To:  Finance, Resources and Customer Services Policy Board 
On:  9 February 2023 
Report by: Director of Environment & Infrastructure 
Heading: Facilities Management Operational Performance Report 
1          Summary
1.1 Environment & Infrastructure brings together a range of Council services and 
activities, with both strategic and operational responsibilities.  This report provides an
operational performance update on Facilities Management (Hard and Soft Services - 
including Building Services) and delivered by Environment & Infrastructure since the
last Policy Board in November 2022. 
2         Recommendations 
It is recommended that the Finance, Resources and Customer Services Policy
Board: 
2.1  Approves the content of this report. 
3 Operational Update 
3.1 Supplies and Materials
Building Services continue to operate normal day to day business and our
emergency out of hours repairs.  However, the service continues to experience
delays in the provision of some resources and materials. This is being managed
within the programming of works.

Page 2

3.2 Responsive Repairs 
The chart below shows the volume of responsive repairs reported by tenants on a
weekly basis for the third quarter of this year. This shows that on average 40-47% of
all repairs reported within this period are classed as ‘Emergencies’ or ‘Qualifying
repairs’ that require either a same day or next day visit. This makes planning repair
works outside of these categories challenging. 
Of the emergencies / qualifying repairs that were reported, 25-30% of these were out
of normal working hours and required a standby operative to attend. 
3.3 Service provision – weather impact
In the week beginning 13 December 2022, Renfrewshire experienced a very cold
snap of weather. Building Services attended over 1,700 emergencies reporting no
heating and hot water and colleagues in Hard FM attended calls across the public
buildings portfolio, including schools. 
As the weather warmed and thawed, the service worked 24/7, 7 days a week to keep
schools open, address heating problems and resolve plumbing issues across the
Council public building estate and housing stock. Most staff gave up planned annual
leave to help ensure every call was responded to as quickly as possible. 
1581
1708
1554 1463
1671 1621 1611
1480 1588
1790
3020
1668
658663 688 662 571 587 683 699 698 738 841
2238
864
559
160 171 151 144 116 164 160 211 193 251
522
204
343
0
500
1000
1500
2000
2500
3000
3500
WC 3-10-22
WC 10-10-22
WC 17-10-22
WC 24-10-22
WC 31-10-22
WC 07-11-22
WC 14-11-23
WC 21-11-24
WC 28-11-22
WC 5-12-22
WC 12-12-22
WC 19-12-22
WC 26-12-22
Repairs reported Quarter 3 - 2022
total number of repairs total emergencies

Page 3

3.4  Domestic Gas Servicing 
In quarter 3 (October - December) 2022/23, the domestic gas servicing and repairs
team carried out 2,379 gas services. Of these, 189 services were not able to be
completed due to no access being granted at the time of the visit. These 189
services will move forward in the Housing Services process so the Council can gain
access to the properties prior to the 1-year anniversary of the gas service and ensure
full compliance. It should be noted that during the winter months, Officers profile to
have less gas servicing to allow the resources to realign onto responsive and
emergency calls as these calls rise substantially as the weather gets colder. The
figures for quarter 3 are in line with the same quarter last year where the Services
carried out 2,436 gas services with 287 instances of no access. 
3.5 Aids and Adaptations
In the third quarter of 2022 (October – December), Building Services completed 30
full adaptations and currently have 13 live jobs at various stages. These are currently
booked in across early February.   
3.6 Voids
3.6.1 Building Services continue to work closely with Housing Services to maximise the
number of houses that are returned to the letting pool and prioritise houses based on
current needs of those requiring housing. A total of 144 voids have been completed
and returned to the letting pool in quarter 3 of 2022/23. This makes a total of 526
voids returned to the letting pool in 2022/23 to the end of quarter three. 
3.6.2 The volume of works within void houses remains high, often due to the age of the
property or the condition that it has been left in by the vacating tenant. 
As at the 31 December, Housing Services have 170 void properties. This is a
reduction of 39 since the previous board report. 
Void Returns Quarter 3 – 2022/23
Full Void Works*
*Inclusive Gas
Central Heating
(GCH) install
*Inclusive
Asbestos
Removal 
(ASB RE)
Preliminary Works
144 19 20 126 
In addition to routine voids there is an additional SHQS programme which 
carries out more extensive works within the properties.  In the last quarter 
there has been 25 SHQS properties returned, in total 94 properties have been 
returned to housing since April 2022. In conjunction with Housing Services 
there is a collective agreement to pause SHQS properties passed to Building
Services to allow resources to be targeted at routine voids.

Page 4

3.7 Electrical Testing programme
As part of the on-going electrical compliance requirement of Landlords, Building
Services, and other external contractors, have been working in partnership with
Housing Services to carry out the statutory 5-year check of electrics within every
tenanted household cross Renfrewshire (approx. 12,500 houses). 
2022 - 2023
Quarter 1 - 639 
Quarter 2 - 280 
Quarter 3 – 42 
Since the beginning of 2021 a total of 3,853 houses have been fully electrical tested
by Building Services. 
Where it has not been possible to gain access to carry out the statutory checks, a
process has been implemented to ensure continued compliance standards are met.
The pilot process commenced on the 12 December 2022. 
3.8 Streetlighting 
In the third quarter of the year the Street Lighting Team performed well with 99.35%
of all reported dark lamps attended within the 7-day timescale. In addition, they
attended 123 emergencies. 
Overall, in the first 3 quarters of 2022/23, April to December, the Street Lighting team
have attended 455 emergencies. 
3.9 Capital Works across Public Building Portfolio
3.9.1 The £1.5 million extended school toilet upgrade programme is progressing well with
11 schools now completed and 2 others in progress with completion of all
programmed for February.  We are also carrying out an additional refurbishment at
Ferguslie Pre 5’s centre and works commenced in late January. 
3.9.2 Works have now been completed on the replacement of two full kitchens in the
specialist HSCP young person’s facilities in Blackhall, Paisley. 
3.9.3 Building Services have prepared quotes for the replacement of five kitchens in
Renfrewshire Health and Social Care Partnership (HSCP) care home premises.  It is
anticipated that this work will commence in mid-February 2023. 
3.10  Work Hub 
Extensive work continues implementing the new Work Hub application across
Building Services. A patch and upgrade has been applied to the system in January
2023 which will allow all operatives in Building Services to use the digital job
management system in February 2023 following appropriate testing of the system. 
Training has also been undertaken with colleagues in Housing Services on the data
information application - Info Suite. This will allow reporting to be undertaken
timeously.

Page 5

Work also continues to manually reconcile all invoices to the ledger to ensure
accurate financial planning for the end of the financial year. 
3.11 Energy  
Installation of LED Lighting 
The installation programme is now complete with a reduction in electricity usage
being noted at each of the completed schools. To date Renfrewshire Council has
spent £1,588,465, with the remaining balance due to be invoiced imminently. Officers
continue to work across the Council and also with colleagues in the PPP schools to
ensure systems are working at their optimal performance.
Local Heat and Energy Efficiency Strategies (LHEES)
The recruitment of an officer to implement the Local Heat and Energy Efficiency
Strategy (LHEES) for Renfrewshire is underway. The Officer will come into post and
working alongside a consultant, look to work with partners to deliver the statutory
requirement of a strategy and action plan by the end of December 2023. Funding has
been provided by the Scottish Government to allow work to be undertaken and works
will align and feed into the wider Renfrewshire Council Net Zero targets. 
CO2 Monitoring
CO2 monitoring within teaching spaces continues with 1,765 monitors installed and
monitored. The funding for the 2 monitoring officers ends in May 2023, by which point
it is expected that the process will be become part of the “business as usual” running
of the school. Discussions remain on-going between Facilities Management and
Children’s Services with a meeting being arranged with the Teaching Trade Unions in
early February to discuss the monitors. 
4 Soft FM (Facilities Management)
4.1  Project Search Placements 
Project Search is an employability programme designed specifically for young adults
with learning disabilities and/or autism. The aim being to assist young adults into full-
time employment through providing skills, coaching and work experience. Soft
Facilities Management are pleased to be working alongside Project Search to provide
work placements for candidates over a period of 10 weeks within school settings.
Project Search candidates have been undertaking tasks such as catering for school
lunches, cleaning of premises and assisting with compliance related duties. Each
candidate has been allocated an onsite mentor within Soft Facilities Management
who has been overseeing their progress and helping with their professional
development. The initial candidates have now completed their full 10-week
programme with some wishing to return to gain further experience within facilities
management. The service has been thrilled to be able assist them on this continued
journey. Soft Facilities Management staff have been excited to welcome the next
group of candidates who started their placements in January 2023.

Page 6

4.2 Suited Lock system 
Soft FM, in conjunction with the approved contractor, have installed a suited lock
system in all Renfrewshire schools, ELCC’s and Community Centres. The system
works using programmable keys and cylinders to help the service have increased
control of building access rights. Soft FM can update each key remotely, removing or
granting access privileges for the key holder in real time. By ensuring only those with
the necessary access rights can enter a property, this eliminates the security risks
associated with lost and stolen keys. In addition, the ability to update access rights
remotely ensures the building can be opened even if the Senior Facilities Operative
usually onsite is not available due to absence, annual leave etc. The contractor had
not considered using the system in this way and felt that this was an innovative
approach to improving the security of Council buildings. The project recently won
Security Project of the year at the Fire & Security Matters Awards. 
4.3 Recruitment of Strategic Facilities Manager (Soft FM) 
Following the above post becoming vacant, Environment & Infrastructure has
undertaken a recruitment exercise with the new Officer taking up post in late
February 2023. 
4.4 Capital Works
The Scottish Government capital funding award of £876,000 will enable full redesign
of kitchens within Barsail Primary School, Erskine, Bushes Primary school, Glenburn
and Mossvale/St James Campus, Paisley. Soft FM have been working in partnership
with Property & Technical Services and Corporate Procurement to progress the
tender award. With an end date of late 2023 for completed development, 75% of
primary schools will have returned to fully functioning production kitchens. These
developments will support the delivery of meals to the remaining school premises
and early years establishments. Further capital award funding from the Scottish
Government may provide scope to increase this number further along with further
improvements to established premises. Since the introduction of Universal Free
School Meals (UFSM) in Aug 2021, production facilities in primary schools have
increased from 12 to 23 kitchens, with a further four scheduled to be producing meals
by March 2023. The increase of production kitchens has created eleven full time
Senior Facilities Operative - Production Catering positions and 39 part time Facilities
Operatives positions throughout Renfrewshire in 2022. It is expected that further
recruitment will be required as works progress in 2023. 
Implications of the Report 
1.  Financial – Any financial elements referenced in this report will be progressed
through the Council’s financial & budget planning process. Capital funding projects
e.g. £876k for school kitchen upgrades are highlighted with the budget allocated to
be spent delivering the project, with appropriate financial monitoring in place.

Page 7

2.  HR & Organisational Development – None 
3. Community/Council Planning – the report details a range of activities which reflect
local community and council planning themes. 
4.  Legal – None 
5.  Property/Assets - None   
6.  Information Technology - None 
7.  Equality & Human Rights – The recommendations contained within this report have
been assessed in relation to their impact on equalities and human rights. No
negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in
the report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored, and the
results of the assessment will be published on the Council’s website. 
8.  Health & Safety – Advice and guidance is being given to protect the health and
safety of employees and service users when carrying out priority services for the
Council in line with government and health guidance. 
9.  Procurement – All capital projects detailed within this report have been discussed
with Corporate Procurement to ensure compliance with national legislation and
guidance. 
10.  Risk – None 
11.  Privacy Impact – None 
12.  COSLA Policy Position – None 
13.  Climate Change – The work undertaken by the Energy Management Unit detailed in
the report assists with Renfrewshire’s Net Zero targets. Close liaison is maintained
with the Climate Emergency Lead Officer to help drive targets, actions and
outcomes. 
List of Background Papers - none 
Author: Gordon McNeil, Director of Environment & Infrastructure