To: Finance, Resources and Customer Services Policy
Board On: 3 April 2025 
Report by: Director of Environment, Housing & Infrastructure 
Heading: Facilities and Property Services - Service Update Report 
1 Summary 
1.1 Environment, Housing & Infrastructure brings together a range of Council
services and activities, with both strategic and operational responsibilities. This
report provides an operational performance update on Facilities Management
(Hard and Soft Services), Building Services and Property Services delivered by
Environment, Housing & Infrastructure since the last Policy Board in February
2025. 
1.2 Due to the date of the Board, data for quarter 4 is currently unavailable and
therefore will be reported to the next Board in June 2025. 
2 Recommendations
It is recommended that members of the Finance, Resources and Customer
Services Policy Board: 
2.1 Note the content of this report. 
3 Operational Update 
Hard Facilities Management (Hard FM) 
3.1 Capital/Lifecycle Projects 
3.1.1 As detailed and discussed at a previous Board, a review of the Core Facts
property condition surveys (5 yearly checks across the Learning Estate), led to a
prioritised list of work to upgrade some schools. Additionally, Net Zero surveys
have been approved to the following properties:

Page 2

 Glenfield Satellite (Pre five nursery)
 Williamsburgh Primary School and Nursery 
3.1.2 Works have been approved to upgrade the Multi-Use Games Arenas (MUGAs)
at the following schools:
 Our Lady of Peace Primary School 
 Arkleston Primary School 
3.1.3 Due to the complexities of lifting and relaying a pitch/MUGA at schools (pitch out
of commission), consultation with the school will be important to ensure safe
working practices and this may delay the installation until later in 2025 or 2026. 
3.1.4 Renfrewshire Schools Partnership (RSP) have provided reports to the Council
following Core Facts Condition surveys.  PPP Facilities Manager will review
these reports with a view to planning future Lifecycle Maintenance works. 
3.2 Lifecycle Replacement works 
3.2.1 The following commissions have been planned/progressed/completed since the
previous Board:
 £500k has now been set aside for various Council wide minor upgrade
works. 
The table below (indicative list) highlights some work that has recently been approved or is
in progress and others yet to be fully explored and agreed but currently being scoped: 
Site Type of Work Work Required Status
Lochwinnoch Nursery Fence gates Alter gate In Progress
Lochfield ELCC Fence gates New fence In Progress
Houston PS Roof works Roof repairs Planned
Williamsburgh PS Roof works Reline Gutter Planned
Rashielea PS Roof works Re-felt roof Planned
St James PS CCTV Renew CCTV
workstation
In Progress
Lochwinnoch Library Roof works Slate and lead
flashing works
In Progress
Tweedie Hall Heating Renew pipework
roof
In Progress
Renfrewshire House Roof Works Roof edge
protection & ladders
In Progress
Heriot PS Painting/Flooring/Joinery Paint GP room and
replace
flooring/units and
tiles following flood.
TBC 
Other works include:
 Storm Eowyn – Officers continue to manage the repair works following
building damage. Over 35 schools and 50 other council buildings
suffered damage during the storm. Engagement with the insurance
team and loss adjuster continues, to ensure any costs are recovered

Page 3

(where appropriate).
 Renfrewshire House – works will be in the roof voids of each floor to
check and undertake fire separation/stopping works. Phase 1 of this
project now complete – lessons learned with further works to follow.
Commission now raised to Property Services for the roll-out across all
areas. Works require a full tender process due to the value of the
contract.
 Lochfield Primary School – Removal of wall and erection of new fence
(or wall). Resident engagement on going. 
 Underwood Road Depot – Installation of new CCTV system within
Building Services stores/offices.
 Howwood Primary School – historic water ingress. (Ongoing – roof
covering fixed but still water ingress).
 Johnstone Community Centre - new roof over stage area (complete).
 LED upgrade works – review of schools that require upgrade, working in
conjunction with our Net Zero colleagues.
 Park Mains High School - LED lighting upgrade (Atrium).
 Renfrewshire House – CCTV upgrade feasibility. 
PPP Lifecycle works: 
 The Council have now reviewed the 2025 Lifecycle Maintenance
programme provided by RSP and have commented on various aspects
under the PPP contractual Review Procedure and now await response
from RSP. 
3.2.2 The Hard FM team are currently working on the following commissions:
 Condition Surveys for OneRen swimming pools
 Condition surveys for various community buildings (19 buildings in total)
 Various works to community/leased buildings
 HQ Building Management System upgrade 
 HQ lining of car park, general clean up and drainage works (on-going)
 HQ lighting and controls upgrade feasibility (sample bespoke fitting now
installed and route to market being determined)
 Foxbar Rivers Community Centre – renewal of fascia/soffit and gutters 
3.2.3 As part of the Council budget, Officers are drafting plans for additional funding
that has been provided:
 £700k for school pitch improvements.
 £800k for Community Facilities to assist in potential CAT transfers
 £1m recurring revenue, including lifecycle works across the Learning
Estate 
3.2.4 Updates will continue to be brought to this Board periodically to update on
plans and spend.

Page 4

3.3 Compliance – Key Performance Indicators (KPIs) 
3.3.1 For this financial year, there was approximately 1700 planned tasks with overall
performance of this period at 87%.  Officers continue to engage with service
providers to ensure target dates are met and performance is improved. 
3.3.2 Overall performance for this period continues at 100% within the PPP Schools
estate. 
3.4 Public Buildings Repairs data 
3.4.1 The repairs profile remains as expected, as detailed below for 2024/25: 
2024/25
Repairs
Education Core Prestige OneRen Total
6441 2243 745 305 9734 
3.4.2 The financial pressure on the repairs budget remains a challenge for the service
and, as reported previously, all non-essential works is now being deferred until
further notice. 
3.4.3 New contract has now been awarded for Lightning Protection Systems
(maintenance and reactive repairs – Council wide). 
3.5 Fire Safety 
3.5.1 All fire risk assessments in sleeping accommodation have now concluded.
Officers are reviewing the reports and actioning any items that will mitigate and
lessen the overall fire risk for each property. These works have been on-going
and checks are being undertaken to ensure all works are complete.  Officers
continue to engage with our colleagues within CPU for the renewal of smoke
vent tender and fire dampers (new tender). 
3.5.2 All fire risk assessments in the PPP Schools Estate have now concluded with
recommended actions being reported as being completed. The PPP - Facilities
Manager reviewed a sample of actions and there are currently only a couple of
items now outstanding and reported back to AMEY. 
3.6 Responsive Repairs 
3.6.1 From the return after the Christmas break to the writing of the report, Building
Services has received 14,002 responsive repairs reported by tenants. This is an
increase of 11.4% compared to the same time period last year. This can be
attributed to the recent cold weather and storms. 
3.6.2 There were over 600 roofing repairs reported due to the recent storms. Building
Services Operatives, as well as sub-contractors are working to complete the
required works as soon as possible. Many require scaffolding in order to carry
out the works safely which can delay the progress.

Page 5

3.6.3 The productivity across the responsive repairs teams is monitored and assessed
weekly. The graph shows the tracking of the average number of jobs completed
per operative per day from April 2024 to February 2025. The industry average is
4.5 jobs, per operative, per day and Building Services have been consistently
above this level. 
3.7 Voids 
3.7.1 Building Services continue to average between 15-16 days to complete all
works required within a void property. However, figures show that the average
hours estimated in each void property continues to rise significantly with a
consistent rise of just over 22% since January 2024. 
3.7.2 From 6 January 2025, until 23 February 2025, Building Services received 80
full void packs in total, averaging 11 a week, this is a drop from Quarters 1
through 3, where Building Services were receiving 16 properties on average
per week. Discussions with colleagues in Housing Services continue to ensure
any issues are resolved quickly before being passed to Building Services. 
3.7.3 Estimated work volume per property, however, continues to increase
substantially. It is currently averaging 156 hours per property, rising from Q1
(119 hours per property), Q2 (130 hours per property) and Q3 (135 hours per
property). The increase in volume of work has made it challenging for Building
Services to return completed voids within the KPI’s, however, efforts continue
to be made to achieve these. 
3.7.4 Building Services continue to attend and change locks to Terminations,
Absconds and evictions which remain averaging at 22 per week which has
been the constant figure throughout 2024/25.  
3.8 Electrical Testing programme 
3.8.1 Building Services are carrying out a program of EICR testing in communal
areas and closes. To date, Building Services have completed 123 communal

Page 6

areas/closes. 
3.8.2 The homes that have failed to engage with the process to have the EICR test
have now moved to the forced entry process. The number of forced entries
from January 2025 to February 2025 is 39. 
3.9 Apprentices/Training 
3.9.1 Building Services are recruiting 7 apprentices over the next few months. There
will be 6 youth apprentices recruited from within the Renfrewshire area and 1
adult apprentice position which is open to all employees of Renfrewshire
Council. 
3.9.2 Building Services are delighted to report that one of our 4th year painting
apprentices has been selected as a finalist in the APSE National Apprentice
awards. 
4     Soft Facilities Management (Soft FM) 
4.1 School Meals 
4.1.1 The Pilot for the rollout of the preorder app commenced on 20 January 2025 in
Park Mains High School. So far over 200 pupils have registered for the use of
the app and Children’s Services has supported the implementation by
promoting the information to parents and pupils. The app pilot is being rolled
out in Johnstone High School after the Easter break. 
4.1.2 The app will be implemented in the PPP school estate to senior pupils at St
Benedicts High School later in the next couple of months. 
4.1.3 HMIE inspection completed at Gleniffer High School week commencing 3
March 2025 and included a Health and Nutrition inspection. Feedback was
noted to be positive and any improvements have been taken on board and
made within the catering area. 
4.2 Special and Complex Diets 
4.2.1 The new process for complex and medical diets was shared with relevant
stakeholders. Feedback and suggestions have been received and will be
reviewed. The new process will be implemented in April 2025 and shared with
all parents, guardians, and other stakeholders thereby establishing a robust
process for the ongoing management of special diet requests. 
4.3 Scottish Child Payment 
4.3.1 Work continues to increase the number of pupils attending universal free
school meals (P1-P5), free school meals and paid meals across both primary
and secondary schools. Work is ongoing to create a process to provide the
required information for pupils in P6-7 who will meet the criteria for a free
school meal based on families in receipt of SCP.  The overall average uptake
figures for School meals (Periods 1-12) currently sits at 58.8%

Page 7

4.3.2 Work continues by the Scottish Government to resolve the data sharing issue.
In the interim period, Renfrewshire Council is working to create an additional
element on the current free school meal application form to include these
criteria. Soft FM remains confident it can facilitate the additional numbers due
to the work undertaken previously, the re-instatement of additional cooking
establishments and the planned capital work forecast for 2025. 
4.3.3 The figure in 4.3.1 are not adjusted due to the timing delay of pupil absence
figures being received. Discussions are being undertaken as to how this can
be improved which will ensure “real time” attendance figures can be utilised to
reflect accurate uptake figures. 
Implications of the Report 
1. Financial – Any financial elements referenced in this report will be progressed
through the Council’s financial & budget planning process. 
2. HR & Organisational Development – Apprentice recruitment detailed in the
report will be undertaken as per standard Renfrewshire Council recruitment
processes. 
3. Community/Council Planning – the report details a range of activities which
reflect local community and council planning themes. 
4. Legal – As detailed within the report. 
5. Property/Assets – As detailed within the report in relation to work on the
Council property portfolio. 
6. Information Technology - None 
7. Equality & Human Rights – The recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following implementation,
the actual impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be published
on the Council’s website. 
8. Health & Safety – Advice and guidance is being given to protect the health
and safety of employees and service users when carrying out priority services
for the
Council in line with government and health guidance. 
9. Procurement – As noted within the report. 
10. Risk – None

Page 8

11. Privacy Impact – The Scottish Government are looking to introduce legislation
to allow the data sharing with local authorities in relation to parents/carers who
receive the Scottish Child Payment. 
12. COSLA Policy Position – None 
13. Children’s Rights – Facilities and Property Services are essential in trying to
assist and deliver in support of Children’s Rights. In particular, the report
demonstrates compliance by ensuring buildings are suitable provides good
educational establishments (Article 28 - Access to Education) and by delivering
schools meals and nutritious food (Article 27 – Food, Clothing, and a safe
home). 
14. Climate Change – Parts of the work undertaken in this report will reduce
carbon emissions and assist in trying the reach Net Zero targets by improving
efficiency of current buildings and new buildings across the portfolio. 
List of Background Papers 
None 
Author: Gordon McNeil, Director of Environment, Housing & Infrastructure