Revenue and Capital Budget Monitoring Report

Renfrewshire Council · 11 September 2025
Back to Finance, Resources and Customer Services Policy Board — 11 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 11 September 2025
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Revenue and Capital Budget Monitoring 2025/26 at 27 June 2025
___________________________________________________________________
1. Summary
1.1 At the close of reporting Period 3 on 27 June 2025, the projected revenue
outturn at 31 March 2026 for those services reporting to the Finance,
Resources and Customer Services Policy Board is an overspend position of
£0.683m (0.6%) against the revised budget for the year. 
1.2 The projected capital outturn at 31 March 2026 for projects reporting to the
Finance, Resources and Customer Services Policy Board is a break-even
position. 
1.3  This is summarised over the relevant services in the table below and further
analysis is provided in the report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
Finance and Resources 49.123 49.192 (0.069) (0.1%)
Environment, Housing and
Infrastructure  27.201 27.741 (0.540) (2.0%)
Chief Executive's Service (Estates) 526 600 (0.074) (14.1%)
Miscellaneous 38.958 38.958 0 0%
Total 115.808 116.491 (0.683) (0.6%)
Capital    
Finance, Resources and Customer
Services Policy Board 9.662 9.662 0 0%

Page 2

2. Recommendations
2.1 Members are requested to: 
a) Note the projected Revenue outturn overspend position of £0.683m;
b) Note the projected Capital outturn break-even position; and
c) Note the budget adjustments detailed at sections 6 and 7. 
3. Revenue Budget Projection – overspend of £0.683m by 31 March 2026
3.1 The tables in Appendix 1 present the projected year-end position for all
services reporting to this Board, by both subjective analysis (what the budget
is spent on) and objective analysis (which division is spending the budget).
Significant variances affecting the projected position are analysed further
below. 
3.2 It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. This is the last Budget monitoring report until the outturn
position is presented to the Council in June. Budget holders are obliged to
seek mitigating action to minimise significant budget variances. 
4. Objective Analysis – Significant Variances
4.1 Finance and Resources - £0.069m overspend
A minor overspend is currently projected in Customer Services, however it is
expected that further turnover and ongoing service reviews will reduce this
amount over the remainder of the financial year. 
4.2 Environment, Housing and Infrastructure - £0.540m overspend
Within Public Building Repairs, there is an anticipated overspend of
£0.500m. This is despite Council investing further into this budget in
2025/26, still owing to the continued inflationary and cost pressures that
have been experienced by the service over the last few financial years. The
position has improved since last year and continues to be closely monitored
by management, with work ongoing to understand the underlying cost
drivers. 
Soft Facilities Management is forecasting an overspend of £0.040m, mainly
due to the continuing inflationary pressures on provisions costs. However,
this overspend is being offset by a projected underspend in employee costs
due to the level of vacancies within the service.

Page 3

4.3         Chief Executive’s Service (Estates) - £0.074m overspend
This forecast position mainly reflects an anticipated under-recovery in rental
income as a result of a property at Houstoun Square held vacant as part of
the delivery of the Johnstone Vision regeneration programme, together with
costs to maintain surplus properties and progress them to sale. 
5. Subjective Analysis – Significant Variances
5.1 Employee Costs - £0.837m underspend 
Environment, Housing and Infrastructure is projecting an underspend of
£1.113m, which reflects current high staff turnover and recruitment
challenges.  This is partly offset by projected overspend in Finance and
Resources (£0.276m) mainly due to lower than expected levels of staff
turnover. This position is being managed and will continue to be monitored
for the remainder of the year. 
5.2 Premises Related - £1.486m overspend 
This projected overspend predominantly relates to repairs and maintenance
in Public Building Repairs due the continued inflationary and cost pressures
that have been experienced by the service over the last few financial years.
It is partly offset by underspends and income elsewhere in the service at
present. The position continues to be closely monitored. 
6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as budget virement. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and
Resources for submission to the relevant policy board for approval. 
6.3. The following significant budget adjustments reflect re-allocations of
approved funding to services, and are therefore for noting only: 
Objective Heading Subjective
Heading
Amount
(£m)
Reason
Miscellaneous Employees (11.839)
Allocation to services of
funding for residual pay
inflation, new ASL funding and
the increase in ENICS

Page 4

Objective Heading Subjective
Heading
Amount
(£m)
Reason
Finance & Resources Employees 0.940 Allocation of funding for ENICS
and residual pay inflation
Environment, Housing
& Infrastructure Employees 0.480 Allocation of funding for ENICS 
7. Capital Budget Projection – break even position by 31 March 2026
7.1 The revised Capital Investment Programme 2025/26 to 2029/30 was
approved by the Council on 1 May 2025. The Finance, Resources and
Customer Services approved capital spend for 2025/26 was £7.577m. 
7.2 The in-year Capital budget is forecast to break even by 31 March 2026,
however, this will be monitored as the projects progress. Further details of
the programme can be found in the Capital Monitoring report at Appendix 2. 
7.3 Budget adjustments have taken place between years to reflect revised
programming of some capital projects. The resulting capital budget for
2025/26 is £9.662m, and details of the adjustments, which amount to
£2.085m, are as follows: 
Project Amount (£m)
Budget brought forward into 2025/26 -  updated cashflows
ICT Infrastructure Maintenance & Renewal Programme 0.214
Lifecycle Capital Maintenance (LCM) Fund 0.828
Artificial Pitch Upgrades 0.486
Digital Infrastructure Provision 0.029
Community Empowerment Fund 0.266
Villages Improvement Fund 0.201
Greenspaces and Parks 0.060
Retail Improvement Fund 0.001
Project Amount 2.085 
Implications of the Report
1. Financial
The projected budget outturn position for Finance, Resources and Customer
Services’ Revenue budget is an overspend of £0.683m (0.6%) at 31 March
2026.  Income and expenditure will continue to be monitored closely for the rest
of the financial year, with steps being taken as far as possible to mitigate any
overspends.

Page 5

The projected outturn position for Finance, Resources and Customer Services’
Capital budget is break-even, after the adjustments outlined at section 7.  
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report.
3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy, and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe, and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report.
5. Property/Assets 
The capital expenditure noted in this report will result mainly in lifecycle
maintenance improvements to existing properties, replacement of ICT assets
and infrastructure and replacement of artificial pitches.
6. Information Technology 
While ICT assets and revenue costs are included within these reported
budgets, there are no direct implications arising from the recommendations in
this report. 
7. Equality & Human Rights 
While new areas of spend may impact on particular groups, any such impact
would be assessed prior to the spend being incurred, therefore there are no
direct implications arising from the recommendations in this report.

Page 6

8. Health & Safety 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets, which may
in some cases improve health and safety measures.
9. Procurement 
While Procurement is an important consideration prior to the Council incurring
any revenue or capital spend, there are no direct implications arising from the
recommendations in this report.
10. Risk 
The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive
and Directors.
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Cosla Policy Position 
N/a
13. Children’s Rights 
There are no direct implications arising from the recommendations in this
report.
14. Climate Change
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report.  
List of Background Papers
 Revenue Budget and Council Tax 2025/26, Council 27 February 2025
 The Capital Investment Programme 2025/26 to 2029/30, Council 27
February 2025 
Author:     Valerie Howie and Lisa Dickie, Finance Business Partners; Alison Burns,
Corporate Finance Manager; and Geoff Borland, Finance Manager.

Page 7

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025              
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES              
Objective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Finance and Resources 47,839 1,284 49,123 49,192 (69) (0.1%)
Environment, Housing and Infrastructure 26,721 480 27,201 27,741 (540) (2.0%)
Chief Executive's Service (Estates) 526 0 526 600 (74) (14.1%)
Miscellaneous 50,960 (12,002) 38,958 38,958 0 0.0%
NET EXPENDITURE 126,046 (10,238) 115,808 116,491 (683) (0.6%)       
Subjective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Employees 116,031 (9,027) 107,004 106,167 837 0.8%
Premises Related 11,074 68 11,142 12,628 (1,486) (13.3%)
Transport Related 2,381 (29) 2,352 2,413 (61) (2.6%)
Supplies and Services 25,907 166 26,073 26,167 (94) (0.4%)
Third Party Payments 1,868 0 1,868 1,859 9 0.5%
Transfer Payments 46,113 505 46,618 46,598 20 0.0%
Support Services 709 (19) 690 688 2 0.3%
Depreciation and Impairment Losses 14,732 0 14,732 14,732 0 0.0%
GROSS EXPENDITURE 218,815 (8,336) 210,479 211,252 (773) (0.4%)
Income (92,769) (1,902) (94,671) (94,761) 90 0.1%
NET EXPENDITURE 126,046 (10,238) 115,808 116,491 (683) (0.6%)

Page 8

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025              
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES              
Objective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Finance and Resources Directorate (964) 105 (859) (850) (9) (1.0%)
Audit Services 604 11 615 605 10 1.6%
Corporate Governance 3,359 82 3,441 3,438 3 0.1%
Digital, Transformation & Customer Services 24,140 590 24,730 24,794 (64) (0.3%)
Finance and Procurement 4,933 67 5,000 4,998 2 0.0%
Business Services 6,884 310 7,194 7,191 3 0.0%
People & Organisational Development 2,223 51 2,274 2,269 5 0.2%
Social care (non-delegated) 818 0 818 836 (18) (2.2%)
Council and Externally Funded Schemes 5,842 68 5,910 5,911 (1) 0.0%
NET EXPENDITURE 47,839 1,284 49,123 49,192 (69) (0.1%)

Page 9

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025              
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES - FINANCE & RESOURCES              
Subjective Summary
Approved
Annual Budget
Budget
Adjustments
Revised Annual
Budget at
Period 3
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Employees 35,328 2,276 37,604 37,880 (276) (0.7%)
Premises Related 2,494 (53) 2,441 2,468 (27) (1.1%)
Transport Related 258 (9) 249 232 17 6.8%
Supplies and Services 11,605 151 11,756 11,710 46 0.4%
Third Party Payments 1,868 0 1,868 1,859 9 0.5%
Transfer Payments 45,518 636 46,154 46,147 7 0.0%
Support Services 428 (19) 409 400 9 2.2%
GROSS EXPENDITURE 97,499 2,982 100,481 100,696 (215) (0.2%)
Income (49,660) (1,698) (51,358) (51,504) 146 0.3%
NET EXPENDITURE 47,839 1,284 49,123 49,192 (69) (0.1%)

Page 10

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025              
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES - ENVIRONMENT, HOUSING AND INFRASTRUCTURE              
Objective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Building Services 109 46 155 155 0 0.0%
Public Building Repairs 6,497 17 6,514 7,014 (500) (7.7%)
Soft Facilities Management Services 19,992 486 20,478 20,518 (40) (0.2%)
Property Services 123 (69) 54 54 0 0.0%
NET EXPENDITURE 26,721 480 27,201 27,741 (540) (2.0%)              
Subjective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised
Annual
Budget at
Period 3
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Employees 33,399 536 33,935 32,822 1,113 3.3%
Premises Related 4,357 121 4,478 5,937 (1,459) (32.6%)
Transport Related 1,812 0 1,812 1,890 (78) (4.3%)
Supplies and Services 12,287 62 12,349 12,464 (115) (0.9%)
Transfer Payments 162 0 162 149 13 8.0%
Support Services 1,240 0 1,240 1,247 (7) (0.6%)
Depreciation and Impairment Losses 1,500 0 1,500 1,500 0 0.0%
GROSS EXPENDITURE 54,757 719 55,476 56,009 (533) (1.0%)
Income (28,036) (239) (28,275) (28,268) (7) (0.0%)
NET EXPENDITURE 26,721 480 27,201 27,741 (540) (2.0%)

Page 11

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025              
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES - CHIEF EXECUTIVE'S SERVICE (ESTATES)              
Subjective Summary
Approved
Annual
Budget
Budget
Adjustments
Revised Annual
Budget at Period 3
Projected
Outturn
Budget Variance 
(Adverse) or Favourable  
£000 £000 £000 £000 £000 %
Employees 0 0 0 0 0 0.0%
Premises Related 1,285 0 1,285 1,285 0 0.0%
Transport Related 0 0 0 0 0 0.0%
Supplies and Services 4 0 4 29 (25) (625.0%)
Third Party Payments 0 0 0 0 0 0.0%
Transfer Payments 66 0 66 66 0 0.0%
Support Services 441 0 441 441 0 0.0%
GROSS EXPENDITURE 1,796 0 1,796 1,821 (25) (1.4%)
Income (1,270) 0 (1,270) (1,221) (49) (3.9%)
NET EXPENDITURE 526 0 526 600 (74) (14.1%)

Page 12

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2025/26
1 April 2025 to 27 June 2025              
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES - MISCELLANEOUS              
Subjective Summary
Approved
Annual Budget
Budget
Adjustments
Revised Annual
Budget at Period
3
Projected
Outturn
Budget
Variance 
(Adverse) or
Favourable  
£000 £000 £000 £000 £000 %
Employees 47,304 (11,839) 35,465 35,465 0 0.0%
Premises Related 2,938 0 2,938 2,938 0 0.0%
Transport Related 311 (20) 291 291 0 0.0%
Supplies and Services 2,011 (47) 1,964 1,964 0 0.0%
Transfer Payments 367 (131) 236 236 0 0.0%
Support Services (1,400) 0 (1,400) (1,400) 0 0.0%
Depreciation and Impairment Losses 13,232 0 13,232 13,232 0 0.0%
GROSS EXPENDITURE 64,763 (12,037) 52,726 52,726 0 0.0%
Income (13,803) 35 (13,768) (13,768) 0 0.0%
NET EXPENDITURE 50,960 (12,002) 38,958 38,958 0 0.0%

Page 13

Appendix 2 
Prior Years Approved  Budget Revised Projected Total Approved Projected
Expenditure Budget Adjustments Budget Outturn Budget Outurn
to 31/03/2025 2025-26 2025-26 2025-26 to 31-Mar-30 to 31-Mar-30
Project Title
£000 £000 £000 £000 £000 £000 £000
CORPORATE PROJECTS
ICT Infrastructure Maintenance & Renewal Programme 0 1,055 214 1,269 1,269 0 0% 4,469 4,469 0 0%
Lifecycle Capital Maintenance (LCM) Fund 0 5,822 828 6,650 6,650 0 0% 22,583 22,583 0 0%
Artificial Pitch Upgrades 1,315 700 486 1,186 1,186 0 0% 1,801 1,801 0 0%
Digital Infrastructure Provision 1,907 0 29 29 29 0 0% 1,936 1,936 0 0%
Commnunity Empowerment Fund 684 0 266 266 266 0 0% 951 951 0 0%
Villages Improvement Fund 349 0 201 201 201 0 0% 550 550 0 0%
Greenspaces and Parks 0 0 60 60 60 0 0% 60 60 0 0%
Retail Improvement Fund 149 0 1 1 1 0 0% 150 150 0 0%
TOTAL FINANCE, RESOURCES & CUSTOMER SERVICES
BOARD 4,404 7,577 2,085 9,662 9,662 0 0% 32,500 32,500 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Budget Variance
(Adverse) or
Favourable
Budget Variance
(Adverse) or
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 27th June 2025
POLICY BOARD: FINANCE, RESOURCES & CUSTOMER SERVICES
Current Year 2025-26 Full Programme - All years