Contract Authorisation Report - Demolition of Tannahill Rd and Tannahill Terrace

Renfrewshire Council · 15 June 2022
Back to Finance, Resources and Customer Services Policy Board — 15 June 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

_________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 15th June 2022
_________________________________________________________________
Report by: The Chief Executive and the Director of Finance and Resources
_________________________________________________________________
Heading: Contract Award: Demolition of Tannahill Road and Tannahill
Terrace (RC-CPU-21-229)
_________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Works
Contract titled Demolition of Tannahill Road and Tannahill Terrace
(RC-CPU-21-229) (the “Contract”) to Caskie Limited. 
1.2 The recommendation to award the Contract follows a mini-
competition in accordance with the Scotland Excel Demolition and
Deconstruction Framework, reference 1119 and the Council’s
Standing Orders Relating to Contracts. 
1.3 A Contract Strategy was approved by the Strategic Commercial
Category Manager and the Head of Property Services on 22nd April
2022.
_________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer
Services Policy Board: 
(a) Authorise the Head of Corporate Governance to award a
Contract titled Demolition of Tannahill Road and Tannahill
Terrace (RC-CPU-21-229) to Caskie Limited;

Page 2

(b) Authorise the Contract Sum of £235,850.00 excluding VAT for
this Contract; and 
(c) Note the works are for a period of 28 weeks, with the intention for
commencement of the works to be 18th July 2022 and a Date for
Completion of 10th February 2023. The actual date for
Commencement of the Works will be confirmed in the Council’s
Letter of Acceptance to Caskie Limited.
________________________________________________________
3. Background
3.1 This procurement is for the appointment of a contractor to carry out
the Demolition and site clearance of seventeen (17) blocks of empty
domestic dwellings and one (1) commercial unit at Tannahill Road
and Tannahill Terrace, Paisley owned by the Council.  The Council is
building 101 new homes on the neighbouring former St Fergus’
Primary School site which will provide a range of properties to house
the needs of tenants and owners who wish to remain within the
Ferguslie area.
3.2 The proposed demolition of these buildings was approved at the
Communities, Housing and Planning Policy Board on 18 May 2021
and is summarised as follows –  
Wholly Empty Council Owned Blocks – Proposed for Demolition
Tannahill Road, Paisley
46 – 52, 57 – 63, 90 – 96, 97 – 103,
98 – 104, 113 – 115, 117 – 123 and 125 – 131.
Tannahill Terrace, Paisley
1 – 3, 18 – 24, 58 – 64, 74 – 80, 90 – 92,
105 – 111, 133 – 139, 141 – 147 and 157 – 163.
Drums Avenue 26 (Commercial property) 
The properties have recently been subject to fire-raising and
instances of anti-social behaviour.  The site will be landscaped on
completion of the demolition works while longer term proposals for
the site are considered within the context of the Community Led
Development Framework that was approved by the Leadership
Board on 01 December 2021. 
Opportunities for the redevelopment of the Tannahill site will be
considered within the context of the community and stakeholder
consultation on the emerging development framework for the wider
Ferguslie Park area.

Page 3

3.4 As part of the contract strategy it was identified that the Scotland
Excel Framework Agreement,  Demolition and Deconstruction,
reference 1119  (“Framework”) was best suited for this contract. This
Framework has a lot specific to Demolition and Deconstruction works
of a value on or over £50,000 (Lot 2). This procurement exercise was
conducted as a mini-competition, and was conducted in accordance
with the conditions of use set out in the Framework.
3.5 There are seventeen (17) companies who confirmed their ability to
service the Renfrewshire Council area within Lot 2 of the Framework.
All seventeen (17) companies were invited to Tender on 28th May
2022.
3.6 During the live tender period, 15 companies expressed an interest in
the Contract. By the closing date set for tender submissions, 12 noon
on 12th May 2022, ten (10) companies had submitted a response and
seven (7) companies did not respond.
3.7 The 10 tender submissions were evaluated against the published
Award Criteria based on weightings of 60% Price and 40% Quality.
This evaluation was carried out by representatives from Property
Services, the Corporate Procurement Unit, Corporate Risk and
Corporate Health & Safety. The ten (10) tender submissions
received complied with the minimum criteria set out in the ITT. The
winning tenderer confirmed that there was no change to the ESPD
information disclosed at the time of Framework inception.
3.8 The scores relative to the Award Criteria of the ten (10) Tenderers
are noted below – 
Company  Quality
(40%) 
Price
(60%) 
Total
(100%)
Caskie Limited 38.25% 55.32% 93.57%
Dem-Master Demolition
Limited
32.50% 56.16% 88.66%
JCJ (Demolition &
Construction) Limited
31.25% 49.69% 80.94%
Central Demolition Limited 20.50% 60.00% 80.50%
JCH Plant Hire Ltd. 18.50% 56.66% 75.16%
Safedem Limited 22.25% 48.93% 71.18%
George Beattie & Sons Limited 27.00% 37.66% 64.66%
Reigart Contracts Limited 23.25% 36.49% 59.74%
Daltons Demolitions Limited 9.75% 46.73% 56.48%

Page 4

William Goodfellow
(Contractors) Limited
21.25% 35.16% 56.41% 
3.9 The evaluation of tender submissions received identified that the
submission by Caskie Limited was the most economically
advantageous tender.
3.10 The form of Contract will be the SBCC Minor Works Building
Contract for use in Scotland, 2016 Edition, amended and/or
supplemented by Employer’s Amendments.
3.11 This Contract is funded from the Housing Capital budget.
3.12 Community Benefits were requested as part of this procurement
process and Caskie Limited confirmed that the following Community
Benefits would be made available to the Council for this Contract –  
Community Benefit Description 
No of
People/Activity
Industry Awareness Event 1
Non-Financial Support for a Community Project 1  
_________________________________________________________________
Implications of the Report
1. Financial – The cost for these works will be met by the Housing
Capital budget as noted in 3.11 above. 
2. HR & Organisational Development – No HR or Organisational
Development implications have arisen or are anticipated. 
3. Community/Council Planning – 
• Our Renfrewshire is safe - removing wholly vacant properties within
regeneration areas that are causing security and safety concerns to
tenants and residents. 
• Working together to improve outcomes - listening to the requests of the
communities in which we operate. 
4. Legal - The procurement of this Contract was conducted as a below
Regulated (Works) Mini Competition  in accordance with the
Scotland Excel  Framework Demolition and Deconstruction,
reference 1119 and  the Council’s Standing Orders Relating to
Contracts.

Page 5

5. Property/Assets – removal of properties highlighted for demolition.   
6. Information Technology – No Information Technology implications
have arisen or are anticipated. 
7. Equality & Human Rights - The Recommendations contained
within this report have been assessed in relation to their impact on
equalities and human rights. No negative impacts on equality groups
or potential for infringement of individuals’ human rights have been
identified arising from the recommendations contained in the report
because it is for noting only. If required following implementation, the
actual impact of the recommendations and the mitigating actions will
be reviewed and monitored, and the results of the assessment will
be published on the Council’s website. 
8. Health & Safety – Caskie Limited’s health and safety credentials
were evaluated by Corporate Health and Safety and met the
Council’s minimum requirements regarding health and safety.
9. Procurement – The procurement procedure outlined within this
report ensures that the Council meets its statutory requirements in
respect of procurement procedures, efficiency and modern
government.
10. Risk – Caskie Limited’s insurances were assessed and evaluated to
confirm that they meet the minimum requirements regarding
insurable risk. 
11. Privacy Impact – No Privacy implications have been identified or
are anticipated. 
12. Cosla Policy Position - No COSLA Policy Position implications
have arisen or are anticipated.
13. Climate Risk – The Scotland Excel Framework Agreement contains
specific conditions that all contractors must adhere to. The
Contractor must comply with Scotland’s Zero Waste Plan on how all
materials arising from the works are sorted, removed from site and
whenever possible re-used, re-manufactured or recycled to recover
some of their inherent value. After initial sorting on site, the
Contractor must evidence to the Client where all materials are taken
for further treatment. Copies of consignment notes will be required to
demonstrate that appropriate proportions of all materials have been
taken to licensed facilities for recycling or landfill. In addition, The
Contractor will monitor the operation and maintenance of all their
plant and equipment for opportunities to reduce emissions, fuel
waste, fuel spillage and noise.
________________________________________________________

Page 6

________________________________________________________
List of Background Papers 
(a) Background  Paper 1 – Communities, Housing and Planning
Board, 18 May 2021. Heading: Tannahill Area, Ferguslie Park –
Housing Regeneration Update 
(b) Background Paper 2 – Leadership Board, 1 December 2021.
Heading: The Making of Ferguslie - framework report and place
plan.