Page 1

PUBLIC 
___________________________________________________________________ 
To: Infrastructure, Land & Environment Policy Board 
On: 5 November 2025
___________________________________________________________________ 
Report by: Director of Finance and Resources 
Director of Environment, Housing & Infrastructure
___________________________________________________________________ 
Heading: Revenue and Capital Budget Monitoring 2025/26 at 19 September
2025
___________________________________________________________________ 
1. Summary 
1.1 At the close of reporting Period 6 on 19 September 2025, the projected
revenue outturn at 31 March 2026 for those services reporting to the
Infrastructure, Land and Environment Policy Board is an overspend position of
£0.252m (0.6%) against the revised budget for the year. 
1.2 The projected capital outturn at 31 March 2026 for projects reporting to the
Infrastructure, Land and Environment Policy Board is a break-even position. 
1.3  This is summarised over the relevant services in the table below and further
analysis is provided in the report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue        
Environment & Infrastructure 39,717 39,969 (252) (0.6%)
Total 39,717 39,969 (252) (0.6%)
Capital        
Environment & Infrastructure 17.058 17.058 0 0.0%

Page 2

PUBLIC
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board: 
2.1 Note the projected Revenue outturn overspend position of £0.252m. 
2.2 Note the projected Capital outturn break-even position. 
2.3 Note the budget adjustments in appendix 1 and 2. 
3. Revenue Budget Projection – overspend of £0.252m by 31 March 2026 
3.1 The tables in Appendix 1 and 2 present the projected year-end position for all
services reporting to this board, by both objective analysis (which division is
spending the budget – appendix 1) and subjective analysis (what the budget
is spent on – appendix 2). Material variances affecting the projected position
are analysed further below. 
3.2 It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. The impact of any change on this projection will be updated at
each board cycle until the close of reporting period 10. Budget holders are
obliged to seek mitigating action to minimise significant budget variances. 
3.3 As reported to Council in February 2025, the Council was notified of an
allocation of funding of £3.054m from the UK Government’s Department for
Environment, Food and Rural Affairs (DEFRA) in relation to packaging
extended producer responsibilities.   
3.4 DEFRA has since notified the Council that a funding award of £2.646m is now
to be paid in 2025/26. The Council has submitted a formal appeal to question
the revised allocation and is linking with the Scottish Government, as
Renfrewshire is not the only Council with a reduced / wrong funding position.
An update on the position, will be reported to a future meeting of this Board. 
4. Objective Analysis – Significant Variances 
Environment, Housing, and Infrastructure – (£0.252m) overspend 
4.1 Waste Services – (£0.240m) overspend by 31 March 2026

Page 3

PUBLIC
4.1.1 This reflects the financial position for Refuse Collection, Refuse Disposal and
Household Waste Recycling Centres. 
4.1.2 The overspend for Refuse Collection (£96k) in the main relates to an
estimated overspend in employee costs (£75k). 
4.1.3 An overspend of £0.131 million is currently projected within Refuse Disposal.
As of Period 6, work by contractor costs are estimated to be overspent by
£0.171m, primarily due to price fluctuations in refuse disposal services. This is
partially offset by an anticipated over-recovery of £0.042m from the sale of
scrap metal. 
4.1.4 The service continues to closely monitor the potential impact of inflationary
pressures and contractual uplifts on the projected outturn. 
4.1.5 A review is currently underway to assess income relating to trade waste and
once the review is complete the outcome will be reported to the Board. 
4.2 Social Transport – (£0.162m) overspend by 31 March 2026 
4.2.1 The projected overspend has increased by £7k since the previous board
report.  The overspend sits within employee-related costs due to the need to
hire agency staff to cover for long-term sickness absence and vacancies. 
4.2.2 The service is adhering to the Council’s policies and procedures regarding
absence management and is actively working with HR to effectively manage
the current long-term sickness within the team. However, this situation is
impacting the financial position of the service, as there is an ongoing need to
rely heavily on agency staff to maintain service levels. 
4.2.3 The service will also be undertaking a review of current service levels to
ensure that the costs recharged to the service users, such as Education and
HSCP, accurately reflect the services provided from 2026/27 onwards. 
4.3 Roads Operations – £0.102m underspend by 31 March 2025 
4.3.1 The reported underspend is primarily due to a revision in the projected spend
relating to work by contractors. The service continues to closely monitor the
potential impact of any inflationary changes may have on this budget.

Page 4

PUBLIC
5. Subjective Analysis – Significant Variances 
5.1 Employee Costs – £0.138m underspend by 31 March 2026 
Overall the employee budgets are underspent by £138K.  This is primarily due
to vacancies and turnover. Recruitment across services is an continual
process to fill vacancies as and when they arise. 
5.2 Supplies and Services – (£0.407m) overspend by 31 March 2026 
The projected overspend in Supplies and Services is primarily driven by
inflation across three key service areas: Neighbourhood Services (£0.116
million), Infrastructure and Assets (£0.070 million), and Refuse Disposal
(£0.173 million). The increased costs are largely due to rising prices for
contractor services, materials, and related services.  
6. Revenue Budget Virements 
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and Resources
for submission to the relevant policy board for approval. There are no such
virements for consideration this period. 
7. Capital Budget Projection – break-even position by 31 March 2026 
7.1 The Capital Investment Programme 2025/26 to 2029/30 was approved by the
Council on 27 February 2025. For Infrastructure Land & Environment the
revised capital spend for 2025/26 is £17.058m. 
7.2 The in-year Capital budget is forecast to break even by 31 March 2026
however, this will be monitored as the projects progress. Further details of the
programme can be found in the Capital Monitoring report at Appendix 3. 
7.3 A number of budget adjustments between years have taken place, to reflect
revised programming of some capital projects. Details of these adjustments,
which amount to £0.408m, are as follows:

Page 5

PUBLIC 
Project Amount
(£m)
Budget increase due to grant award
SPT – People in Place Fund 0.110
Scottish Government – Road Safety 0.396
Budget reallocated to revenue
Transport Scotland - People and Place: Local Authority Direct
Award (LADA) (0.098)
Total 0.408 
Implications of the Report 
1. Financial 
The projected budget outturn position for the Infrastructure, Land and
Environment Revenue budget is an overspend of £0.252m. Income and
expenditure will continue to be monitored closely for the rest of the financial
year and as far as possible, steps will be taken to mitigate any overspend.   
The projected outturn position for the Infrastructure, Land and Environment
Capital budget is a break-even position. 
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report. 
3. Community/Council Planning 
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe

Page 6

PUBLIC
Council Plan
Reshaping our place, our
economy, and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe, and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report. 
5. Property/Assets 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets and
infrastructure. 
6. Information Technology 
There are no direct implications arising from the recommendations in this
report. 
7. Equality & Human Rights 
There are no direct implications arising from the recommendations in this
report. 
8. Health & Safety 
There are no direct implications arising from the recommendations in this
report. 
9. Procurement 
While Procurement is an important consideration prior to the council incurring
any revenue or capital spend, there are no direct implications arising from this
report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for the
year will be managed at a Council-wide level by the Chief Executive and
Directors.

Page 7

PUBLIC
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Climate Change 
The Council aims to reduce its carbon and other emissions to net zero by
2030, however there are no direct implications arising from the
recommendations in this report. 
13. Children’s Rights 
There are no direct implications arising from the recommendations in this
report. 
14. Cosla Policy Position 
N/A 
List of Background Papers
• The Capital Investment Programme 2025/26 to 2029/30, Council 27
February 2025 
Author:           Lisa Dickie, Finance Business Partner, 
Gordon McNeil, Director of Environment, Housing & Infrastructure and
Linsey Mcgregor, Senior Accountant (Capital)

Page 8

PUBLIC
Appendix 1 
Objective Summary
Annual
Budget at
Period 3
Budget
Adjustments
Revised
Annual
Budget at
Period 6
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000
Directorate and Service Co-ordination 1,425 64 1,489 1,478 11 0.7% 15 (4)
Refuse Collection 5,734 346 6,080 6,176 (96) (1.6%) (103) 7
Household Waste Recycling Centres 1,392 37 1,429 1,442 (13) (0.9%) (15) 2
Refuse Disposal 7,624 0 7,624 7,755 (131) (1.7%) (53) (78)
Neighbourhood Services 7,282 328 7,610 7,597 13 0.2% 107 (94)
Fleet Services 405 (44) 361 349 12 3.3% 4 8
Social Transport 1,210 45 1,255 1,417 (162) (12.9%) (155) (7)
Roads Operations 5,752 80 5,832 5,730 102 1.7% 0 102
Infrastructure and Assets 2,971 28 2,999 3,014 (15) (0.5%) 40 (55)
Transportation & Development 732 (12) 720 795 (75) (10.4%) (173) 98
Parking of Vehicles (36) 2 (34) (59) 25 73.5% 10 15
Street Lighting Maintenance Work 542 12 554 453 101 18.2% 57 44
Energy Management Unit 405 14 419 419 0 0.0% 0 0
Strathclyde Partnership for Transport
Requisition
3,379 0 3,379 3,403 (24) (0.7%) (24) 0
NET EXPENDITURE 38,817 900 39,717 39,969 (252) (0.6%) (290) 38
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 19 September 2025
Budget Variance
(Adverse) or Favourable
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 9

PUBLIC
Appendix 2 
Subjective Summary
Annual
Budget at
Period 3
Budget
Adjustments
Revised
Annual
Budget at
Period 6
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 25,855 1,260 27,115 26,977 138 0.5% 51 87
Premises Related 1,353 81 1,434 1,537 (103) (7.2%) (63) (40)
Transport Related 8,321 295 8,616 8,587 29 0.3% (480) 509
Supplies and Services 15,526 206 15,732 16,139 (407) (2.6%) (731) 324
Third Party Payments 3,672 (28) 3,644 3,668 (24) (0.7%) (23) (1)
Transfer Payments 164 5 169 193 (24) (14.2%) (50) 26
Support Services 698 (37) 661 676 (15) (2.3%) (15) 0
Depreciation and Impairment Losses 2,180 0 2,180 2,180 0 0.0% 0 0
GROSS EXPENDITURE 57,769 1,782 59,551 59,957 (406) (0.7%) (1,311) 905
Income (18,952) (882) (19,834) (19,988) 154 0.8% 1,021 (867)
NET EXPENDITURE 38,817 900 39,717 39,969 (252) (0.6%) (290) 38
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 19 September 2025
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 10

PUBLIC
Appendix 3 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2025 2025-26 since previous 2025-26 2025-26 Budget Outurn
Project Title Board report to 31-Mar-30 to 31-Mar-30
£000 £000 £000 £000 £000 £000 £000
ENVIRONMENT & INFRASTRUCTURE
Active Travel Funding Tier 1 0 1,411 0 1,411 1,411 0 0% 4,611 4,611 0 0%
LADA 49 147 (98) 49 49 0 0% 98 98 0 0%
Bus Infrastructure Fund 0 105 0 105 105 0 0% 105 105 0 0%
Vehicle Replacement Programme 0 2,382 0 2,382 2,382 0 0% 12,102 12,102 0 0%
Bridge Assessment/Strengthening - 6XN004 0 347 0 347 347 0 0% 1,547 1,547 0 0%
Roads/Footways Upgrade Programme -6XN004 0 8,012 0 8,012 8,012 0 0% 59,437 59,437 0 0%
Lighting Columns Replacement - 6XN004 0 840 0 840 840 0 0% 3,240 3,240 0 0%
Improvements to Outdoor Access and Play Area Programm 1,207 68 0 68 68 0 0% 1,207 1,207 0 0%
Total Active Travel Transformation Fund 331 90 0 90 90 0 0% 421 421 0 0%
SPT - People in Place Fund 0 0 110 110 110 0 0% 110 110 0 0%
Multi Pupose Bins 0 56 0 56 56 0 0% 56 56 0 0%
Renewal of Play Parks 0 1,167 0 1,167 1,167 0 0% 1,967 1,967 0 0%
Nature Restoration Fund (Biodiversity) 483 330 (114) 216 216 0 0% 558 558 0 0%
Nature Restoration Fund (Rivers) 95 0 114 114 114 0 0% 350 350 0 0%
Underwood Depot Improvement 12 388 0 388 388 0 0% 400 400 0 0%
Public Realm - Abbey 0 300 0 300 300 0 0% 300 300 0 0%
Recycling Improvement Fund 486 271 0 271 271 0 0% 757 757 0 0%
Road Safety 952 0 396 396 396 0 0% 1,348 1,348 0 0%
Open Spaces Infrastructure 0 200 0 200 200 0 0% 200 200 0 0%
Strathclyde Partnership Transport 0 300 0 300 300 0 0% 300 300 0 0%
TOTAL INFRASTRUCTURE, LAND & ENVIRONMENT
BOARD 4,451 16,650 408 17,058 17,058 0 0% 90,186 90,186 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 19th September 2025
POLICY BOARD: INFRASTRUCURE, LAND & ENVIRONMENT
Current Year 2025-26 Full Programme - All years
Budget Variance
(Adverse) or Favourable
Budget Variance
(Adverse) or