To: Finance, Resources and Customer Services Policy Board
On: 17 November 2022
___________________________________________________________________
Report by: The Chief Executive 
___________________________________________________________________
Heading: Annual Procurement Report 2021/2022
___________________________________________________________________
1. Summary 
1.1 Section 18 of the Procurement Reform (Scotland) Act 2014, requires
that any contracting authority which is required to prepare or revise a
procurement strategy in relation to a financial year must prepare an
annual procurement report on its regulated procurement activities as
soon as reasonably practicable after the end of that financial year. 
1.2 As a minimum this report must include: 
• a summary of the regulated procurements that have been completed
during the year covered by the report;
• a summary of community benefits fulfilled during the year covered by
the report;
• a summary of any steps taken to facilitate the involvement of supported
businesses in regulated procurements during the year covered by the
report; and 
• a summary of the regulated procurements the authority expects to
commence in the next two financial years. 
2 The Annual Report attached in Appendix 1, provides an update on key
indicators set in the Corporate Procurement Strategy for the period
April 2020-2023.

Page 2

___________________________________________________________________ 
2. Recommendations 
2.1 The Finance, Resources and Customer Services Policy Board are
asked to note the content of the Annual Report for the Financial Year
2021-2022.  
_________________________________________________________
3. Background
3.1 Section 18 of the Procurement Reform (Scotland) Act 2014 requires
that all public sector contracting authorities with a spend of more than
£5million per annum publish an Annual Report relating to Regulated
procurement activity.  The content of the Annual Report is analysed by
Scottish Government Procurement and the information included in the
Scottish Ministers Annual Report on Procurement Activity in Scotland.
3.2 The Annual Report provides an opportunity to provide an update on
procurement activity undertaken over the last financial year, and to give
an indication of future contracting opportunities.
3.3 A Regulated Procurement is any procurement for: 
• Goods, Supplies and Services (excluding services covered under
Schedule 3 Social and Other Specific Services of the Public Contracts
(Scotland) Regulations 2015) with a total value of £50,000 up to
£177,896.99;
• Services defined under Schedule 3 Social and Other Specific Services
of the Public Contracts (Scotland) Regulations 2015 with a total
contract value of £50,000 up to £552,949.99;
• Works contracts with a total value of £2million up to £4,447,446.99.
3.4 A procurement at or above the Threshold set by the Government
Procurement  Agreement is any procurement for:
• Goods, Supplies and Services (excluding services covered under
Schedule 3 Social and Other Specific Services of the Public Contracts
(Scotland) Regulations 2015) with a total value of £177,897 and above;
• Services defined under Schedule 3 Social and Other Specific Services
of the Public Contracts (Scotland) Regulations 2015 with a total
contract value of £552,950 and above; and
• Works contracts with a total value of £4,447,447 and above.
(The above amounts are excluding VAT)

Page 3

3.5 The information provided in the Annual Report is gathered by Scottish
Government and included in the national “Annual Report on
Procurement Activity in Scotland.”  
3.6 The Annual Report provides an opportunity to recognise the
contribution that procurement can make to the economy and
communities in Renfrewshire and to celebrate the success of the
procurement team. 
3.7 Appendix 1 contains the Annual Report for the Financial year 2020 –
2021. 
___________________________________________________________________
Implications of the Report
1. Financial - None.   
2. HR & Organisational Development - None. 
3. Community/Council Planning –   
All of the activities carried out by the Corporate Procurement Unit
contribute to Renfrewshire Council’s Plan for 2017 - 2022 “Thriving
People, Connected Communities”.  The 5 Strategic Outcomes set out
in the plan are at the heart of our procurement activities and CPU work
with client services to ensure that Council funds are spent in a way that
can deliver the most benefit to Renfrewshire’s communities.  
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been
assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for
infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report. 
8. Health & Safety – None.

Page 4

9. Procurement – the attached Annual Report identifies how the Council
is meeting the requirements of the Procurement Reform (Scotland) Act
2014.
10. Risk - None 
11. Privacy Impact - None. 
12. Cosla Policy Position – None.
13. Climate Risk - None
_________________________________________________________ 
Author:           Bridget Lambert (Strategic Procurement Manager) 
bridget.lambert@renfrewshire.gov.uk

Page 5

APPENDIX 1 – ANNUAL PROCUREMENT REPORT 2019/2020
(Attached)