EH&I SIP Outturn Report

Renfrewshire Council · 12 June 2025
Back to Finance, Resources and Customer Services Policy Board — 12 June 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

2 
___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board 
On: 12 June 2025
___________________________________________________________________ 
Report by: Director of Environment, Housing and Infrastructure 
___________________________________________________________________ 
Heading: Environment, Housing and Infrastructure - Service Improvement
Plan 2024-27 Outturn Report
___________________________________________________________________
1. Summary 
1.1 The Environment, Housing and Infrastructure Service Improvement Plan
2024-27 was approved by the Finance, Resources and Customer Services
Policy Board on 13 June 2024. The plan sets out the priorities for the
development of the service over a three year period.   
1.2 The Service Improvement Plan is part of a suite of documents which describe
the strategic direction of the service and the Council and also includes the
Council Plan, Community Plan, Risk Management Plan and the Workforce
Plan. 
1.3 The Service Improvement Plan is a comprehensive statement of the
outcomes the service aims to achieve, and the actions it will take to achieve
these. It fits within the wider planning framework of the Council by taking
account of Community Planning themes and Council priorities as set out in the
Council Plan which was refreshed in June 2024. 
1.4 Full details of Environment, Housing and Infrastructure performance and
achievements over the period 1 April 2024 to 31 March 2025 are appended to
this report. The main purpose of the report is to provide: 
• details of the key achievements of the service over the period;
• a progress update on implementing the action plan linked to the 2024-27
Service Improvement Plan; and

Page 2

3 
• an assessment of performance in relation to the service scorecard of core
performance indicators; 
1.5 During 2024/25, the service has made good progress in delivering positive
outcomes for Renfrewshire and its residents. This includes through the
actions within the Service Improvement Plan and also other areas of activity
which did not form part of the Service Improvement Plan actions which have
subsequently arisen during 2024/25. 
1.6 A new Service Improvement Plan covering the period 2025-28 is also being
presented to this meeting of the Finance, Resources and Customer Services
Policy Board. 
2. Recommendations 
It is recommended that the Finance, Resources and Customer Services
Policy Board: 
2.1 Note the content of this report 
2.2 Note the progress to date on delivering the actions contained within the
Environment, Housing and Infrastructure - Service Improvement Plan; 
2.3 Note the current performance of the service as measured by the scorecard
indicators. 
3.  Background 
3.1 The Service Improvement Plan is a comprehensive statement of the
outcomes the service aims to achieve, and the actions it will take to achieve
these. It fits within the wider planning framework of the Council by taking
account of Community Planning themes and Council priorities as set out in the
Council Plan. It enables elected members to have oversight of developments
within the service and to consider and develop policy options which reflect
customer need and resource availability. 
3.2 The Service Improvement Plan also provides a mechanism by which elected
members can evaluate the performance of the service. It contains an action
plan and performance indicators against which progress can be measured.
This outturn report provides an update on progress against the 2024-27 plan.

Page 3

4 
4. Key Achievements April 2024 to March 2025 
4.1 Environment, Housing & Infrastructure continues to deliver essential frontline
services across Renfrewshire. Key achievements for Environment, Housing &
Infrastructure under the remit of the Finance, Resources and Customer
Services Policy Board are detailed throughout the action plan and performance
indicators in the appendix. 
5. Areas where actions have been delayed or cancelled 
5.1 There has been no significant delay in the delivery of the actions contained
within the Service Improvement Plan. 
6. Progress against performance measures 
6.1 Environment, Housing and Infrastructure report on 10 performance indicators,
which are reported quarterly. 
Implications of the Report
1. Financial – The Service Improvement Plan highlights resourcing pressures
arising from increasing demand for services and the current financial
environment.  
2. HR & Organisational Development – The Service Improvement Plan also
highlights workforce development and wellbeing considerations.
3. Community/Council Planning – The report details a range of activities which
reflect Council and Community Planning themes and a direct link to the delivery
of the Council Plan.
4. Legal – none.
5. Property/Assets – none.
6. Information Technology – Service developments relating to information
technology are key enablers of service improvement and modernisation and
support service-level and corporate objectives.
7. Equality & Human Rights – The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights.  No
negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in
the report.  If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored, and
the results of the assessment will be published on the Council’s website. 
8. Health & Safety – none.

Page 4

5 
9. Procurement – none.
10. Risk – Risks related to the delivery and management of services are regularly
monitored and included in Renfrewshire Council’s Corporate and Strategic Risk
Registers and the service’s risk register.
11. Privacy Impact – none. 
12. Climate Change – Actions and indicators within the SIP covers the ‘green’ theme
of Renfrewshire’s Council Plan which highlights activities across the Council to
tackle climate change. 
13. Children’s Rights - none
14. Cosla Policy Position – none. 
___________________________________________________________________ 
List of Background Papers: 
Finance, Resources and Customer Services Policy Board; 13 June 2024 (Agenda
item 9) - Environment, Housing and Infrastructure – Service Improvement Plan 2024-
27 
Finance, Resources and Customer Services Policy Board; 21 November 2024
(Agenda item 13) - Environment, Housing and Infrastructure - Service Improvement
Plan 2024-27 Mid-Year Monitoring Report 
___________________________________________________________________ 
Author  Gordon McNeil, Director of Environment, Housing & Infrastructure  
Email: gordon.mcneil@renfrewshire.gov.uk

Page 5

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ENVIRONMENT,  HOUSING AND
INFRASTRUCTURE SERVICES
SERVICE IMPROVEMENT PLAN 2024-2027
Outturn Report
June 2025

Page 6

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
WELCOME TO OUR OUTTURN REPORT
 This update reflects progress over the last year of our Service Improvement Plan, highlighting areas where
we are already making progress and some areas we want to focus on more, perhaps because
performance isn’t moving in the direction we anticipated or because of other pressures or factors that
makes this even more of a priority for us.
 The following pages shine a spotlight on some great projects or practice and highlight areas where we’d
like to improve or develop further.  At a service level, there is a stronger focus on some of the Council Plan
Strategic Outcomes than others. Towards the end of this document, you’ll find a full update against all the
actions and performance indicators we use to measure progress.
 We report on 10 performance indicators, which are reported quarterly.

Page 7

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ABOUT US
This update covers the Environment, Housing and Infrastructure service areas within the remit of Finance,
Resources and Customer Services Policy Board. These are:
Facilities & Property Services covers four key service areas:
• Soft Facilities Management - cover janitorial, cleaning, catering, caretaking, housekeeping
and school crossing patrollers
• Building Services - cover building services operations, compliance, repairs and maintenance
for housing and public buildings
• Hard Facilities Management - responsible for compliance in schools and public buildings, life
cycle maintenance in schools & public buildings and PPP contract management
• Property Services is a multi-disciplinary design consultancy commissioned by Council
departments to deliver projects, including capital works.

Page 8

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Many of our Business as
Usual functions are
determined by reports
approved at board.  For
Environment, Housing &
Infrastructure, reports are
presented to different Policy
Boards depending on the
topic. Papers and access to
video recordings of past
meetings are available on
the Council’s website.
KEY PLANS, STRATEGIES AND REPORTS APPROVED DURING 2024/25
A revised Scheme of
Assistance for
Private Homeowners
Fireworks Control
Zones Process
Local Heat and
Energy Efficiency
Strategy Delivery
Plan
A revised Temporary
Accommodation
Charging Policy
The CCTV Installation
Policy
Roads Adoption
Policy
A new Cemetery
Management &
Memorial Safety
Policy
A revised Waste
Operations Policy
Pavement Parking
Policy/ Orders

Page 9

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE COUNCIL PLAN
Place: Partnership working
informs the facilities
management provision across
new developments.
The delivery and turnaround of
void properties review continues
to work towards returning
properties to the letting pool as
soon as possible.
The Strategic Property review
across the Council estate is
progressing well.
Economy: Environment,
Housing & Infrastructure
continue to provide
apprenticeship and trainee
opportunities across services,
encouraging positive
destinations.
Green: Renfrewshire’s focus on
the journey to Net Zero is
supported by efforts in Facilities
and Property Services through
new build e.g. Passivhaus or
retrofitting/future proofing the
property portfolio

Page 10

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
PLACE
Achievements:
• We have completed capital projects for Paisley Town Hall, Paisley Central Library and the Paisley Arts Centre.
• Work continues on major capital projects which includes Paisley Grammar School Community Campus and the new
Thistle Primary School in Dargavel.
• By 1 April 2025, Operational and Management void numbers had been reduced from 518 to 334 and void rent loss had
been reduced to less than 4.00%. By 28 February 2025 net void turnaround time had been reduced from 50.4 days in
2023–2024 to 37.7 days.
• The Single Voids Team (in conjunction with Housing Services) has been established and noted to be working well with re-
let times being reduced. Whilst Building Services are a key part of the team, the turnaround times have remained static
between 14 and 16 days .

Page 11

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ECONOMY
Achievements:
• Our Property Services (Technical Unit) has employed two vocational trainees; a building surveyor in June 2024 (6-month
appointment) and an architect in October 2024 (11-month appointment).
• Building Services have 7 current apprentices qualifying in summer 2025 with hope that they will secure employment within
Building Services. Interviews have taken place for the 2025 intake where there will be 5 youth apprentices and 2 adult
apprentices appointed from the Renfrewshire area.  Building Services now have 24 apprentices at various stages in their
apprenticeship journey.
• We continue to support Project Search with 2 interns carry out work experience in our premises.
• In January we launched a pathway for 6 school leavers to gain work experience in Soft FM for 6 months, with an
opportunity to apply for permanent posts.  This pathway will continue for another 6 summer school leavers.

Page 12

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
FAIR
Achievements:
• Soft FM have been awarded ‘Food for Life’ Bronze.
• A pre-order pilot in Park Mains high school has resulted in a quarter of the school roll sign up and begin to order
in advance. 
• School meals survey issued with 1500 responses which have helped the next menu cycle change in June 2025.
• Tasting sessions have been carried out within schools of the new planned menu items within our new menu.
• We continue to work with Children’s Services to review the whole breakfast offering within schools.

Page 13

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
LIVING OUR VALUES: MAKING A DIFFERENCE TOGETHER
Achievements:
• EHI continue to proactively support and encourage development of new ways of working where possible including the widespread
use of technology, such as M365 and GIS mapping, to improve collaborative working and streamline processes.
• Robust and up to date business continuity arrangements are in place across all services and are supported with ongoing training,
scenario planning and exercises
• Teams from EHI have completed Trauma Informed Training with almost 100 staff participating in 2024/25.  Trauma informed
approaches already aligned closely with the ethos of the service, but the additional training has highlighted opportunities to build
on existing good practice.
• Work has been undertaken to complete actions identified from Audit reports (Internal Audit and External Audit) and accreditations,
including maintaining British Standards ISO 9001 for identified services, have been retained.

Page 14

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
IMPROVING OUTCOMES FOR CHILDREN AND FAMILIES
Achievements:
• Environment, Housing & Infrastructure have been liaising with the Council's Promise
lead officer to ensure the service is supporting The Promise.
• Head of Housing Services (or nominated representative) continues to be a member of
Renfrewshire’s Promise Strategic Oversight Group. 
• There continues to be ongoing connection and dialogue between The Promise Manager
and the Homeless & Housing support Services Manager.
• There is currently activity taking place to review the Throughcare Partnership
Agreement. The new draft agreement has been updated to reflect the inclusion of “care
leavers in the transition of moving on from local authority care
Across all of our work and all of our efforts, we hope for loving and happy lives for Renfrewshire’s children – working together to
get it right for children, families and communities – protecting, learning, achieving and nurturing. Every priority of our Council
Plan contributes to improving the lives of Renfrewshire’s children and their families.

Page 15

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ACTIONS AND INDICATORS
Finance, Resources and Customer Services Policy Board
June 2025

Page 16

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Work with colleagues to advise on facilities
management requirements at new 
developments e.g. Paisley Grammar and the handover
of upgraded properties e.g. Paisley Town Hall 31 March 2025
Work has been undertaken to hand over cultural buildings from the Contractor/Property
Services to the Hard FM team. This has included meetings, physical handover of documents
and walkarounds of the Central Library, Paisley Arts Centre and Paisley Town Hall.
Officers are meeting regularly to discuss Paisley Grammar School Community Campus and
the new Thistle Primary School in Dargavel to ensure early input to design and that all
information that is required, is handed over for future compliance and maintenance.
As part of the new Department, Officers will work
together to review the delivery and turnaround of void
properties across Renfrewshire to minimise times,
wherever possible, to allow properties to be re-let.
31 March 2025
By 1 April 2025, Operational and Management void numbers had been reduced from 518 to
334 and void rent loss had been reduced to less than 4.00%. By 28 February 2025 net void
turnaround time had been reduced from 50.4 days in 2023–2024 to 37.7 days.
The Single Voids Team has worked well in reducing the Average re-let time over the last 12
months. The team has been extended to the end of June 2025 until further Organisational
Development work with a consultant. On-going discussion required around the continuation
of the team.
Building Services have performed consistently over this period and despite increasing works,
the turnaround time remains static between 14 – 16 days.
Review and strategically plan both proactive planned
preventative maintenance and reactive repairs to public
buildings in Renfrewshire including schools 31 March 2025
Hard FM are currently developing a boiler replacement programme for the whole estate.
Officers have also reviewed the recent condition survey data for the school estate and plan to
conduct feasibility studies for the 5 schools that are condition ‘C’ rated. This will help drive the
future short and medium-term capital investment (dependent on Strategic Property Review
and Learning Estate Strategy). This will carry forward into the new financial year.
Continue to review and deliver an electronic job
management and stores system. 31 December
2024
There remain ongoing issues surrounding the delivery of the system. The contractual
position regarding the delivery of the system was formalised and a new arrangement put in
place in January 2025. A new implementation programme is now in place and will be
monitored over the coming months until July 2025. Further deadlines will flow thereafter to
move the remaining workforce onto the system.
PLACE

Page 17

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Lead and drive the Strategic Property Review
across Renfrewshire Council’s estate.
31 March 2025
An updated report was taken to the Infrastructure, Land and Environment Policy Board in
January 2025. A new Asset Management Oversight Group has also been established to
provide oversight and Governance for all reviews and projects involving assets.
A lot of data gathering now complete and building categories established to allow engagement
with building users, communities and Elected Members. The plan is to rationalise the estate to
make efficiencies.  Several buildings have been released including Old Farmhouse, additional
lease for Corporate Records and securing of Montrose Care Home, Falcon Day Centre and
sale/removal of staff from Robertson Centre.
Work with Savills to produce a robust business
plan that looks at the short medium and long
term for Building Services. 31 March 2025
Due to continuous changes in information required for the Business Plan, the final draft has
been delayed. This is to ensure it is fully accurate and captures all pertinent information e.g.
introduction of a new team to undertake kitchen and boiler works for Housing Services.
Key data and structures required for final report – staffing, workforce age profile, key
performance indicators etc.  Draft discussed with consultant and updates currently being
made.
Develop and focus on repairs and compliance -
short-, medium- and long-term plan on property
portfolio.
31 March 2025
We are proactively ensuring greater diligence across the public buildings funding model. This
involves greater collaboration with our Building Services and Finance partners to ensure the
budget spent appropriately. A focus group has been established and, in addition, have
monthly meetings with Building Services to ensure spend is being monitored in greater detail.
Data management systems still pose a challenge, and we are hopeful we can evidence some
improvement how these system integrate with one, in the coming months.
Continue to develop large capital projects,
including schools for Renfrewshire Council.
31 March 2025
Technical Unit now in progress of delivering Paisley Grammar School Community Campus
(on site since March 2024), Thistle Primary School in Dargavel (enabling works now on site),
Park Mains High School Extension (now awarded to Stage 1 Main Contractor) and
discussions around a new primary school in Johnstone (feasibility options undertaken).
PLACE

Page 18

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current
Status
2022/2023 2023/24 2024/25 Q1 Q2 Q3 Q4 2024/25 Explanation of performance
Value Target Value Target Target Value Value Value Value Value
% of Overall
repairs completed
within time by
building services
93.43% 95% 92.1% 95% 95% 94.5% 95.37% 94.36% 90.2% 93.2% Year-end performance has improved
compared to the previous year.
Average length of
time taken to
complete non-
emergency repairs
– public
buildings (days)
N/A 6.1 days 15 days 7.9 days 15 days 15 days
Data unavailable
The challenges remain in connection with the
WorkHub system implementation currently and
Officers continue to close jobs in a manual
basis across multiple system areas.
The manual processes in place continue to
operate as intended with additional close
monitoring in place across, Finance, Building
Services and the Support Services teams.
The Workhub upgrades required are now in
the testing and development stage and it’s
intended that the system should be able to
provide ongoing meaningful KPI data for the
fiscal period 25/26 onwards.
% of compliance
tasks undertaken
per year –Statutory
compliance for
public buildings
82% 90% 88% 90% 90% 84% 89% 87% 87% 87%
Good performance across compliance tasks
within the portfolio with Officers working to
meet the 90% target. Officers continue to
review and strive to increase at all times.
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 19

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Provide employment, training, and
apprenticeship opportunities for identified
groups of young people in Renfrewshire.
31 March 2025
Property Services (Technical Unit) had employed two vocational trainees; a building surveyor
in June 2024 (6-month appointment) and an architect in October 2024 (11-month
appointment). The 6 month placement for the building surveyor trainee has now finished but
another 6 month placement, with a different trainee, is planned for June-December 2025.
Soft FM continue to support Project Search, currently have 2 Interns doing work experience
in our premises
Launched Pathway for School Leavers in January 2025. 6 Christmas School leavers who
don’t want to go on to further education have secured 6 months FTC in Soft FM.  The
trainees will be given training on Cleaning, Catering, Food Orders as well as classroom
training on Managing Money, Interview Skills.  At the end of the 6 months, trainees will have
the opportunity to apply for permanent posts.  The pathway will be offered to another 6 school
leavers in the summer.
Interviews now completed for the August 2025 apprenticeship intake. There will be 5 youth
apprentices and 2 adult apprentices all of whom live in the Renfrewshire area. They will
commence their apprenticeship in August this year.
There will be 7 current apprentices qualifying in the summer of 2025 and it is hoped that they
will secure employment within Building Services. This will ensure that Building Services
continue to have 24 apprentices at various stages in their apprenticeship journey.
We provided a young person through the “Promise” two weeks work experience. The
individual did very well and enjoyed the work. The Invest team will now use this experience to
enhance his CV.
We also work with invest to support work placements and recently recruited an invest
candidate to a permanent post within the service. 
ECONOMY

Page 20

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do                        Due Date Status Progress Update
Work with Children’s Services/pupils to enhance dining
experience and develop the menus to be more
attractive whilst meeting requirements of the Nutritional
Requirements for Food and Drink in Schools
(Scotland) Regulations 2020
31 March 2025
Soft FM issued school meals survey in January 2025; 1500 responses which have helped
create the next menu cycle change in June 2025
Tasting sessions have been carried out within schools of the new planned menu items within
our new menu.
A pre-order pilot in Park Mains high school has resulted in a quarter of the current school roll
sign up and begin to order in advance. This has helped to reduce queuing times, which are
one of the biggest complaints we receive.
The next planned roll out school is Castlehead high school after the spring break
Work with Childrens Services to provide a healthy
breakfast to school pupils where possible.
31 March 2025
.
We are working with Children’s Services to review the whole breakfast offering within Schools.
£269K capital investment from Scottish Government to
enhance the dining experience in preparation for
eligibility of the Scottish child payment for the
entitlement free universal school meals for P6 and P7.
Continue to collaborate with Property and Technical to
plan improvements across in up to 5 schools.
31 August 2025
Parents/Carers of pupils in primary 6 and 7 who are eligible for Scottish child payment will be
eligible for free school meals from 22 April 2025.  Applications will open on 4 April 2025.
Government Data will be available in May 2025, any eligible parents/carers that have not yet
applied will be contacted and offered free school meals for pupils in P6/7.
FAIR

Page 21

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current
Status
2022/2023 2023/24 2024/25 Q1 Q2 Q3 Q4 2024/25 Explanation of performance
Value Target Value Target Target Value Value Value Value Value
% uptake of free
school meals in
primary schools
53.4% 52% 52.5% 60% 60% 53.4% 61% 62% 63.5% 60.2%
The uptake for 24/25 is 60.2%
which is an improvement on the
23/24 uptake of 52.5%
% uptake of free
school meals in
secondary schools
39.1% 35% To follow 42% 42% 31.1% 41.1% 40.9% 39.3% 41.3%
The uptake for 24/25 is 41.3%
which is slightly below the
target of 42%. We are
continuing to work on getting
this data as accurate as
possible and including the
adjustment for study leave
during quarter 1.
DELIVERING THE SERVICE IMPROVEMENT PLAN– FAIR

Page 22

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Provide our employees with the appropriate
support to manage their attendance, health, and
wellbeing
31 March 2025 All employees are supported to manage their attendance, health and wellbeing including the
use of Occupational Health referrals and Counselling where appropriate.
Better use of data and technology to improve
services performance and delivery
31 March 2025 Better use of data and technology underpins our drive to improve service performance and
delivery. Work in 2024/25 has included supporting the Waste & Recycling Service with a
rerouting project, Roads & Transportation to implement a new system and GIS mapping for
our trees and using robotic cleaning machine to ensure our resources are allocated efficiently
and effectively.
Implement the next phase of transformation as
part of Right for Renfrewshire
31 March 2025 EHI has completed the Right for Renfrewshire Programme.
Engage and participate in trauma informed and
responsive Renfrewshire programme
31 March 2025 Teams from Environment, Housing and Infrastructure have completed Level 1 (Trauma
informed) and Level 2 (Trauma Skilled) Training with almost 100 staff participating in 2024/25.
Trauma informed approaches already aligned closely with the ethos of the service, but the
additional training has highlighted opportunities to build on existing good practice, not only in
terms of working with service users but also in supporting colleagues.  Staff from EHI were
invited to the Trauma Informed and Responsive Renfrewshire Steering Group to present on
how the training has benefitted them and how they have implemented the learning.
Work with Services across EH&I to support
further digitisation and business improvement of
our processes to meet the needs of our
customers.
31 March 2025 Work has been undertaken to engage with services to identify opportunities for digitisation
and business improvement of our processes so that they continue to meet and exceed the
needs of our customers.
LIVING OUR VALUES

Page 23

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Continue to develop new approaches to staff
communication and engagement across all areas
of the service
31 March 2025 Prioritising employee engagement and communication actions identified through the
organisational workplace survey and insights from staff comms pulse survey, including forums
for direct employee feedback and working with managers to develop effective approaches to
communications and engagement with frontline operational teams.
Ensure robust and up to date business continuity
arrangements are in place and maintained
31 March 2025 Robust and up to date business continuity arrangements are in place across all services and
are supported with ongoing training, scenario planning and exercises.
Embed the enquiry systems for public and
elected members across Environment, Housing
& Infrastructure services
31 March 2025 The enquiry system for public and elected members is established and embedded across
Environment and Infrastructure Services and supports ongoing work to identify recurring
issues or concerns and service improvement.
The work to establish and embed an enquiry system for Housing Services within Environment,
Housing & Infrastructure is progressing, staff have been recruited, work has commenced on
complaints and investigations and in the first quarter for 25/26 work will commence on elected
member enquiries.
Review Health & Safety and Risk Assessments 31 March 2025 The Environment, Housing & Infrastructure Health and Safety Plan 2024/25 end of year report
and an updated Environment, Housing & Infrastructure Health & Safety Plan 2025 – 2028 will
also be considered by the appropriate Board in May/June 2025. Work has taken place across
services throughout 2024/25 to review health and safety and risk assessments.
Ensure robust financial monitoring 31 March 2025 Regular financial monitoring discussions with Senior Management and the Finance Team are
well established to support ongoing monitoring and planning of resources with the financial
position reported to the Board on a regular basis.
Review and maintain continuous improvement
frameworks
31 March 2025 Work has been undertaken to complete actions identified from Audit reports (Internal Audit
and External Audit) and accreditations, including maintaining British Standards ISO 9001 for
identified services, have been retained,
LIVING OUR VALUES

Page 24

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Support the Council in developing New Ways of
Working
31 March 2025 Environment, Housing & Infrastructure continue to proactively support and encourage
development of new ways of working where possible including the widespread use of
technology, such as M365 and GIS mapping, to improve collaborative working ad streamline
processes.
Develop and undertake a Strategic Property
Review of Council operational, non-operational
and surplus assets
31 March 2025 An updated report was taken to the Infrastructure, Land and Environment Policy Board in
January 2025. A new Asset Management Oversight Group has also been established to
provide oversight and Governance for all reviews and projects involving assets.
A lot of data gathering now complete and building categories established to allow engagement
with building users, communities and Elected Members.
The plan is to rationalise the estate to make efficiencies.
Several buildings have been released including Old Farmhouse, additional lease for
Corporate Records and securing of Montrose Care Home, Falcon Day Centre and
sale/removal of staff from Robertson Centre.
LIVING OUR VALUES

Page 25

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current
Status
2022/2023 2023/24 2024/25 Q1 Q2 Q3 Q4 2024/25 Explanation of performance
Value Target Value Target Target Value Value Value Value Value
Average number of
workdays lost
through sickness
absence per
employee (FTE)
(cumulative)
15 13.7 14.91 13.7 13.7 4.15 3.58 4.06 3.62 15.41
The cumulative total for 24/25 is 15.41 days
lost which is slightly higher than cumulative
total for 23/24 14.91 days lost.
% of Members
enquiries completed
within timescale 93% 85% 92% 85% 85% 92% 94% 89% 92% 89.2%
Environment, Housing & Infrastructure
received 6,659 members enquiries in
2024/25, of which 89.2% were responded to
within timescale.
% of frontline
resolutions dealt
with within
timescale
87% 85% 85% 85% 85% 40% 58% 68% 84.2% 62.3%
Environment, Housing & Infrastructure
received 10,820 front line resolutions in
2024/25, of which 62.3% were responded to
within timescale.
% of complaint
investigation
completed within
timescale 
93% 95% 89% 85% 85% 45% 40% 47% 64.5% 50.4%
Environment, Housing & Infrastructure
received 361 complaint investigations in
2024/25, of which 50.4% were responded to
within timescale.
% of FOI request
completed within
timescale 99% 100% 100% 100% 100% 98.51% 97.37% 98% 99.2% 98.6%
Environment, Housing & Infrastructure dealt
with 645 Freedom of Information requests in
2024/25, of which 636 (98.6%) were
responded to within timescale. 215 of these
requests were cross departmental and 430
were departmental.
DELIVERING THE SERVICE IMPROVEMENT PLAN– LIVING OUR VALUES

Page 26

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
CROSS CUTTING THEME 
IMPROVING OUTCOMES FOR CHILDREN AND FAMILIES
“Across all of our work and all of our efforts, we hope for loving and happy lives for Renfrewshire’s children - working together to get it right for children, families and communities –
protecting, learning, achieving and nurturing.  Every priority of this Council Plan will contribute to improving  the lives of Renfrewshire’s children and their families.  It is our fundamental
duty as an organisation and our shared responsibility as citizens of this place to ensure that our children inherit a Renfrewshire where their wellbeing is nurtured, their futures are
bright, and their environment is safe and healthy.’
What we will do Due Date Status Progress Update
EH&I will work towards keeping The Promise 31 March 2025 Head of Housing (or nominated representative) continues to be a member Renfrewshire’s
Promise Strategic Oversight Group. 
There continues to be ongoing connection and dialogue between The Promise Manager and the
Homeless & Housing support Services Manager.
There is currently activity taking place to review the Throughcare Partnership Agreement. The
new draft agreement has been updated to reflect the inclusion of “care leavers in the transition of
moving on from local authority care”.
Deliver a programme of engagement with
schools, parents, and pupils, encouraging
participation in the development of school meal
menus
31 March 2025 Pupil tasting sessions of proposed new items have been underway in Howwood primary school.
Meeting with pupil council in Lochfield primary in January was held with menu & nutrition officer.
SFO have been trialling new items in each site for feedback    Promotion of meals undertaken by
SMFO in each cluster to encourage pupils who take packed lunches to try the menu.
Consider implementing robotics for cleaning
Secondary schools to improve the service
provided.
31 March 2025 Business Case submitted and approved. Robotics to be introduced in Secondary Schools, waiting
funding in order to purchase.

Page 27

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
EHI SERVICE IMPROVEMENT PLAN
OUTTURN REPORT
JUNE 2025