To: Finance, Resources and Customer Services Policy Board
On: 08 June 2023
___________________________________________________________________
Report by: The Chief Executive and the Director of Finance and Resources
___________________________________________________________________
Heading: Paisley Museum Reimagined Project – Notification of Cost Increases on
technical consultant appointments
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to notify the Finance, Resources and Customer
Services Policy Board, in accordance with Standing Order 20.3 of the
Standing Orders Relating to Contracts, of an increase in cost to the
consultancy contracts listed in item 3.3 of this Report. 
1.2 The original contracts were approved by the Finance, Resources and
Customer Services Policy Board on 28 March 2018. 
1.3 The reasons for the increase in costs are set out in item 3.6 of this Report. 
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Finance, Resources and Customer Services
Policy Board: 
2.1 Note the increase in the approved Contract Sum for: 
i. Paisley Museum Reimagined Project Multi-Disciplinary Design Team
(MDDT) from £2,598,349.00 (excluding VAT) to a revised fee of
£4,164,804.00 (excluding VAT);

Page 2

ii. Paisley Museum Reimagined Project – Project Management from
£193,856.80 to a revised fee of £341,114.00 (excluding VAT); 
iii. Paisley Museum Reimagined Project – Quantity Surveyor from
£258,000.00 to a revised fee of £375,082.31 (excluding VAT); 
2.2 Note the Paisley Museum Reimagined Project Multi-Disciplinary Design Team
(MDDT) contract is now anticipated to complete at the end of January 2024; 
2.3 Note the Paisley Museum Reimagined Project – Project Management contract
and the Paisley Museum Reimagined Project – Quantity Surveyor contract
are both anticipated to complete by the end of May 2024. 
2.4 Note that variations to each of these contracts have been negotiated and
agreed with the respective Consultant in accordance with Standing Orders
Relating to Contracts 34.4 and 34.5. 
3. Background 
3.1 In January 2014 Renfrewshire Council approved the Paisley Town 
Centre Heritage Regeneration Strategy (The Untold Story), setting out 
the need for change to the function and performance of the town based 
on its outstanding heritage and cultural assets. The redevelopment of 
Paisley Museum is the signature project identified within this Strategy. 
The ambition is to create a world class experience for visitors and local 
communities, showcasing the internationally significant collections, and 
embodying the spirit and character of the communities of Renfrewshire 
and the regional connections with the World. 
3.2 The Paisley Museum Re-imagined project team required a series of consultants
including a multidisciplinary design team to prepare the detailed design for the
extension / refurbishment of the building; external project management services
and, external quantity surveyor services to support with the management of the
design and build contracts and the exhibition design and fit out contracts. 
3.3 On 28 March 2018 the Finance, Resources and Customer Services Policy
Board approved the recommendation to award three contracts as follows: 
i. Contract for Paisley Museum Reimagined Project Multi-Disciplinary
Design Team (MDDT) to Amanda Levete Architects Limited in the
Contract Sum of £2,598.349.00 (excluding VAT); 
ii. Contract for Paisley Museum Reimagined Project – Project
Management to Currie & Brown UK Limited in the Contract Sum of
£193,856.80 (excluding VAT); and

Page 3

iii. Contract for Paisley Museum Reimagined Project -Quantity Surveyor
to Gardiner & Theobald LLP in the Contract Sum of £258,000.00
(excluding VAT). 
3.4 Since the three Consultants were appointed, the Paisley Museum Re-imagined
project has encountered several challenges which have led to prolongation of
these external consultant appointments and required the Council to modify
these contracts to instruct additional services. 
3.5 The PMR Project Team have worked closely with each Consultant over the
duration of the project to mitigate the impact challenges have had on the
Consultant’s programme and fees planned for under the respective contract
modification. 
3.6 Summarised below are the key events which have impacted the project. 
 Delay to the overall Paisley Museum Re-imagined project programme
related to Covid-19 pandemic. The progress on the development of the
design slowed down impacted by restrictions on travel and non-essential
construction works and access to the buildings. The PMR project team
worked closely with each Consultant to agree reduced fees which
reflected the actual resource and services for the period affected by the
Covid-19 pandemic. Ensuring the continuity of the Consultant’s team
protected the project resources and allowed the project team to resume
project delivery quickly once Covid restrictions were lifted. 
 Delay to the anticipated completion of the main build programme from
November 2022 to January 2024. This is driven by the complexity of the
works and site discoveries which impact on sequencing of the works and
necessitate changes to the main build design. The Project Team require
the MDDT consultant to amend designs where appropriate. For each
change in scope, the MDDT consultant submits a proposal detailing the
work required and associated fee. This is interrogated by the PMR Project
Team to ensure it is robust, meets the requirements and ensures value for
money. Additional scope changes have also been agreed with both the
Project Management Consultant and Quantity Surveyor for additional
services. 
 The delay in main build programme has also required prolongation of
these external consultant appointments to cover the services required for
the duration of the main build contract this includes cost management
services, project management and contract administration support as well
as design checking, site supervision services.  The majority of the issues
encountered are Employer risk events including the identification of
asbestos containing materials and unforeseen structural and ground
condition complications. The Project Team have worked closely with each
Consultant to agree fees which are reasonable and reflect the activities
required by each consultant at each stage of the programme.

Page 4

 Anticipated delay to completion of the exhibition fit out contract from
November 2023 to May 2024 which is linked to the delay in the main build
programme. There will be prolongation to the Project Management and
Quantity Surveyor contracts to cover this period. 
3.7 The modifications and instruction changes have been fully documented and
approved in accordance with the Change Control process and the project
governance, which requires the approval of the Cultural Infrastructure
Programme Board prior to agreeing the final modifications / changes with each
Consultant for their contract. 
3.8 As a result of the changes noted above, these external consultant fees have
increased by £1,830,785.51 across the three external consultant appointments. 
3.9 The funding for the increase in fees for the external consultant appointments will
utilise existing project resources with the Paisley Museum Reimaged project
which was earmarked for contingencies.  
3.10 This Report is submitted in accordance with Standing Order 20.3 which requires
that where it becomes apparent that the total value of a contract as previously
reported to the Finance, Resources and Customer Services Policy Board is
likely to be exceeded by more than the greater of £100,000 or 25% of the
approved contract value, that a report on the matter be submitted to the
Finance, Resources and Customer Services Policy Board.   
Implications of the Report
1. Financial 
The additional costs outlined in the report will be met from contingency
funding within the existing project budget. Contingency funding is determined
based on an assessment of the total risks inherent in each project and is
anticipated to be sufficient to meet all risk classes. While the current level of
contingency is sufficient to accommodate the costs outlined in the report,
there is an increased risk that the total contingency funding available will be
insufficient to meet all cost pressures which may materialise.
 
2. HR & Organisational Development 
Not applicable.
 
3. Community/Council Planning –
 Reshaping our place, our economy and our future - The contracts will
assist the project team in delivering the strategic aims and outcomes
of the Paisley Museum Reimagined Project and manage and
administer the various design and build contracts for the main build
and exhibition fit out.

Page 5

4. Legal 
The modifications to the external consultant appointments have been made in
accordance with the Council’s Standing Orders relating to Contracts and with
consideration to Regulation 72 (1) (b) of the Public Contract Scotland
Regulations 2015. 
 
5. Property/Assets 
None 
6. Information Technology 
None
. 
7. Equality & Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report.   
 
8. Health & Safety 
None 
9. Procurement 
The modifications were considered in accordance with the Council’s Standing
Orders relating to Contracts and Regulation 72 (1) (b) of the Public Contracts
(Scotland) Regulations 2015. 
10. Risk 
None  
11. Privacy Impact 
No Privacy Impact implications have been identified or are anticipated. 
12. Cosla Policy Position 
No Cosla Policy implications have arisen or are anticipated. 
13. Climate Risk
No climate risk implications have arisen or are anticipated. 
_________________________________________________________
List of Background Papers 
None

Page 6

_________________________________________________________ 
Author:  Rebecca Park, Category Manager – City Deal and Infrastructure,
rebecca.park@renfrewshire.gov.uk