Contract Authorisation Report - Paisley Grammar School Community Campus Principal Contractor

Renfrewshire Council · 15 June 2022
Back to Finance, Resources and Customer Services Policy Board — 15 June 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board 
On: 15th June 2022
___________________________________________________________________
Report by: Report by the Chief Executive and the Director of Finance and
Resources
___________________________________________________________________
Heading: Contract Award: Paisley Grammar School Community Campus
(PGSCC) – Principal Contractor (PC) (RC-CPU-21- 247)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance, Resources
and Customer Services Policy Board to award a Pre-Construction Services
Agreement for Paisley Grammar School Community Campus (PGSCC) –
Principal Contractor (RC-CPU-21-247) (the “PCSA ”) to Galliford Try
Construction Limited, T/A Morrison Construction Scotland, and to inform the
Board of the intention to subsequently award a Design and Build Works
Contract for Paisley Grammar School Community Campus (PGSCC) –
Principal Contractor (RC-CPU-21-247) to Galliford Try Construction Limited,
T/A Morrison Construction Scotland on completion of the Pre-Construction
Services (the “D&B Contract”). 
1.2 The recommendation to award the PCSA (and subsequently the D&B
Contract) follows a procurement exercise which was conducted in accordance
with the Competitive Procedure with Negotiation (CPN) under the Public
Contracts (Scotland) Regulations 2015 and the Council’s Standing Orders
Relating to Contracts. 
1.3 A Contract Strategy addendum was approved by the Strategic Commercial
and Procurement Manager and the Head of Property Services on 5th

Page 2

November 2021, this was to amend and update the Contract Strategy
approved on 7th September 2021.
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board: 
(a) Authorise the Head of Corporate Governance to award a Pre-
Construction Services Agreement (PCSA) for the Paisley Grammar
School Community Campus (PGSCC) – Principal Contractor (RC-
CPU-21-247) to Galliford Try Construction Limited, T/A Morrison
Construction Scotland. 
(b) Authorise the value of the PCSA  at £228,862.21 exclusive of VAT.   
(c) Note the pre-construction services are scheduled for
commencement on Monday 11th July 2022. The actual date will be
confirmed in the Council’s Letter of Acceptance to Galliford Try
Construction Limited, T/A Morrison Construction Scotland. 
(d) Note that, on completion of the Pre-Construction Services, a further
report will be brought to the Finance, Resources and Customer
Services Policy Board seeking approval to enter into the Design and
Build Contract with Galliford Try Construction Limited, T/A Morrison
Construction Scotland. 
_________________________________________________________
3. Background
3.1 This procurement is for the appointment of a Principal Contractor for
the Paisley Grammar School Community Campus project (“PGSCC”).
The requirement is for a single Principal Contractor for both pre-
construction services and the construction itself. 
Renfrewshire Council require to replace the existing Paisley Grammar
School and wishes to integrate the school with both the local
community and enterprise organisations to form a new Paisley
Grammar School Community Campus.
This Contract is for the appointment of a Principal Contractor to design
and construct a new Passivhaus school in line with the Scottish Futures
Trust (SFT) Learning Estate Investment Programme (LEIP)
requirements. The School will be constructed on a site which has been

Page 3

acquired by the Council and which formed part of the former Chivas
Brothers bottling plant at 111-113 Renfrew Road, Paisley, PA3 4DY. 
3.2  The Council identified the construction of a new Paisley Grammar
School Community Campus as it’s learning estate investment priority in
May 2019. The new school and community campus will accommodate
a roll of circa 1200 pupils and will benefit from a community café and
community space. 
During 2020, formal consultation on the proposal which was supported
by Education Scotland was undertaken and a decision to progress the
proposal was approved by the Council’s Education and Children’s
Services Policy Board in January 2021. Having met all the qualifying
criteria identified by ministers, the project has now been included in
Stage 2 of the Scottish Government’s £1 billion Learning Estate
Investment Programme.
The project will require to attain the SFT LEIP metrics which set out
specific targets and outcomes which must be achieved to ensure that
the project delivers a high quality, sustainable, low carbon and digitally-
enabled learning environment.  The outcomes include ambitious energy
targets and a requirement to support inclusive economic growth
through the creation of jobs to deliver the funded facilities.
3.3 Early contractor engagement is being sought in this Project and it is
anticipated that the Principal Contractor shall be appointed no later
than the commencement of RIBA Stage 2 under a bespoke Pre-
Construction Services Agreement. The Principal Contractor will work
closely with the Multidisciplinary Design Team (MDDT) up to
completion of RIBA stage 4.  The appointment of the MDDT was
approved by this board on 30th March 2022.  At the point that the
project is ready to proceed to the construction phase, a further report
will be brought to the Finance, Resources and Customer Services
Policy Board seeking approval to enter into the Design and Build
Contract with Galliford Try Construction Limited, T/A Morrison
Construction Scotland. At this point, the appointed MDDT will be
novated to the appointed Principal Contractor. This is anticipated to be
at the end of RIBA Stage 4.
3.4 The Pre-Construction Services will be in the form of a bespoke Pre-
Construction Services Agreement (PCSA).  The Pre-Construction
Services will be carried out to RIBA stages 2-4 (inclusive). Following
satisfactory completion of the Pre Construction Services, a report will
be submitted to the Finance, Resources and Customer Services Policy
Board seeking approval to proceed with the full Design and Build
Contract.  If the Board approves the recommendation, the Council will

Page 4

enter into a Design and Build Contract with Galliford Try Construction
Limited, T/A Morrison Construction Scotland at the end of RIBA stage
4. The form of Design and Build Contract will be SBCC Design and
Build Contact for use in Scotland 2016 edition accompanied with
bespoke Employer’s Amendments and Preliminaries. 
3.5 The CPN process that was adopted was mapped by the following stages;
- Stage 1 (Invitation to Participate - Selection);
- Stage 2 (Invitation to Tender – Initial ITT);
- Stage 3 (Negotiation);
- Stage 4 (Final Tender - Award). 
The Council reserved the right to award at the end of Stage 2 if a fully
compliant offer was received, without the requirement to proceed to
stages 3 and 4. 
3.5 Stage 1 of this process was open to all interested bidders, who met the
minimum criteria set out in the Invitation to Participate - Selection. The
contract notice was published on the Find a Tender and Public
Contracts Scotland websites on 8th November 2021 with the Invitation
to Participate documents available for download from the Public
Contracts Scotland – Tender portal on the same date. 
3.7 During Stage 1, fourteen (14) companies expressed an interest in the
Contract.  By the closing date set for Stage 1 submissions, 10:00 on
09th December 2021, six (6) Candidates had submitted a request to
participate (RTP). 
3.8 The six (6) RTPs were each evaluated against a pre-determined set of
criteria in the form of the Single Procurement Document (SPD)
Scotland by representatives from the Council’s Corporate Procurement
Unit, Property Services and a Category Manager from Scotland Excel
provided as additional agency support to help resource the project. 
All six (6) Candidates satisfied the Council’s minimum requirements
within the SPD selection criteria.
3.9  As part of the selection process, and to reduce the number of
otherwise qualified Candidates, in accordance with the Invitation to
Participate, Candidates had to respond to questions relating to previous
experience, technical capacity and capability with projects similar in
nature, scope and scale to this Contract.  
3.10 A panel of representatives from the Council’s Property Services team
assessed each of the six (6) Candidate responses to the questions and
the five (5) highest scoring Candidates were selected to proceed to
Stage 2 (Invitation to Tender – Initial ITT).  The Contract Notice for this

Page 5

procurement indicated the Council’s intention to reduce the number of
Candidates to five (5) who will be selected to Stage 2 initial tender.
3.11 The selection score for each Candidate within Stage 1 – RTP is noted
below: 
Candidate Weighting Technical
Rank
Galliford Try Construction Limited,
T/A Morrison Construction
Scotland
95.50% 1
Keir Construction Limited 94.50% 2
Morgan Sindall Construction &
Infrastructure Ltd  87.50% 3
BAM Construction Limited 87.50% 3
Bowmer & Kirkland Ltd  78.50% 5
Sir Robert McAlpine Limited 74.00% 6 
3.12 The top 5 ranked Candidates from Stage 1 were invited by invitation
issued on 17th January 2022 via the Public Contracts Scotland –
Tender portal to submit an initial tender for Stage 2.  By the closing
date and time set for return, 2pm on 15th February 2022, four (4)
Candidates submitted a response and one (1) failed to respond. 
3.13 The tenders received were assessed against the published Award
Criteria based on weightings of 20% price and 80% Quality.  These
were assessed by an evaluation panel consisting of the Council’s
Property Services team, Corporate Procurement Unit, the Category
Manager from Scotland Excel (agency support) and an External
Consultant.  The Tenderer scores relative to the Award Criteria are
detailed in the table below: 
Tenderer Price Score Quality Score Total score
Galliford Try
Construction
Limited, T/A
Morrison
Construction
Scotland
20.00% 78.20% 98.20%
Keir
Construction
Limited
16.82% 73.60% 90.42%
Morgan
Sindall
Construction
10.82% 69.00% 79.82%

Page 6

&
Infrastructure
Ltd
BAM
Construction
Limited
10.79% 62.40% 73.19% 
3.14 The Council had an option with the Competitive Procedure with
Negotiation to proceed to further stages (Stage 3 and Stage 4), it was
agreed by the project team that it was not necessary to take up these
options as tenders received were within budget and all tenders met the
minimum requirements as set out within the Invitation to Tender
Documents. In the Stage 2 Invitation to Tender, the Council had
reserved the right not to utilise these stages.
3.15 The Council is satisfied that the Tender Submission from Galliford Try
Construction Limited, T/A Morrison Construction Scotland is the most
economically advantageous tender submission. To note, the evaluation
was set to assess the tenderers for both the pre-construction services
and the construction itself, for both elements Galliford Try Construction
Limited, T/A Morrison Construction Scotland is the most economically
advantageous tender submission. 
3.16  Mandatory Community Benefits were included as a condition of this
contract which Galliford Try Construction Limited, T/A Morrison
Construction Scotland confirmed they would adhere to. The
commitment is to deliver 15 new employment opportunities. 
In addition to the mandatory Community Benefits requested, and
subject to the Council entering into the Design and Build Contract,
Galliford Try Construction Limited, T/A Morrison Construction Scotland
confirmed in their offer that the following Community Benefits would
also be made available to the Council: 
Community Benefit Description
No of
People /
Activity
Job for a young person (age 16-24) from a recognised
priority group e.g. from the councils' most deprived
datazones
1
Job for an unemployed individual 1
Modern Apprenticeship 2

Page 7

Graduate 1
Work Experience Placement for an individual 16+ years of
age 20
Work Experience Placement for an individual in full time
education 10
Business advice/support to a local SME /Social Enterprise/
Voluntary organisation 10
Commitment to ensure that supply chain opportunities are
prioritised for Renfrewshire based businesses 4
S/NVQ (or equivalent) for  
• New Employee
• Existing Employee  
• Supply Chain Employee
15
Industry Awareness Events 
• Schools
• Invest in Renfrewshire – Employability
• Further Education
20
Industry Skill Transfer to Schools 8
Financial Support for a Social Enterprise 2
Non financial support for a Social Enterprise 2
Financial Support for other community initiatives which
meet the Council's community policies/strategies 15
Non-financial Support for other community initiatives which
meet the Council's community development
policies/strategies
5
___________________________________________________________________
Implications of the Report
1. Financial – No financial implications have arisen or are anticipated.
Financial and Economic Standing have been assessed as part of the
tender selection criteria – which Galliford Try Construction Limited, T/A
Morrison Construction Scotland met. The project will be part funded by
the Scottish Futures Trust (SFT) within the Stage 2 Learning Estate
Investment Programme (LEIP).   
2. HR & Organisational Development - No HR & Organisational
Development implications have arisen or are anticipated. 
3. Community/Council Planning –

Page 8

• Our Renfrewshire is fair - Tenderers were assessed within Award
Criteria regarding their approach to ensuring fair working practices
throughout their organisation and supply chain i.e. payment of the
living wage, training and development opportunities etc. 
• Reshaping our place, our economy and our future - The work from
the design to the main works will create many employment
opportunities across Renfrewshire.  The Community Campus itself
will redevelop an empty space and it will provide a base for learning
and development for current and future generations.    
• Building strong, safe and resilient communities - The new Paisley
Grammar is not just a school, but a Community Campus a place
that provides space for those in Community, a place of safety and
security that will help nurture and bring communities together.   
• Tackling inequality, ensuring opportunities for all - This project and
the objectives and work that will be achieved has the power to
tackle the inequalities that exist here in Renfrewshire throughout all
communities.  It has the ability to deliver opportunities for all this
could be through Community Benefits and the wider work of the
project.   
• Creating a sustainable Renfrewshire for all to enjoy - In the design,
the main works and the final outcome of the new Paisley Grammar
School Community Campus it will provide a fresh new learning
base for over a thousand young people.  It will give back to the
communities that it serves a new community space to be utilised
and it will create a sustainable energy efficient place for all to enjoy
and be part of. 
• Working together to improve outcomes - The new Paisley Grammar
School Community Campus will improve many outcomes
throughout its lifetime.  This will be through the strengthening of the
partnership working between school and community.  Providing
good quality services and improving new ICT developments and
opportunities.   
4. Legal - The procurement of this contract has been conducted in
accordance with the Competitive Procedure with Negotiation under the
Public Contracts (Scotland) Regulations 2015 and the Council’s
Standing Orders Relating to Contracts. 
5. Property/Assets – The Council identified the construction of a new
Paisley Grammar Community Campus as its learning estate investment
priority in May 2019 and the purpose of this project is to inform the
design of environmentally and economically sustainable buildings. The
Council’s investment in its learning estate offers the opportunity for a

Page 9

place-based approach to local outcomes. integrating local services to
support communities. 
6. Information Technology - No IT implications have arisen or are
anticipated. 
7. Equality & Human Rights - The Recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report because for
example it is for noting only.   If required following implementation, the
actual impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website.   
8. Health & Safety – Galliford Try Construction Limited, T/A Morrison
Construction Scotland health and safety credentials are being
evaluated by Corporate Health and Safety who will confirm that they
meet the Council’s minimum requirements regarding health and safety.
9. Procurement – The procurement procedure outlined within this report
ensures that the Council meets its statutory requirements in respect of
procurement procedures, efficiency and modern government.
10. Risk – Galliford Try Construction Limited, T/A Morrison Construction
Scotland insurances are being assessed and evaluated to confirm that
they have met the minimum requirements regarding insurable risk.
11. Privacy Impact – No Privacy Impact implications have been identified
or are anticipated. 
12. Cosla Policy Position – No Cosla Policy Position implications have
arisen or are anticipated.
13. Climate Risk - Tackling Climate Change and working towards Net Zero
are addressed throughout this contract. The environmental impacts
considered are broad and range from the disposal of waste generated
from the works being carried out to the type of vehicles and machinery
being used on the site. The Contractor will require to consider the
emissions from their vehicles when working on site and to switch
engines off when not in use to prevent unnecessary emissions. The
level of impact associated with provision of these works has been
assessed using the Scottish Government Sustainability Test and is
considered to be overall low risk.
________________________________________________

Page 10

List of Background Papers 
(a) None 
___________________________________________________________________ 
Author:           Joanna Tannock, Assistant Category Manager, Corporate procurement