ARGYLL AND BUTE COUNCIL                                               OBAN LORN AND THE
ISLES AREA COMMITTEE                                                                                                         
ROADS AND INFRASTRUCTURE          DECEMBER 2023
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 A Roads and Infrastructure standing report was a fixture on Area Committee
agendas throughout the life of the last Council. In the first two rounds of Area
Committee meetings in the new Council feedback was sought on the value of
these updates, and their format and frequency. Generally Members felt having a
standard item was beneficial and it was acknowledged that the Roads and
Infrastructure weekly briefings issued to all members each Friday afternoon
provide for the main sources of live information on current activities. On top of
these briefings there is a bank of resources on the new Member Zone system
which include the weekly briefings, subject specific briefings, ad hoc short
briefings on issues, relevant previous committee reports, operational service
procedures, legislation and Council policies. 
1.2 In the last Council the purpose of these reports was to provide an update on
service activities but since weekly briefings were introduced around 18 months
ago (at the time of writing this report we are on to briefing Edition 127) these
have largely superseded the original stated purpose of these reports. 
1.3 On the basis of the above this new format has been agreed through the
December 2022 round of area committees for this standing item. This format
removes duplication for Officers and rather links to existing published
information, with additional updates only in the body of the reports if these are
specifically requested/noted from previous meetings. The report remains as a
standing item and continues to provide the opportunity for Officer engagement at
the committee meetings.   
2.0 RECOMMENDATIONS 
It is recommended that the Area Committee: 
2.1 Note and consider the contents of this report.

Page 2

3.0 DETAIL 
3.1 Roads and Infrastructure Services provides Members with weekly briefings on
topical service activities which are all available here.   
3.2 As part of the resources on the new Member Zone system there are various key
documents available in an online library here. 
3.3 Members will be aware of a significant rain event which took place on 6/7 October
this year. There were a number of areas affected by flood water around the Oban
and Lorn area including significant parts of Oban around Lochavullin. The trunk
road network into Oban and also Mid Argyll was closed due to a combination of
flood water and landslips meaning that on the Saturday afternoon, access into
many parts of Argyll and Bute was not possible by road. In the Oban, Lorn and
the Isles area, the following locations were also affected: 
• Kilninver bridge was severely affected by scour (water washing out parts
of the masonry structure). Extensive repair works have been carried out.
• Kilmelford bridge was so badly affected it had to be demolished and a new
structure is now in place to allow access. Whilst the bridge is open to all
traffic, a hydrology study is being carried out which will inform the design
and style of the wing walls (the walls that stand in the river and direct water
into and out of the bridge structure).
• Scammadale – high river levels washed away an embankment that
supports the road. Repairs are being carried out during night shift working
which allows the road to be blocked off to allow positioning of the
crane/excavator. Good communication shave been established with local
residents and arrangements in place for the delivery of essential supplies
such as heating oil and animal feed etc.
• A816 south of Ardfern – whilst this is not within the OLI area it provides a
strategic connection between Oban and Lochgilphead. At the time of wiring
the road remains closed due a significant landslide and slope stability
concerns.  A bund and ditch are being constructed together with an
emergency bypass road which is scheduled to open on 16 December
subject to weather and any other unforeseen matters. 
3.4 Presentations have been made as part of the Members Seminar sessions, the
slides from which can be found on the Members Portal. There was also a report
taken to the Environment, Development and Infrastructure Committee on 30th
November which summarised the impact of the weather event across the whole
of Argyll and Bute. The full report can be viewed on the Council website.   
4.0 CONCLUSION 
4.1 This report provides links to existing published information on service activities
and provides for the opportunity for Officer attendance and engagement at
committee meetings.

Page 3

5.0 IMPLICATIONS 
5.1 Policy – Roads and Infrastructure work to a number of policies across the range
of service areas 
5.2 Financial – revenue and capital budgets are in place to deliver projects and
cyclic work 
5.3  Legal – none known 
5.4  HR – none known 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – where appropriate EqSEIAs will be
carried out to identify any implications 
5.5.2   Socio-economic Duty – where appropriate EqSEIAs will be carried out to
identify any implications 
5.5.3 Islands – where appropriate Island impacts assessments will be carried out to
identify any implications 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise 
5.7  Risk – risk managed through toolbox talks, safety briefings and where
appropriate risk registers – all of the above are monitored through the RIS
leadership and management teams 
5.8  Customer Service – none known 
Executive Director with responsibility for Roads and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
November 2023                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services