Democracy Spraffa

Minutes of meeting

Renfrewshire Council · 11 September 2025
Back to Finance, Resources and Customer Services Policy Board — 11 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Minute of Meeting
Finance, Resources and Customer Services Policy Board
Date Time Venue
Thursday, 11 September
2025
10:00 Remotely via MS Teams,
Present: Councillor Fiona Airlie-Nicolson, Councillor Alison  Ann-Dowling, Councillor
Jacqueline Cameron, Provost Lorraine Cameron, Councillor Graeme Clark, Councillor
Audrey Doig, Councillor Chris Gilmour, Councillor Edward Grady, Councillor Neill Graham,
Councillor Robert Innes, Councillor Bruce MacFarlane, Councillor Sam Mullin, Councillor Iain
Nicolson, Councillor John Shaw
Chair
Councillor Shaw, Convener, presided.
In Attendance
A MacArthur, Director of Finance & Resources; L McIntyre, Head of Policy & Partnerships
and B Walker, Programme Director (City Deal & Infrastructure) (both Chief Executive's); C
Dalrymple, Head of Facilities & Property Services, L Feely, Head of Housing Services and
P MacIver, Technical Services Programme Manager (all Environment, Housing &
Infrastructure); and R Cree, Head of People & Organisational Development, M Conaghan,
Head of Corporate Governance, C McCourt, Head of Finance & Procurement, P Murray,
Head of Digital, Transformation & Customer Services, E Shields, Strategic Service Delivery
Manager, J Bowles, Purchase to Pay – Programme Operational Lead, L Gillan, Interim
Corporate Procurement Manager, G Beattie, A Donaldson and R Park, all Strategic
Category Managers, B Bradley and J Tannock, both Assistant Category Managers, G
Gordon, Senior Procurement Specialist, E Simpson, Strategic Lead Partner (Organisational
Development), L Currie, Managing Solicitor (Projects), Y McLachlan, People Adviser and E
Gray and R Devine, both Senior Committee Services Officers (all Finance & Resources).
Webcasting of Meeting
Prior to the commencement of the meeting the Convener intimated that this meeting of the
Policy Board would be filmed for live or subsequent broadcast on the Council's internet site.

Page 2

Declarations of Interest
There were no declarations of interest intimated prior to the commencement of the
meeting.
Transparency Statements
Councillor Gilmour declared a connection to item 10 by reason of being a supporter of
Johnstone Burgh Football Club and an ex-officio member of Howwood Community
Council. However, he indicated that he had applied the objective test and did not
consider he had an interest to declare.
1 Joint Consultative Board (Non-Teaching)
There was submitted the Minute of the meeting of the Joint Consultative Board (Non-
Teaching) held on 12 June 2025, a copy of which forms Appendix 1 of this Minute.
DECIDED: That the Minute be noted.
2 Investment Review Board
There was submitted the Minute of the meeting of the Investment Review Board held
on 11 June 2025, a copy of which forms Appendix 2 of this Minute.
DECIDED: That the Minute be noted.
3 Revenue and Capital Budget Monitoring 2025/26 at 27 June 2025
There was submitted a revenue and capital budget monitoring report by the Director
of Finance & Resources for the period to 27 June 2025. The report intimated that the
projected revenue outturn at 31 March 2026 for those services reporting to this Policy
Board was an underspend of £0.683 million (0.6%) against the revised budget for the
year. The projected capital outturn at 31 March 2026 was a breakeven position. A
number of revenue and capital budget adjustments were detailed at sections 6 and 7
of the report respectively.
DECIDED:
(a) That the projected revenue outturn overspend position of £0.683 million be noted;
(b) That the projected capital outturn break-even position be noted; and
(c) That the budget adjustments detailed at sections 6 and 7 of the report be noted.

Page 3

4 Revenue and Capital Budget Monitoring – Council Overview as at 27
June 2025
There was submitted an update report by the Director of Finance & Resources
relative to an overview of revenue and capital budget expenditure for the Council as at
27 June 2025. The report detailed that the total projected revenue outturn position for
the Council, the Health & Social Care Partnership and Housing Revenue Account as
at 31 March 2026 was an overspend of £7.823 million (1.3%) and the projected
capital outturn for all services was a breakeven position, split between General Fund
services and the Housing Revenue Account. Further analysis was detailed in the
appendices of the report.
DECIDED:
(a) That the projected revenue outturn overspend position of £7.823 million be noted;
(b) That the projected capital outturn break-even position be noted; and
(c) That the prudential indicators detailed in section 7 of the report be noted.
5 Business Services Performance Report
There was submitted a report by the Director of Finance & Resources relative to the
performance of key business services functions, including revenue collection and
benefit administration, for the period ending 28 July 2025.  Appendices to the report
provided information on revenue collection and key performance indicators.
DECIDED: That the content of the report be noted.
6 Business Services Accounts for Write Off
There was submitted a report by the Director of Finance & Resources relative to a
proposed write off of Council Tax, Non-Domestic Rates, housing benefit overpayment
and sundry debtors' accounts for sums over £10,000 where recovery was no longer
viable. The value of the debt to be written off was £553,486.52 and a breakdown of
this figure was provided at tables 1 - 4 and Appendix 1 of the report.
Councillor Shaw proposed that a development session for elected members be
arranged to cover the process followed by officers prior to proposing that debts be
written off and that the session would take place prior to the consideration of the
next Business Services Accounts for Write Off report, scheduled to be submitted to
the meeting of this Policy Board to be held on 5 February 2026. This was agreed
unanimously.
DECIDED: 
(a) That the write off of £553,486.52, as detailed in tables 1 - 4 of the report, be
authorised; and
(b) That it be agreed that a development session for elected members be arranged to

Page 4

cover the process followed by officers prior to proposing that debts be written off and
that the session would take place prior to the consideration of the next Business
Services Accounts for Write Off report at the meeting of this Policy Board to be held
on 5 February 2026.
7 Customer Services Performance Report
There was submitted a report by the Director of Finance & Resources relative to
performance of key customer services functions including call centre, face-to-face and
digital support for customers during July 2025. The report provided an update on the
overall contact centre call handling volumes, implementation of the Digital Advisor
(Millie) and indicated that face-to-face services continued in Renfrewshire House.
Details of customer volumes were provided in the report. The report advised that
demand for Digital Services remained high and provided an update on the level of
online transactions being completed.
DECIDED: That the contents of the report be noted.
8 Local Government Terms and Conditions of Employment
Under reference to item 7 of the Minute of the meeting of this Policy Board held on 12
June 2025, there was submitted a report by the Director of Finance & Resources
relative to the ongoing process to modernise the Council's terms and conditions of
employment. The report provided detail on the progress of negotiations between the
Council and Trade Unions and summarised the final offer which had been presented
to the Unions. It was expected that Union members would be balloted on the
proposals and a report on the outcome and proposed next steps would be submitted
to the meeting of this Policy Board to be held on 20 November 2025.
DECIDED:
(a) That the status of discussions with Unison, Unite, and GMB Trade Unions be
noted;
(b) That it be noted that officers were fully prepared to implement the proposals
promptly should the ballot results return an acceptance;
(c) That it be noted that formal negotiations would conclude if the ballot results return
a rejection, as all reasonable efforts to reach agreement had been made; and
(d) That it be noted that a final update detailing the ballot outcome and the Council’s
intended next steps would be submitted to the meeting of this Policy Board to be held
on 20 November 2025.
9 ‘People Strategy 2021/26’ - Revised HR&OD Policies
There was submitted a report by the Director of Finance & Resources relative to
proposed revisions to the Councils Equality, Diversity & Inclusion and Respect at
Work Policies. The revised policies were set out at Appendices 1 and 2 of the report
respectively and the key changes were noted within the report.

Page 5

DECIDED: That both the revised Equality, Diversity & Inclusion Policy and Inclusion
and Respect at Work Policy, set out at Appendices 1 and 2 of the report respectively,
be approved.
10 Civic Hospitality
There was submitted a report by the Director of Finance & Resources relative to
consideration of requests received by the Provost for civic hospitality from
organisations for specific events as detailed within the report. The proposed type and
cost of civic hospitality to be provided in respect of each civic event was set out in
Section 1 of the report and authorisation was sought for the Director of Finance &
Resources, in consultation with the Provost, to make the necessary arrangements to
provide civic hospitality, or in the case of events that had already been arranged, to
homologate the action taken by the Head of Corporate Governance. The report
advised that the budget provision for 2025/26 for civic hospitality (including
international links) was £46,460 and it was noted that should the proposed hospitality
be agreed, taking account of previous decisions, the remaining balance would be
approximately £10,900.
DECIDED:
(a) That the provision of hospitality as detailed in Section 1 of the report for Johnstone
Burgh Football Club, Paisley & District Battalion of the Boys Brigade, 14th Paisley
Company of the Boys Brigade, Paisley Abbey, Howwood Community Council, the
Christmas Card Competition winners and Carol Concert, Renfrewshire Carers Centre
and Paisley & District Short Carpet Bowling Association Ladies Section be approved;
(b) That the Director of Finance & Resources, in consultation with the Provost, be
authorised to make the necessary arrangements for the hospitality detailed above;
and
(c) That the action taken by the Head of Corporate Governance, in terms of his
delegated authority, in respect of the Renfrew Burgh Flag Raising and the 90th
Anniversary of Lochfield Bowling Club Ladies Section be noted.
11 Facilities and Property Services - Service Update Report
There was submitted an update report by the Director of Environment, Housing &
Infrastructure relative to the operational performance of Facilities Management (Hard
and Soft Services, including Building Services) and Property Services as delivered by
Environment, Housing & Infrastructure since the last meeting of this Policy Board.
DECIDED:
(a) That the content of the report be noted; and
(b) That the addition of the cobotics project, as detailed in section 4.3.3 of the report,
into the Capital Plan 2025/26, with funding secured from revenue underspends
(CFCR) be approved.

Page 6

12 Contract Authorisation Report: Framework Agreement for the
Provision of Trades Contractors (RC-CPU-24-163)
There was submitted a joint report by the Directors of Finance & Resources and
Environment, Housing & Infrastructure relative to the award of a Framework
Agreement for the Provision of Trades Contractors, reference RC-CPU-24-163
(“Framework Agreement”). The scores achieved by each tenderer per lot were set out
at Appendix 1 of the report together with a summary of the ranking and places on the
Framework to be award at Appendix 2.
DECIDED:
(a) That the Head of Corporate Governance be authorised to enter into a multi-
supplier Framework Agreement for the Provision of Trades Contractors, reference
RC-CPU-24- 63 (“Framework Agreement”) with the Suppliers listed in Appendix 2 of
the report;
(b) That the cumulative spend made under this Framework Agreement be authorised
to be up to the maximum approved value of £25,000,000 excluding VAT over the
potential Framework Agreement term of four years, made up as follows:
Participating Organisation Estimated Value excluding VAT
Renfrewshire Council £15,000,000
Renfrewshire Leisure Limited trading
as OneRen £250,000
East Renfrewshire Council £9,750,000
(c) That it be noted that this was a lotted Framework Agreement and that each Lot
was ranked based on the total score achieved by a tenderer during the evaluation
process -  Appendix 1 of the report detailed the scores achieved by each tenderer per
Lot and Appendix 2 detailed those tenderers awarded a place on the Framework as
ranked per Lot;
(d) That it be noted that any Work Packages made under this Framework Agreement
would be awarded using either the selection procedure or the quotation procedure as
contained in the Framework Agreement, that selection of the most appropriate
procedure was at the sole discretion of the purchaser and that Work Packages
ordered by the Council would be subject to the Council’s Standing Orders Relating to
Contracts, the requirements of the individual Work Package and the need to secure
best value; and
(e) That it be noted that the Framework Agreement was intended to commence on 3
November 2025, that the Framework Agreement would be for a period of two years
with the Council, not other purchasers, having sole discretion to extend the
Framework Agreement for a period of up to 12 months on two occasions and that the
exact date of commencement would be confirmed in the Letter of Acceptance for
each of the successful tenderers as noted in Appendix 2 of the report.

Page 7

13 Contract Authorisation Report: Thistle Primary School Advance
Works Contract
There was submitted a joint report by the Directors of Finance & Resources and
Environment, Housing & Infrastructure relative to entry into a Design and Build
Development Agreement (DBDA) for Advance Works with Hub West Scotland Limited
who would wholly subcontract all the Advance Works under this Contract to BAM
Construction Limited.
DECIDED:
(a) That the Head of Corporate Governance be authorised to enter into a Design and
Build Development Agreement (DBDA) for Advance Works with Hub West Scotland
(HWS) Limited who would wholly subcontract all the Advance Works under this
Contract to BAM Construction Limited;
(b) That the award of the Advance Works Contract for £3,048,163.00 excluding VAT
(the Contract Sum) to HWS be authorised;
(c) That a contingency spend of £457,224.45 in relation to the Advance Works
Contract, which equated to 15% of the Contract Sum, be authorised; 
(d) That a total Approved Contract Value for Advance Works of £3,505,387.45, the
total of the Contract Sum plus the contingency spend, be authorised;
(e) That the acceptance of a Limitation on HWS’s Liability for uninsured losses up to
the value of the Contract Sum for the Advance Works Contract, this being the market
standard position, be authorised;
(f) That it be noted that construction associated with the Advance Works Contract was
anticipated to commence in October 2025 and be completed by January 2026.
Specialist design, early procurement and consultant services associated with the
Advance Works Contract commenced in August 2025. Those services and associated
costs were deemed to be subsumed and incorporated into the Advance Works
Contract;
(g) That the acceptance of a Limitation of Liability on Design Consultants to the sums
referred to in section 3.5 of the report on an each and every claim basis except for
claims relating to pollution, contamination, and asbestos, where the limit will be in the
annual aggregate, this being the market standard position, be authorised; and
(h) That it be noted that a further report would be brought to a future meeting of this
Policy Board to seek approval of the award of a Main Works Contract with HWS, and
that this would also be wholly sub-contracted to BAM Construction Limited.

Page 8

14 Contract Award: Construction Works for the Advance Manufacturing
and Innovation District Scotland South (AMIDS-S) Project (RC-CPU-
22-352)
There was submitted a joint report by the Chief Executive and the Director of Finance
& Resources relative to the award of a Contract for Construction Works for the
Advance Manufacturing and Innovation District Scotland South (AMIDS-S) Project
(RC-CPU-22- 52) to Northstone (NI) Limited, trading as Farrans Construction. The
Contract was awarded following a procurement process conducted in accordance with
the Competitive Procedure with Negotiation of the Public Contracts (Scotland)
Regulations 2015 and the Council’s Standing Orders relating to Contracts 1 January
2024.
DECIDED:
(a) That it be noted that the Contract for the Construction Works for the Advance
Manufacturing and Innovation District Scotland South (AMIDS-S) Project (RC-CPU-
22-352) was approved for award under delegated authority to the Chief Executive by
the Council on 26 June 2025;
(b) That it be noted that the contract was awarded to Northstone (NI) Limited, trading
as Farrans Construction;
(c) That the total of the Prices of £34,714,649.54 excluding VAT, a contingency spend
of £4,314,978.56 excluding VAT which equated to 12.43% of the total of the Prices
and total Approved Contract Value of £39,029,628.10, the total of the Prices plus the
contingency spend, be noted;
(d) That it be noted that the Contract Award was 14 August 2025, the starting date
was14 September 2025, the completion date was 130 weeks from the starting date,
and that the Contract included a key date for completion of the works contained in the
East-West Link 1 component (which included the access road to the new Paisley
Grammar School Community Campus) by 30 June 2026;
(e) That it be noted that the contractor’s liability to the Council in accordance with the
published terms detailed in section 3.22 of the report was limited for each of the
following:
• Contractor’s liability to the Client (Council) for indirect or consequential loss was
limited to an amount equivalent to 5% of the total of the Prices at Contract Award;
• Contractor’s total liability to the Client for all matters arising under or in connection
with the contract, other than excluded matters, was limited to an amount
equivalent to 50% of the total of the Prices at Contract Award; and
• Contractor’s liability for Defects due to Contractor design which had not been
listed on the Defects Certificate was limited to £10,000,000 for each and every
claim.
(f) That it be noted that the contractor was required to provide a Performance Bond, in
the form contained in the Final Invitation to Tender, within 4 weeks of Contract Award;
and

Page 9

(g) That it be noted that the contractor was required to provide an Advance Payment
Bond, in the form contained in the Final Invitation to Tender, prior to the Council
making any payment for bridge materials and fabrication off Site.
15 Notification of the award of the Contract for Surface Treatment
2025/2026 (RC-CPU-25-043) under delegated authority granted to the
Corporate Procurement Manager
There was submitted a joint report by the Directors of Finance & Resources and
Environment, Housing & Infrastructure relative to the award of a Contract for Surface
Treatment 2025/2026, reference RC-CPU-25-043, approved for award under
delegated authority granted for the Framework Contract for Roads Related
Maintenance Works, reference RC-CPU-20-172 (“the Framework Contract”), to the
Corporate Procurement Manager by the Finance, Resources & Customer Services
Policy Board on 2 February 2022.
DECIDED: 
(a) That the details of the Contract for Surface Treatment 2025/2026, reference RC-
CPU-25-043, approved for award under delegated authority granted to the Corporate
Procurement Manager at the meeting of this Policy Board on 2 February 2022 for the
Framework Contract for Roads Related Maintenance Works, reference RC-CPU-20-
172, detailed in section 3 of the report, be noted;
(b) That it be noted that the contract starting date was 28 July 2025, and the
completion date was 31 August 2025; and
(c) That the Contract sum of £793,868.50 excluding VAT be noted.