7 - CAR - Design and Build for Plymuir Bridge Replacement Scheme

Renfrewshire Council · 30 March 2023
Back to Finance, Resources and Customer Services Policy Board — 30 March 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 30 March 2023
___________________________________________________________________
Report by: Chief Executive and the Director of Environment and Infrastructure 
___________________________________________________________________
Heading: Design and Build for Plymuir Bridge Replacement Scheme (RC-CPU-
18-415)
___________________________________________________________________
1. Summary
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Contract
for the Design and Build for Plymuir Bridge Replacement Scheme to
Amalgamated Construction Ltd t/a AmcoGiffen. 
1.2 The tendering procedure for this Works Contract was conducted as a
below Regulated Open Procedure in accordance with Renfrewshire
Council’s Standing Orders Relating to Contracts. 
1.3 A Contract Strategy was approved by the Head of Operations and
Infrastructure, the Head of Policy and Commissioning and the Strategic
Commercial Category Manager in November 2022. 
 
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board:

Page 2

2.1 Authorise the Head of Corporate Governance to award the Contract for
the Design and Build for Plymuir Bridge Replacement Scheme to
Amalgamated Construction Ltd t/a AmcoGiffen;
2.2 Note that the intended starting date is 9 May 2023 with the completion
date being six (6) months from the starting date. The actual starting
date will be confirmed in the Council’s Letter of Acceptance.  
2.3 Note that the contract value is £468,242.03 excluding VAT. The cost of
this contract will be met from Capital – General Services funds. 
_________________________________________________________
3. Background
3.1 Renfrewshire Council has a statutory obligation to maintain roads
related structures within the Council boundary. The load carrying
capacity of the Plymuir Bridge is restricted to 7.5 tonnes. The Council
has a requirement for a suitably qualified and experienced contractor to
design and build a replacement bridge that will remove the restriction.  
3.2 The Contract will be formed based on the NEC3 Engineering and
Construction Contract A: Priced Contract with Activity Schedule April
2013 with bespoke Z clauses.
3.3 A contract notice was published on the Public Contracts Scotland
advertising portal on Friday, 11 November 2022 and the tender
documentation available for downloading from the Public Contracts
Scotland – Tender platform. 
3.4 During the tender period, fifteen (15) companies expressed an interest
in the Contract. By the closing date for return of electronic tenders, 12
noon on Tuesday, 27 January 2023, one (1) company submitted a
response, nine (9) declined to respond and five (5) failed to respond.
3.5 The one (1) Tender Submission received was evaluated against a pre-
determined set of criteria in the form of the Single Procurement
Document (SPD) as required by the Council’s Standing Orders Relating
to Contracts 11.5 by representatives from Corporate Procurement Unit,
Health and Safety and Risk which assessed competence, expertise
and economic and financial standing. The Tenderer was assessed as
meeting the minimum criteria following the methodology stated in the
Invitation to Tender.

Page 3

3.6 The Tender Submission was then assessed against the published set
of Award Criteria where were based upon a price/quality ratio of
60%/40%.
3.7 The scores relative to the Award Criteria for the Tenderer are noted
below: 
Price
(60%)
Quality
(40%)
Total
(100%)
Amalgamated
Construction Ltd t/a
AmcoGiffen
60.00% 33.00% 93.00% 
3.8 The evaluation of Tender Submissions received identified that the
submission by Amalgamated Construction Ltd t/a AmcoGiffen was the
most economically advantageous tender. As they were the only
Tenderer, the value for money assessment is required to ensure there
is no need to go back out to market.
3.9 The costs arising from the contract will be met by Capital – General
Services funds.
3.10 Community Benefits were requested as part of the procurement
process and Amalgamated Construction Ltd t/a AmcoGiffen have
committed to the following Community Benefits: 
Community Benefit Description No of People /
Activity
Work Experience Placement for an individual
16+ years of age 1
Business advice/support to an SME/Social
Enterprise/Voluntary  1
Financial Support for a Community Project 1
Non Financial Support for a Community Project 1 
___________________________________________________________________
Implications of the Report
1. Financial 
The cost of this Contract will be met by Capital – General Services
funds. 
2. HR & Organisational Development 
Not applicable.

Page 4

3. Community/Council Planning
Reshaping our place, our economy and our future – the Contract
proposed will support the delivery of this outcome. 
4. Legal 
The tendering procedure for this Works Contract was conducted in
accordance with a below Regulated Open Procedure under the
Council’s Standing Orders relating to Contracts. 
5. Property/Assets
This contract will improve the Plymuir Bridge. 
6. Information Technology
No Information Technology implications have been identified or are
anticipated. 
7. Equality & Human Rights
The Recommendations contained within this report have been
assessed in relation to their impact on equalities and human rights. No
negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health & Safety
Amalgamated Construction Ltd t/a AmcoGiffen’s health and safety
credentials were evaluated by Corporate Health and Safety and met
the Council’s requirements regarding health and safety. 
9. Procurement 
The procurement procedures outlined within this report shall ensure
that the Council meets its statutory requirements in respect of
procurement procedures, efficiency and modern Government. 
10. Risk 
Amalgamated Construction Ltd t/a AmcoGiffen have been assessed
and evaluated to confirm that they have met the minimum requirements
regarding insurable risk.

Page 5

11. Privacy Impact 
No Privacy Impact implications have been identified or are anticipated. 
12. Cosla Policy Position 
No Cosla Policy implications have been identified or are anticipated. 
13. Climate Risk
The level of impact associated with the provision of this work has been
assessed using the Scottish Government Sustainability Test and is
considered to be low risk.  Amalgamated Construction Ltd t/a
AmcoGiffen have an Environmental Management Framework and an
established carbon strategy which seeks to minimise their
environmental impact and reduce their carbon emissions.
___________________________________________________________________ 
Author:           Brian Bradley, Assistant Category Manager, 0141 487 1522,
brian.bradley@renfrewshire.gov.uk