To: Finance, Resources and Customer Services Policy Board 
On: 8 June 2023
___________________________________________________________________ 
Report by: Chief Executive
___________________________________________________________________ 
Heading: Chief Executive’s Service - Service Improvement Plan 2022-23
Outturn Report
___________________________________________________________________ 
1 Summary 
1.1 The purpose of this report is to provide an update on performance of the Chief
Executive’s service for the twelve-month period covering 1 April 2022 to 31
March 2023 in relation to the Service Improvement Plan approved by this
Board in June 2022. 
1.2.  The plan aligns with the new Council Plan and Community Plan and provides
the strategic direction for the service. A new Service Improvement 2023-26 is
being presented to this Board for approval. 
1.3.  The action plan (attached as Appendix 1) is at the core of the Service
Improvement Plan. It sets out the priorities being addressed, the key tasks to
be implemented, the implementation timetable and the measures of success.
The service scorecard (Appendix 2) sets out a range of key indicators against
which performance of the service is measured. This report provides a
summary of performance for both the action plan and the service performance
indicators, which are included as appendices to this report. This outturn report
includes services which were under the remit of the Chief Executive’s service
prior to restructuring at the end of March 2023. 
1.4. The Chief Executive’s service has continued to deliver on its priorities over the
last twelve months and service updates and key achievements are highlighted
in Section 4 of this report.

Page 2

2 
2. Recommendations 
2.1 It is recommended that the Finance, Resources and Customer Service Policy
Board:
(a) Notes the progress made in delivering the Service Improvement Plan in
2022-23; and 
(b) Notes that incomplete actions have been carried over into the new Service
Improvement Plan 2023-2026. 
3. Background 
3.1 The Chief Executive’s service is responsible for setting the strategic direction
of the organisation and for delivering a range of strategic services and
projects.  It also manages the public profile and reputation of the Council and
leads on collaboration with national organisations and partnerships across the
public, private and third sectors.  The service has four main areas of work: 
Policy and Partnerships (previously Policy and Commissioning); Marketing
and Communications; Economy and Development; City Deal and
Infrastructure. 
3.2 The Service delivers a range of provisions and activities, such as: 
 Coordinating Council policy, performance, and data analytical and GIS
activity to support continuous improvement;
 Managing the Council’s reputation through media, marketing and crisis
management; 
 Delivering Renfrewshire’s City Deal and associated infrastructure projects,
including manufacturing sites of national importance;
 Delivering major cultural infrastructure projects including the new Paisley
Learning and Culture Hub and the redeveloped Paisley Museum;
 Co-ordinating the Council’s approach and working with partners to tackle
inequalities which exist across Renfrewshire’s communities, through the
Fairer Renfrewshire programme;
 Leading the development of major initiatives such as harm from Alcohol and
Drugs, leading Renfrewshire to Net Zero, and becoming a Trauma-informed
and Responsive area;
 Delivering an annual programme of major events that attract visitors, deliver
positive economic impact, create volunteering opportunities and increase
cultural participation;
 Leading on Future Paisley, a partnership approach to cultural regeneration
impacting all communities in Renfrewshire;
 Operating Paisley Museum Reimagined Ltd, a registered Charity established
to deliver the capital appeal for Paisley Museum;
 Promoting Renfrewshire as a place to live, work and visit to a national
audience;

Page 3

3 
 Supporting delivery of Renfrewshire’s Economic Strategy and action plan
alongside the Renfrewshire Economic Leadership Panel;
 Delivering a programme of support to Renfrewshire’s business community to
support economic growth and an increase in local jobs;
 Leading on employability for Renfrewshire and supporting unemployed
people into work, including those which are part of the Glasgow City Region
City Deal programme;
 Preparing and updating the Council’s Local Development Plan, our 10 year
land use strategy;
 Receiving and assessing almost 2000 planning applications and building
warrants every year;
 Managing the Council commercial property portfolio;
 Marketing and disposing of surplus property assets;
 Processing Community Asset Transfer applications;
 Leading the Council’s procurement activity to deliver best value, improved
environmental sustainability and wider Council and community benefits (from
1 April 2023, procurement is part of Finance and Resources);
 Working closely with community groups and Local Partnerships to
strengthen relationships and promote community empowerment; and
 Delivering internal communications to build employer brand and maximise
staff engagement. 
4. Key Service Achievements during 2022/23 
4.1 The service progressed a number of projects last year, with the high-level
achievements outlined below.  Details of specific actions are included in the
action plan in Appendix 1 
4.2 The delivery of the AMIDS (Advanced Manufacturing Innovation District
Scotland) site progressed significantly throughout 2022/23. The Medicines
Manufacturing Innovation Centre (MMIC) was the first facility to open at
Netherton in November 2022 and is forecast to bring an estimated £200million
in advanced technology investment in the first 5 years, and 100 initial high-
value jobs. The building of the second of the two anchor facilities, the National
Manufacturing Institute Scotland (NMIS) is now complete and is due to open
in the first quarter of 2023/24.  The City Deal and Infrastructure team has
been working with the Strategic Advisory Group, and a collaborative approach
is allowing NMIS and MMIC to lead on engaging with sector specific
organisations to progress further occupation at the AMIDS site. Planning
consent was obtained in January 2023 to progress the AMIDS South site and
improve transport links between Paisley and the main AMIDS site.

Page 4

4 
4.3 Regeneration work across our towns has continued with key initiatives and
projects supported by the service. The transformation of Paisley town centre
is continuing. Goals such as creating an international culture and heritage
destinations and acting as a stimulus for property investment, development
and reuse have already been realised. The service is now looking at
delivering refreshed strategies for other major settlements in
Renfrewshire.  The first will be in Johnstone, with further updates for Erskine,
Linwood, and Renfrew in the pipeline. 
4.4 There are several significant cultural regeneration projects currently under
construction nearing completion including the restoration of the Museum,
Town Hall and Arts Centre and the creation of a new Culture and Learning
Hub in the High Street. 
4.5 A new Strategic Housing Investment Plan was approved in October 2022
following a period of consultation with residents, stakeholders, registered
social landlords and private developers in August and September 2022. The
plan covers the period 2023 to 2028 and sets out how investment in
affordable housing will be targeted to meet the objectives of Renfrewshire's
Local Housing Strategy whilst meeting current and future affordable housing
supply targets.   
4.6 The Council’s procurement and economic development teams have been
working to engage with local Renfrewshire suppliers in order to increase the
number of Council contracts won by local businesses. The teams hosted an
event at Johnstone Town Hall in November 2022 for local businesses titled
“Doing Business with Renfrewshire Council”. This event provided information
about how to register as a supplier on Public Contracts Scotland, how to
access Council tenders and the range of contracts the Council has on offer
each year and had 58 Renfrewshire-based businesses attend in person. A
follow up event in April 2023 at the Tweedie Hall, Linwood included
presentations from Robertson Acom, a local SME charting their tendering
journey and experiences of working with the Council, and Morrison
Construction, highlighting supply chain opportunities on the upcoming Paisley
Grammar and Community Campus Construction.  This event was attended by
135 people. 
4.7 Renfrewshire’s events programme returned fully in-person during 22/23,
drawing large audiences – over 150,000 attendees, across Paisley Food and
Drink Festival, Renfrew and Barshaw Gala Days, Sma Shot Day and Renfrew
Pipe Bands,

Page 5

5 
The Spree, Spree for All and Wee Spree, Paisley Halloween Festival,
Remembrance and Christmas events. In addition, the team have continued to
drive delivery of Future Paisley, a partnership approach to cultural
regeneration in Renfrewshire, providing £360,000 of funding for local groups
and cultural organisations, and delivering a range of interventions targeting
children and families, care experienced children and young people, criminal
justice and adult health and social care. 
4.8 During 2022/23, the fundraising strategy for Paisley Museum continued to
attract significant commitments from Trusts and Foundations, Corporates and
individual donors. Almost £1.2 million has been secured from pledged and
received income.  Of this total, £965,600 has been secured from Trusts and
Foundations, £59,493 from corporate income and £168,016 from individuals,
including Gift Aid. A targeted campaign to drive Corporate fundraising was
launched in March 2023. 
4.9 The service continued to provide strategic leadership to support the Council’s
goal of working towards Net Zero by 2030. A key element of Renfrewshire’s
approach is a just transition with community collaboration to ensure no one is
left behind. The service led on the development and approval process of
Renfrewshire’s Plan for Net Zero.  In June 2022, the Planning and Climate
Change Policy Board approved the award of just over £49k from the
Community Climate Fund to support 18 community projects. These projects
are located across all 7 Local Partnership Areas and deliver across the 5 key
themes within Renfrewshire’s Plan for Net Zero. Projects include a number of
areas of unused or neglected land being transformed into community gardens,
play areas or parks, a project focused on repairing clothes that would
otherwise go to landfill, and a project focusing on reducing food waste. 
4.10 The team also continues to support and implement work to address the
recommendations of the Alcohol and Drugs Commission Report. The change
programme has work to: Reduce risk of harm, such as the new My Life Ahead
programme providing wraparound support for sustainment and the Harm
Reduction Response Team; Mental Health such as the new Trauma informed
and Responsive Renfrewshire programme; prevention and early intervention
such as revising partners substance use policies; and Recovery, such as the
peer worker model which involves people with lived experience supporting
recovery, and  the Connected and Caring Renfrewshire programme of
activities and local events. The launch of the Recovery Change Fund has also
enabled local groups to fill any gaps in provisions and provide projects in their
local communities.

Page 6

6 
4.11 The service has worked throughout 2022/23 to support communities through
the cost-of-living crisis, particularly with food and fuel insecurity. The Council
has invested £4.4million in a range of initiatives, including £600,000 into a
programme to provide financial insecurity payments to cover fuel and
essentials, £100,000 for a fuel emergency support and advice pilot delivered
with third sector partners, and £50,000 into the Community Food Fund for
local community food initiatives. Our Winter Connections programme was
allocated £70,000 for community groups to deliver winter activities and a
further £10,000 for OneRen. The Tackling Poverty Programme funding has
continued to deliver cost of the school day funding, funding for Energy
Advocates to provide savings advice, and the provision of additional resource
to Street Stuff to provide meals and activities for children in the evenings,
holidays and weekends. 
4.12 The Marketing and Communications team has been working to increase the
positive news stories surrounding Renfrewshire and the Council, with several
successes in 2022/23. Positive coverage about the events festival, including
the Paisley Food and Drink Festival, The Spree, Sma’ Shot Day, Paisley
Halloween Festival were featured in a number of newspapers, with total
opportunities to see or hear something positive about the area reaching over
30 million over the year. 
5. Actions that have been delayed or cancelled 
5.1 The work on active travel remains in development and some elements are
already complete.  Additional phases are being brought forward as funding
becomes available and this action will be carried forward into the new Service
Improvement Plan.
5.2 Work on the regeneration of prominent buildings in our town centres will also
be carried forward as the service continues to proactively seek out
opportunities to work with property owners on regeneration opportunities.
5.3 A refreshed approach to corporate self-assessment was developed during
2022/23 and workshops continue to take place; this action will carry over into
2023/24. Work to refresh the Council’s Performance Management Framework
will also progress to December 2023, and will align to the new Council and
Community plans.
5.4  Some of our Community Empowerment work will continue into this year, such
as progressing the development of local partnerships to encourage local
community participation, as well as the huge task to mainstream Participatory
Budgeting across the Council with the development of a Participatory
Budgeting Framework.

Page 7

7 
6. Progress against performance measures 
6.1 The Chief Executive’s Service has a total of 36 performance indicators, 25 of
which are measured quarterly and 10 of which are measured annually.  Seven
indicators were new last year and therefore have no set targets until a
baseline can be established. Of the 29 indicators with targets, 17 met or
exceeded target, 8 missed the target and four do not have data yet available
for last year. 
6.2 The service exceeded many measures of positive progress last year, including:
 
 1,370 new people registered with the Employability Service, INVEST
 538 people were supported into paid employment
 206 new businesses were supported by Business Gateway to start up 
 151,000 people attended the events programme
 69,287 people are engaged with Council social media/ digital channels 
6.3 Renfrewshire Council’s Employability Programme, INVEST, continued to
provide employment and training support, with the team supporting 1,370 new
registrations to the service throughout the year, 538 people into paid
employment and 340 into sustained work after 6 months following support
from the service. A further 507 people were supported to secure qualifications
which could help them in seeking paid, or higher paid work through the
service. 
6.4 The service supported existing and new businesses throughout the year, with
the Business Gateway service supporting a total of 206 new businesses to
start up through the year. The total number was fewer than the 272 supported
last year reflected in a fall in start-ups across the country due to economic
uncertainty but there are early signs that numbers are increasing again. 
Additionally, 350 local businesses were supported with growth advice, training
or grants in 2022/23, and 89 Social Enterprises were supported to develop,
grow, or generate new income with the support of the team. 
6.5 As noted in Section 4, the events programme was very successful throughout
the year, with the level of interest suggesting a desire for live events following
recovery from the pandemic. The events programme attracted a total of
151,000 people which far exceeded expectations and was more than double
the target for the year. Additionally, there were 3,140 participating in events
over the year and 42 volunteers.

Page 8

8 
6.6 The experience of our customers is important to the service with ongoing
efforts to improve this. A review of the Council website is underway in order to
modernise content and design and make it more user-friendly. Engagement
with the Council’s digital channels reflect these efforts with the number of
people engaging at 69,287 at the end of 2022/23 period, growing from 64,822
the year before. 
6.7 Targets remain challenging in some areas of service. The number of new
business start-ups supported by Business Gateway has been impacted by the
current economic conditions, with fewer people choosing to start new
businesses. However, there was an increase in Quarter 4 which also
compares favourably with the same period in 2021/22. 
6.8 The time taken to issue first reports and building warrants is not meeting
targets at present - this is linked to resource pressures. An increase in the
average time taken to process planning applications was also due to short-
term staffing issues. Recruitment and retention in these areas of work remains
a challenge nationally, due to competition for skills from the private sector. 
7. Monitoring progress 
7.1 Progress on the implementation of the new Service Improvement Plan for
2023-2026 will be monitored by the extended Senior Leadership Team and
reported to the Finance, Resources and Customer Service Policy Board on a
six-monthly basis.  A mid-year review of progress will be brought to this Board
in Autumn/ Winter 2023, with an annual report in Spring 2024.   
Implications of the Report 
1. Financial – The Service Improvement Plan highlights resourcing pressures
arising from increasing demand for services and the current financial
environment.  
2. HR & Organisational Development – The Service Improvement Plan highlights
workforce development and wellbeing considerations.
3. Community/Council Planning – The report details a range of activities which
reflect Council and Community Planning themes and a direct link to the delivery
of the Council Plan.
4. Legal – none.
5. Property/Assets – none.

Page 9

9 
6. Information Technology – Service developments relating to information
technology are key enablers of service improvement and modernisation and
support service-level and corporate objectives.
7. Equality & Human Rights – The recommendations contained within this report
have not been assessed in relation to their impact on equalities and human rights
because it is a performance report on past actions. Assessments will be
undertaken on activities relating to individual actions, as required.
8. Health & Safety – none.
9. Procurement – none.
10. Risk – Risks related to the delivery and management of services are regularly
monitored and included in Renfrewshire Council’s Corporate and Strategic Risk
Registers. 
11. Privacy Impact – none. 
12. COSLA Policy Position – none.
13. Climate Change – Actions and indicators within the Service Improvement Plan
under the ‘green’ theme highlights how the service will contribute Council
activities to mitigate climate change. 
___________________________________________________________________ 
List of Background Papers:  None
___________________________________________________________________
Author:  Seony Ross, Senior Planning & Policy Development Officer
Contact:  Seony.Ross@renfrewshire.gov.uk or 0141 487 1548

Page 10

10 
Appendix 1:  CE SIP 2022-25 Actions 
 
Council Plan Theme 1: Place 
Code Title Status Assigned To Progress Due Date Latest Note
CESDP21 - 01 - 11 Pilot and test the creation of
active travel routes between
neighbourhoods, town
centres and business
locations using these to test
SMART travel solutions and
evaluate benefits to
biodiversity, air quality and
access 
Regeneration Manager 60% 31-Mar-2023 Work has advanced on a number of routes. The
Renfrew-Paisley Cycleway is on site; construction
works along Greenock Road, Inchinnan are now
complete as per the original scope and provide a
sustainable transport option between AMIDS and
Inchinnan Business Park. The new road infrastructure
around GAIA was completed last year.
LUF funding for new transport infrastructure between
AMIDS and Paisley includes extensive active travel
provision.  Work is currently in progress in developing
these proposals further. 
Stantec have completed a study which identified
further phases and designs of active travel
infrastructure to economic locations for delivery as
funding becomes available.  E&I are now prioritising
projects from this report.  
E&I are also delivering on a number of projects
identified in the Council’s Cycling Strategy.  There are
several cycling infrastructure projects which are
currently at concept design /public consultation design
stage. The routes for these are –

Page 11

11 
1.Southolm Roundabout Erskine 
2.Linside Avenue 
3.Hawkhead Rd/ Glasgow Rd junction  
4.Linclive Roundabout
5. Inchinnan Business Park
6. Barnsford Road, Glasgow Airport.
CESDP21 - 01 - 13 Deliver on the ambitions of
our town centre strategies
and specifically working
with partners to transform
Paisley Town Centre
through the Paisley Town
Centre Action Plan 2016-
2026. 
Regeneration Manager 85% 31-Mar-2025 The transformation of Paisley on the back of the
Action Plan is advancing at pace.  Goals such as
creating an international culture and heritage
destination and acting as a stimulus for property
investment, development and re-use has already
been realised.  
There are a number of significant regeneration
projects currently under construction nearing
completion including the restoration of the Museum,
Town Hall and Arts Centre and the creation of a new
Culture and Learning Hub in the High Street. 
The publication of the Paisley Vision document will
also act as a further catalyst to inspire future
development in and around the town centre. The
Liberal Club, which was identified as a key building in
the Vision, is currently under restoration, securing its
long-term status. 
The Regeneration Team will be looking to refresh our
town centre strategies to reflect changes that have
taken place in a post pandemic environment.  These
Strategies will align with the guidance and principles
outlined in NPF4.  We await the publication of
applicable supplementary guidance.  In the meantime,
work has been ongoing in respect of outlining
potential regeneration priorities and projects.  This
includes commissioning visioning work in Johnstone,
a review of potential projects in Erskine and the
submission last year of a bid to the Levelling Up Fund
in respect of a project in Renfrew.  The team will
continue to bring forward regeneration proposals
across our town centres.  This action carries forward

Page 12

12 
into the new Service Improvement Plan but has been
widened in scope.
CESDP21 - 01 - 15 Proactively work with
property owners to bring
some of the area’s most
valued assets back into use 
Regeneration Manager 75% 31-Mar-2025 The Council have been proactive in seeking out
property owners of prominent buildings within our
town centres in respect of potential regeneration
opportunities.
This includes the potential redevelopment of the
Paisley Centre into a thriving mixed-use development.
Recent and ongoing investment in a number of listed
buildings includes St Matthew’s Church, County
Place, 5 George Place and the Liberal Club.  These
have been facilitated with in-depth discussions with
the respective owners.  The goal is to get these
buildings back into use.
CESDP21 - 01 - 27 Monitor benefits of City
Deal Projects, including
Glasgow Airport Investment
Area, Clyde Waterfront and
Renfrew Riverside and City
Region wide employment
programmes 
Programme Director, City Deal
and Infrastructure
80% 31-Mar-2025 Clyde Waterfront & Renfrew Riverside
Community Benefits:
110 of 150 community benefits have been delivered to
date. The remainder are on track/have been re-
baselined to be completed as part of the project
lifespan.
Project Benefits:
Project is advancing with construction work now
moving at pace and all expected benefits in terms of
infrastructure, economy and wider regeneration on
track.
Glasgow Airport Investment Area
Community Benefits:
All 70 community benefits have been delivered.
Project delivery is closed and now moved to defects
management period. The infrastructure in place has
allowed the progression of the AMIDS site to take

Page 13

13 
place with key link road throughout and new
connecting bridges opened.
CESIP22.01.01 Establish a programme of
engagement work with
communities on the
Community Benefits that
might be derived from the
Council’s procurement
activity. 
Strategic Procurement Manager 35% 31-Mar-2024 The procurement team continue to work closely with
Engage Renfrewshire to capture the views of
Renfrewshire based Social Enterprises and
community groups in our approach to community
engagement community benefits.
The procurement manager, working with colleagues in
Economic Development continues to review web
based platforms offered by public sector bodies to
support delivery of targeted community benefits. 
Current collaboration includes sharing of information
and best practice with NHS National Procurement.
Procurement officers have also asked if they could
attend community forums established by other
services to talk to them about community benefits, to
explain what can be offered by contractors and to
provide information about how these opportunities can
be accessed.
CESIP22.01.02 Maximise funding for
regeneration of
Renfrewshire’s places
through grant submissions
to external sources
including UK and Scottish
Governments. 
Regeneration Manager 100% 31-Mar-2023 The Regeneration and Place Team have successfully
been able to secure and receive funding through
various external sources.  Between 21/22 and 25/26
we have been allocated £4.4m from the Place Based
Investment Fund for capital regeneration projects.
Between 22/23 and 24/25 we have received £1.5m in
funding for capital and revenue regeneration spend
from the Shared Prosperity fund. This will be used for
various projects, including providing capital/revenue
money to supplement the upcoming Sustainable
Communities Fund.  It will also be used to develop
and deliver a number of projects identified in Ferguslie
Green Line Masterplan.
The council has consistently been successful in
RCGF funding applications.  The most recent

Page 14

14 
successful application received £1m in funding for the
PACE theatre project.
Last year the team secured £35k in funding from Visit
Scotland to develop a strategic Tourism Infrastructure
Development Plan for Clyde Muirshiel Regional Park.
This year the team is looking to submit bids to the
Scottish Government’s RCGF and Vacant Derelict
Land Fund for potential projects in the Ferguslie area.
The team are continuing to have dialogue with Historic
Environment Scotland and the National Lottery
Heritage Fund in respect of a future bid for funding for
heritage schemes around Johnstone/Kilbarchan.
CESIP22.01.03 Develop a Strategic
Property Review of Council
operational, non-operational
and surplus assets 
Regeneration Manager 75% 31-Mar-2023 The review is ongoing and is now being led by
Environment, Housing and Infrastructure. 
CESIP22.01.04 Carry out evaluation of
Future Paisley and prepare
a transition plan for the
mainstreaming/external
funding of projects beyond
April 2024. 
Head of Marketing and
Communications
75% 31-Mar-2024 The Evaluation Framework was completed in
December 2022 and rolled out to all Project Leads in
January 2023. Additional resources have been put in
place to support Project Leads using the Evaluation
Framework effectively, empowering them to clearly
evidence the impact of the activity and how it aligns
with Future Paisley’s strategic objectives. This
mechanism enables the collection and analysis of
data which will demonstrate the impact made from
Future Paisley’s investment. As part of the rollout of
the Evaluation Framework, Future Paisley continues
to support Project Leads through ongoing 1-2-1
sessions, online training on how to navigate the
framework, and a Library of Resources offering
additional source material. Projects to be investigated
through case studies have been confirmed with two
now completed, which have focused on the Glen
Cinema Commemoration and the Open Mind Summit
respectively, with CCSE PhD research being applied.

Page 15

15 
Step Change 2 and 3 activity is being prioritised due
the nature of interventions, and the challenge in
establishing long-term cumulative impact. The review
and evaluation of individual Future Paisley funded
projects and activity is ongoing, with project details
being uploaded to create a Future Paisley Dashboard
that offers ‘at a glance’ overview of activity.
CESIP22.01.05 Expand destination
marketing to promote
Renfrewshire as a visitor
and investment destination,
maximising audience and
product intelligence and
ensuring brand relevance
for all of Renfrewshire. 
Marketing Manager 100% 31-Dec-2023 The destination marketing plan for 2022 was
successfully delivered. An overview of the activity is
provided below:
• Planning and implementation of the summer 2022
visitor campaign which promoted a Renfrewshire-wide
visitor offer. The campaign ran June ‘22 - 30
September ‘22.  The final marketing evaluation
delivered the following results: 
o 5.1 million paid-for opportunities to see and
hear (OTSH) summer campaign messaging
o 57K website page views (campaign pages
and blogs)
o Visit section +120% compared to 2019
o Homepage +61% compared to 2019
o Social media totals - Reach/Impressions:
111,377. Engagements: 2,210
• Paisley.is was awarded a total of £56,000 from the
VisitScotland Destination and Sector Marketing Fund
to help drive tourism recovery and encourage footfall
to Paisley Town Centre. The ‘Paisley.is Calling’
marketing campaign ran from December 2021 to
September 2022 to increase visits to Paisley Town
Centre and subsequent visitor spend and dwell time.  
• Campaign evaluation was presented to VisitScotland
in September 2022, and included data from the Moffat
Centre’s Visitor Attraction, which reported an increase
in visits to Paisley attractions of 237.6% in 2022, year-
to-date compared to August 2021 (impact of Covid19
restrictions), and an increase in visits of 6.7% in
August alone, compared with the previous year. STP

Page 16

16 
hotel occupancy data highlighted an increase in hotel
occupancy from 59% in July 21 to 91% in July 22. In
addition, the reach of the marketing campaign was
also measured:  Throughout the year, marketing
campaigns were delivered to support the Council’s
major events programme.
The overall Paisley.is evaluation statistics for Year
5 (1 April 2022 – 31 March 2023): 
• Opportunities to see and hear – 204,403,562 
• Social media reach – 2,960,472 
• Webpage visits - 574,374 
CESIP22.01.06 Successfully deliver the
Capital Appeal for Paisley
Museum Reimagined Ltd. 
Head of Marketing and
Communications
35% 31-Mar-2024 To-date, £1,193,109 has been secured from pledged
and secured income. £965,600 has been secured
from Trusts and Foundations, £59,493 from corporate
income and £168,016 from individuals.  Future focus
will be to increase corporate donations and support
from high net worth individualsI.
CESIP22.01.07 Lead development of a new
event strategy for
Renfrewshire, expanding
programming across
Renfrewshire and
undertaking work to
understand the social
impact of events for
Renfrewshire communities 
Events Manager 50% 31-Dec-2023 The 2022/23 programme was fully delivered through
Q1/Q3, evaluation data is now available for the 2022
programme of local and visitor events and will be used
to shape the development of the new events strategy.
A review of each event and the social and economic
impacts delivered will be produced in spring to allow
the development of a new events strategy and revised
events programme.
CESIP22.01.08 Participate in and Monitor
progression of the Clyde
Metro in partnership with
GCC, TS and other
stakeholders. 
Programme Director, City Deal
and Infrastructure
5% 31-Mar-2025 GCR Project team now liaising with UK Infrastructure
Bank on project to accelerate project outcomes.

Page 17

17 
 
Council Plan Theme 2: Economy 
 
Code Title Status Assigned To Progress Due Date Latest Note
CESDP21 - 01 - 02 Develop a refreshed
employability programme
for Renfrewshire (utilising
Youth Guarantee and
Kickstart funding) to reduce
unemployment among
young people (18-24 yrs.)
and to support local
businesses 
Economic Development Manager 100% 31-Mar-2023 Both Youth Guarantee and Kickstart have now
completed. We have a very well performing
employability service and this will continue to support
unemployed people into work.
CESDP21 - 01 - 03 Support and grow supply
chain management and
knowledge exchange
among manufacturing
SMEs to supply Scottish /
UK businesses and global
supply chain 
Head of Economy and
Development
100% 31-Mar-2023 The creation of a supply chain management
programme for manufacturing SMEs is a priority to
support economic recovery in Renfrewshire. In
progressing this, partners (SE, Chamber, NMIS group
and WCS) agreed to create a new a Manufacturing
Business Forum.
This work continues forward and will be augmented by
a refocus on key growth sectors supporting the ELP
and development of an account management
process.
As part of a recent growth sector study we
commissioned, a need for a better understanding of
local businesses and their supply chains in
Renfrewshire was noted.  
A key recommendation was the need for these supply
chains to be mapped and active collaboration with
organisations such as NMIS and MMIC is

Page 18

18 
Code Title Status Assigned To Progress Due Date Latest Note
required.  Economy and Development will be looking
into actioning this.
CESDP21 - 01 - 09 Promote a Renfrewshire
Apprentice Framework that
can be rolled out across
local businesses wishing to
participate 
Economic Development Manager 100% 31-Mar-2023 Now business as usual, we will continue to promote
and deliver apprenticeships.
CESDP21 - 01 - 26 Work with partners to
deliver the Advanced
Manufacturing Innovation
District – Scotland (AMIDS) 
Programme Director, City Deal
and Infrastructure
90% 31-May-2023 The first two centres of employment are significantly
progressed with occupation of the 1st now completed
in late 2022 and the other due for completion shortly.
Procurement of a joint venture partner for the
remaining AMIDS site is nearing completion, with
agreement anticipated May 2023. A strategic group
has been established with key stakeholders informing
progression of development. The key enabling
infrastructure is now complete together with new
public realm space.
CESIP20 - 01 - 07 Participate fully in all
aspects of the new National
Manufacturing Institute
Scotland (NMIS)
Governance arrangements
and Medicine
Manufacturing Innovation
Centre (MMIC) delivery. 
Programme Director, City Deal
and Infrastructure
100% 31-Mar-2023 Renfrewshire Council has strong links with NMIS and
MMIC as they are represented on the NMIS One
Scotland Collaboration Group and chair the AMIDS
Strategic Advisory Group with both organisations
represented. CD&I team members work closely with
both organisations daily and continue to assist with
the commissioning of their buildings. MMIC building is
already operational with NMIS now build complete
and in fit out phase, expected to open in June 2023.
Work has progressed with the Strategic Advisory
Group to ensure partnerships are in place and a
collaborative approach is allowing NMIS and MMIC to
lead on engaging with sector specific organisation to
hopefully progress to further occupation at the AMIDS
site.

Page 19

19 
Code Title Status Assigned To Progress Due Date Latest Note
CESIP22.02.01 Progressing the AMIDS
South project to maintain
the programme
requirements of the UK
Government Levelling Up
Fund award. 
Programme Director, City Deal
and Infrastructure
20% 31-Mar-2025 Planning consent obtained (Jan 2023). Liaison with
stakeholders and continuing development of detailed
designs ongoing in advance of construction tender
issue during 2023. Dialogue with UK Government
agencies continuing on all aspects including delivery
programme.
CESIP22.02.02 Actively engage with
Renfrewshire suppliers to
increase the percentage of
procurement spend 
Strategic Procurement Manager 75% 31-Mar-2024 The procurement team and Economic Development
team co-hosted an event at Johnstone Town Hall on
29 November 2022 for local businesses titled “Doing
Business with Renfrewshire Council”.  58
Renfrewshire based businesses attended this in
person event which provided information about how to
register as a supplier on Public Contracts Scotland,
how to access council tenders and the range of
contracts the council has on offer each year.
A follow up event took place on 18 April 2023 at the
Tweedie Hall, Linwood.  This event was advertised
widely across Renfrewshire and beyond.  As well as
providing a presentation about first steps for bidding
for contracts, presentations were also delivered by
Robertson Acom – a local SME charting their
tendering journey and experiences of working with the
Council - and Morrison Construction, highlighting
supply chain opportunities on the upcoming Paisley
Grammar and Community Campus Construction.  The
event, attended by 135 people also offered workshops
for Renfrewshire SME’s assisting them with
registering on Public Contracts Scotland.  
 
Council Plan Theme 3: Fair

Page 20

20 
Code Title Status Assigned To Progress Due Date Latest Note
CESIP22.03.01 Develop the new Fairer
Renfrewshire programme 
Strategic Partnerships and
Inequalities Manager
65% 31-Mar-2025 The Fairer Renfrewshire Sub-Committee has been
meeting since August 22 and a Fairer Renfrewshire
Officers Group made up of officers from across
services is meeting monthly. Work with partners to
develop the Fairer Renfrewshire Programme is
ongoing. There are four key emerging themes which
are shared across all elements of the programme, and
these are:
• Improving financial security 
• Advancing equality of opportunity 
• Building community capacity and resilience 
• Listening to lived experience 
Funding has been allocated from the Fairer
Renfrewshire budget to a number of projects to
support residents with immediate Cost of Living
increases. These include supports around food, fuel
and advice. Work is also ongoing around digital
access and supporting residents to get online through
the Citizen Voice group, with a new post of Digital
Champion in libraries has been recruited. Our Winter
Connections programme was set up to support
residents over the Winter 22/23 period, and has
provided grants to a number of organisations to run
activities.  The development of a panel of people with
lived experience of poverty to inform the Council’s
policy and practice is ongoing. A diverse panel has
been recruited and have met formally six times, with
test of change being evaluated by Poverty Alliance.
In addition, officers are undertaking a ‘deep dive’ child
poverty data exercise, to support the Local Child
Poverty Action Plan as well as the wider Fairer
Renfrewshire programme.
CESIP22.03.02 Develop and implement the
action plan for the Trauma-
Head of Policy & Partnerships 30% 31-Mar-2024 A coordinator post has been created to lead this
programme of work going forward, with the

Page 21

21 
Informed and Responsive
Renfrewshire Programme.
coordinator starting in late October 2022. Further
engagement with the Improvement Service and other
local authorities has taken place through national
networks for trauma champions and trauma leads,
and the steering group reconvened in March 2023 to
further explore the draft plan for the Programme.
Leadership training for the Corporate Management
Team was also undertaken in March 2023.
CESIP22.03.03 Deliver the
Stigma/Language Matters
project. 
Head of Policy & Partnerships 20% 31-Mar-2024 The work of the Alcohol and Drugs Commission
identified the need for partners to act robustly to
eradicate stigma and promote positive conversations
around recovery. Although the initial focus for this
initiative was focused on alcohol and drug stigma,
there is the opportunity to widen its scope to include
other existing and emerging priorities, such as The
Promise, Tackling Poverty, Trauma Informed and
Responsive Renfrewshire and Our Values for
example. High level themes and initial actions have
been identified, including supporting staff to
understand the power of language, be confident in
their use of language, and to challenge stigma by
speaking up when people make negative or wrong
comments; and supporting national campaigns to help
people in Renfrewshire understand the power and
impact of language. A review of the resources
required to deliver this project is currently underway.
CESIP22.03.04 Progress the next phase of
Local Partnerships
development 
Strategic Partnerships and
Inequalities Manager
40% 31-Dec-2023 An initial internal review was undertaken in 2022 and
a paper will be submitted to the Leadership Board
June 2023 to set out process for full review during
remainder of 2023.  
The due date will be revised from 31 March 2023
2023.

Page 22

22 
CESIP22.03.05 Deliver a framework that
ensures that 1% of council
spend is now determined
through participatory
budgeting. 
Strategic Partnerships and
Inequalities Manager
30% 31-Mar-2024 This year £1.2M was allocated by Environment &
Infrastructure through their #Youdecide programme.
Housing and Regeneration teams are participating in
training with COSLA for the use of the CONSUL
platform which will support PB activity in the four
housing regeneration areas, this is ongoing. £25k has
been approved for a pilot in Johnstone for the
Christmas event. This work is at the early planning
stages.
The due date has been revised from, 31 March 2023
CESIP22.03.06 Develop and implement
targeted interventions to
supporting communities
through the cost-of-living
crisis, with a particular
focus on food and fuel
insecurity 
Strategic Partnerships and
Inequalities Manager
100% 31-Mar-2023 The Community Food Fund has supported community
food provision across Renfrewshire. Three allocations
of funding have been made to the Fuel Insecurity Pilot
which continues to support fuel vouchers augmented
with energy advice and the increase in payment
amount and continuation of the Financial Insecurity
Winter Payment supports households who are
struggling to purchase essentials like food and fuel. In
addition, the Tackling Poverty programme continues
to support an Energy Adviser in the Energy
Management Unit.
CESIP22.03.07 Develop mechanisms for
supporting individuals with
lived experience of poverty
to influence policy in this
area. 
Strategic Partnerships and
Inequalities Manager
100% 31-Mar-2024 The development of a panel of people with lived
experience of poverty to inform the Council’s policy
and practice is ongoing with Poverty Alliance and
STAR Project being contracted to organise, chair
facilitate and support the panel. A diverse panel of 15
people has been recruited and have met formally six
times, as well as meeting in-between panel meetings
to debrief and develop the work alongside a
community artist to create a record of their
experience. Initial meetings with Officers and Elected
members have been held to commence the panel’s
input to policy.
Work is also underway to plan an event which will
bring the Panel together with the Fairer Renfrewshire

Page 23

23 
Sub-Committee to discuss the Panel’s deliberations
and recommendations.
An evaluation of the process has also been carried
out by Poverty Alliance to explore how these types of
participation processes can inform work going
forward, and to inform the development of the model
moving forward. Officers are currently undertaking
contract arrangements to extend the existing panel
arrangements for a further year.
CESIP22.03.08 Undertake a
recommissioning exercise
for the provision of
independent advice
services in Renfrewshire. 
Strategic Partnerships and
Inequalities Manager
100% 31-Mar-2023 The contract for advice services has been
renegotiated with Renfrewshire Citizens Advice
Bureau, with the agreed contract running until 30 June
2025 with the option to extend for one year. This
contract has been approved and commences on 1
July 2023.
CESIP22.03.09 Carry out an evaluation of
the Tackling Poverty
programme and develop a
transition plan for
mainstreaming this work. 
Strategic Partnerships and
Inequalities Manager
40% 30-Sep-2023 Work commenced in Q2 and initial projects identified
for evaluation. This work is ongoing with PMU support.
CESIP22.03.10 Support local strategic
activities which facilitate the
integration refugees and
asylum seekers across
Renfrewshire. 
Head of Policy & Partnerships 100% 31-Mar-2023 The Policy & Partnerships Team continue to support
other council services with the delivery of refugee,
UDP and UASC programmes.  A current priority is
support for the Ukrainian Displaced Persons scheme.
CESIP22.03.11 Bring forward actions to
reduce health inequalities,
improving economic
participation, more secure
earnings and greater
earning power. 
Economic Development Manager 100% 31-Mar-2024 The Health Inequalities Group has met regularly and
recently provided an update report to the LEP on
where additional service requirements were being
identified. 
The Employer Recruitment Initiative has now been
launched, new disability services contracted and in
place, and new initiatives have been identified and will
be delivered for the next 2 years via funding secured.

Page 24

24 
CESIP22.03.12 Launch a new council
website –
Renfrewshire.gov.uk – and
implement the digital
experience strategy,
transforming how citizens
interact with the council
across digital platforms. 
Communications & Public Affairs
Manager
60% 31-Oct-2023 The Alpha phase of development has completed.
• Testing of the long-term technical solution and
its integration across existing systems 
• Delivery of new.gov.uk designs and pattern
library 
• Testing and delivery of a new user-centred
design process to make services more efficient 
• Procurement strategy for the Live phase (inc
web build) 
• Timeline for the next phases prioritising high
usage and high impact services 
• Recruitment of the wider DXP team 
 
Council Plan Theme 4: Green 
Code  Title Status Assigned To Progress Due Date Latest Note
CESIP22.04.01 Complete the District
Heating Network at AMIDS,
with supplies to NMIS and
MMIC. Develop the first
stage of Renfrewshire’s
Plan for Net Zero 
Programme Director, City Deal
and Infrastructure
100% 31-Mar-2023 First phase of Project now complete with heat
supplied to first two AMIDS occupiers. 
CESIP22.04.02 Develop the first stage of
Renfrewshire’s Plan for Net
Zero 
Strategy, Policy and Insight
Manager
100% 31-Dec-2022 The Plan for Net Zero was developed in partnership
with other services, stakeholders and our citizens
through Renfrewshire’s Climate Panel. The Plan was
approved by the Planning and Climate Change Policy
Board on 23rd August.
The next steps include the development of a child-
friendly and an easy read versions of the Plan and a

Page 25

25 
detailed phased road map, including quantified
delivery plans.
CESIP22.04.03 Ensure that climate
considerations are taken
into account in our
procurement strategies and
tenders with a focus on
reducing emissions. 
Strategic Procurement Manager 100% 31-Mar-2025 The contract strategy template provides an
opportunity for procurement officers to identify
opportunities to help tackle the climate emergency
and maximise opportunities to achieve energy
efficiency and carbon reduction.
CESIP22.04.04 Implement a plan for
managing supply chain
disruption arising from
external events 
Strategic Procurement Manager 100% 31-Mar-2023 A risk management approach is taken to all critical
contracts.  The procurement team contract-manage
key suppliers and monitor markets to identify risks
associated with volatility.
 
Council Plan Theme 5: Living Our Values 
Code  Title Status Assigned To Progress Due Date Latest Note
CESIP22.05.01 Undertake a corporate self-
assessment exercise in line
with revised best value
audit methodology 
Strategy, Policy and Insight
Manager
75% 31-Dec-2023 The approach and model were agreed by the
Corporate Management Team and the survey element
of the CSA has been completed. Follow up workshops
are scheduled to take place early next quarter, and
then a consideration around how to take self-
assessment activity forward more generally in light of
the revised best value audit methodology. As a result,
this action has been carried forward into the new SIP
with the due date revised to 31 December 2023.  
CESIP22.05.02 Review and refresh the
Council’s performance
management framework 
Strategy, Policy and Insight
Manager
75% 31-Dec-2023 All services are being supported by the policy team to
update their performance indicators and targets as
required. This work also fed into the development of a

Page 26

26 
new Council Plan scorecard, which was approved at
Leadership Board in November 2022.
Sitting alongside this, a new CMT scorecard is being
developed, with a new quarterly performance focus at
CMT and we are also reviewing how we present
performance data to ensure this is accessible for all
audiences – elected members, employees, citizens
and partners.
Work on this continues and will continue into the new
SIP term, with a due date of 31 December 2023.
CESIP22.05.03 Lead implementation of the
council brand, prioritising
tone of voice, inclusive
communications and
audience insights 
Head of Marketing and
Communications
40% 31-Mar-2025 Work is ongoing to increase visibility and access to
the council’s brand toolkit and embedding its
consistent use across services.
Brand narrative is successful embedded in the
council’s man strategic documents and the use of
approved corporate templates is increasing through
self-serve.
Audience segmentation work is underway to deliver
up-to-date insights into the local Renfrewshire
audience that will help to maximise the reach and
impact of marketing and communication activity.
Further work continues to refine the brand colour
palette to meet triple A web content accessibility
requirements.
Review of the council services written communication
with residents is underway, to ensure they meet the
council’s agreed Tone of Voice and reflect the council
values.
Standardised corporate, place and service
information, has been developed to support council
recruitment.

Page 27

27 
CESIP22.05.04 Lead implementation of
strategic communications to
support the council’s
financial strategy 
Head of Marketing and
Communications
100% 31-Mar-2023 Phase 1 – a public and staff campaign to raise
awareness of the council’s financial challenge, linked
to Cost-of-Living support ran in autumn 2022.
Campaign reach exceeded 100,000. Phase 2 -
communications to support the 23/24 budget process
were delivered in February 2023.
Work to support the council’s budget strategy will
continue in 23/24.
CESIP22.05.05 Undertake a workforce
planning exercise across
procurement to address
challenges in recruitment
and retention 
Strategic Procurement Manager 100% 31-Mar-2023 The majority of long-standing vacancies have now
been filled.  The procurement team are implementing
the national procurement competency framework to
identify training needs and develop career plans with
the team.
CESIP22.05.06 Undertake CIPS self-
assessment activity. 
Strategic Procurement Manager 100% 31-Mar-2023 The corporate procurement team have completed
individual self assessments using the national
procurement Competency Framework.  The basis of
this self assessment has provided information which
allowed the procurement manager to offer tailored
support to the team in the form of professional
development, coaching and access to CIPS.
The education / training and development programme
will continue into 2024 and beyond to ensure that all
members of the team are provided with suitable
training and development opportunities.
CESIP22.05.07 Ensure a service-wide
focus on absence -
supporting managers with
training, embedding policies
and supporting the health
and wellbeing of
employees. 
CEX Senior Management Team 100% 31-Dec-2023 It was previously noted that employees are being
supported in the return to work through flexible office
and home working options. Employees are supported
to look after their wellbeing by encouraging home
working where appropriate, and this is proving to be a
useful mechanism that promotes recovery and
wellbeing to maintain high levels of attendance at
work.

Page 28

28 
CESIP22.05.08 Implement the Council’s
People Strategy across the
service, with a particular
focus on employee
wellbeing. 
CEX Senior Management Team 100% 31-Dec-2023 Regular full team meetings are now scheduled for a
monthly basis and this will include communication
about key policies, training and awareness as a
theme.
CESIP22.05.09 Enhance staff engagement
through internal
communications, providing
equity of access to
information and developing
communication as a core
management skill. 
Communications & Public Affairs
Manager
100% 31-Mar-2023 Delivery of the internal communications action plan for
2022-23 is now complete and all actions were
completed to enhance staff engagement and
circulating information about surveys, ongoing
projects, and how internal policies affects staff. 
The new action plan for 2023-24 is now in progress
with a new section developed on the staff info section
to support staff with the cost of living, further
development of channels, support for HROD and
review of staff policies, roll out of Living our Values
and Ren Talks.

Page 29

29 
Appendix 2: Chief Executives Service Improvement Plan 2022-25
Scorecard 
 
Strategic Outcome 1: Place 
 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
DHS.CP.R
R01
Number of properties
on Buildings at Risk
Register   
27 42 27 27 27 27 27 27 27 27 27 27
The Buildings at Risk Register,
prepared and managed by Historic
Environment Scotland, includes 27
Renfrewshire properties, with 5 in
progress of restoration.  Properties are
located across the council area
including Kilbarchan, Lochwinnoch,
Paisley and Renfrew.
HPSIP01 Affordable housing
completions    170 243 369 200 Not measured for Quarters
The affordable newbuild housing
programme involves both Council and
Housing Association developments
across a range of sites in
Renfrewshire. In 2022/2023 there were
369 affordable housing completions
across Renfrewshire including new
homes being built in Paisley,
Johnstone, Renfrew and Bishopton.
The Council continues to increase the
supply and delivery of a range and

Page 30

30 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
choice of affordable homes to meet the
housing needs of different groups.
SOA10.10
a
Private housing
completions    572 500 * 500 Not measured for Quarters
*The Renfrewshire Housing Land Audit
is completed annually. The audit is a
snapshot in time covering the duration
between the 1 April to the 31 March
each year. The Housing Land Audit
2023 is not yet complete.
The Finalised Housing Land Audit
2022 confirmed that there were 572
new private homes for sale completed.
The private completions for the period
2022/2023 are currently being collated
in the Housing Land Audit 2023. In
relation to all homes under
construction or future housing sites,
88% of these new homes will be built
on previously used brownfield land,
creating attractive and sustainable
places.
DHS.BSTA
N.1b
Time to issue a first
report (95% issued
within 20 days)   
53.4 95.0 * 95.0 68.0 95.0 63.3 95.0 67.0 95.0 * 95.0
* Data not yet available for Q4/full
year.
Performance is lower than anticipated
and primarily stems from carrying two
vacancies in Building Standards.
Recent recruitment campaigns have
been successful to attract new officers
to the team but the level of training and
mentoring required is resource
intensive, which can have an impact
upon performance although this should
ease over the course of the year.
DHS.VDL.
01
Amount of land
brought forward for re-
use and development   
28 20 * 20 Not measured for Quarters *Data currently unavailable

Page 31

31 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
contributing to
economic activity and
enhancing the built
and natural
environment
For 2021/22, 28 hectares of land was
developed or brought back into use
including to support the delivery of new
affordable and private homes and the
delivery of new developments at the
Advanced Manufacturing and
Innovation District Scotland and
Hillington Business Park.
FRCMT14
a
The proportion of
operational
accommodation in
satisfactory condition.   
94.41% 94% * 94% Not measured for Quarters
*The latest data is from the LGBF and
refers to 2021/22.
There has been very little change to
the operational estate.  A number of
janitors houses have transferred to
HRA account, these were in good
condition.
There was a new Nursery built at
Erskine. 
A lease was returned to the landlord at
High Street, Paisley.
No major school additions or
upgrades.  
The additions and deletions largely
balance so no meaningful movement
It should be noted that due to
continued financial pressures, the
2021/22 maintenance budget will be
used to prioritise statutory health and
safety obligations and wind and
watertight repairs
FRCMT14
b
The proportion of
operational
accommodation that is   
91.46
% 96% n/a 96% Not measured for Quarters The latest data is from the LGBF and
refers to 2021/22.

Page 32

32 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
suitable for its current
use. 
CE.%SPE
NDLE.01
% of procurement
spend spent on local
enterprises   
18.87% 23% * 23% Not measured for Quarters
*This is an LGBF indicator and
therefore the 2022/23 data is not
available yet. 
In the period 2021-2022 Renfrewshire
Council recorded direct spend of £36.5
million with businesses based directly
in Renfrewshire.  This accounted for
18.8% of our total spend.  A further
26.5% of our spend was with
businesses located in bordering local
authorities (Glasgow, Inverclyde, North
Ayrshire, East Renfrewshire and West
Dunbartonshire), therefore 45% of the
council’s total spend of approx. £196m
is spent within Renfrewshire and our
neighbouring council areas.
Increasing direct spend with local
businesses is a key element of
Community Wealth Building and the
corporate procurement team are
working closely with Economic
Development to identify ways in which
we can support local businesses with
tendering for council contracts.  An
event was held in Johnstone Town
Hall on 29 November 2022 “Doing
Business with Renfrewshire Council”,
over 70 attendees representing 58
Renfrewshire businesses attended this
event.  100% of those who responded
to the post event evaluation survey
said they were likely or very likely to
take action as a result and 100%
would be willing to attend future
events.  Further events will take place

Page 33

33 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
this year, starting in March.  These
events will offer support to local
businesses to enable them to bid for
contracts with the council and the
wider public sector.
CE.LBUSB
IDPCS.01
Number of local
businesses bidding for
work on Public
Contracts Scotland
New for 2022/23 New for 2022/23 Not measured for quarters
This indicator was new for 2022/23.  It
was anticipated that the Public
Contracts Scotland website would
allow us to access data on local
suppliers registering but the system is
unable to provide this.  This indicator
cannot be reported on at present and
will be removed from the scorecard.
CE.LBUSR
EGPCS.01
Number of local
businesses registered
on Public Contracts
Scotland
New for 2022/23 New for 2022/23 Not measured for quarters
This indicator was new for 2022/23.  It
was anticipated that the Public
Contracts Scotland website would
allow us to access data on local
suppliers registering but the system is
unable to provide this.  This indicator
cannot be reported on at present and
will be removed from the scorecard.
DHS.EMP.
08
Number of new
business start-ups in
Renfrewshire with
Business Gateway
support   
272 320 206 320 51 80 47 80 50 80 58 80
Growth in the number of start-ups in
Renfrewshire has risen slightly. There
were 5% more businesses start-ups in
the last quarter compared with the
corresponding period of last year.
CE.NSE.0
1
Number of Social
Enterprises supported
to grow / develop /
income generate with
Council support   
New
indicator * 89 * 27 * 12 * 28 * 22 *
*New indicator, baseline to be
established in order to set targets
moving forward.
Cumulative detail of support is :
Supported to grow - 26 organisations
received one to one support to grow

Page 34

34 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
Supported to develop – 42
organisations received one to one
support to develop
Supported to income generate – 21
organisations received support to
income generate.
CE.RCBT.
01
Number of local
businesses securing
growth support,
training or grants from
Renfrewshire Council
Business Team   
New
indicator * 350 * 98 * 86 * 79 * 87 *
*New indicator, baseline to be
established in order to set targets
moving forward.
Businesses still face a challenging
period ahead as the future of the
economy remains uncertain with the
cost of living and energy crisis still
being felt.
CEX.OTS
H.PI
Opportunities to see or
hear something
(OTSH) positive about
Paisley and
Renfrewshire as part
of Paisley is
destination brand   
314,04
1,621
240,00
0,000
204,63
8,668
240,00
0,000
55,990,
769
60,000,
000
87,944,
833
60,000,
000
29,727,
128
60,000,
000
30,975,
938
60,000,
000
This indicator is focused on measuring
the reach of the Paisley,is destination
brand.  OTSH figures do not reflect the
coverage achieved by Paisley
Christmas Partners (Paisley First and
Scotland’s Theme Park).
Events coverage in Q1 - Paisley Food
and Drink Festival (Daily Record, The
Skinny, Scottish Field, Scotland on
Sunday, The Herald, The National,
Evening Times), The Spree
programme (BBC Radio Scotland,
Daily Record, Evening Times,) and
Sma’ Shot Day pre-event activity
(Evening times and locals).
Events coverage in Q2 – including
Sma’ Shot Day (Glasgow Times, local
press), The Spree and related activity
(BBC Radio Scotland, Daily Mail, The
Skinny, Daily Record, The Scotsman,

Page 35

35 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
Glasgow Live, The Metro, Glasgow
Times, local press) and the
announcement of Paisley Halloween
Festival (Daily Record, Clyde 1,
Glasgow Live, Glasgow Times, local
press).
Events coverage in Q3 - Paisley
Halloween Festival saw large numbers
of print coverage through a variety of
media outlets, including The Times,
The Metro, Daily Telegraph, Sunday
Mail, The Scotsman, Practical Caravan
and Renfrewshire local titles. The
Festival also featured online through
Daily Record, Glasgow Live, The
National, STV and The Skinny, while
live television broadcast from the
Festival featured on STV East and
West as part of the evening STV
News.
Perth’s handover of the Royal National
Mὸd to Paisley as 2023 host also
featured in The Herald, The Glasgow
Times, Press and Journal, Oban
Times and Renfrewshire local titles.
Events coverage in Q4 - the Council’s
annual events programme
announcement (Daily Record,
Glasgow Times and local press) and
the programme announcements for
Paisley Food and Drink Festival (Daily
Record, Glasgow Times, What’s On
Network, Great British Life and local
press). We saw a great deal of
coverage referencing Paisley’s hosting
of the Royal National Mὸd (Press and
Journal, The National, Yahoo! UK and
Ireland, What’s On Network and local

Page 36

36 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
press around the country). The OTSH
figures do not reflect the coverage
achieved by Paisley Christmas
Partners (Paisley First and Scotland’s 
CEX/FUN
D/01
Fundraising Income
Target   
384,61
14
500,00
0
548,19
1
500,00
0 Not measured for Quarters
2022/23 highlights include:
• April 2022 - £25,000 payment (Trust
and Foundation) 
• June 2022: £50,000 payment (Trust
and Foundation) 
• October 2022: £550,000 worth of
pledges drawn down
• December 2022: £20,000 pledge 
(Renfrewshire Chamber of Commerce
• March 2023: Launch of the corporate
campaign.
• Corporate Brochure completed and
now public.
• Monthly site-visits held to support
major donor cultivation.   
• HMWI Prospect List developed and
targeted cultivation ongoing 
• Bi-annual Supporters Newsletter
shared with donors and prospects 
• All four trustee meetings were held
and charity governance adhered to. 
 
Strategic Outcome 2: Economy

Page 37

37 
 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
DHS.EMP.
01
Number of
unemployed/ low
waged people being
supported through
Renfrewshire Council
Employability
Programme (INVEST)   
859 1,100 1,370 1,100 377 275 297 275 337 275 359 275 There were 359 new registrations in
Q4.
CE.EMP.0
1
Number of
unemployed/ low
waged people moving
into paid employment
through Renfrewshire
Council Employability
Programme   
686 350 538 350 112 87.5 95 87.5 133 87.5 198 87.5
198 unemployed/low waged people
secured new paid employment in
quarter 4.
CE.EMP.0
2
Number of
unemployed / low
waged people
securing qualifications
through Renfrewshire
Council Employability
Programme (INVEST)   
New
indicator * 507 * 82 * 123 * 118 * 184 *
*New indicator, baseline to be
established in order to set targets
moving forward.
184 unemployed/low waged people
achieved a qualification in quarter 4.
DHS.EMP.
03
Number of people
supported, sustained
in work at 6 Months
through Renfrewshire
Council Employability
Programme (INVEST)   
221 180 340 180 Not measured for Quarters
This end of year figure will continue to
rise at there is a degree of time lag
with this indicator. Scottish
Government have supported a
development initiative named
“Kickstart Plus” in Renfrewshire to
provide a further 6 months support to
Kickstart trainees (with employers also
contributing) to allow them to continue
in the workplace.

Page 38

38 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
CE.TRAIN
EERC.01
Number of trainee type
posts created for
unemployed people at
Renfrewshire Council 
New
indicator * 68 * 31 * 10 * 13 * 14 *
*New indicator, baseline to be
established in order to set targets
moving forward.
CE.CIVIC.
01
Measure of civic pride
relating to events    
New
indicator * 84% * Not measured for Quarters
*New indicator, baseline to be
established in order to set targets
moving forward.
In the first year of evaluating the local
and visitor events programme across
Paisley, Renfrew and Johnstone 84%
strongly agreed or agreed that the
events made them feel proud of their
hometown. The percentages ranged
from 73% based on Renfrew Gala Day
through to 97% at Johnstone
Christmas lights switch on. A target will
be set for 23/24 at 85%.
CEX/EVE
NTS/01
Number of people
participating in the
events programme,
digitally or in person   
789 300 3,140 300 1,004 75 892 75 1,244 75 0 75
The events programme was fully
delivered in Q1/Q3.  The total number
of participants across the programme
was 3140 against a target of 300.
CEX/EVE
NTS/02
Number of people
performing in the
events programme,
digital or live
performance   
307 100 568 150 101 37.5 162 37.5 305 37.5 0 37.5
The events programme was fully
delivered through Q1/Q3 with no
events taking place in Q4.  The total
number of performers across the
programme was 568 against a target
of 150.
CEX/EVE
NTS/03
Number of volunteers
supporting the
development and
delivery of the events   
8 15 41 15 8 3.75 11 3.75 22 3.75 0 3.75
The events programme was fully
delivered across Q1/Q3 with 42
volunteering opportunities delivered
against an annual target of 15.

Page 39

39 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
CEX/EVE
NTS/04
Number of people
viewing or attending
the events programme   
63,630 65,000 151,50
0 65,000 45,000 16,250 21,700 16,250 84,800 16,250 0 16,250
The events programme was fully
delivered over Q1/Q3 and the number
of people attending totalled 151,000
against a target of 65,000.  This
exceeded expectations and evidenced
the desire for a return to live events
post pandemic.
Strategic Outcome 3: Fair 
 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
FRAMT01
Asset Management
Transfer - number of
months from receipt of
an application to a
determination being
issued from the
Council   
0 6 4 6 Not measured for Quarters
During 2022/23, two full CAT requests
have been approved and one
application has been rejected. One
new application has been validated
awaiting final determination in May
2023 and a further 3 applications are
ongoing awaiting validation. There
have been 9 new Expressions of
Interest. 
On average it takes 3-4 months from
acknowledgement (validation) of a full
application to a determination being
issued from the Council. This
timescale has been reduced
significantly from over 6 months in the
previous period.

Page 40

40 
Strategic Outcome 4: Green 
 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
CE.BUSN
ETZERO.0
1
Number of local
businesses working
with the Council to
progress the Net Zero
agenda (NEW)   
New
indicator * 50 * 18 * 30 * 50 * 0 *
*New indicator, baseline to be
established in order to set targets
moving forward.
Work is ongoing to raise awareness of
the Net Zero agenda amongst the
business community and we are
continuing to engage with colleagues
at Renfrewshire Chamber of
Commerce, Business Gateway,
Engage Renfrewshire, Invest in
Renfrewshire & Scottish Enterprise.
We are also collaborating with
Strathclyde University and the City
Region to expand green business
support. This has enabled a range of
businesses and third sector
organisations to begin their Net Zero
journey. We continue to expand our
engagement. 
CE.BUSN
ETZERO.0
2
Number of local
businesses securing
Net Zero growth
grants from
Renfrewshire Council
Business Grants
(NEW)   
New
indicator * 2 * 0 * 0 * 2 * 2 *
*New indicator, baseline to be
established in order to set targets
moving forward.
Currently supporting a number of
businesses through the application
process to ensure compliance with
funding requirements.

Page 41

41 
 
Strategic Outcome 5: Living our Values 
 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
PT.DS.PP
F.CMT01
Average Time for
processing Planning
Applications
(Householder)   
7.2 8 * 8 10.8 8 13.4 8 *  8 * 8
*Data for this indicator is verified
biannually by the Scottish
Government; data for Q3 and Q4
should be available in summer 2023.  
Performance for Q1 and Q2 is below
target due to resource pressures.
DHS.BSTA
N.1a
Time to issue a
building warrant or
amendment to warrant
from receipt of
application (days)   
101.2 60.0 * 60.0 93.5 60.0 106.0 60.0 90.0 60.0 * 60.0
The internal target has been set at 60
days and measures the overall time it
takes from receipt of a valid building
warrant application to issuing the
building warrant approval. This KPO
measures both building standards
officers and external agents response
times and, as a result, there are
aspects of this KPO that are out with
our control. The KPO stems from the
Building Standards Performance
Framework - KPO1, which places a
responsibility on LA verifiers to
constantly seek to reduce and
minimise turnaround times for building
warrant applications. Given current
performance and that elements of this
KPO are out with our control,
consideration should be given to
reviewing this target.
DHS.BSTA
N.1c
Percentage of building
warrants or
amendments issued   
60.1 90.0 * 90.0 80.2 90.0 79.9 90.0 81.5 90.0 * 90.0 Performance has improved but is still
lower than target and this primarily
stems from carrying two vacancies.

Page 42

42 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
within 10 days of
receipt of all
satisfactory
information
Recent recruitment campaigns have
been successful to attract new officers
to the team but  the level of training
and mentoring required is resource
intensive, which can have an impact
upon performance although this should
ease over the course of the year.
CE08
% of FOI requests in a
quarter completed
within timescale in the
Chief Executive's
Department   
93.5% 100% 97% 100% 100% 100% 100% 100% 95% 100% 93% 100%
During 2022/23, CE received 107
single service FOIs. 104 were
completed within timescale.
CEX/COM
P/01
% of frontline
response complaints
responded to within
timescales agreed with
customer (Chief
Executive’s)   
40% 85% 0% 85% 0% 85% 80% 85% 29% 85% 0% 85%
Two frontline complaints were received
during QTr 4 - both were completed
outwith timescale.
Targeted support is offered to assist
the service areas where meeting the
complaints’ timescales is challenging
CE153
% of investigation
complaints responded
to within timescales
agreed with customer
(Chief Executive’s)   
77% 85% 71% 85% 50% 85% 100% 85% 50% 85% 66% 85%
There were 3 investigation complaints
received in Q4, and 2 were responded
to within the agreed timescale.
Targeted support is offered to assist
the service areas where meeting the
complaints’ timescales is challenging  
Complaints which require investigation
and/or are escalated to the Chief
Executive tend to be more complex
and may require input from multiple
services.
CEABS01
dii
Average number of
work days lost through
sickness absence per   
5.98 6.5 * 6.5 1.5 1.3 1 1.2 1.35 1.8 * 2.2
*Data not yet available for Q4/year
end.
It has been noted that absence is
within target for Qtr 3.  Service

Page 43

43 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
employee (Chief
Executive's) (FTE)
absence monitoring continues, and
absence statistics are reported to both
CMT and Board. 
CEX.DIGC
HANNELS
Number of people
engaging with the
Council’s digital
channels (not
including website).   
64,822 56,800 69,287 54,000 66,875 54,000 67,897 54,000 68,624 54,000 69,287 54,000
The followers on our social media
channels have been rising steadily
since the introduction of our Social
Media Content Strategy in August
2021 and continue to do so. The
merging of our 2 LinkedIn profiles in
August 2021 has also helped increase
our follower numbers. Our Twitter
followers dropped slightly in Q3
following the change in ownership of
the social media network but are rising
again and are now almost back to their
October 2022 figure. Followers on our
other channels have continued to rise
steadily, with our Facebook following
increasing to over 28,000 for the first
time in December 2022. Our Instagram
following also rose to over 3,000 for
the first time in December 2022.
Renfrewshire Council is currently a
member of the majority of most
popular local community Facebook
groups in the region.
CEX.OTS
H.RC
Opportunities to see or
hear something
(OTSH) positive about
Renfrewshire Council
activity   
371,06
1,673
125,00
0,000
316,56
0,958
200,00
0,000
80,149,
479
50,000,
000
127,77
3,956
50,000,
000
49,301,
105
50,000,
000
59,336,
418
50,000,
000
47% of media coverage in Q1 was
positive. Media reach in Q2 increased
overall from the previous quarter. 43%
of articles were positive, including
coverage of exam results, river safety
and drowning prevention campaigns,
spotless September and extensive
coverage of the council’s events
programme. Media coverage in Q3
was less than in previous quarters
which is reflected in a lower OTSH

Page 44

44 
Code  Performance Indicator Current
Status
Short
Term Long Term
2021/22 2022/23 Q1 2022/23 Q2 2022/23 Q3 2022/23 Q4 2022/23 Explanation of performance
Value Target Value Target Value Target Value Target Value Target Value Target
figure. 53% of all coverage in Q3 was
positive with the majority of this local
stories in local media. Highlights
include the winter events programme,
and positive coverage of various
council funding programmes including
the Future Paisley cultural grants,
Celebrating Renfrewshire fund and the
Green Spaces, Parks and Play Areas
fund. 52% of coverage in q4 was
positive. Highlights also included the
outcomes of the #YouDecide
campaign and the Provost’s
Community Awards.
CEX/COM
MS/01
% of staff who feel that
the information they
receive from internal
communications is
helpful   
85% 85% * 85% Not measured for Quarters
*Data not available – see note below. 
Based on results of the Smarter Ways
of Working Survey issued to all staff in
June 2021. The survey results show
that 85% feel the information they
receive from internal communications
is very helpful (26%) or helpful (59%)
This is normally measured annually
however the survey for 2022-23 was
paused to enable other staff
engagement to take place. A short
pulse survey will be held in May 2023
with a full survey in the new year 2024.