Revenue and Capital Budget Monitoring 2025-26 at 27 June 2025

Renfrewshire Council · 27 August 2025
Back to Infrastructure, Land and Environment Policy Board — 27 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

___________________________________________________________________ 
To: Infrastructure, Land & Environment Policy Board 
On: 27 August 2025
___________________________________________________________________ 
Report by: Director of Finance and Resources 
Director of Environment, Housing & Infrastructure
___________________________________________________________________ 
Heading: Revenue and Capital Budget Monitoring 2025/26 at 27 June 2025
___________________________________________________________________ 
1. Summary 
1.1 At the close of reporting Period 3 on 27 June 2025, the projected revenue
outturn at 31 March 2026 for those services reporting to the Infrastructure,
Land and Environment Policy Board is an overspend position of £0.290m
(0.7%) against the revised budget for the year. 
1.2 The projected capital outturn at 31 March 2026 for projects reporting to the
Infrastructure, Land and Environment Policy Board is a break-even position. 
1.3  This is summarised over the relevant services in the table below and further
analysis is provided in the report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue        
Environment & Infrastructure 38,817 39,107 (290) (0.7%)
Total 38,817 39,107 (290) (0.7%)
Capital        
Environment & Infrastructure 16,650 16,650 0 0.0%

Page 2

2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board: 
2.1 Note the projected Revenue outturn overspend position of £0.290m; 
2.2 Note the projected Capital outturn break-even position; and 
2.3 Note the budget adjustments in appendix 1 and 2. 
3. Revenue Budget Projection – overspend of £0.290m by 31 March 2026 
3.1 The tables in Appendix 1 and 2 present the projected year-end position for
all services reporting to this board, by both objective analysis (which division
is spending the budget – appendix 1) and subjective analysis (what the
budget is spent on – appendix 2). Material variances affecting the projected
position are analysed further below. 
3.2 It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. The impact of any change on this projection will be updated at
each board cycle until the close of reporting period 10. Budget holders are
obliged to seek mitigating action to minimise significant budget variances. 
4. Objective Analysis – Significant Variances 
4.1 Environment, Housing, and Infrastructure – (£0.290m) overspend 
Waste Services – (£0.171m) overspend by 31 March 2026 
This reflects the financial position for Refuse Collection, Refuse Disposal
and Household Waste Recycling Centres. 
The overspend for Refuse Collection in the main relates to an estimated 
overspend in employee costs (£0.221m) as a result of overtime being
required to cover absence and vacancies.  However this will be partially
offset by income from special uplift collections. 
At present, the Trade Waste income budget is forecast to break even. A
review is currently underway to assess income relating to trade waste and
once the review is complete the outcome will be reported to the Board.

Page 3

Social Transport – (£0.155m) overspend by 31 March 2026 
The current projected overspend is due to employee-related costs. This is
largely a result of the need to hire agency staff to cover for long-term
sickness absence and vacancies. 
Transport and Development – (£0.173m) overspend by 31 March 2026 
The projected overspend is primarily relates to staffing costs and an
overspend within work by contractors of £0.102m, which is in line with last
year’s outturn, with increased maintenance requirements on traffic signal
assets. Due to the reactive nature of the service, the projections will continue
to be closely monitored for the remainder of the financial year.   
5. Subjective Analysis – Significant Variances 
5.1 Transport Related – (£0.480m) overspend by 31 March 2026 
The current projected overspend of 5.8% is mainly driven by a substantial
rise in the cost of replacement parts for equipment and vehicles (£116k),
along with vehicle hire expenses (£0.239m) required to meet service
demands. In addition, there is an anticipated overspend within Non-Fair
Wear and Tear of £0.159m, this is partially offset by an £0.080m underspend
within Fair Wear and Tear repairs. 
5.2 Supplies and Services – (£0.731m) overspend by 31 March 2026 
The projected overspend in Supplies and Services is concentrated across
four key service areas: Fleet (£0.336m), Neighbourhood Services (£0.090m),
Parking (£0.098m), and Transport and Development (£0.103m). In each of
these areas, inflation is the primary driver, with rising costs for contractor
work, materials, and related services. However, the overspends in Fleet and
Parking are offset by higher than anticipated income recovery (£0.122m). 
5.3 Income – £1.021m over-recovery by 31 March 2026 
The majority of the over-recovery is attributed to Fleet Services, primarily
due to recharges for external vehicle hire and costs associated with non-fair
wear and tear, amounting to £0.676 million.  Additionally, as previously noted
above, there are income over-recoveries within Refuse Collection (£0.170m),
Parking (£0.122m) as noted in above.

Page 4

6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and
Resources for submission to the relevant policy board for approval. 
6.3. Budget holders are obliged to seek mitigating action to minimise significant
budget variances. The Board is therefore asked to approve the following
virements, which are not currently applied to the budget: 
Revenue Budget Adjustments
Service Subjective
Heading Amount (£m) Reason
Fleet Services Transport Related 0.676  Alignment of the non fair
and tear costs budget and
income budget for Fleet
recharges
Fleet Services Income
(0.676)
Total   0   
7. Capital Budget Projection – break-even position by 31 March 2026 
7.1 The Capital Investment Programme 2025/26 to 2029/30 was approved by
the Council on 27 February 2025. For Infrastructure Land & Environment the
revised capital spend for 2025/26 is £16.650m. 
7.2 The in-year Capital budget is forecast to break even by 31 March 2026
however, this will be monitored as the projects progress. Further details of
the programme can be found in the Capital Monitoring report at Appendix 3. 
7.3 A number of budget adjustments between years have taken place, to reflect
revised programming of some capital projects. Details of these adjustments,
which amount to £3.859m, are as follows:

Page 5

Project Amount
(£m)
Budget increase due to grant award from Transport Scotland
Active Travel Funding Tier 1 0.598
People and Place: Local Authority Direct Award (LADA) 0.147
Bus Infrastructure Fund 0.105
Budget carried forward from 2024/25 into 2025/26
Vehicle Replacement Programme 0.182
Bridge Assessment/Strengthening 0.054
Roads/Footways Upgrade Programme 1.037
Lighting Columns Replacement 0.240
Improvements to Outdoor Access and Play Area Programme 0.068
Total Active Travel Transformation Fund  0.090
Multi-Purpose Bins 0.056
Nature Restoration Fund 0.190
Underwood Depot Improvements 0.238
Public Realm – Abbey 0.300
Recycling Improvement Fund 0.271
Strathclyde Partnership Transport 0.300
Total 3.859 
Implications of the Report 
1. Financial 
The projected budget outturn position for the Infrastructure, Land and
Environment Revenue budget is an overspend of £0.290m. Income and
expenditure will continue to be monitored closely for the rest of the financial
year and as far as possible, steps will be taken to mitigate any overspend.   
The projected outturn position for the Infrastructure, Land and Environment
Capital budget is a break-even position. 
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report.

Page 6

3. Community/Council Planning 
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy, and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe, and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report. 
5. Property/Assets 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets and
infrastructure. 
6. Information Technology 
There are no direct implications arising from the recommendations in this
report. 
7. Equality & Human Rights 
There are no direct implications arising from the recommendations in this
report. 
8. Health & Safety 
There are no direct implications arising from the recommendations in this
report.

Page 7

9. Procurement 
While Procurement is an important consideration prior to the council incurring
any revenue or capital spend, there are no direct implications arising from this
report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for the
year will be managed at a Council-wide level by the Chief Executive and
Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Climate Change 
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report. 
13. Children’s Rights 
There are no direct implications arising from the recommendations in this
report. 
14. Cosla Policy Position 
N/A 
List of Background Papers
• The Capital Investment Programme 2025/26 to 2029/30, Council 27
February 2025 
Authors: Lisa Dickie, Finance Business Partner, 
Gordon McNeil, Director of Environment, Housing & Infrastructure and
Linsey Mcgregor, Senior Accountant (Capital)

Page 8

No embedded text on this page.

Page 9

Appendix 1 
Objective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
£000 £000 £000 £000 £000 %
Directorate and Service Co-ordination 1,400 25 1,425 1,410 15 1.1%
Refuse Collection 5,457 277 5,734 5,837 (103) (1.8%)
Household Waste Recycling Centres 1,369 23 1,392 1,407 (15) (1.1%)
Refuse Disposal 7,624 0 7,624 7,677 (53) (0.7%)
Neighbourhood Services 7,118 164 7,282 7,175 107 1.5%
Fleet Services 79 326 405 401 4 1.0%
Social Transport 1,182 28 1,210 1,365 (155) (12.8%)
Roads Operations 5,705 47 5,752 5,752 0 0.0%
Infrastructure and Assets 2,929 42 2,971 2,931 40 1.3%
Transportation & Development 777 (45) 732 905 (173) (23.6%)
Parking of Vehicles (38) 2 (36) (46) 10 27.8%
Street Lighting Maintenance Work 535 7 542 485 57 10.5%
Energy Management Unit 361 44 405 405 0 0.0%
Strathclyde Partnership for Transport
Requisition
3,379 0 3,379 3,403 (24) (0.7%)
NET EXPENDITURE 37,877 940 38,817 39,107 (290) (0.7%)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025
Budget Variance
(Adverse) or Favourable
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT

Page 10

No embedded text on this page.

Page 11

Appendix 2 
Subjective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
£000 £000 £000 £000 £000 %
Employees 25,033 822 25,855 25,804 51 (0.4%)
Premises Related 1,335 18 1,353 1,416 (63) (6.1%)
Transport Related 7,753 568 8,321 8,801 (480) (8.0%)
Supplies and Services 14,497 1,029 15,526 16,257 (731) (4.1%)
Third Party Payments 3,447 225 3,672 3,695 (23) (7.2%)
Transfer Payments 168 (4) 164 214 (50) (30.5%)
Support Services 700 (2) 698 713 (15) (2.1%)
Depreciation and Impairment Losses 2,180 0 2,180 2,180 0 0.0%
GROSS EXPENDITURE 55,113 2,656 57,769 59,080 (1,311) (2.3%)
Income (17,236) (1,716) (18,952) (19,973) 1,021 (5.4%)
NET EXPENDITURE 37,877 940 38,817 39,107 (290) (0.7%)
POLICY BOARD : INFRASTRUCTURE, LAND AND ENVIRONMENT
Budget Variance
(Adverse) or Favourable

Page 12

No embedded text on this page.

Page 13

Appendix 3 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2025 2025-26 2025-26 2025-26 Budget Outurn
Project Title to 31-Mar-30 to 31-Mar-30
£000 £000 £000 £000 £000 £000 £000
ENVIRONMENT & INFRASTRUCTURE
Active Travel Funding Tier 1 0 813 598 1,411 1,411 0 0% 4,611 4,611 0 0%
LADA 49 0 147 147 147 0 0% 196 196 0 0%
Bus Infrastructure Fund 0 0 105 105 105 0 0% 105 105 0 0%
Vehicle Replacement Programme 0 2,200 182 2,382 2,382 0 0% 12,102 12,102 0 0%
Bridge Assessment/Strengthening - 6XN004 0 293 54 347 347 0 0% 1,547 1,547 0 0%
Roads/Footways Upgrade Programme -6XN004 0 6,975 1,037 8,012 8,012 0 0% 59,437 59,437 0 0%
Lighting Columns Replacement - 6XN004 0 600 240 840 840 0 0% 3,240 3,240 0 0%
Improvements to Outdoor Access and Play Area Programm 393 0 68 68 68 0 0% 461 461 0 0%
Total Active Travel Transformation Fund 331 0 90 90 90 0 0% 421 421 0 0%
Multi Pupose Bins 0 0 56 56 56 0 0% 56 56 0 0%
Renewal of Play Parks 0 1,167 0 1,167 1,167 0 0% 1,967 1,967 0 0%
Nature Restoration Fund (Biodiversity) 578 140 190 330 330 0 0% 908 908 0 0%
Underwood Depot Improvement 12 150 238 388 388 0 0% 400 400 0 0%
Public Realm - Abbey 0 0 300 300 300 0 0% 300 300 0 0%
Recycling Improvement Fund 486 0 271 271 271 0 0% 757 757 0 0%
Open Spaces Infrastructure 0 200 0 200 200 0 0% 200 200 0 0%
Strathclyde Partnership Transport 0 0 300 300 300 0 0% 300 300 0 0%
TOTAL INFRASTRUCTURE, LAND & ENVIRONMENT
BOARD 3,637 12,791 3,859 16,650 16,650 0 0% 89,032 89,032 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 27th June 2025
POLICY BOARD: INFRASTRUCURE, LAND & ENVIRONMENT
Current Year 2025-26 Full Programme - All years
Budget Variance
(Adverse) or Favourable
Budget Variance
(Adverse) or