Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 30th March 2023
___________________________________________________________________
Report by: The Chief Executive and Director of Finance and Resources
___________________________________________________________________
Heading: Contract Award: West Primary Electrical Upgrade Phase 2 (RC-
CPU-22-220)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Works
Contract for West Primary Electrical Upgrade Phase 2 to Atalian
Servest AMK Limited T/A Arthur McKay & Company. 
1.2 The recommendation to award the Contract follows a procurement
exercise conducted in accordance with the Council’s Standing Orders
relating to Contracts 1st January 2022 for a below Regulated (Works)
contract using the Open Procedure. 
1.3 A Contract Strategy was approved by the Strategic Commercial and
Procurement Manager on 22nd December 2022 and the Head of
Property Services on 23rd December 2022.  
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Finance, Resources and Customer Services
Policy Board:

Page 2

(a) Authorise the Head of Corporate Governance to award a Contract
for West Primary Electrical Upgrade Phase 2 (RC-CPU-22-220) to
Atalian Servest AMK Limited T/A Arthur McKay & Company. 
(b) Authorise the Tendered Total of £534,767.28 excluding VAT and an
additional 10% contingency for any unforeseen works. 
(c) Note that, the Contract has sectional completion requirements, the
proposed Dates of Possession and proposed Dates for Completion are
noted below. Any changes to these dates will be confirmed in the
Council’s Letter of Acceptance: 
Dates of Possession
of Sections 
Dates of Completion
of Sections
Section 1 28th June 2023 13th August 2023
Section 2 28th June 2023 6th September 2023
Section 3 14th August 2023 22nd October 2023 
(d) Note the Contract requires the provision of a Performance Bond and
Collateral Warranties as indicated within the tender documentation. 
________________________________________________
3. Background
3.1 This procurement exercise is for the appointment of a competent and
experienced contractor to carry out the electrical upgrades at West
Primary School, Newton Street, Paisley. This work is Phase 2 of the
rewire works, Phase 1 was completed in Summer 2022. A large portion
of the works will be carried out during the summer holiday while the
remainder will be carried out on a phased basis outside school hours.                
3.2 To initiate this procurement process a Contract Notice was published
on the Public Contracts Scotland advertising portal on Friday 6th
January 2023 with the tender documentation available for downloading
from the Public Contracts Scotland - Tender portal from this date. 
3.3 During the live tender period, ten organisations expressed an interest in
the tender. By the closing date set for the return of electronic tender
submissions, 12 noon on Wednesday 8th February 2023, three
organisations submitted a tender response, three organisations
declined to respond, and four organisations did not respond.

Page 3

3.4  In accordance with the Council’s Standing Orders relating to Contracts
1 January 2022 standing order 11.5, Tenderers were required to
complete a Single Procurement Document (SPD) to be submitted with
their tender submission. All three tender submissions were evaluated
against a pre-determined set of criteria in the form of the SPD by
representatives from the following Council services: Property Services,
the Corporate Procurement Unit, Corporate Risk and Corporate Health
& Safety. 
3.5  All three tender submissions received, complied with the minimum
selection criteria of the SPD. The three tender submissions were each
evaluated against the Award Criteria of 60% Quality and 40% Price.
3.7  The scores relative to the Award Criteria for each of the three tender
submissions are noted below: 
Price
(40%)
Quality
(60%)
Total
(100%)
1 Atalian Servest AMK Limited T/A Arthur
McKay & Company  30.56% 52.50% 83.06%
2 Clark Contracts Limited  25.27% 56.25% 81.52%
3 Emtec Group Limited 40.00% 38.50% 78.50% 
3.8  The evaluation of tender submissions received identified that the
submission by Atalian Servest AMK Limited T/A Arthur McKay &
Company was the most economically advantageous tender.
3.9  The form of Contract is SBCC Standard Building Contract Without
Quantities 2011 Edition (SBC/XQ/Scot), incorporating the Employer
Amendments.
3.10  The costs for the West Primary Electrical Upgrade Phase 2 will be met
through the Capital General Services budget.
3.11  Community Benefits were requested as part of the procurement
process and Atalian Servest AMK Limited T/A Arthur McKay &
Company confirmed that the following Community Benefits would be
made available to the Council for this Contract. 
Community Benefit 
Description 
No of People / Activity
Modern Apprenticeship 2

Page 4

___________________________________________________________________
Implications of the Report
1. Financial – No financial implications have arisen or are anticipated.
The Financial and Economic Standing of the recommended bidder has
been assessed as part of the tender selection criteria, which Atalian
Servest AMK Limited T/A Arthur McKay & Company passed.  The cost
for these works will be met by the Capital General Services budget 
2. HR & Organisational Development – No TUPE implications. 
3. Community/Council Planning –  
 Our Renfrewshire is fair- Addressing the inequalities that limit life’s
chances. Tenderers were assessed within the procurement process
regarding their approach to Fair Work First throughout their
organisation and supply chain i.e. payment of the living wage,
training and development opportunities 
 Our Renfrewshire is safe – A central requirement for Property
Services is to ensure that Council operated property, facilities and
assets are property maintained in a manner that complies with
existing statutory legislation (Statutory Compliance)
 Tackling inequality, ensuring opportunities for all – Promoting skills
and learning for life.
 Creating a sustainable Renfrewshire for all to enjoy Atalian Servest
AMK Limited T/A Arthur McKay & Company has committed to
deliver Community Benefits as set out within 3.11 of this report. 
4. Legal – The Procurement of this Contract was conducted as a below
Regulated (Works) Open Procedure in accordance with the Council’s
Standing Orders Relating to Contracts. 
5. Property/Assets - The Contract will facilitate the electrical upgrade of
West Primary School Phase 2 that will ensure that the Council’s assets
are upgraded to a proper standard and maintained in a manner that
complies with statutory legislation. 
6. Information Technology - No information Technology implications
have arisen or are anticipated.  
7. Equality & Human Rights - The Recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report.

Page 5

If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health & Safety – Atalian Servest AMK Limited T/A Arthur McKay &
Company health and safety credentials were evaluated by Corporate
Health and Safety and met the Council’s minimum requirements
regarding health and safety.
9. Procurement – The procurement procedures outlined within this report
ensures that the Council meets its statutory requirements in respect of
procurement procedures, efficiency, and modern
Government.                                                                                            
10. Risk – Atalian Servest AMK Limited T/A Arthur McKay & Company
insurances have been assessed and evaluated to confirm that they
meet the minimum requirements regarding insurable risk.
11. Privacy Impact - No Privacy Impact implications have been identified
or are anticipated.   
12. Cosla Policy Position – No COSLA Policy Position implications have
arisen or are anticipated.  
13.              Climate Risk – The level of impact associated with provision of these
works has been assessed using the Scottish Government Sustainability
Test and is considered high risk.
 Carbon Energy Consumption – The contractor will be required
to consider energy saving measures where possible.  As part of
the rewire all lighting is being changed to low energy LEDs.  
 Waste Production – Contractor will be required to consider
waste reduction and recycling measures while undertaking these
works.  Contractors are required to provide details of their
proposed Waste Carrier.  
_______________________________________________________
List of Background Papers 
(a)  None
___________________________________________________________________ 
Author:           Abimbola Olutola, Procurement Advisor, Corporate Procurement Unit,
Abimbola.olutola@renfrewshire.gov.uk