Page 1

To: Finance, Resources and Customer Services Policy Board
On: 30 March 2023
Report by: Director of Finance and Resources
Heading:  Revenue and Capital Budget Monitoring as at 6 January 2023 
1. Summary of Financial Position 
1.1. The projected revenue outturn at 31 March 2023 for those services reporting to
the Finance, Resources and Customer Services Policy Board is an overspend
position of £1.473m (1.5%) against the revised budget for the year. 
1.2. The projected capital outturn at 31 March 2023 for projects reporting to the
Finance, Resources and Customer Services Policy Board is a break-even
position.   
1.3. This is summarised over the relevant services in the table below and further
analysis is provided in the Appendices.
 
Table 1: Revenue
Division
Revised
Annual
Budget
£000
Projected
Annual
Outturn 
£000
Budget
Variance 
£000
Budget
Variance 
%
Finance and Resources 44,091 44,444 (353) (0.8%)
Environment and Infrastructure 21,775 22,895 (1,120) (5.1%)
Miscellaneous 30,730 30,730 0 0%
Total 96,596 98,069 (1,473) (1.5%)

Page 2

Table 2: Capital
Division
Revised
Annual
Budget
£000
Projected
Annual
Outturn 
£000
Budget
Variance 
£000
Budget
Variance 
%
Finance, Resources and
Customer Services 6,884 6,884 0 0%
 
2. Recommendations 
Members are requested to: 
2.1. Note the projected Revenue outturn position detailed in Table 1 above; 
2.2. Note the projected Capital outturn position detailed in Table 2 above; and 
2.3. Note the budget adjustments detailed at sections 4 and 6.
 
3. Revenue 
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £1.473m (1.5% of total budget) for all services reporting to
this Policy Board.  Detailed division service reports can be found at the end of
this report, along with an explanation of any significant projected variances.
3.2. The projected outturn is based on information currently available, and
assumptions made by service budget holders.  Any changes to these
projections will be detailed in future reports to this Board.
3.3. The main reasons for the projected outturn position are indicated below the
tables showing both the subjective analysis (what the budget is spent on) and
the objective analysis (which division is spending the budget).
 
4. Revenue Budget Adjustments 
4.1. Members are requested to note from Appendix 1 that budget adjustments
totalling £11.594m have been processed since the last report, with the main
reasons as follows:
 + £2.0m allocated to Finance and Resources, and £1.6m to Environment and
Infrastructure, which mainly relates to non-teacher pay inflation
 - £5.9m transfer from Miscellaneous to earmarked reserves to support Fairer
Renfrewshire and other programmes of work beyond 2023/24; 
 - £9.2m budget realignment from Miscellaneous to other Council Services in
respect of the non-teacher pay award.

Page 3

5. Capital 
5.1. The Capital Investment Programme 2022/23 to 2026/27 was approved by the
Council on 3 March 2022.  For Finance, Resources and Customer Services the
approved capital spend for 2022/23 is £6.884m (£9.107m approved Capital
Plan). 
5.2. The budget movement primarily results from reprofiling in the approved capital
programme for the year, and grant awarded for kitchen refurbishment for the
expansion of school meals. Further detail can be found at Appendix 2. 
6. Capital Budget Adjustments 
6.1. Since the last report, budget changes totalling £2.711m have arisen, which
reflect the following:
 Budget carried forward into 2023/24 from 2022/23 (£2.711m): 
o ICT Infrastructure and Renewal Programme (£0.238m) to reflect expected
delivery dates in early 2023/24;
o Lifecycle Capital Maintenance Fund (£2.473m) to reflect timing of
expected improvements across a range of properties.

Page 4

_______________________________________________________________
 
Implications of this report
 
1.  Financial – The projected budget outturn position for Finance, Resources
and Customer Services’ Revenue budget is an overspend of £1.473m. 
Income and expenditure will continue to be monitored closely for the rest of
the financial year and, as far as possible, steps will be taken to mitigate any
overspend.   
The projected outturn position for Finance, Resources and Customer
Services’ Capital budget is break-even. The Capital programme will
continue to be monitored closely for the rest of the financial year and,
where necessary, steps will be taken to mitigate any overspend.   
Any changes to current projections in either Revenue or Capital budgets
will be reported to the board as early as possible, along with an explanation
for the movement. 
2.  HR and Organisational Development - None directly arising from this
report. 
3. Community/Council Planning - None directly arising from this report. 
4.  Legal - None directly arising from this report. 
5.  Property/Assets - The Capital expenditure in this board will result in
lifecycle maintenance improvements to existing properties and replacement
of ICT assets and infrastructure. 
6.  Information Technology - None directly arising from this report. 
7.  Equality and Human Rights - The recommendations contained within this
report have been assessed in relation to their impact on equalities and
human rights. No negative impacts on equality groups or potential for
infringement of individuals’ human rights have been identified arising from
the recommendations contained in the report because for example it is for
noting only.  If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety - None directly arising from this report.

Page 5

9. Procurement - None directly arising from this report. 
10. Risk - The potential risk that the Council will overspend its approved
budgets for the year will be managed at a Council-wide level by the Chief
Executive and Directors. 
11. Privacy Impact - None directly arising from this report. 
12. Cosla Policy Position - N/a. 
13. Climate Risk - None directly arising from this report.
__________________________________________________________________ 
List of Background Papers 
Revenue Budget and Council Tax 2022/23, Council 3 March 2022. 
The Capital Investment Programme 2022/23 to 2026/27, Council 3 March 2022
__________________________________________________________________ 
Authors:        Valerie Howie / Lisa Dickie / Kevin Festorazzi / Geoff Borland

Page 6

APPENDIX 2 
 
 
 
 
Objective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Finance and Resources 42,165 1,926 44,091 44,444 (353) (0.8%) (353) 0
Environment and Infrastructure 20,154 1,621 21,775 22,895 (1,120) (5.1%) (750) (370)
Miscellaneous 45,871 (15,141) 30,730 30,730 0 0.0% 0 0
NET EXPENDITURE 108,190 (11,594) 96,596 98,069 (1,473) (1.5%) (1,103) (370)
Subjective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Employees 101,966 (7,892) 94,074 93,138 936 1.0% 138 798
Premises Related 8,984 (107) 8,877 9,704 (827) (9.3%) (557) (270)
Transport Related 1,682 0 1,682 1,962 (280) (16.6%) (40) (240)
Supplies and Services 21,912 1,453 23,365 23,235 130 0.6% (280) 410
Third Party Payments 2,078 0 2,078 2,054 24 1.2% 24 0
Transfer Payments 58,648 (5,047) 53,601 53,600 1 0.0% 1 0
Support Services 2,740 1 2,741 2,724 17 0.6% 50 (33)
Depreciation and Impairment Losses 7,177 0 7,177 7,177 0 0.0% 0 0
GROSS EXPENDITURE 205,187 (11,592) 193,595 193,594 1 0.0% (664) 665
Income (96,997) (2) (96,999) (95,525) (1,474) (1.5%) (440) (1,034)
NET EXPENDITURE 108,190 (11,594) 96,596 98,069 (1,473) (1.5%) (1,104) (369)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
POLICY BOARD :  FINANCE, RESOURCES & CUSTOMER SERVICES
Budget Variance 
(Adverse) or Favourable
Budget Variance 
(Adverse) or Favourable

Page 7

APPENDIX 2 
 
 
 
 
Objective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Finance and Resources Directorate (353) (190) (543) (542) (1) (0.2%) (1) 0
Audit Services 601 31 632 638 (6) (0.9%) (3) (3)
Corporate Governance 3,207 137 3,344 3,249 95 2.8% 78 17
Digital, Transformation & Customer Services 20,879 1,113 21,992 22,101 (109) (0.5%) (102) (7)
Finance and Business Services 11,034 626 11,660 11,588 72 0.6% 68 4
Housing Benefits 4,043 0 4,043 4,047 (4) (0.1%) (3) (1)
People & Organisational Development 2,463 125 2,588 2,627 (39) (1.5%) (32) (7)
Property Services (527) 84 (443) (352) (91) (20.5%) (91) 0
Social care (non‐delegated) 818 0 818 1,088 (270) (33.0%) (267) (3)
NET EXPENDITURE 42,165 1,926 44,091 44,444 (353) (0.8%) (353) 0
Objective Heading
Digital, Transformation & Customer Services
Property Services
Social care (non‐delegated)
1 April 2022 to 6 January 2023
Budget Variance 
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
POLICY BOARD :  FINANCE, RESOURCES & CUSTOMER SERVICES
Key Reasons for Significant Projected Variances
An overspend in Premises Costs is projected. This is due to an expected increase in energy costs across operational Council 
properties.
An overspend in Premises Costs is projected. This is due to an expected increase in energy costs across Health and Social Care 
properties
The projected overspend reflects the one off costs of migration for the Council's telephony system over the course of the current 
financial year.

Page 8

APPENDIX 2 
 
 
 
 
Subjective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Employees 33,897 2,142 36,039 35,984 55 0.2% 58 (3)
Premises Related 2,728 (190) 2,538 2,881 (343) (13.5%) (343) 0
Transport Related 76 0 76 54 22 28.9% 22 0
Supplies and Services 9,325 (26) 9,299 9,479 (180) (1.9%) (173) (7)
Third Party Payments 1,745 0 1,745 1,721 24 1.4% 24 0
Transfer Payments 55,156 0 55,156 55,155 1 0.0% 1 0
Support Services 694 0 694 652 42 6.1% 50 (8)
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 103,621 1,926 105,547 105,926 (379) 21.2% (361) (18)
Income (61,456) 0 (61,456) (61,482) 26 0.0% 8 18
NET EXPENDITURE 42,165 1,926 44,091 44,444 (353) (0.8%) (353) 0
POLICY BOARD :  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ FINANCE & RESOURCES
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance 
(Adverse) or Favourable

Page 9

APPENDIX 2 
 
 
 
 
Objective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Building Services (240) 0 (240) (240) 0 0.0% 0 0
Street Lighting Maintenance Work 376 6 382 554 (172) (45.0%) (152) (20)
Public Building Repairs 3,866 77 3,943 4,281 (338) (8.6%) 0 (338)
Soft Facilities Management Services 16,152 1,538 17,690 18,300 (610) (3.4%) (598) (12)
NET EXPENDITURE 20,154 1,621 21,775 22,895 (1,120) (5.1%) (750) (370)
Objective Heading
Building Services
Street Lighting Maintenance Work
Public Building Repairs
Soft Facilities Management Services
The forecast projection arises from anticipated cost increases within Building Services being passed on to Public Building Repairs, 
owing to pay and materials inflationary pressures.
There is a projected overspend on repairs and maintenance of street lighting columns due to increased costs of materials, which 
will be closely monitored for the rest of the financial year.
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
Budget Variance 
(Adverse) or Favourable
1 April 2022 to 6 January 2023
POLICY BOARD :  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ ENVIRONMENT AND INFRASTRUCTURE
Key Reasons for Significant Projected Variances
The service is currently forecast to break even this year; however, it is recognised that costs are under considerable pressure from 
supply price increases. This will affect the Housing Revenue Account as Public Building Repairs as the two main recharges of 
Building Services costs.
There is an anticipated under‐recovery of income, which is offset by some vacancies and an underspend in supplies and services 
across the service; this will continue to be closely monitored for the rest of the financial year.

Page 10

APPENDIX 2 
 
 
 
 
Subjective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Employees 26,730 1,581 28,311 27,430 881 3.1% 80 801
Premises Related 3,239 16 3,255 3,739 (484) (14.9%) (214) (270)
Transport Related 1,594 0 1,594 1,896 (302) (18.9%) (62) (241)
Supplies and Services 10,119 24 10,143 9,833 310 3.1% (107) 417
Third Party Payments 0 0 0 0 0 0.0% 0 0
Transfer Payments 43 0 43 43 0 0.0% 0 0
Support Services 1,082 0 1,082 1,107 (25) (2.3%) 0 (25)
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 42,807 1,621 44,428 44,048 380 0.9% (302) 682
Income (22,653) 0 (22,653) (21,153) (1,500) (6.6%) (448) (1,052)
NET EXPENDITURE 20,154 1,621 21,775 22,895 (1,120) (5.1%) (750) (370)
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance 
(Adverse) or Favourable
POLICY BOARD :  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ ENVIRONMENT AND INFRASTRUCTURE

Page 11

APPENDIX 2 
 
 
 
 
 
Subjective Summary
Approved 
Annual Budget 
at Period 8
Budget 
Adjustments
Revised Annual 
Budget at 
Period 10
Projected 
Outturn
Previous 
Projected 
Outturn 
Variance
Movement
 
£000 £000 £000 £000 £000 % £000 £000
Employees 41,338 (11,614) 29,724 29,724 0 0.0% 0 0
Premises Related 3,018 66 3,084 3,084 0 0.0% 0 0
Transport Related 12 0 12 12 0 0.0% 0 0
Supplies and Services 2,469 1,454 3,923 3,923 0 0.0% 0 0
Third Party Payments 333 0 333 333 0 0.0% 0 0
Transfer Payments 3,449 (5,047) (1,598) (1,598) 0 0.0% 0 0
Support Services 965 0 965 965 0 0.0% 0 0
Depreciation and Impairment Losses 7,177 0 7,177 7,177 0 0.0% 0 0
GROSS EXPENDITURE 58,761 (15,141) 43,620 43,620 0 0.0% 0 0
Income (12,890) 0 (12,890) (12,890) 0 0.0% 0 0
NET EXPENDITURE 45,871 (15,141) 30,730 30,730 0 0.0% 0 0
Subjective Heading
Budget Adjustments
Key Reasons for Significant Projected Variances
The budget transfer relates to the allocation of budgets to other Council services for the 2022/23 local government pay award, as 
well as transfers to earmarked reserves.
Budget Variance 
(Adverse) or Favourable
POLICY BOARD :  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ MISCELLANEOUS
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023

Page 12

APPENDIX 2 
 
 
 
 
Prior Years Approved   Budget  Revised  Projected 
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2022* 2022‐23 in 2022‐23 2022‐23 2022‐23 Budget Outurn 
Project Title to 31‐Mar‐27 to 31‐Mar‐27
£000 £000 £000 £000 £000 £000 £000
CORPORATE PROJECTS
ICT Infrastructure Maintenance & Renewal Programm 0 1,585 (88) 1,497 1,497 0 0% 3,927 3,927 0 0%
Strategic Asset Management Fund 0 1,800 (1,800) 0 0 0 0% 0 0 0 0%
Energy Efficiency Programme 0 102 0 102 102 0 0% 102 102 0 0%
Lifecycle Capital Maintenance (LCM) Fund 0 5,090 (2,730) 2,360 2,360 0 0% 12,456 12,456 0 0%
Artificial Pitch Upgrades 0 0 1,200 1,200 1,200 0 0% 1,200 1,200 0 0%
Digital Infrastructure Provision 1,546 0 390 390 390 0 0% 1,936 1,936 0 0%
Commnunity Empowerment Fund 349 293 309 602 602 0 0% 951 951 0 0%
Greenspaces and Parks 946 237 (237) 0 0 0 0% 936 936 0 0%
Villages Improvement Fund 0 0 350 350 350 0 0% 350 350 0 0%
Retail Improvement Fund 0 0 150 150 150 0 0% 150 150 0 0%
CO2 Monitors 0 0 233 233 233 0 0% 233 233 0 0%
TOTAL FINANCE, RESOURCES & CUSTOMER 
SERVICES BOARD 2,841 9,107 (2,223) 6,884 6,884 0 0% 22,241 22,241 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Budget Variance (Adverse) or 
Favourable
Budget Variance (Adverse) or 
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY ‐ NON‐HOUSING SERVICES
1st April to 6th January 2023
POLICY BOARD: FINANCE, RESOURCES & CUSTOMER SERVICES
Current Year 2022‐23 Full Programme ‐ All years