Environment, Housing & Infrastructure Services - Service Improvement Plan 2025-28 Mid-Year Monitoring Report - FULL REPORT

Renfrewshire Council · 5 November 2025
Back to Infrastructure, Land and Environment Policy Board — 5 November 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
To: Infrastructure, Land and Environment Policy Board
On: 5 November 2025 
Report by: Director of Environment, Housing & Infrastructure 
Heading: Environment, Housing & Infrastructure Services - Service
Improvement Plan 2025-28 Mid-Year Monitoring Report 
1. Summary 
1.1 The Environment, Housing & Infrastructure Services Service Improvement
Plan 2025-28 was approved by the Infrastructure, Land and Environment
Policy Board on 21 May 2025. The plan sets out the priorities for the
development of the service over a three-year period. 
1.2 The Service Improvement Plan is part of a suite of documents which
describe the strategic direction of the Service and the Council, and also
includes the Council Plan, Community Plan, Risk Management Plan and the
Workforce Plan. 
1.3 The Service Improvement Plan sets out the actions which will ensure
continuous improvement across the service and the performance indicators
which ensure the impact can be measured. These reflect the priority themes
of the new Council Plan which was approved by Council on 29 September
2022. 
1.4 This report contains details of Environment, Housing & Infrastructure
performance and achievements over the period 1 April 2025 to 30
September 2025. The main purpose of the report is to provide: 
• details of the key achievements of the service over the period;
• a progress update on implementing the action plan linked to the 2025-28
Service Improvement Plan;
• an assessment of performance in relation to the service scorecard of
core performance indicators; and
• an overview of priorities for the service over the next six months.

Page 2

PUBLIC
1.5 Over the past six months, the service has made good progress in delivering
positive outcomes for Renfrewshire and its residents. This includes through
the actions within the Service Improvement Plan and also other areas of
activity which did not form part of the Service Improvement Plan actions
which have subsequently arisen over the first six months of 2025/26. 
1.6 To compliment the six monthly update on the Service Improvement Plan, a
Service Update report will be presented to each cycle of the Infrastructure,
Land and Environment Policy Board. This report will provide an overview of
key service activities, an operational performance update on the services
and key projects and updates on any other relevant changes to service
areas covered within the remit of the Board. 
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board note: 
2.1 The contents of this report. 
2.2 The progress to date on delivering the actions contained within the
Environment, Housing & Infrastructure - Service Improvement Plan. 
2.3 The current performance of the service as measured by the
scorecard indicators. 
3. Background 
3.1 The Service Improvement Plan is a comprehensive statement of the
outcomes the service aims to achieve, and the actions it will take to achieve
these. It fits within the wider planning framework of the Council by taking
account of Community Planning themes and Council priorities as set out in
the Council Plan which was refreshed in June 2024. It enables elected
members to have oversight of developments within the service and to
consider and develop policy options which reflect customer need and
resource availability. 
3.2 The Service Improvement Plan also provides a mechanism by which elected
members can evaluate the performance of the service. The appendix to the
plan contains an action plan and performance indicators against which
progress can be measured. This mid-year monitoring report provides an
update on progress against the 2025-28 plan. 
3.3 Section 4 gives details of service activity and achievements over the period
April-September 2025. Section 5 discusses any actions delayed since the
Service Improvement Plan was approved. Section 6 provides a narrative on
performance against the scorecard included as appendix 1.    
3.4 An outturn report detailing full-year performance will be brought before this
board in spring 2026.

Page 3

PUBLIC
4. Service Update and Key Achievements April-September 2025 
Key Achievements 
Environment, Housing & Infrastructure continues to deliver essential frontline
services across Renfrewshire. Key achievements for Environment, Housing &
Infrastructure under the remit of the Infrastructure, Land and Environment
Policy Board are detailed throughout the action plan and performance
indicators in the appendix.
5. Areas where actions have been delayed 
5.1 All actions within the action plan are on plan within their timescale, although
there are three actions whose start has been delayed; two within the PLACE
theme and one within the LIVING OUR VALUES theme due to internal
staffing changes. All three are now being progressed. 
6. Progress against performance measures 
6.1 Environment, Housing & Infrastructure Services has 25 performance
indicators in its current scorecard. Of these, 10 are reported quarterly and 15
are reported annually. This appendix report contains data pertaining to quarter
1 and quarter 2 of 2025/26 and annual figures for 2024/25. 
Implications of the Report 
1. Financial – The Service Improvement Plan highlights resourcing pressures
arising from increasing demand for services and the current financial
environment. 
2. HR & Organisational Development – The Service Improvement Plan also
highlights workforce development and wellbeing considerations. 
3. Community/Council Planning – The report details a range of activities which
reflect Council and Community Planning themes and a direct link to the
delivery of the Council Plan. 
4. Legal – none. 
5. Property/Assets – none. 
6. Information Technology – Service developments relating to information
technology are key enablers of service improvement and modernisation and
support service-level and corporate objectives.

Page 4

PUBLIC
7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following
implementation, the actual impact of the recommendations and the mitigating
actions will be reviewed and monitored, and the results of the assessment will
be published on the Council’s website. 
8. Health & Safety – none. 
9. Procurement – none. 
10. Risk – Risks related to the delivery and management of services are regularly
monitored and included in Renfrewshire Council’s Corporate and Strategic
Risk Registers. 
11. Privacy Impact – none. 
12. COSLA Policy Position – none. 
13. Children’s Rights - none 
14. Climate Change – A section of the actions and performance indicators within
the SIP covers the ‘Green’ theme of Renfrewshire’s Council Plan which
highlights activities across the Council to tackle climate change. 
List of Background Papers: 
Infrastructure, Land & Environment Policy Board – 21 May 2025 Item 4
Environment, Housing & Infrastructure 2025-2028 Service Improvement Plan 
Author: Gordon McNeil, Director of Environment, Housing and Infrastructure,
Email: gordon.mcneil@renfrewshire.gov.uk

Page 5

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ENVIRONMENT,  HOUSING AND INFRASTRUCTURE
SERVICE IMPROVEMENT PLAN 2025-2028
Six monthly progress update
November 2025
Infrastructure, Land and Environment Policy Board

Page 6

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
WELCOME TO OUR SIX-MONTHLY UPDATE
• This update reflects on the first six months of our Service Improvement Plan, highlighting areas where we
are already making progress and some areas we want to focus on more, perhaps because performance
isn’t moving in the direction we anticipated or because of other pressures or factors that makes this even
more of a priority for us.
• The following pages shine a spotlight on some great projects or practice and highlight areas where we’d
like to improve or develop further.  At a service level, there is a stronger focus on some of the Council Plan
Strategic Outcomes than others. Towards the end of this document, you’ll find a full update against all the
actions and performance indicators we use to measure progress.
• We report on 25 performance indicators, 15 are reported annually and 10 reported quarterly. This report
contains data pertaining to Quarter 1 and Quarter 2 of 2025/26 with annual figures referring to 2024/25.

Page 7

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ABOUT US
This update covers the Environment, Housing and Infrastructure service areas within the remit of the
Infrastructure, Land and Environment Policy Board. These are:
Operations
Responsibilities include:
• Waste Services,
• Fleet & Social Transport,
• Neighbourhood Services
,
• Grass, Grounds & Cemeteries
Maintenance,
• Burials,
• Country Park Management
Service Development
Responsibilities include:
• Service Modernisation,
• Elected Member enquiries,
public enquires & complaints
and Freedom of Information
requests,
• Operational Training
• Civil Contingencies
Roads and Transportation
Responsibilities include:
• Council’s roads and
infrastructure, including bridges
• Winter maintenance,
• Public Transport
• Parking & Active Travel services

Page 8

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
HELPING TO DELIVER THE COUNCIL PLAN
Place
GreenOur £90m 10 year roads investment strategy is
in place delivering carriageway and footway
improvements across Renfrewshire.
Living our Values
Support delivery of a refreshed approach to workforce planning
and workforce innovation, with a focus on recruitment and
retention; learning and development and career pathways
EHI fully supports Renfrewshire ‘Keeps the
Promise’ to deliver improved outcomes for
individuals who are care experienced, wherever
possible.
Fair
Support the delivery of a regional approach to Public
Electric Vehicle Charging
Continue to invest in infrastructure to support growth
– from road and rail links to bridges, cycle and
pedestrian routes
Economy
We will implement full recycling facilities within Renfrewshire House.
Sustainability Team is progressing with scoping of work required including
completing a bin audit within Renfrewshire House and liaising with key
colleagues including Facilities Management and Procurement.
Exploring expansion of solar PV and other renewables on council buildings
is now approved as part of a 25/26 Climate Capital Programme. Energy
Team is currently liaising with procurement as a first step in the project.

Page 9

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
PLACEAchievements
Priorities till March 2026
The Carriageway programme for 2025/26 is progressing well and on programme. Of the 46 areas within year 1 of the programme,
36 have been completed and another 9 are either already on site or will be delivered by the end of March 2026.
The action to review existing processes for managing work allocation and cyclical maintenance programmes has been postponed due to internal staffing changes
and is now being developed as the new Manager has now taken up the role and is progressing this project.
We are delivering our Streetlighting Capital programme, replacing life expired streetlighting schemes and
the work in Easwald Bank Kilbarchan is almost complete.
As part of our Streetlighting Capital programme for Main Street Lochwinnoch – We have now completed the tender process  and have a preferred
bidder. Work will commence in January 2026 after Christmas lights have been removed and this will be completed by the end of March 2026.
Officers have begun work on a three-year Renfrewshire wide, roundabout upgrade programme, which looks to transform,
tired, overgrown roundabouts, into tidy, easily maintained assets, that will enhance the road network.
The final design to build packaging and recycling bulking facility within Renfrewshire has been reviewed with contractors, who are currently evaluating options
to inform the development of the final business plan.
A dedicated team has been established to focus specifically on weed management. Their schedule will mirror the 14-day grass
cutting cycle to ensure a consistent and coordinated approach across Renfrewshire.
We continue to invest in the renewal of Play Parks with Phase 1 of the 2025–2026 renewals programme is underway, with the tendering process completed in
September 2025. Phase 2 will begin later in the year and will include tenders for additional play parks, two outdoor gyms and the BMX track in Barshaw
The footway programme commenced in October 2025. This consists of 32 footways and 3 commenced and were completed ahead of schedule and the remaining
29 will be completed before the end of March 2026.

Page 10

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ECONOMY
Achievements
We provide a wide range of employment, training and apprenticeship opportunities for
identified groups of young people in Renfrewshire
Priorities till March 2026
Comprehensive engagement complete on our new Transport Strategy with a report being prepared for Board for approval. Active travel
priority routes identified and concept design work for the top priorities are underway.
Renfrewshire Council successfully delivered the new Renfrew Bridge as part of the
£117million Clyde Waterfront and Renfrew Riverside (CWRR) project, which included
£39million in support from both the Scottish and UK governments and £1.7million from
Transport Scotland.
Since recording started on 21 June, more than 1 million cars have crossed the bridge, as well as
over 26,000 cyclists and 45,000 walkers and runners, with the bridge becoming a vital travel link
enhancing connectivity and supporting sustainable travel across the region.
The study is ongoing on Phase 1 (Renfrew and Johnstone) of assessment of parking
provision and the expansion of the parking strategy. We are currently preparing a survey
to gather the views of residents.

Page 11

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
FAIR
Achievements
Priorities till March 2026
We are progressing the design and implementation of the villages traffic calming projects with the majority of
Phase 1 implemented in Howwood.
Amendments in Houston and Kilbarchan are nearing agreement with the Community Councils.
Work is ongoing to implement the statutory 20mph speed limit on all residential Renfrewshire
streets where it is appropriate  - and the Concept phase is now complete. Transport Scotland
award for next phase has been agreed. Detailed project scoped out and tender documents have
been prepared.
The next stage to work towards the implementation of the statutory 20mph speed limit will be to prepare
temporary traffic order for implementation on-street next year. Performance will be  monitored for a year before
the production of permanent order.
Concept designs agreed in Bishopton, Elderslie and Bridge of Weir as part of phase 2 of the villages traffic
calming projects with detailed designs to follow. Investigations in Langbank have recently begun.

Page 12

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
GREEN: LEADING RENFREWSHIRE TO NET ZERO
The Carbon Management Plan is 90% complete and will be submitted to the ILE Board in early 2026 with the final
project details for each service area.
The full recycling facilities within Renfrewshire House will be implemented. Sustainability Team progressing with scoping of work required
including completing a bin audit within Renfrewshire House and liaising with key colleagues including Facilities Management and
Procurement.
Exploring expansion of solar PV and other renewables on council buildings. This is now approved as part of the 2025/26 Climate Capital
Programme. Energy Team is currently liaising with procurement as a first step in the project.
Develop Climate Change Impact Assessments process across appropriate projects. Currently being piloted across a number of Project
Management Unit led projects to help inform further development of the process and criteria prior to being finalised and rolled out across the
Council.
Achievements
Priorities till March 2026
Our plan looking to expand Building Management Systems to reduce energy use and water use was approved as part of a 2025/26
Climate Capital Programme. The project has been planned into 3 phases of building installations, and phase 1 implementation is nearing
completion.
The new route management system with in-cab technology to support the delivery of a revised waste collection re-routing programme has been
successfully launched and is currently operational within Waste Services.
Development of new waste collection routes are in progress for 82,000 properties across Renfrewshire. The new routes will be implemented in early Summer
2026.

Page 13

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Living our Values: making a difference together
Achievements
• We continue to maintaining the commitment to eradicating youth homelessness, aligning with strategic priorities and local
initiatives.
• There are 380 Renfrewshire Promise Keepers across the network, and we are continuing to raise awareness and promote
awareness of The Promise across homeless and housing services, embedding/aligning its principles where appropriate.
• Public Protection - There are currently several Officers completing training
• one as a Food Safety Officer and
• two others who are undertaking training to complete the Modern Apprentice in Regulatory Services qualification
• Our new Environmental Health Officer qualified in October 2025.
• Direct support by the EHI senior leadership Team to the Renfrewshire Promise Team.
• Ongoing support for Renfrewshire’s Promise Approach through active participation in: Renfrewshire’s Promise Oversight
Group Relevant workstreams and strategic groups.
• The service has continued collaboration with partners to develop tailored, affordable Housing Pathways for Care Experienced
young people.
• Actively raise awareness of Renfrewshire’s Promise Keeper Network and Renfrewshire’s Language Policy.
• Encouraged team-wide completion of The Promise i-learn module across EHI.
• Supported council-led initiatives to recruit Care Experienced young people, including: The Guaranteed interviews for Care Experienced applicants meeting
essential criteria.
Priorities till March 2026

Page 14

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ACTIONS AND INDICATORS
INFRASTRUCTURE, LAND AND ENVIRONMENT POLICY BOARD

Page 15

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE
What we will do Due Date Status Progress Update
Deliver year 1 of the £90m 10 year roads
investment strategy.
March 2026
At full Council in February 2025, the Climate, Public Protection and Roads service were awarded £90M for road
improvements over a 10-year period.  This equates to £9M per annum, which as well as being the highest level of
yearly funding Roads have ever been awarded, also provides the opportunity to plan works over a longer period,
with a greater degree of certainty. 
The Carriageway programme for 2025/26 is progressing well and on programme. Of the 46 areas within year 1 of the
programme, 36 have been completed and another 9 are either already on site or will be delivered by the end of
March 2026.
The remaining  1 has been found to contain coal tar and has been moved to the micro surfacing programme.
All Capital machine patching (5,635 m²) and surface treatments (31) have been completed.
Within the micro surfacing programme 7 are complete  with the remaining X are on programme to be complete by
March 2026.
The footway programme commenced in October 2025. This consists of 32 footways and 3 commenced and were
completed ahead of schedule and the remaining 29 will be completed before the end of March 2026.
Roads and Neighbourhood Services will
work in partnership to deliver
improvements to the infrastructure and
aesthetics of the roundabout asset in
Renfrewshire.  Proposed works include
replacing 'keep left' bollards, repairing sign
lighting, planting, weed removal, chevron
enhancement, vegetation clearance, and
pressure cleaning. This will be year 1 of a
rolling programme of roundabout
improvements to systematically enhance
the infrastructure.
March 2026
As part of the £90m 10 year roads investment strategy, officers have begun work on a three-year Renfrewshire wide,
roundabout upgrade programme, which looks to transform, tired, overgrown roundabouts, into tidy, easily
maintained assets, that will enhance the road network.
The section of Barnsford Road from St James Interchange to Inchinnan Drive was resurfaced during September and
as part of this, the roundabout was upgraded.
During year 1 of this programme the following improvements will be completed by March 2026:
• Hurlet Road at Grahamston Road, Paisley
• Beith Road at Cochranemill Road, Spateston
• Ferry Road, Bishopton
• Inchinnan Road at Sanderling Road, Glasgow Airport
• A761 at John Neilston Avenue, Paisley
• Barrhead Road at Hawkhead Road, Paisley
• Kings Inch Road at Laymoor Avenue, Renfrew
• Inchinnan Road at Argyll Avenue, Renfrew
• Greenock Road at India Tyres, Inchinnan
• Newshot Drive at Parkway, Erskine

Page 16

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE
What we will do Due Date Status Progress Update
Work with Linwood and Erskine Community
Councils to deliver enhanced festive lighting in
these two towns, by agreeing options, procuring
new features, and installing the new display on an
annual basis
November 2025
Erskine – we are working in collaboration with the Community Council and the planning service to
develop a new Erskine hub adjacent to the sports centre which will become the focal point for
festive lighting from 2026 onwards. There is a budget in place of £25k for 2026.
Linwood – Community Council are in the process of agreeing on features and fittings for the festive
lighting which will be in place from 2026.
Deliver Streetlighting Capital programme,
replacing life expired streetlighting schemes in
Easwald Bank Kilbarchan, Main Street
Lochwinnoch, and phase 1 of North Street in
Houston.  Installations in Houston and
Lochwinnoch villages will be sympathetic to the
conservation nature of these village centres,
incorporting appropriate columns and lanterns.
March 2026
Easwald bank – this is almost complete –we are currently in the process of removing the old
redundant columns.
Main Street Lochwinnoch – We have now completed the tender process  and have a preferred
bidder. Work will commence in January 2026 after Christmas lights have been removed and this will
be completed by the end of March 2026.
Houston – this has still to be progressed, and it is anticipated that this  may move into 2026/27.
Complete the design for drainage and full road
footway / construction for Burnbrae Road in
Linwood, a vital  industrial / commercial link
road.
March 2026
We are about to instruct a series of testing and coring at this site to be undertaken to get an
understanding of the current make up, and test for coal tar. The results of testing will
determine the proposed solution.
We will finalise designs for improvements to
Abbey Close
March 2026
We have a finalised design, which has been fully costed. Some funding is already in place,
however this does not cover the full price of the design. We are currently exploring additional
funding means including a capitol bid from Council.

Page 17

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE
What we will do Due Date Status Progress Update
Waste Services will explore opportunities and
develop a business case to design and build a
packaging and recycling bulking facility within
Renfrewshire. March 2026
The final design to build packaging and recycling bulking facility within Renfrewshire has been
reviewed with contractors, who are currently evaluating options to inform the development of
the final business plan.
Improvement works will be carried out at
Underwood Road Depot to improve safety and
security.  A Depot Improvement Plan will be
developed and delivered for 2025/2026.
March 2026
The Depot Improvement Plan has been developed.
A working group of key depot-based services are delivering the Depot Improvement Plan
collaboratively.
Improvement works are ongoing in line with the Depot Improvement Plan.
Improve and simplify record keeping for the
Cemetery Service.
Neighbourhood Services will procure a Cemetery
Management System to manage cemetery
records and support mapping and billing.
December 2025
The specification for the Cemetery Management System is in progress and being developed in
collaboration with procurement and IT. 
Neighbourhood Services will review existing
processes for managing work allocation and
cyclical maintenance programmes. A digital
system that can deliver an end-to-end solution
will be procured.
December 2025
This action to review existing processes for managing work allocation and cyclical
maintenance programmes has been postponed due to internal staffing changes and is now
being developed as the new Manager has now taken up the role and is progressing this
project.

Page 18

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE
What we will do Due Date Status Progress Update
Neighbourhood Services will establish a
dedicated Weed Response Team focused
exclusively on the removal of weeds and detritus
across Renfrewshire.
July 2025
A dedicated team has been established to focus specifically on weed management. Their
schedule will mirror the 14-day grass cutting cycle to ensure a consistent and coordinated
approach across Renfrewshire.
Neighbourhood Services will explore
opportunities to improve the Street Litter Bin
Service. A review of the service will be carried out
and will take into consideration routing
inefficiencies, location and condition of litter
bins.
March 2026
The solar compactor bin pilot was launched in September 2025. Data captured from the pilot
will be used to inform the review of the litter bin service.
Neighbourhood Services will progress the
development of an Open Space Strategy for
Renfrewshire Council. A specialist resource will
be procured to support the development of the
Strategy.
December 2025
This action has been postponed  due to internal staffing changes and will be progressed in the
near future.
Continue to invest in the renewal of Play Parks.
The Play Park Renewal Programme will be
delivered throughout 2025 to 2027. March 2027
Phase 1 of the 2025–2026 renewals programme is underway, with the tendering process
completed in September 2025.
Phase 2 will begin later in the year and will include tenders for additional play parks, two
outdoor gyms and the BMX track in Barshaw.
Further develop our tree asset management
capability by exploring options to procure a tree
asset management system that supports the
identification, management and monitoring of
our tree assets.
March 2026
A temporary solution has been developed internally and is in place whilst a permanent
solution for a tree asset management system is identified.

Page 19

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current
Status
2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
(Maintenance) Carriageway Condition: % of road network considered for treatment
(i) A Class Roads 18% 18% 17% Not measured for Quarters
These are Local Government
Benchmarking
Framework(LGBF)Indicators.
This data is published by the
Improvement Service on an annual basis
as part of the LGBF.
These are annual LGBF Indicators and
relate to financial year 2024/25.
(ii) B Class Roads 25% 21% 21% Not measured for Quarters
(iii) C Class Roads 31% 30% 30% Not measured for Quarters
(iv) Unclassified Roads 31% 32% 32% Not measured for Quarters
(Maintenance) Carriageway Condition: %
of roads network considered for
treatment Overall
33% 30% 30% Not measured for Quarters
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 20

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current
Status
2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
% of Statutory roads inspections categories completed on target:
(i) Category A 100% 100% 100% Not measured for Quarters In 2024/25, 100% of the statutory road
inspections were completed for all
categories. The three categories of
statutory inspections relate to the timing
of inspections and are categorised as
follows: A–Undertaken during the
progress of the works B–Undertaken
within the six months following interim
or permanent reinstatement C–
undertaken within the three months
preceding the end of the guarantee
period. The inspection procedure is
designed to enable roadwork authorities
to monitor statutory undertakers (Gas,
electric, and telecom etc).
(ii) Category B 100% 100% 100% Not measured for Quarters
(iii) Category C 100% 100% 100% Not measured for Quarters
% Pothole repairs completed within
timescales TBC 95% 95% TBC TBC TBC
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 21

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – ECONOMY
What we will do Due Date Status Progress Update
Deliver year 1 of our new Local Transport Strategy March 2026 Comprehensive engagement complete. Report being prepared for Board for approval. Active travel priority
routes identified and concept design work for the top priorities are underway.
Commencing the first year of operating the new
Renfrew Bridge, the first ever opening vehicle bridge
over the River Clyde.
March 2026
Renfrewshire Council successfully delivered the new Renfrew Bridge as part of the £117million Clyde
Waterfront and Renfrew Riverside (CWRR) project, which included £39million in support from both the
Scottish and UK governments and £1.7million from Transport Scotland.
Renfrewshire Council has created a Bridge Operation Team that manages the structure to ensure the River
Clyde continues to operate unimpeded on a 24/7 basis, 365 days a year.
Since recording started on 21 June, more than 1 million cars have crossed the bridge, as well as over 26,000
cyclists and 45,000 walkers and runners, with the bridge becoming a vital travel link enhancing connectivity
and supporting sustainable travel across the region.
This has coincided with the successful openings of the bridge to accommodate over 450 vessel movements
(approximately 3 openings a day).
The numbers of users highlight the success of the bridge, which was designed to improve infrastructure,
reduce congestion and promote active travel – with the bridge quickly becoming an essential part of daily life
for residents and visitors.
The Bridge Operation Team publish all bridge closures in advance on our web page and WhatsApp update
channels as soon as we are notified, as well as displayed on the digital approach signs (VMS). The web page is
the most viewed page on the Council platform while the WhatsApp is now followed by over 14,000 users.
Due to the success of the WhatsApp channel, we are now looking to extend the use of this medium to cover
other areas of the service, beginning with winter gritting.
We will undertake assessment of parking provision
and the expansion of the parking strategy into
Renfrew, Johnstone, Erskine and Linwood which is
now being taken forward by consultants.
March 2026
Consultant study ongoing on Phase 1 (Renfrew and Johnstone). Initial parking behaviour studies complete.
Draft on-line public survey being prepared. Comms Team will advise publication method.

Page 22

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – FAIR
What we will do Due Date Status Progress Update
We will implement the statutory 20mph speed
limit on all residential Renfrewshire streets
where it is appropriate – subject to Scottish
Government funding
TBC – subject to public
consultation and
funding.
Concept phase complete. Transport Scotland award for next phase agreed.
Detailed project scoped out and tender documents prepared for award through
City of Edinburgh Council  (in lieu of Scotland Excel).  To prepare temporary traffic
order for implementation on-street next year. Performance will be  monitored for a
year before the production of permanent order.
We will continue to design and implement the
villages traffic calming project, including
Langbank. March 2028
Majority of Phase 1 implemented in Howwood. Amendments in Houston and
Kilbarchan nearing agreement with Community Councils. Phase 2 concept designs
agreed in Bishopton, Elderslie and Bridge of Weir. Detailed designs to follow.
Investigations in Langbank have begun.

Page 23

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – GREEN
What we will do Due Date Status Progress Update
Waste Services have procured specialist route
management software with in-cab technology
to support the delivery of a revised waste
collection re-routing programme.
A project team has been created to progress the
integration and implementation of the new
route management system.
July 2025
The new route management system with in-cab technology to support the delivery of a revised
waste collection re-routing programme has been successfully launched and is currently
operational within Waste Services.
Utilising the new route management software,
Waste Services will progress modelling of fully
optimised collection routes.
November 2025
Development of new collection route are in progress for 82,000 properties across Renfrewshire.
The new routes will be implemented in early Summer 2026.
The relaunch of the Sustainable Travel Scheme,
with a particular focus on staff travel. March 2026
We have had initial dialogue with McGills to investigate the feasibility of some form of cheaper bus
pass to support the relaunch.
Red Smiddy to Erskine Active Travel route, being
dependant on receiving funding from Active
Travel Infrastructure with decision being made
in May/ June 2025.
December 2026
Detail design of segregated active travel path near complete. Design of ramp to footbridge in
Erskine nearing completion. Tier 1 funds to be used once construction tender publicised in spring
2025, for construction start May 2026. 
Replacement of all Halogen signal equipment in
all traffic signals  with energy saving LED. This
project will commence during 2025/26 subject
to appropriate funding.
March 2030
An outline business case has been produced and submitted as a capital request to fund this
programme.
Ad hoc junction replacements have been done at the moments with the major traffic signalised
junctions of Broomlands Street and Maxwellton Street in Paisley have been upgraded with LED
traffic signal infrastructure.

Page 24

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – GREEN
What we will do Due Date Status Progress Update
Support the delivery of a regional approach to
Public Electric Vehicle Charging
March 2026
The programme of work continues to progress, with the details of the proposals nearing being
finalised. This includes reviewing and refining a proposed list of on-street and off-street charging
locations across Renfrewshire and carrying out further feasibilities and grid capacity analysis through
Scottish Power Energy Networks
Implement full recycling facilities within
Renfrewshire House March 2026
Sustainability Team progressing with scoping of work required including completing a bin audit
within Renfrewshire House and liaising with key colleagues including Facilities Management and
Procurement.
Exploring expansion of solar PV and other
renewables on council buildings including
schools.
March 2026
This is now approved as part of a 25/26 Climate Capital Programme. Energy Team is currently
liaising with procurement as a first step in the project.
Development of investment grade business
cases for 2 potential district heating networks. 1
Paisley central, 1 expansion of AMIDS.
Summer 2025
The development of Business Cases for both networks continues and has now progressed to a key
final phase of the project. The programme timeline has been extended from the initial agreed plan
due to the requirement for further exploration and analysis activity.

Page 25

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – GREEN
What we will do Due Date Status Progress Update
Looking to expand Building Management
Systems to reduce energy use and water use. March 2026
This was approved as part of a 25/26 Climate Capital Programme. The project has been planned
into 3 phases of building installations, and phase 1 implementation is nearing completion. Phase
2 is planned to begin in September/October 25.
Develop the following strategies and plans - 
• Renfrewshire’s Adaptation Plan
• Renfrewshire’s Circular Economy Strategy
• Renfrewshire Council’s Carbon Management
Plan (CMP)
March 2026
• Sustainability Strategy Lead Officer now in post and will lead on the development of
Renfrewshire’s Adaptation Plan. Key themes have been identified through previous
engagement, with further external, community engagement to follow.
• Sustainability Strategy Lead Officer now in post and will lead on the development of
Renfrewshire’s Circular Economy Strategy. Key themes have been identified through previous
engagement, with further external, community engagement to follow.
• The Council’s Carbon Management Plan {CMP} is currently being finalised with the final
project details for each service area. The plan will be submitted to the ILE board for approval.
Develop Climate Change Impact Assessments
process across appropriate projects. March 2026
Currently being piloted across a number of Project Management Unit led projects. This will help to
inform further development of the process and criteria prior to being finalised and rolled out
across the Council.
Establish a carbon budget for Renfrewshire
Council February/March 2026
Sustainability Strategy Lead Officer now in post to progress with development of a carbon budget
for the Council. This includes revisiting previous work done to date and identifying key next steps in
development and implementation.

Page 26

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – GREEN
Indicator Current
Status
2024/25 2025/
26
Q1 2025/26 Q2 2025/26 Explanation of performance
Value Target Target Value Value
Street cleanliness Score -
% of areas assessed as
clean
92% 92% 92% Not measured for Quarters
This is an annual target, and the cleanliness score is based on 3 sample
surveys carried out throughout the year by both the Council and Keep
Scotland Beautiful (KSB). This score represents the percentage of areas
assessed as acceptably clean(categories A and B) using KSB’s Local
Environment Audit and Management System(LEAMS) methodology
Amount of CO2 emitted by
the public vehicle fleet 3,180 3,000 3,000 777.56 777.50
The total for the first 6 months of the year is 1,555.06 tonnes of CO2e. If
this trend continues, whilst comparatively small, the emissions would be
slightly over target of 3,000 tonnes of CO2e.
% of the vehicle fleet
which uses alternative
fuels, such as electricity
29.7% 25% 25% 29.7% 30.1%
The current fleet using alternative fuels includes 97 electric vehicles
from a total fleet of 326 vehicles. In addition, there are 2 vehicles using
alternative fuel.
% of bins uplifted first
time 99.7% 99.8% 99.8% 99.5% 99.6% Based on approximately 17,000 collections.
Reduce the amount of CO2
emitted from public space
lighting
1,217 1,100 1,100 Not measured for Quarters
This performance indicator is an annual indicator and not measured for
quarters. Although not measured in quarters, the emissions levels are
anticipated to level out year on year as the LED programme is
substantially complete.

Page 27

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – GREEN
Indicator Current
Status
2024 2025 Q1 Jan –
March
2025
Q2 Apr – June
2025
Explanation of performance
Value Target Target Value Value
% of Household Waste
Recycled
Data to be
validated 50% 50% Data to be
validated
Data to be
validated
There has been a  delay in getting the 2024 figures validated via SEPA due
to a technical issue with them. % of Household waste
collected which is
landfilled
Data to be
validated 2% 2% Not measured for Quarters

Page 28

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
What we will do Due Date Status Progress Update
We will continue to develop and support our
workforce through training and development
demonstrating our value as a learning
organisation.
March 2026
• The Service Development Team continue to support employees to undertake a range of training
including mandatory training.
• To date 49% of frontline employee have completed mandatory toolbox talks and 85% of network staff
have completed mandatory training on iLearn.
• Training courses have included driver training, First Aid, Health & Safety and specific role specific
training such as Chainsaw training.
• Soft FM “job characteristic” project is still at an early stage and will be progressed, subject to further
discussion with Corporate Teams, in the second half of 2025/26. Longer term this work will be used to
inform identification of training requirements across EHI.
We will support wider employee health and
wellbeing across Environment, Housing,
Infrastructure.
March 2026
• In response to the Employee Survey 2024 to support the opportunity fore more regular time and
engagement between managers/ supervisors and employees a “Personal Development Plan” (PDP) for
networked staff has recently been launched.  This template supports employees to reflect on
achievements and challenges, agree objectives and identify training support required. 
• Work is ongoing to promote health and wellbeing across EHI and more front-line staff are trained as
Metal Health First Aiders.
• The NHS Wellbeing Calendar themes will be considered to deliver more focussed and appropriate
activities to increase awareness and offer support to the health and wellbeing of staff.
We recognise that Health & Safety is an integral
part of our business.  We will deliver our actions
outlined in the Environment, Housing &
Infrastructure (EHI) Health & Safety Plan 2025 –
2028. March 2026
• The review of the EHI Quality, Health and Safety manual and related documentation will be undertaken
in the second half of 2025/26.
• IOSH Managing Safely has been rolled out to 56 managers, supervisors and employees across EHI. An
additional 9 Senior Managers undertook IOSH Leading Safely. Further courses will be run during
2025/26, and Housing Services are progressing similar training focused on that service needs.
• Work to undertake health and safety internal audits will be undertake in the second half of 2025/26.

Page 29

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
What we will do Due Date Status Progress Update
As part of the strategic fleet review the fleet
service will develop a Fleet Asset Management
Plan to map out vehicle specifications and type
to ensure existing fleet is fully maximised and
meets the operational requirements of services
and assists the Council to achieve its Net Zero
targets.
March 2026
This action has been postponed due to internal staffing changes and will be progressed once
the new Fleet Team Leader is recruited and in post.
Fleet Services will implement a new fleet
management system to manage Renfrewshire
Council’s vehicles, assets and equipment. A
project team has been created to implement
the new system.
December 2025
A new fleet management system to manage Renfrewshire Council’s vehicles, assets and
equipment has been procured and implementation is in progress.

Page 30

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
Indicator Current
Status
2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
Average number of workdays lost through
sickness absence per employee (FTE)
(cumulative)
15.41 13.7 13.7 3.25 3.32
The cumulative total so far for 25/26 is 6.57 days lost which is
lower than cumulative total at the same time last year 24/25
which was 7.73 days lost.
% of Members enquiries completed within
timescale 89.2% 85% 85% 86% 87%
In the first six months of 2025/26 Environment, Housing &
Infrastructure received 4,934 members enquiries of which
87% were responded to within timescale.
% of frontline resolutions dealt with within
timescale
62% 85% 85% 58% 79%
In the first six months of 2025/26 Environment, Housing &
Infrastructure received 5,240 front line resolutions of which
68% were responded to within timescale.  Please note for
September there are 14 frontline complaints still outstanding
but are within timescale – and have not been included in Q2
figure.
% of complaint investigation completed
within timescale 
50% 85% 85% 45% 67%
In the first six months of 2025/26, Environment, Housing &
Infrastructure received 289 investigations of which 56% were
responded to within timescale.  Please note for September
there are 62 complaint investigations still outstanding but are
within timescale – and have not been included in Q2 figure.
% of FOI request completed within timescale
99% 100% 100% 97% 95%
In the first six months of 2025/26 Environment, Housing &
Infrastructure dealt with 498 Freedom of Information requests
of which 96% were responded to within timescale. 85 of these
requests were cross departmental and 413 were
departmental.

Page 31

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
Indicator Current Status 2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
% of corporate induction completed
within 30 days of starting employment
with the Council N/A TBC Not measured for
quarters
Not measured for
quarters
These are four new indicators.  Evaluation of
progress will take place midway through 2025/26,
and this will help inform the creation of
targets/timescales across the whole service.
Progress will be reported annually.
Although these will be reported annually, for
information, as of 30 September 2025 - 49% of
frontline employee have completed mandatory
toolbox talks and 85% of network staff have
completed mandatory training on iLearn.
% of mandatory training courses for
frontline employees completed N/A TBC Not measured for
quarters
Not measured for
quarters
% of mandatory training courses for
employees with access to the Council’s
network completed N/A TBC Not measured for
quarters
Not measured for
quarters
% of Personal Development Plans
completed N/A TBC Not measured for
quarters
Not measured for
quarters

Page 32

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DATA STRATEGY: PRIORITY ACTIVITIES
What we will do Due Date Status Progress Update
Strategic: We will align service data activities with the Digital Strategy for
Renfrewshire objective: Data is a critical asset.  Ensure visibility of data activities
at Directorate (Director & Head of Service Level)
March 2026
The Directorate (Director and 4 Heads of Service) regularly consider a range of
data which is used to inform decision making.  There is ongoing support for
data activities and training to enhance this capability across the Department.
Skills: We will identify skills gaps (eg data input, data analysis) and training
needs across EHI and address through our Workforce Development plan in line
with the Renfrewshire Council People Strategy.
March 2026
Information on skills gaps and training needs will be identified as part of the
Personal Development Plan (PDP) currently being rolled out for networked
employees. 
Internal training on data analysis tools has been undertaken to support
knowledge and understanding of our data.
Data Quality: We will review data quality in key business systems and processes
and develop an improvement plan. December 2025
As part of wider projects data for Roads and Waste Services has been
reviewed and the quality of data (accuracy, completeness and up to date)
will be improved, supporting data driven decision.
Further work to review data quality in key systems will be undertaken in the
second half of 2025/26.
Analysis: We will further define analysis requirements to improve decision-
making and build capabilities locally within services where required. December 2025
Work is ongoing to improve how data is presented including using standard
tools.  Although at an early stage it is hoped this work will improve how our
data is presented to Services allowing them to make more informed
decisions
ERP: We will work with Corporate Teams to promote and increase the use of
standard dashboards as business as usual. March 2026
Work is underway to support services to ensure that the data held in the ERP
in accurate.  This has included asking employees to review their personal
details and update as required.
Data Advisory Group (DAG): We will ensure EHI representation at the DAG to
ensure our data activities align with the Data Strategy Framework; cross-service
data sharing opportunities are identified and that data improvement activities
are carried out in a consistent manner across the organisation.
March 2026 The Senior Service Development Manager represents EHI at the DAG and will
continue to ensure that data is used collaboratively across services where
appropriate.

Page 33

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE COUNCIL PLAN – CROSS CUTTING THEME
IMPROVING OUTCOMES FOR CHILDREN AND FAMILIES
“Across all of our work and all of our efforts, we hope for loving and happy lives for Renfrewshire’s children -  working together to get
it right for children, families and communities – protecting, learning, achieving and nurturing.  Every priority of this Council Plan will
contribute to improving  the lives of Renfrewshire’s children and their families.  It is our fundamental duty as an organisation and our
shared responsibility as citizens of this place to ensure that our children inherit a Renfrewshire where their wellbeing is nurtured, their
futures are bright, and their environment is safe and healthy.’
What we will do Due Date Status Progress Update
EHI will work towards Keeping The Promise and
support our Care Experienced Community.
March 2026
• The service has continued collaboration with partners to develop tailored, affordable Housing
Pathways for Care Experienced young people.
• Maintained commitment to eradicating youth homelessness, aligning with strategic priorities
and local initiatives.
• Ongoing support for Renfrewshire’s Promise Approach through active participation in:
Renfrewshire’s Promise Oversight Group Relevant workstreams and strategic groups.
• Direct support by the EHI senior leadership Team to the Renfrewshire Promise Team.
• Promoted awareness of The Promise across homeless and housing services,
embedding/aligning its principles where appropriate .
• Actively raised awareness of Renfrewshire’s Promise Keeper Network and Renfrewshire’s
Language Policy.
• Encouraged team-wide completion of The Promise i-learn module across EHI.
• Supported council-led initiatives to recruit Care Experienced young people, including: The
Guaranteed interviews for Care Experienced applicants meeting essential criteria.

Page 34

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
EHI SERVICE IMPROVEMENT PLAN
SIX MONTHLY PROGRESS UPDATE
NOVEMBER 2025