CAR Notification of Increase in Costs - Traffic Signals

Renfrewshire Council · 9 February 2023
Back to Finance, Resources and Customer Services Policy Board — 9 February 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 9 February 2023
___________________________________________________________________
Report by: The Chief Executive and the Director of Environment and
Infrastructure
___________________________________________________________________
Heading: Notification of Increase in Value for the Contract for Traffic
Signals Planned and Unplanned Inspection and Maintenance
reference RC-CPU-19-173
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to notify the Finance, Resources and Customer
Services Policy Board of an increase in the value of the Contract for Traffic
Signals Planned and Unplanned Inspection and Maintenance reference RC-
CPU-19-173 as a result of additional traffic signal improvement work that was
instructed as unplanned maintenance under this contract. 
1.2 This increase in value for this contract is reported in accordance with Standing
Orders Relating to Contracts 20.3. 
1.3 Approval was given at the Finance, Resources and Customer Services Policy
Board on 25 March 2020 to award the contract for Traffic Signals Planned and
Unplanned Inspection and Maintenance reference RC-CPU-19-173, to Dynniq
UK Ltd (who subsequently changed their name to Swarco UK & Ireland Ltd)
for the value of £800,000 excluding VAT.
___________________________________________________________________ 
2. Recommendations
2.1 The Finance, Resources and Customer Services Policy Board is asked to:

Page 2

2.1.1 Note that this report is made in accordance with Standing Order 20.3 of the
Standing Orders Relating to Contracts 2022.
2.1.2 As a result of the additional traffic signal improvement work, authorise an
increase in the contract value from £800,000 up to £1,200,000 excluding VAT
to include for the works detailed in 3.3 below and to allow for the current
planned maintenance works to be able to continue until the contract can be
retendered. 
_________________________________________________________
3. Background
3.1 Renfrewshire Council has a statutory obligation to maintain and approve all
the traffic signals in operation within the Council area. 
3.2 Traffic signals improvement work was part of the specification requirements
under the Traffic Signals Planned and Unplanned Inspection and Maintenance
contract, reference RC-CPU-19-173. The contract was awarded to Dynniq UK
Ltd who subsequently changed their name to Swarco UK & Ireland Ltd.
3.3 The scope of the additional work was not included as part of the original
contract however additional funding was awarded to the Council to allow
traffic signal improvement work to be undertaken.  The increase in contract
value for the traffic signals improvement work is noted below:
Location Description of Works Total Amount
Penilee Rail Bridge,
Paisley
Refurbishment of existing
traffic signals
£19,441.33
Blackstoun
Road/Falcon
Crescent, Paisley
Refurbishment of existing
pedestrian crossing
£12,051.35
Hawkhead Road/St
Andrews Academy,
Paisley
Refurbishment of existing
pedestrian crossing
£12,875.35
Glasgow
Road/Kirkaig
Avenue, Renfrew
Refurbishment of existing
dual pedestrian crossing
£21,521.38
Pegasus
Avenue/Phoenix
Retail Park, Paisley
Refurbishment of existing
dual pedestrian crossing
£21,536.28
Sandy Road
Junctions, Renfrew
Design costs for 3 junctions £13,959.49
Sandy
Road/Broadloan,
Renfrew
Supply and Install new
signalised junction
£103,783.37
Sandy
Road/Newmains
Road, Renfrew
Supply and Install new
signalised junction
£125,752.69

Page 3

Brediland
Road/Mannering
Road, Paisley
Supply and install new
signalised pedestrian
crossing
£21,620.70
Glenburn
Road/Braehead
Road, Paisley
Supply and install new
signalised pedestrian
crossing
£53,887.65
Greenock Road
near Clark Street,
Paisley
Supply and  install new
signalised pedestrian
crossing
£46,084.80
Penilee Road near
School Road,
Paisley
Supply and install new
signalised pedestrian
crossing
£35,046.00
Sandy
Road/Haining Road,
Renfrew
Supply and Install new
signalised junction
£101,941.63
Gleniffer
Road/Donaldswood
Road, Paisley
Supply and install new
signalised pedestrian
crossing
£27,665.64
B790 Houston Road
between the
roundabout and
Leeburn Avenue
Supply and install new
signalised pedestrian
crossing
£50,126.00 
3.4 The Traffic Signals Planned and Unplanned Inspection Maintenance
contract has provision for instructing this type of work. Regulation 72(1)(b)
of the Public Contracts (Scotland) Regulations 2015 allows for
modifications of contracts during their term without a new procurement
procedure: (b)to provide for additional works, supplies or services by the
original contractor that have become necessary and were not included in
the initial procurement, where a change of contractor—
(i)cannot be made for economic or technical reasons such as
requirements of interchangeability or interoperability with existing
equipment, services or installations procured under the initial
procurement; and
(ii)would cause significant inconvenience or substantial duplication of
costs for the contracting authority,
provided that any increase in price does not exceed 50% of the initial contract
value. 
3.5 A new procurement exercise for Traffic Signals Planned and Unplanned
Inspection and Maintenance is currently being prepared and is expected that
this new contract will commence July 2023. 
___________________________________________________________________

Page 4

Implications of the Report
1. Financial 
The cost of this additional work was met by funding from Capital –
General Services and Strathclyde Partnership for Transport. 
2. HR & Organisational Development 
Not applicable 
3. Community/Council Planning –
Reshaping our place, our economy and our future – the Contract
supports the delivery of this outcome. 
4. Legal 
The work was instructed under an existing Council contract and is
subject to the Council’s Standing Orders Relating to Contracts. 
5. Property/Assets
The Contract will improve the Council’s road infrastructure. 
6. Information Technology 
No Information Technology implications have been identified or are
anticipated.
. 
7. Equality & Human Rights
The Recommendations contained within this report have been
assessed in relation to their impact on equalities and human rights. No
negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report because.  
8. Health & Safety 
Swarco UK & Ireland Ltd’s health and safety credentials were
evaluated by Corporate Health and Safety and met the Council’s
requirements regarding health and safety. 
9. Procurement 
The procurement procedures outlined within this report shall ensure
that the Council meets its statutory requirements in respect of
procurement procedures, efficiency and modern Government. 
10. Risk 
Swarco UK & Ireland Ltd have been assess and evaluated to confirm
that they have met the minimum requirements regarding insurable risk.

Page 5

11. Privacy Impact 
No Privacy Impact implications have been identified or are anticipated. 
12. Cosla Policy Position 
No Cosla Policy implications have arisen or are anticipated. 
13. Climate Risk 
The level of impact associated with the provision of this work has been
assessed using the Scottish Government Sustainability Test and is
considered to be low risk.
_________________________________________________________
Author:          Brian Bradley, Assistant Category Manager, Corporate Procurement