disposal of residual waste. 
1.2 Since its commencement, the contract has diverted over 900,000 tonnes of
waste from landfill, recovered 66,000 tonnes of plastics and metals, and
generated 110 GWh of electricity, enough to power 43,000 homes. Operational
performance has been strong, with minimal delays and KPI breaches accounting
for less than 0.03% of deliveries, ensuring compliance with Waste Scotland
Regulations and delivering significant environmental benefits. 
1.3 The contract has delivered a range of community benefits including 3
apprenticeships and 80 capacity-building workshops. Additionally, 30 pupils have
completed Net Zero Virtual Work Experience placements toward a target of 100.
Viridor has distributed £19,661 through its ‘We Share Fund’ for community
projects and introduced a Clyde Valley-specific STEM programme, providing S2
students with hands-on experience and Industrial Cadet Bronze Accreditation. 
1.4 The contract has evolved through variations to meet legislative and operational
requirements, making the current Inter-Authority Agreement (IAA) outdated.
Amendments to the IAA are required to reflect current arrangements and
obligations without changing the contract’s purpose or participating councils.
Approval is sought for the proposed amendments set out in section 4.10 of this
report.

Page 2

PUBLIC
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board: 
2.1 Note the content of the report. 
2.2 Approve the proposed changes to the Inter-Authority Agreement. 
2.3 Approve delegated authority to the Director of Environment, Housing &
Infrastructure to sign the updated agreement on behalf of the Council. 
___________________________________________________________________ 
3. Background 
3.1 In 2009 the Scottish Government released a report by Sir John Arbuthnott in
relation to savings Councils could achieve through collaboration of Services
across the Clyde Valley Authorities, these being Glasgow, North Lanarkshire,
South Lanarkshire, Inverclyde, East Dunbartonshire, East Renfrewshire, West
Dunbartonshire and Renfrewshire Councils.  In 2010 North Lanarkshire Council
were lead on investigating the ability to collaborate on waste management
services.    
3.2 Initially all aspects of waste management were reviewed, however the project
team focused on a solution for the upcoming Landfill Ban enforced by the Waste
Scotland Regulations 2012 (this subsequently moved from 2017 to 2020 and
now to 2025). 
3.3 The Final Business case was presented to the Authorities in late 2012 and four
of the Clyde Valley Authorities (North Lanarkshire, East Renfrewshire,
Renfrewshire and East Dunbartonshire Council) and North Ayrshire gained
approval to procure a long-term solution for the treatment and disposal of
household residual waste which aligned to the Landfill Ban.    
3.4 The solution had to provide a delivery point for each Partner within their
boundary with only North Lanarkshire Council needing to provide such a facility
as all other four had existing waste transfer sites. 
3.5 Procurement for a solution took place from 2013-2016, the Contract was signed
with the preferred bidder (Viridor) in May 2016 with the Contract going live in
January 2020. 
3.6 North Lanarkshire Council continue to act as the Lead Authority for the Contract,
and all obligations are backed off through an Inter-Authority Agreement (IAA)
with the other four Partners.    
3.7 The solution provided by Viridor offered the following: 
• Contract for 25 years for the treatment of household residual waste up to a
maximum of 190K tonnes per annum: 
• Provision of 4 Waste Transfer Stations to serve East Dunbartonshire, East
Renfrewshire, Renfrewshire and North Ayrshire Councils.

Page 3

PUBLIC
• A purpose-built recycling and waste transfer facility at Bargeddie which would
accept and sort all waste from the above 4 facilities along with all waste
delivered direct from North Lanarkshire Council. The key purpose of this
facility would be to remove all plastics and metals from the waste resulting in
a minimum recycling rate from the residual waste of 4%. 
• The provision of an energy from waste plant at Dunbar which would accept all
waste from the Bargeddie facility which in turn would be incinerated to
produce electricity. 
3.8 The Contract commenced on 7 January 2020 and has now been live for six and
a half years.  The Contract Management Team has been in place since the
Contract was signed in May 2016 to ensure successful delivery of the Contract. 
3.9 The Inter-Authority Agreement (IAA) was signed in 2016 however as the contract
has progressed, it has been noted that there are a few practical amendments to
be made. 
4.  Report 
4.1 The first six years of the contract have been a success with over 900,000 tonnes
have been diverted from landfill and approximately 66,000 tonnes of plastic and
metal have been recycled or repurposed, when they would have otherwise gone
to landfill.  The treatment of Clyde Valley residual waste produces in the region of 
110GWh of electricity (equivalent of powering 43,000 homes) and was fed back
into the national grid. 
4.2 Operational delays have been minimal, with the 15 minute turnaround time KPI
(for RCVs delivering waste to the facilities) only being exceeded 45 times over the
first six years over the five Partner Councils, which is estimated to equate to less
than 0.03% of total deliveries for all RCVs over this time period. 
4.3 The first six years of the contract have been a success with over 900,000 tonnes 
diverted from landfill and approximately 66,000 tonnes of plastic and metal have
been recycled or repurposed, when they would have otherwise gone to
landfill.  The treatment of Clyde Valley residual waste produces in the region of
110GWh of electricity (equivalent of powering 43,000 homes) and was fed back
into the national grid. 
4.4 The tonnages have fallen gradually from the first full contract year 2020/21 to
2024/25, as the Partner Councils aim to reduce residual waste arisings by
recycling kerbside. Individual tonnages are detailed below:   
Partner  2020/21 Tonnage 2024/25 Tonnage % Difference
East Dunbartonshire 25,184.62 21,966.27 -12.78
East Renfrewshire  19,003.89 18,165.31 -4.41
North Ayrshire 28,853.6 27,897.98 -3.31
North Lanarkshire  69,550.43 66,052.96 -5.03
Renfrewshire  38,814.1 37,680.04 -2.92
Totals 181,406.64 171,762.56 -5.32  
NOTE: there was a period of time in 2020 when all waste was collected in the
residual bin due to the restrictions of the COVID19 pandemic.

Page 4

PUBLIC
4.5 To date, through Community Benefits, the contract has delivered 3
apprenticeships (out of a 25-year commitment of 16), 80 capacity building
workshops, and over £4.5m has been spent with SMEs and SEO at the
Bargeddie Facility. To date, a total of 30 pupils have completed work experience
with Viridor as part of the Clyde Valley Contract, and they are on track to achieve
the commitment of providing a minimum of 100 work placements across the
contract term. The pupils undertook the Net Zero Virtual Work Experience
programme in partnership with the Engineering and Development Trust (EDT). 
4.6 As part of their We Share Fund, Viridor have distributed £15, 993 from the
Bargeddie Facility, and £3,668 from the Authority Transfer Stations in 2024/25. 
This is a Corporate fund set up by Viridor which enables members of the
community to apply for funding for projects that help the environment/community.
This is not Clyde Valley specific and is additional to the requirements set out in
the Contract. 
4.7 Viridor have developed a Clyde Valley specific STEM (Science, Technology,
Engineering and Maths) programme in conjunction with the Engineering
Development Trust (EDT).  This is an annual programme open to all of the Clyde
Valley schools where teams of S2 students work together within their school
groups to gain an insight into the STEM sector and to receive an Industrial Cadet
Bronze Accreditation on completion of their challenge. 
4.8 The Contract has evolved through a number of variations and updates to suit
both legislation requirements and the logistics of actually managing the Contract. 
These are summarised in the table below. 
Contract
Variation
Number 
Date Submitted Summary of Variation Reason for Variation
1 04/07/2017
Vary Schedule Part 4
(Payment Mechanism) in
order to provide for
reconciliation of National
Non-Domestic Rates
To close the loop of
reconciliation on forecasted
tonnages
2 15/03/2023
Vary Schedule Part 4
(Payment Mechanism) in
order to reflect current
practices
To reflect current practices
3 03/11/2023
Vary Schedule Part 1
(Definitions) "ATS Site
Plans" and
"Renfrewshire ATS Site"
To remove a part of the
Linwood site at the back of the
site to give this land back to
RC.  This involves varying the
site plans and areas of
responsibility and also moving
one borehole to within this new
boundary and taking new
samples to re-establish the
baseline
4 21/10/2024
Vary Schedule Part 1
(Definitions) "ATS Site
Plans" and "East
Renfrewshire ATS Site"
Review areas of responsibility
at the ERC ATS Facility

Page 5

PUBLIC
5 15/03/2023
Updated PA for data
protection, change in
addresses, changes to
definitions, Authority
ATS Works,
To reflect current practices
6 03/11/2023
Vary Schedule Part 1
(Definitions) "ATS Site
Plans" and
"Renfrewshire ATS Site"
Amended area of responsibility
to match fence line 
4.9 As a result, the Inter Authority Agreement (IAA) has become outdated and this
needs to be updated to reflect current Contract positions and those obligations
now being passed to the Partner Councils as well as practical matters being
updated. Although there are a number of highlighted changes, they do not
represent any fundamental change in the purpose of the contract or the
participating local authorities. 
4.10 The table below explains the substantive amendments made to the IAA and does
not include minor changes which are stylistic; or are factual updates. Definitions
used within this document are contained in either the IAA, or the Project
Agreement between North Lanarkshire Council (as Lead Authority) and Viridor. 
Relevant Clause(s) Original Drafting  New drafting 
Data Protection 
• Amended and
deleted
definitions
• Amended
Clause 18 
In line with legal position
at the time of entering into
IAA in 2016. 
Drafting updated to reflect change in legal
position including Data Protection 2018
and UK GDPR (post Brexit version of EU
GDPR). 
This is standard drafting across all Local
Authority contracts, and a similar
amendment was made to the Project
Agreement 
Clause 4 Duties of
Lead Authority and
Other Authorities –
General Duties of
All Authorities 
• Amended
Clause 4.5
• New Clauses
4.5A, 4.5B,
4.5C and
4.5D 
Original drafting in IAA
envisioned that each
Authority’s share of the
Minimum Tonnages and
Maximum Tonnages1
agreed before Services
Commencement 
(7 January 2020) would be
reviewed and agreed 5
years from Services
Commencement and
every 5 years thereafter 
New drafting reflects agreement by
Steering Group in November 2024 that
the Authority’s want the power to review
and amend (by agreement) the Minimum
and Maximum Tonnages annually. It was
agreed that experience has shown that it
is better for Authorities to have more
flexibility to make changes, and not be
locked in for 5 years. 
It was agreed that this will be based on
the tonnages provided in the previous
Contract Year and will commence from
the 1 April immediately occurring after
Steering Group approval. For example, in 
1 The Minimum Tonnage is defined in the Project Agreement as “100,000 tonnes of Contract Waste
(excluding Ad Hoc Waste) per Contract Year (pro rated for any Contract Year of less than 12 months)”
and the Maximum Tonnage is defined in the Project Agreement as “190,000 tonnes of Contract Waste
(excluding Ad Hoc Waste) per Contract Year.”

Page 6

PUBLIC 
advance of the 5th anniversary of
Services Commencement the Steering
Group approved the relevant tonnages in
November 2024 to apply from 1 April
2025 and this was based on the tonnages
in Contract Year 2023- 24. 
The Steering Group members also have
the power to amend the metric being
used to calculate Minimum and Maximum
Tonnages 
Furthermore, the drafting states that each
year the Steering Group must make a
decision on the share of tonnages
between 1 November and 31 December. 
Additional drafting has also been inserted
placing duties on the Contract Manager
to confirm the allocation of the Authorities’
share and monitor the tonnages delivered
throughout the Contract Year and
highlight any issues to the Steering
Group. 
Where appropriate, the word
“Authorities’” (apostrophe after the ‘s’)
has been amended to “Authority’s”. 
Clauses 7.8 – 7.9
Share of CMT
Annual Budget 
• Amended
Clause 7.9 
The share of the tonnages
split between the
Authorities impacts the
share of the CMT Annual
Budget 2and the CMT
Annual Budget
Proportions3. The original
drafting envisioned that
this would be adjusted 5
years from Services
Commencement and
every 5 years thereafter. 
The position remains that share of the
tonnages split between the Authorities
impacts the share of the CMT Annual
Budget Proportions. The drafting at
clause 7.9 has been amended to reflect
the change in position relating to updating
the Minimum and Maximum Tonnages
share at clause 4 (see above).
Accordingly, the CMT Annual Budget
Proportions will also be updated annually,
instead of every 5 years. 
Clause 12
Payments 
The original drafting
placed an obligation on
each Authority to pay their 
The drafting has been amended to
change the obligation to make payment in
cleared funds within 21 days of receipt of 
2 Defined in IAA as “the sum set in accordance with Clause 7 (Contract management Team (CMT)
Annual Budget) and Schedule Part 5 (CMT Annual Budget) which represents the upper limit of the
financial threshold calculated by the Joint Steering Board for each Authority's annual contribution to the
necessary funding of the Lead Authority to discharge its functions on behalf of all the Authorities under
this Inter-Authority Agreement as managed by the Joint Steering Board, notified to the Joint Steering
Board and approved by each Authority in respect of this Project (and the Authorities acknowledge that the
CMT Annual Budget does not include the Monthly Unitary Payment made under the Project Agreement).”
3  Defined in Schedule Part 5 of IAA as “CMT Annual Budget does not include the Monthly Unitary
Payment made under the Project Agreement.” The Initial CMT Annual Budget Proportions are set out at
Schedule Part 5 and cover Contract Year 2016 – 2017.

Page 7

PUBLIC
• Amended
Clause 12.6
monthly payment
proportion (in cleared
funds) to the Lead
Authority (NLC) by the 25th
day of the month in which
the instruction or invoice
for payment has been
served. 
an instruction for payment or invoice. This
is due to a change made to the Project
Agreement that afforded more time for
NLC to make payment, and NLC has
passed this on to other Local Authorities. 
Clause 15 Liability
of the Councils 
• Amended
Clause 15.11
• New clause
15A 
The original drafting did
not reflect how the Project
Agreement and associated
insurances work in
practice. It suggested that
the Lead Authority (NLC)
would have responsibility
for administering all
Project insurances where
not administered by
Viridor. 
Amendments have been made to reflect
how the insurance obligations work in
practice. Where the Project Agreement
requires any insurances from both the
Lead Authority (NLC) or other Authorities,
as co-insured or otherwise, there is a
responsibility to administer this in
accordance with the Project Agreement. 
A new clause 15A was inserted to narrate
the position in relation to North Ayrshire
Council ATS Site as the insurance is held
differently to all of the other ATS Sites.
North Ayrshire Council is liable to insure
the building at North Ayrshire ATS Site
under a Property Damage Policy and
include Viridor as a named party on the
relevant policy, in accordance with Part X
– Insurance of the Project Agreement. 
Clause 27 Notices 
• Amended
Clauses 27.1
and 27.2 and
corresponding
amendments
at Schedule
Part 4.   
The original drafting
allowed notices to be
served by fax, and allowed
notice by email to be
served. However, it was
not clear as to how this
would work in practice. 
The amended drafting deletes references
to notices by fax, and adds in additional
detail as to how a notice would be served
by email. 
Schedule Part 1:
Project Tasks 
The original list set out the
correct authority for certain
decisions and obligations,
either being Contract
Manager Matter, Lead
Authority Matter, Project
Director Matter, Joint
Steering Board Metter,
Matters Reserved to
Authorities and Statutory
Officer Matter. 
Additional entries have been made to
reflect the amendments made to the IAA.

Page 8

PUBLIC
Schedule Part 2:
Joint Steering
Board Functions
and Terms of
Reference 
• Paragraph
2.7 amended  
Paragraph 2.7 originally
required the Lead
Authority's internal audit
service to provide a
statement of assurance
annually.
Paragraph 2.7 amended to require that
that the Lead Authority's internal audit
service provides a statement of
assurance, every two years (instead of
annually). 
Schedule Part 4:
Addresses of the
Authorities   
The original list set out
addresses for each
Authority where notices
should be sent to. 
The amendments expand this list to
include email addresses for each
Authority so that notices by email can be
issued to the Head of
Service/Manager/Director acting as Joint
Steering Board member for Clyde Valley
Project, copied to Head of Legal
Services/Corporate Governance (or such
role as amended or updated) at the time
of issuing of the notice. 
Schedule Part 8:
Part 2 – Cost
Sharing Principles 
The original drafting
contained cost sharing
principles between the
Local Authorities. 
The cost sharing principles largely remain
but have been expanded to include some
detail not originally provided in relation to
the East Renfrewshire ATS Ancillary
Waste Payment. There is now a
recognition of the possibility of a payment
arising due to the East Renfrewshire ATS
Ancillary Income Share.  
The amendments make it clear that any
sum payable in respect of the East
Renfrewshire ATS Ancillary Waste
Payment shall be borne wholly by and/or
allocated wholly to East Renfrewshire
Council. This reflects the position in the
payment mechanism contained in the
Project Agreement. 
The text relating to Monthly Unitary
Charge has also been amended to reflect
the change in Minimum and Maximum
Tonnages being agreed annually instead
of every 5 years following Service
Commencement. 
4.11 The contract has been set up to be flexible to deal with the ever-changing waste
legislative environment and includes provisions for Qualifying Changes in Law if
they arise as well as specific Contractor and Authority Changes should either Party
want those as the Contract progresses.

Page 9

PUBLIC
5 Measures of Success 
5.1 The ongoing delivery of a public partnership model for the treatment and disposal
of residual waste which will ensure all partner local authorities comply with the
relevant legislative provisions and that the performance targets associated with
the contract are maintained.   
5.2 Community Benefits delivered as part of the Contract benefit the local
businesses and schools.  Viridor have partnered with the Education
Development Trust (EDT) to deliver a bespoke STEM programme for the schools
within the five Partner Councils. Each year this is well attended and has involved
impressive partnerships that mentor the pupils during the programme. 
5.3 The Contract Management Team manage the Contract on behalf of the Partner
Councils and have received a Substantial Assurance rating from NLC audit every
time.  In addition to this, the team continue to investigate other projects that the
Partner Councils could collaborate on to deliver savings and also look into other
waste streams that can be brought to the Contract to provide best value to the
Partner Councils.

Page 10

PUBLIC 
Implications of the Report 
1. Financial – none 
2. HR & Organisational Development – none 
3. Community/Council Planning – none 
4. Legal – none 
5. Property/Assets – none 
6. Information Technology - none 
7. Equality & Human Rights – none 
8. Health & Safety – none 
9. Procurement – none 
10. Risk – none 
11. Privacy Impact – none 
12. COSLA Policy Position – none 
13. Children’s Rights - none 
14. Climate Change – none 
List of Background Papers: none 
Author: Gordon McNeil, Director of Environment, Housing and Infrastructure,
Email: gordon.mcneil@renfrewshire.gov.uk